Update #30 Downtown Campus 
Reinvestment Project
City Council Workshop
February 25, 2025
Presenter: Eddie Garcia

2
Site Activities

3
Site Activities

4
Site Activities

5
Site Activities

6
Caissons

7
Exterior Envelope

8
Interior Framing

9
Interior Framing

10
Existing HVAC

11
Roof  Top Mechanical

12
Roof  Top Mechanical

13
Roof  Top Mechanical

14
Building Envelope

15
Energy Reduction 
$191,215

16
Energy Reduction

17
Commissioning

18
In Progress
Scope
Schedule
Budget
• Storm Water Lift station in place
• Roof Top Equipment & Screen Wall Structure
• Caissons drilled and placed
• Rough overhead Mech., Fire Sprinkler, Plumbing (2-4)
• Electrical Rooms: Transformers and Panels
• Interior Framing
• Site Work along Glendale Ave. and Glenn Drive
Next Month
• Roof Top Dry In
• Building Envelope (Water Proofing and Masonry)