Amendment No.1 to Agreement with B&F Contracting

City of Glendale — Regular Meeting (2025-03-25)

View PDF Item 7 Meeting page

Extracted text (via pymupdf) 470256 characters
City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
Project Name: Arrowhead Sewer Line Phase 1.1 - Construction Manager at Risk 
Project No.: 
202104.1 
Amendment No: 1 
Date: 
 
      
 
This Amendment to that certain Standard Form Agreement dated June 11, 2024 by and between the City of Glendale 
and B & F Contracting, Inc. (CM@Risk) for services, deliverables and work related to Project No. 202104.1, Project 
Name: Arrowhead Sewer Line Phase 1.1 - Construction Manager at Risk, (the “Agreement”) is made and entered 
into effective this       day of      , 2025. 
 
1. This Amendment #1 establishes a Guaranteed Maximum Price (“GMP”) and Construction Phase Fee for 
Construction Services and incorporates such terms into the Agreement, making the Agreement effective 
for Construction Phase Services: 
 
a. 
The total fee for Construction Phase Services, which is included in the Guaranteed Maximum Price (GMP) 
as defined under the Agreement, shall be fixed at One Hundred Seventeen Thousand Eight Hundred 
Seventy Dollars and Thirty Cents Dollars ($117,870.30). [INSERT ADDITIONAL LANGUAGE HERE 
IF PHASED AGREEMENT.] 
 
b. The Guaranteed Maximum Price (“GMP”) for Construction Services, as defined under the Agreement, shall 
be Two Million Three Hundred Twenty-Nine Thousand Two Hundred Fifty Dollars and Seventy-Four 
Cents Dollars ($2,329,250.74). [INSERT ADDITIONAL LANGUAGE HERE IF PHASED 
AGREEMENT.] 
 
c. 
The total compensation under the Agreement, as amended by this Amendment, shall be: 
 
 
Pre-Construction Phase 
Construction Phase 
Total 
Original Agreement: 
$143,068.20 
$      
$143,068.20 
 
 
 
 
Previous Amendments: 
$      
$      
$      
 
 
 
 
This Amendment: 
$      
$2,329,250.74 
$2,329,250.74 
 
 
 
 
Total (including this 
Amendment): 
 
$143,068.20 
 
$2,329,250.74 
 
$2,472,318.94 
 
 
2. DELETE the blank template “Exhibit C – Cost of the Work – Schedule of Values” from the Agreement, 
and ADD “Exhibit C – B & F Contracting, Inc. Cost of the Work – Schedule of Values” dated January 27, 
2025 (8 Pages), attached herein. 
 
3. ADD “Exhibit E – Construction Documents necessary to define Scope of Work and deliverables for the 
Construction Phase Services, including plans, designs, drawings, specifications and other required 
Contract Documents” dated Ocotber 29, 2024 (214 Pages), attached herein. 
 
4. ADD “Exhibit F - Statement of All Clarifications and Assumptions” dated January 28, 2025 (2 Pages), 
attached herein. 
 
5. ADD “Exhibit G – Schedule of Major Milestones” dated January 28, 2025 (1 Pages), attached herein. 
 
6. All other provisions, terms and conditions of the Agreement shall remain unchanged and in full effect. 
 
(Signature on following page)

Kevin R. Phelps
City Manager

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
EXHIBIT C 
Cost of the Work 
 
(One (1) page - template) 
(8 pages - final document to be included with GMP Amendment) 
 
SEE ATTACHED

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
T H I S P A G E I S B L A N K

ROC-089744   |   BFCONTRACTING.COM   |   11011 N. 23rd Avenue|   Phoenix, AZ 85029 
P: 623.582.1170   |   F: 623.582.3761 
 
 
 
EXHIBIT C: COST OF THE WORK 
Arrowhead Phase 1.1 
 
GMP-001 
 
PROJECT NO. 202104 
 
January 27, 2025  
 
 
 
SUBMITTED BY B&F CONTRACTING, INC. 
 
 
 
B&F Contracting, Inc., serving as the Construction Manager at Risk, is providing GMP-001 for 
Arrowhead Phase 1.1 Sewer and Manhole Rehabilitation. The scope of work for GMP-001 is outlined 
in further detail in this Exhibit C and Exhibit E. Note, a GMP-002 will be developed for the Waste 
Activated Sludge Line Realignment Phase.

Cost Code
Item of Work
Quantity
Unit of Measure
Unit Cost 
Total GMP
Mobilization/Demobilization
1
 LS 
$62,308.14  $                        62,308.14 
SWPPP
3
MO
$6,435.04  $                        19,305.12 
Project Indirect Cost
3
 MO 
$63,690.73  $                      191,072.19 
 $                      272,685.45 
PCCP Replacement
222
 SY 
$420.04  $                        93,248.88 
Curb & Sidewalk Replacement
4
 EACH 
$4,338.82  $                        17,355.28 
Sewer Bypass Installation And Removal
1
 EACH 
$242,842.72  $                      242,842.72 
Bypass Operation
30
 DY 
$8,360.75  $                      250,822.50 
Rehabilitate 42" Pipe With CIPP
1058
 LF 
$346.56  $                      366,660.48 
Dewater, Clean, & CCTV Pipe
1058
 LF 
$22.10  $                        23,381.80 
Install Manhole
1
 EACH 
$119,101.25  $                      119,101.25 
Rehabilitate And FRP Wrap Manhole Bench
2
 EACH 
$17,406.86  $                        34,813.72 
Install Manhole Composite Insert
2
 EACH 
$26,233.35  $                        52,466.70 
 $                                     -   
 $                   1,200,693.33 
 $                   1,473,378.78 
FEE
Fixed Fee, Equal to 8% of DCC
1
 LS 
 $                  117,870.30  $                      117,870.30 
 $                      117,870.30 
BONDS
CMR Performance and Payment Bonds - Actual Cost, not-to-Exceed 1% of DCC
1
 LS 
 $                    15,912.49  $                        15,913.49 
CMR-managed Sub-Contractor Bond Program - Actual Cost not-to- exceed 0% of 
DCC of covered Sub-Contractors (if applicable)
$                                     -   
INSURANCE
CMR Insurances (Worker's Comp, General Liability, Auto Liability, Umbrella) - 
Actual Cost, not-to-exceed 1.1% of DCC
1
 LS 
 $                    17,678.79  $                        17,679.79 
Builder's Risk - Actual Cost not-to-exceed 0% of DCC
$                                     -   
CMR-managed Sub-Contractor Inssurance Program - Actual Cost
not-to-exceed 0% of DCC of covered Sub-Contractors (if applicable)
$                                     -   
TAXES
Actual Cost, Equal to 5.98% of DCC + Fee + Bond + Insurance
1
 LS 
 $                    97,165.57  $                        97,166.57 
 $                   1,722,008.93 
ALLOWANCES & CONTINGENCIES
Traffic Control
1
 AL 
 $                  150,000.00  $                      150,000.00 
Off-Duty Officers
1
 AL 
 $                    62,700.00  $                        62,700.00 
Survey/GIS
1
 AL 
 $                      6,500.00  $                          6,500.00 
Quality Control Material Testing 
1
 AL 
 $                      8,500.00  $                          8,500.00 
Odor Control Allowance
1
 AL 
 $                    23,216.00  $                        23,216.00 
Striping Allowance
1
 AL 
 $                    15,000.00  $                        15,000.00 
Landscaping Allowance
1
 AL 
 $                    10,000.00  $                        10,000.00 
Owner's Contingency (10%)
1
 CONT 
 $                  331,325.80  $                      331,325.80 
 $                   2,329,250.74 
City of Glendale Exhibit C - Construction Manager at Risk Agreement Cost of the Work (November 26, 2024)
SUBTOTAL INDIRECT CONSTRUCTION COST  (ICC)
TOTAL GMP  =  DCC + FEE + ICC
ADDITIONAL GMP PROPOSAL REQUIREMENTS AND INFORMATION
Attach to this Cost of the Work a detailed breakdown of the complete GMP, including General Conditions, using the CM@Risk's own format.
B&F Contracting, Inc.
CONSTRUCTION MANAGER AT RISK AGREEMENT - Exhibit C - Cost of the Work
DIRECT CONSTRUCTION COST
General Items Subototal:
INDIRECT CONSTRUCTION COSTS  (ICC)
SUBTOTAL DIRECT CONSTRUCTION COST  (DCC)
SUBTOTAL CONSTRUCTION PHASE FEE
Arrowhead Phase 1.1
CONSTRUCTION PHASE FEE
ARROWHEAD PHASE 1.1 GMP-001 SCHEDULE OF VALUES
General Items
Phase 1.1
Date: 1/27/2025

Cost Detail
Project Name:
Arrowhead Sewer Rehab
Customer:
City of Glendale
Job Number:
24-3330-01
Bid Number: 24-3330-00
Billing Address:
5850 West Glendale Ave, Suite 315
Bid As:
B&F Contracting, Inc.
Glendale, AZ 85301  USA
Estimator:
Phone:
Joshua Onstott
Project Address:
Union Hills And SR 101, Glendale, AZ
Contact:
Hugh Alter
Completion Date:
11/19/2024
Pay Items
Total
Unit
Description
Quantity UM
Unit Price
Direct Cost
Total Price
Direct Cost
Markup
Percent
01 - Mobilization And Demobilization
1.00 LS
$62,308.14
$62,308.14
$62,308.14
$62,308.14
0.00%
Mobe / Demobe
12.00 EACH
$668.92
$8,027.04
GC-Mobilization Crew (2.00 EACH/DY, 6.00 
DY)
12.00 EACH
$668.92
$8,027.04
Water
850.00 MGAL
$6.00
$5,100.00
CIPP Mobe
1.00 LS
$30,000.00
$30,000.00
Shoring, Barrier Wall, And Plate Move
10.00 EACH
$400.00
$4,000.00
Pothole
14.00 EACH
$905.79
$12,681.10
GC-Combo Hydro Truck Crew (2.80 
EACH/DY, 5.00 DY)
14.00 EACH
$905.79
$12,681.10
Project Signs
2.00 EACH
$1,250.00
$2,500.00
02 - SWPPP
3.00 MO
$6,435.04
$19,305.12
$6,435.04
$19,305.12
-0.00%
SWPPP Permit And Inspections
3.00 MO
$1,450.00
$4,350.00
Sweeping
3.00 MO
$2,000.00
$6,000.00
Maintenance
3.00 MO
$2,985.04
$8,955.12
GC-Landscaping Crew (EACH) (1.00 MO/DY, 
3.00 DY)
3.00 MO
$2,985.04
$8,955.12
03 - Indirect
3.00 MO
$63,690.73
$191,072.20
$63,690.73
$191,072.19
-0.00%
Project Management
3.00 MO
$16,226.40
$48,679.20
JI-Project Manager Crew (15.00 DY/MO, 
45.00 DY)
3.00 MO
$16,226.40
$48,679.20
Project Engineer
3.00 MO
$13,197.60
$39,592.80
JI-Project Engineer Crew (15.00 DY/MO, 
45.00 DY)
3.00 MO
$13,197.60
$39,592.80
Project Superintendent
3.00 MO
$20,022.40
$60,067.20
JI-Project Superintendent Crew (20.00 
DY/MO, 60.00 DY)
3.00 MO
$20,022.40
$60,067.20
Porta Johns
3.00 MO
$850.00
$2,550.00
Porta John
3.00 MO
$850.00
$2,550.00
Water Meter
3.00 MO
$833.33
$2,500.00
Weter Meter
1.00 EACH
$2,500.00
$2,500.00
Temp Fence
3.00 MO
$750.00
$2,250.00
Temp Fence
3.00 MO
$750.00
$2,250.00
ST&S
5,836.00 MH
$3.00
$17,508.00
Job Office Expense
3.00 MO
$350.00
$1,050.00
Field Connectivitiy
3.00 MO
$275.00
$825.00
Yard Location
3.00 MO
$4,500.00
$13,500.00
Connex
3.00 MO
$550.00
$1,650.00
Sanitation Station
3.00 MO
$300.00
$900.00
Page 1 of 5
12/2/2024 10:17:20 AM

Total
Unit
Description
Quantity UM
Unit Price
Direct Cost
Total Price
Direct Cost
Markup
Percent
04 - PCCP Replacement
222.00 SY
$420.04
$93,248.05
$420.04
$93,248.88
0.00%
CP-Concrete Driveway Crew (42.50 SY/DY, 5.22 
DY)
222.00 SY
$77.91
$17,296.57
CP-Concrete Demo Driveway Crew (48.57 
SY/DY, 4.57 DY)
222.00 SY
$131.74
$29,247.38
CP-Concrete Dowell And Bar (48.57 SY/DY, 
4.57 DY)
222.00 SY
$86.69
$19,245.10
Ready Mix Concrete - MAG AAA 5000
84.00 CY
$162.25
$13,629.00
Rebar - # 4 (1/2in) 20ft
500.00 EACH
$6.00
$3,000.00
Form Work
1.00 EACH
$2,850.00
$2,850.00
Sawcut
500.00 LF
$8.00
$4,000.00
Epoxy
40.00 UNIT
$42.00
$1,680.00
Cure/Form Oil/ Stakes
1.00 LS
$1,500.00
$1,500.00
Dump Fee - Concrete
8.00 LOAD
$100.00
$800.00
05 - Curb & Sidewalk Replacement
4.00 EACH
$4,338.82
$17,355.27
$4,338.82
$17,355.28
0.00%
CP-Concrete Sidewalk Crew (1.33 EACH/DY, 
3.00 DY)
4.00 EACH
$2,552.16
$10,208.64
Concrete Formwork
1.00 EACH
$850.00
$850.00
Ready Mix Concrete - MAG AA 4000
10.50 CY
$155.13
$1,628.87
CP-Concrete Demo Sidewalk Crew (4.00 
EACH/DY, 1.00 DY)
4.00 EACH
$1,116.94
$4,467.76
Dump Fee - Concrete
2.00 LOAD
$100.00
$200.00
06 - Sewer Bypass Installation And 
Removal
1.00 EACH
$242,842.72
$242,842.72
$242,842.72
$242,842.72
-0.00%
Dig And Replace Suction / Discharge Pit
2.00 EACH
$19,549.85
$39,099.71
RH-Excavation & Backfill Suction Pit Crew 
(0.33 MO/DY, 6.00 DY)
2.00 MO
$12,861.60
$25,723.20
Ready Mix Concrete - MAG AA 4000
2.10 CY
$155.13
$325.77
Ready Mix - Slurry ABC Slurry 1/2 Sack
26.25 CY
$114.13
$2,995.91
Manhole - Manhole Coated 60in
2.00 EACH
$675.00
$1,350.00
Frame & Cover - Manhole Frame & Cover 
30in
2.00 EACH
$912.00
$1,824.00
Concrete - Short Load Fee
2.00 EACH
$250.00
$500.00
RH-Manhole Adjust Crew (2.00 EACH/DY, 
1.00 DY)
2.00 EACH
$1,234.92
$2,469.84
Coating Repair
1.00 EACH
$3,718.98
$3,718.98
Manhole Coating (0.67 EACH/DY, 1.50 DY)
1.00 EACH
$2,893.98
$2,893.98
Ready Mix Concrete - C-120
10.00 BAG
$20.50
$205.00
Sewer Shield Epoxy
4.00 EACH
$155.00
$620.00
Trenching And Removal & Backfill
150.00 LF
$463.32
$69,497.86
RH-Bypass Pipe Trench & Backfill Crew 
(28.75 LF/DY, 8.00 DY)
230.00 LF
$241.79
$55,612.80
Ready Mix - Slurry ABC Slurry 1/2 Sack
27.30 CY
$114.13
$3,115.75
Aggregate - ABC Non Spec
46.20 TON
$22.25
$1,027.95
Asphalt - Cold Mix
22.00 TON
$165.00
$3,630.00
CP-Sawcutting Large Crew (75.00 LF/DY, 
2.00 DY)
150.00 LF
$37.41
$5,611.36
Dump Fee - Concrete
2.00 LOAD
$100.00
$200.00
Dump Fee - Asphlat
1.00 LOAD
$75.00
$75.00
Dump Fee - Dirt
3.00 LOAD
$75.00
$225.00
Bypass Installation
1.00 EACH
$64,497.80
$64,497.80
RH-Bypass Sewer Setup Crew (0.17 MO/DY, 
6.00 DY)
1.00 MO
$22,055.04
$22,055.04
RH-Bypass Fusion 12-18in Crew (0.13 
MO/DY, 8.00 DY)
1.00 MO
$26,170.88
$26,170.88
Set And Remove Plugs (0.33 EACH/DY, 3.00 
DY)
1.00 EACH
$6,350.76
$6,350.76
Test Pipe
2,024.00 LF
$2.48
$5,014.08
GC-Chlorine & Pressure Test Crew 
(1,012.00 LF/DY, 2.00 DY)
2,024.00 LF
$2.48
$5,014.08
Crossing Delays
3.00 UNIT
$1,635.68
$4,907.04
RH-Bypass Fusion 12-18in Crew (2.00 
MO/DY, 1.50 DY)
3.00 MO
$1,635.68
$4,907.04
Bypass Takedown
1.00 EACH
$33,576.48
$33,576.48
Page 2 of 5
12/2/2024 10:17:20 AM
Arrowhead Sewer Rehab

Total
Unit
Description
Quantity UM
Unit Price
Direct Cost
Total Price
Direct Cost
Markup
Percent
RH-Bypass Sewer Takedown Crew (0.13 
MO/DY, 8.00 DY)
1.00 MO
$27,932.16
$27,932.16
RH-Pipe Pigging Crew (0.50 EACH/DY, 2.00 
DY)
1.00 EACH
$5,644.32
$5,644.32
Mobilization / Demobilization
24.00 LOAD
$668.92
$16,054.08
GC-Mobilization Crew (2.00 LOAD/DY, 12.00 
DY)
24.00 LOAD
$668.92
$16,054.08
Bypass Calcs
1.00 EACH
$1,500.00
$1,500.00
JI-Bypass Super (0.07 EACH/DY, 15.00 DY)
1.00 EACH
$15,016.80
$15,016.80
Pave Patch Discharge
1.00 EACH
$3,600.00
$3,600.00
07 - Bypass Operation
30.00 DY
$8,360.75
$250,822.64
$8,360.75
$250,822.50
-0.00%
Pump Watch-3 Attendants (2 Main Bypass 1On 
21" Bypass)
30.00 DY
$3,818.56
$114,556.80
RH-Bypass Sewer Pump Watch Crew (1.00 
DY/DY, 30.00 DY)
30.00 DY
$3,818.56
$114,556.80
Bypass Support - .5 Rent
30.00 DY
$1,076.20
$32,286.00
Fuel Tank
1.00 MO
$500.00
$500.00
08 - Rehabilitate 42" Pipe With CIPP
1,058.00 LF
$346.56
$366,659.85
$346.56
$366,660.48
0.00%
CIPP  (B&F Lining Solutions)
1,058.00 LF
$316.00
$334,328.00
RH-CIPP Lining Support Crew (211.60 LF/DY, 
5.00 DY)
1,058.00 LF
$5.87
$6,207.20
Remove Inversion Manhole Bench Modifications
2.00 EACH
$13,062.33
$26,124.65
Remove Manholes For Inversion (0.50 
EACH/DY, 4.00 DY)
2.00 EACH
$8,574.40
$17,148.80
Ready Mix Concrete - MAG AA 4000
2.10 CY
$155.13
$325.77
Ready Mix - Slurry ABC Slurry 1/2 Sack
24.15 CY
$114.13
$2,756.24
Manhole - Manhole Coated 60in
2.00 EACH
$675.00
$1,350.00
Frame & Cover - Manhole Frame & Cover 
36in
2.00 EACH
$912.00
$1,824.00
Concrete - Short Load Fee
1.00 EACH
$250.00
$250.00
RH-Manhole Adjust Crew (2.00 EACH/DY, 
1.00 DY)
2.00 EACH
$1,234.92
$2,469.84
09 - Dewater, Clean, & CCTV Pipe
1,058.00 LF
$22.10
$23,381.44
$22.10
$23,381.80
0.00%
GC-Combo Hydro Truck Crew (264.50 LF/DY, 
4.00 DY)
1,058.00 LF
$9.01
$9,528.32
GC-CCTV Crew (529.00 LF/DY, 2.00 DY)
1,058.00 LF
$3.33
$3,524.00
Clean Pipe (529.00 LF/DY, 2.00 DY)
1,058.00 LF
$5.76
$6,097.12
Post Pano
1,058.00 LF
$4.00
$4,232.00
10 - Install Manhole
1.00 EACH
$119,101.25
$119,101.25
$119,101.25
$119,101.25
0.00%
Manhole - Polymer Manhole - 72"
1.00 EACH
$51,450.00
$51,450.00
RH-Manhole Adjust Crew (2.00 EACH/DY, 0.50 
DY)
1.00 EACH
$1,234.92
$1,234.92
Install And Backfill (0.25 EACH/DY, 4.00 DY)
1.00 EACH
$28,151.68
$28,151.68
SD-Collar 48in Crew (0.50 EACH/DY, 2.00 DY)
1.00 EACH
$11,236.32
$11,236.32
Ready Mix Concrete - MAG B 2500
10.50 CY
$147.50
$1,548.75
Rebar - # 4 (1/2in) 10ft
1.05 EACH
$650.00
$682.50
Frame & Cover - Manhole Frame & Cover 30in
1.00 EACH
$912.00
$912.00
Concrete - Short Load Fee
1.00 EACH
$250.00
$250.00
Ready Mix Concrete - MAG AA 4000
1.05 CY
$155.13
$162.89
Ready Mix - Slurry ABC Slurry 1/2 Sack
122.07 CY
$114.13
$13,932.19
42" PVC Pipe
14.00 LF
$360.00
$5,040.00
Crane
1.00 DY
$4,500.00
$4,500.00
11 - Rehabilitate And FRP Wrap Manhole 
Bench
2.00 EACH
$17,406.86
$34,813.72
$17,406.86
$34,813.72
0.00%
RH-Manhole Coated Support Crew (0.25 
EACH/DY, 8.00 DY)
2.00 EACH
$9,019.36
$18,038.72
Ready Mix Concrete - C-120
150.00 BAG
$20.50
$3,075.00
FRP Wrap Materials
2.00 EACH
$6,650.00
$13,300.00
Rebar Coating
1.00 LS
$400.00
$400.00
12 - Install Manhole Composite Insert
2.00 EACH
$26,233.35
$52,466.69
$26,233.35
$52,466.70
0.00%
Install FRP Insert
2.00 EACH
$26,233.35
$52,466.69
Page 3 of 5
12/2/2024 10:17:20 AM
Arrowhead Sewer Rehab

Total
Unit
Description
Quantity UM
Unit Price
Direct Cost
Total Price
Direct Cost
Markup
Percent
RH-Excavation & Backfill Suction Pit Crew 
(0.50 MO/DY, 4.00 DY)
2.00 MO
$8,766.40
$17,532.80
Ready Mix Concrete - MAG AA 4000
2.10 CY
$155.13
$325.77
Ready Mix - Slurry ABC Slurry 1/2 Sack
36.75 CY
$114.13
$4,194.28
Frame & Cover - Manhole Frame & Cover 
30in
2.00 EACH
$912.00
$1,824.00
Concrete - Short Load Fee
2.00 EACH
$250.00
$500.00
RH-Manhole Adjust Crew (2.00 EACH/DY, 
1.00 DY)
2.00 EACH
$1,234.92
$2,469.84
Manhole - Insert - 54" Various Sizes
2.00 EACH
$12,810.00
$25,620.00
Page 4 of 5
12/2/2024 10:17:20 AM
Arrowhead Sewer Rehab

Direct Cost Totals
Amount
Equipment Rented:
Direct Cost
Percent of
Equipment Owned:
Materials Owned:
Materials Purchased:
Labor:
Subcontracted:
Trucking Owned:
Trucking Hired:
Miscellaneous:
Plug:
Direct Cost:
$452,750.72
$367,387.87
$33,939.86
$161,835.64
$365,810.00
$0.00
$0.00
$1,500.00
$90,153.00
$0.00
$1,473,377.09
30.73%
2.30%
0.00%
24.83%
0.00%
0.00%
0.10%
6.12%
24.94%
10.98%
Bid Price
$1,473,378.78
$1.69
Pay Item Summary
Amount
Total Bond:
Total Indirect Cost:
Total Overhead:
Total Profit:
Total Direct Cost:
Total Bid Price:
$1,473,377.09
$0.00
$0.00
$0.00
Total DC Adds/Cuts:
$0.00
100.00%
0.00%
0.00%
0.00%
0.00%
0.00%
$1,473,377.09
Total Overall Cost:
$1.69
Total Margin:
100.00%
0.00%
Percent of
Page 5 of 5
12/2/2024 10:17:20 AM
Arrowhead Sewer Rehab

SUBCONTRACTOR / SUPPLIER 
SELECTED
CONTACT
EMAIL
BID RESPONSE
COST
UOM
SOLICITATION/SELECTION NOTES
CIPP LINING SCOPE
Total Price
B&F Contracting, Inc.
X
Geoff Tucker
Geoff.Tucker@bfcontracting.com
Yes
316.00
$                    
LF
Selected as lowest bidder.
Insituform Technologies
Seth Ganesan
Sganesan@aegion.com
No
328.00
$                    
LS
Utilized recent 42" & 36" lining quote to Compare unit price 
and this project will have additional cost to provide water 
supply to the inversion which will increase overall cost and 
additional 3 day on bypass due to 3 day schedule per lining 
shot. In addition access for lining will be extremely difficult 
for semi and boiler compared to UV. 
SAK Contstruction, LLC
Patrick Hale
Phale@sakcon.com
No
347.00
$                    
LS
FRP Rehabilitation
Total Price
B&F Contracting, Inc. 
X
Josh Onstott
jonstott@bfcontracting.com
Yes
17,381.80
$               
Ea
Selected as lowest bidder.
JPCI Services
Becky Durfee
bdurfee@jpciservices.com
No
-
$                          
Ea
B&F followed up via email, but JPCI missed due date and 
did not provide price.
NEW 72" MANHOLE MATERIAL
Unit Price
Armorock
X
Nick Gardiner
Nick Gardiner <ngardiner@armorock.com>
Yes
51,450.00
$               
Ea
Selected as lowest bidder.
Olsen Polymer
William Vallery
william@opmb.net
Yes
53,594.00
$               
Ea
Manhole Insert Materials
Total Price
Sewer Sheild Composites Services
X
Becky Durfee
bdurfee@jpciservices.com
Yes
12,910.00
$               
EA
Faster Installation verse polymer would cost more money to 
install Polymer verse monlithic one piece of FRP. Will have 
better adhersion with FRP bench treatment. 
Armorock
Nick Gardiner
Nick Gardiner <ngardiner@armorock.com>
14,535.00
$               
EA
Olson Polymer
William Vallery
william@opmb.net
10,386.00
$               
EA
READY MIX MATERIALS
Unit Price
Arizona Materials
X
Randy Schmolke
randy.schmolke@azmatl.com
Yes
111.00
$                    
CY
Average top Two 
Desert Ready Mix
X
Bruce Tabet
btabet@desertrm.com
Yes
117.25
$                    
CY
Average top Two 
Martin Marietta
Raul Villegas
raul.villegas@martinmarietta.com
No
124.50
$                    
CY
MAG SPEC ABC
Unit Price
Desert Ready Mix
X
Bruce Tabet
btabet@desertrm.com
Yes
22.25
$                      
TN
Selected as lowest bidder.
Vulcan Materials Company
Kristin Gigis
gigisk@vmcmail.com
Yes
23.20
$                      
TN
Cemex
Jared Matkin
jared.matkin@cemex.com
Yes
25.15
$                      
TN'
ARROWHEAD PHASE 1.1
PROJECT NO.: 202104
GMP-001
SUBCONTRACTOR & SUPPLIER SOLICITATIONS & SELECTIONS

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
EXHIBIT E 
Construction Documents necessary to define Scope of Work and Deliverables for the 
Construction Phase Services, including plans, designs, drawings, specifications and other 
required Contract Documents 
 
(214 pages - To be Incorporated by Amendment) 
 
SEE ATTACHED

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
T H I S P A G E I S B L A N K

SCOPE OF WORK 
Arrowhead Phase 1.1 
COG PROJECT NUMBER: 202104 
GMP-001 
PROJECT OVERVIEW 
This GMP-001 is based off the 100% project drawing to rehabilitate 42-inch sewer line from the east side of SR-101 to 
the Arrowhead Water Treatment facility. The GMP-001 includes 1,058 LF of 42-inch CIPP, 1 each new polymer 72-
inch manhole, 2 each sewer shield composite manhole inserts, 2 each manhole bench rehabilitation with FRP treatment. 
In order to accommodate the work the GMP includes the full bypass of the 42-inch line and 21-inch line at the 
Arrowhead Water Treatment Facility.  
SCOPE OF WORK BID ITEMS: 
General Items 
1) Mobilization & Demobilization:
a)
Mobilization and demobilization of equipment, shoring, and steel plates.
b) Mobilization for CIPP lining subcontractor.
c)
Furnishing and installing 2 project signs.
2) Storm Water Pollution Prevention
a)
Dust permit.
b) Construction water meter and construction water.
c)
Street Sweeping.
3) Indirect Project Management Cost
a)
Project Manager – 2/3rd Time Project Manager
b) Project Engineer – 2/3rd Time Project Engineer
c)
Project Superintendent – Full-Time Project Superintendent
d) Waste management service and trash disposal.
e)
Water and ice for the crews
f)
Yard rental for project materials, equipment, and personnel.
g) Project Sanitation portable restrooms, handwashing station, and disinfection supplies.
h) Temporary fence rental for project security.
i)
ST&S, Safety Supplies, Training, Fall Protection, and small tools – Per Direct Labor Manhours.
Arrowhead Phase 1.1 
4) PCCP Replacement
a)
Labor, materials and equipment to replace PCCP at temporary sewer crossing for bypass pumping.
5) Curb and Sidewalk Replacement
a)
Labor, equipment, and materials to replace sidewalk and curb and gutter damaged for the temporary bypass
installation.
6) Sewer Bypass Installation and Removal
a)
All labor, equipment, and materials to install and removal 2 sewer bypass systems.

7) Bypass Operation 
a) Labor and equipment to operate and maintain bypass pumps 24 hours a day 7 days a week during the 
rehabilitation of the sewer line.  
 
8) Rehabilitate 42" Pipe with CIPP 
a) Labor, equipment, and materials to complete the full installation of 1,058 LF of UVGFRP CIPP.  
 
9) Dewater, Clean, & CCTV Pipe 
a) Labor, equipment, and disposal of all materials from the sewer and complete the prevideo assessment of the 
sewer line prior to CIPP.  
b) Post Pano Video supplied by Dukes Root Control.  
 
10) Install Manhole 
a) Labor, Materials, and Equipment to provide and install one 72” polymer manhole on the existing 42” line.  
b) Manhole adjustment with new ring and cover post insert installation.  
 
11) Rehabilitate And FRP Wrap Manhole Bench 
a) Labor, Materials, and Equipment to provide and install FRP coating treatment on two manholes tying into the 
new FRP insert.   
 
12) Install Manhole Composite Insert 
a) Labor, equipment and materials, install two sewer shield composite inserts as designed.  
b) Manhole adjustment with new ring and cover post insert installation.  
 
 
Allowance – All allowance work will be approved by the Owner in writing prior to execution.  
 
14) Traffic Control (Allowance) 
a) Allowance for all costs associated with Traffic Control, including, but not limited to: traffic control plans, 
permits, device rental, labor and equipment, sandbags, flags and dowels, pedestrian relocations, visual message 
boards, etc. 
 
15) Off-Duty Officers (Allowance) 
a) Allowance for all required Off-Duty Officers. 
 
16) Striping (Allowance) 
a)  Allowance for reimbursement of required striping.  
 
17) Landscape Restoration (Allowance) 
a) Allowance for any landscape restoration post installation of manhole, rehabilitation, and bypass installation and 
removal.  
 
18) Odor Control (Allowance) 
a) Allowance for reimbursement of any required odor control for Phase 6B 67th Ave and Butler 39-inch sewer 
bypass.

b) Allowance will be utilized for any odor mitigation efforts above standard tarping and sealing of suction or 
discharge pits. Generally, an odor scrubber is deployed, or upstream chemical injection or dosing is completed 
as an additional mitigation effort.  
 
19) Survey/GIS (Allowance) 
a) Allowance to capture Project specific GIS and as-built data for the city. 
 
20) Quality Control Material Testing (Allowance) 
a) All costs associated with third party material testing on the project include but not limited to compaction, 
concrete cylinder, sieve analysis, proctor, etc.  
 
21) Additional Rehabilitation (Allowance) 
a) Additional work that is located during the investigation or pre rehabilitation work that were unforeseen in the 
original assessment including but not limited to point repairs, coating repairs, manhole ring and cover 
replacement, CIPP, or manhole replacement or manhole insert installation.  
b) Additional bypass work related to the additional rehabilitation or complication due to unknown or unforeseen 
conditions.  
c) Additional hardscape surface restorations or landscape restorations as a result from the additional rehabilitation.  
d) Heavy cleaning of the sewer over the estimated 3-pass cleaning in the pay item above.  
 
22) ADOT Loop Protection (Allowance) 
a) To replace damaged loop detectors when crossing the PCCP on the west off ramp at SR101 and Union Hills 
Drive.  
 
23) Owner’s Contingency 
a) Owner’s Contingency is based on 10% of the Project Direct Cost, excluding allowance and contingency totals. 
b) This contingency is for additional Owner directed scope of work.

EXHIBIT E: CONSTRUCTION DOCUMENTS 
ARROWHEAD PHASE 1.1 
COG PROJECT NUMBER: 202104 
GMP-001 
 
 
 
DOCUMENTS: 
 
• 
Drawings: City of Glendale, Arrowhead Sewer Lines Phase 1.1, Project No. 202104.01 Sealed 10-
29-2024 
• 
Technical Specifications: City of Glendale, Arrowhead Sewer Lines Phase 1.1, Project No. 202104.01 
Sealed 10-25-2024 
• 
Arrowhead Sewerlines Phase 1.1 Scope of Work Description

PHASE I.I
PHASE I.I
SHT. #
SHEET INDEX                       
C1.0
C1.1
COVER
GENERAL NOTES
C1.2
ABBREVIATIONS & LEGEND
C1.3
KEY MAP
C2.0-C2.7
PLAN AND PROFILE
TITLE
01
02
03
04
05A-12A
15
LEANDRO BALDENEGRO
13
D1
CIVIL DETAILS
3020 EAST CAMELBACK ROAD  SUITE 201
PHOENIX, ARIZONA 85016
3020 EAST CAMELBACK ROAD  SUITE 201
PHOENIX, ARIZONA 85016
*PHASE 1.1 PLANS ACCEPTANCE
CITY ENGINEER
DATE
WATER SERVICE DIRECTOR
DATE
14-16
BP1-BP3
CONCEPTUAL BYPASS PLAN

GLENDALE ARROWHEAD SEWER LINE
GENERAL NOTES
02
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
GENERAL NOTES
STREET NOTES
SEWER NOTES
ADOT NOTES
ENGINEER'S NOTES
C1.1
16

GLENDALE ARROWHEAD SEWER LINE
ABBREVIATIONS & LEGEND
03
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
STANDARD ABBREVIATIONS & LEGEND
EXISTING
NEW
EXISTING
NEW
C1.2
16

GLENDALE ARROWHEAD SEWER LINE
04
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
5850 W GLENDALE AVE
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
UNION HILLS DR
UNION HILLS DR
C1.3
16

CONSTRUCTION NOTES
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
GLENDALE ARROWHEAD SEWER LINE
 PLAN & PROFILE
05A
ARWRF
REMOVAL NOTES
CONSTRUCTION NOTES
REFERENCE NOTES
C2.0
16
PHASE I.I

CONSTRUCTION NOTES
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
GLENDALE ARROWHEAD SEWER LINE
 PLAN & PROFILE
06A
C2.1
REMOVAL NOTES
CONSTRUCTION NOTES
REFERENCE NOTES
16
PHASE I.I

CONSTRUCTION NOTES
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
GLENDALE ARROWHEAD SEWER LINE
 PLAN & PROFILE
07A
C2.2
REMOVAL NOTES
CONSTRUCTION NOTES
REFERENCE NOTES
16
PHASE I.I

CONSTRUCTION NOTES
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
GLENDALE ARROWHEAD SEWER LINE
 PLAN & PROFILE
08A
REMOVAL NOTES
CONSTRUCTION NOTES
REFERENCE NOTES
C2.3
16
PHASE I.I

CONSTRUCTION NOTES
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
UNION HILLS DR
GLENDALE ARROWHEAD SEWER LINE
 PLAN & PROFILE
09A
C2.4
16
PHASE I.I

CONSTRUCTION NOTES
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
UNION HILLS DR
GLENDALE ARROWHEAD SEWER LINE
 PLAN & PROFILE
10A
C2.5
16
PHASE I.I

CONSTRUCTION NOTES
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
UNION HILLS DR
GLENDALE ARROWHEAD SEWER LINE
 PLAN & PROFILE
11A
C2.6
16
PHASE I.I

CONSTRUCTION NOTES
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
UNION HILLS DR
GLENDALE ARROWHEAD SEWER LINE
 PLAN & PROFILE
12A
C2.7
16
PHASE I.I

D1
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
GLENDALE ARROWHEAD SEWER LINE
CIVIL DETAILS
PHASE I.I
13
16
B
B
A
A

BP1
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
GLENDALE ARROWHEAD SEWER LINE
CONCEPTUAL BYPASS PLAN
ARWRF
PHASE I.I
14
16

15
BP2
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
GLENDALE ARROWHEAD SEWER LINE
CONCEPTUAL BYPASS PLAN
ARWRF
PHASE I.I
16

BP3
ARROWHEAD SEWER LINES PHASE I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104
CITY OF GLENDALE
51
GLENDALE ARROWHEAD SEWER LINE
CONCEPTUAL BYPASS PLAN
PHASE I.I
16
16
Please indicate if
bypass piping is south
of barrier wall or north
of barrier wall.

Arrowhead Sewer Lines Phase 1.1 
 
Contract No.: 202104.01 
 
TECHNICAL SPECIFICATIONS 
 
 
 
 
 
 
 
 
 
 
 
Submitted To: 
CITY OF GLENDALE 
 
October 25, 2024 
 
Mayor 
Jerry P. Weiers 
 
City Council 
Prepared by: 
Ray Malnar 
Bart Turner 
Ian Hugh   
Lauren Tolmachoff 
 
 
 
 
 
   
    www.dibblecorp.com 
Leandro Baldenegro 
Joyce Clark

[This page intentionally left blank for double sided printing]

_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
TOC - 1 
October 25, 2024 
 
 
Arrowhead Sewer Lines Phase 1 
 
TECHNICAL SPECIFICATIONS 
 
  
TABLE OF CONTENTS 
Section 
Subject 
 
 
 
 
 
 
             Pages 
 
DIVISION 1 – GENERAL REQUIREMENTS 
 
01010 
Summary of Work 
01010-2 
01014 
Work Sequence 
01014-4 
01015 
Contractor’s Use of Premises 
01015-2 
01060 
Health and Safety 
01060-4 
01062 
Permits and Easements 
01062-2 
01064 
Inspection and Testing 
01064-2 
01071 
Standard References 
01071-6 
01102 
Contractor’s Hazardous Materials Management Program 
01102-4 
01300 
Submittals 
01300-6 
01310 
Progress Schedule 
01310-2 
01380 
Photographs and Video Recordings 
01380-2 
01400 
Public Awareness 
01400-4 
01550 
Contractor’s Utilities 
01550-2 
01560 
Environmental Controls 
01560-8 
01700 
Restoration of Improvements 
01700-2 
01999 
Reference Forms 
01999-10 
 
 
DIVISION 2 – SITE WORK 
 
02100 
Traffic Control 
02100-2 
02145 
Diversion of Sewage Flow and Dewatering 
02145-6 
02148 
CIPP Lining of Existing Sewers 
02148-20 
02720 
Fiber Reinforced Polymer (FRP) 
02720-24 
02760 
Sewer Pipe and Sewer Structure Cleaning 
02760-4 
02761 
Remote CCTV Inspection of Existing and Rehabilitated Sewers 
02761-6

_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
TOC - 2 
October 25, 2024 
TABLE OF CONTENTS (continued) 
 
Section 
Subject 
Pages  
 
DIVISION 9 – FINISHES 
 
09710 
Concrete and Masonry Coating 
09710-30 
 
 
DIVISION 13 – MISCELLANEOUS 
 
 
13128 
Composite Material Manhole Insert 
13128-16 
13130 
Polymer Concrete Manhole Insert 
13130-14 
13133 
Polypropylene Grade Adjustment Rings 
13133-4

SECTION 01010 
SUMMARY OF WORK 
______________________________________________________ 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
01010 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01 
SCOPE  
  
A. All construction shall be provided in accordance with the requirements of the 2015 City 
of Glendale Engineering Design Standards & Details and the 2024 revision to the 2024 
Maricopa Association of Government (MAG) Standard Specifications and Details for 
Public Works Construction. 
  
B. The Contractor shall provide all materials, equipment, and labor necessary to 
rehabilitate sanitary sewer pipe utilizing techniques and methods as described in the 
project Drawings and Technical Specifications. 
 
C. Major work to be performed under this contract includes, but is not limited to the 
following:   
1. Provide traffic control as necessary for CIPP lining, bypass operations and sanitary 
sewer access manhole rehabilitation. Traffic control plans shall be submitted to the 
City for approval and receive a traffic control permit prior to construction activities. 
2. Restore area disturbed by construction activities back to pre-construction 
conditions. 
3. When Public Outreach is not performed by the City, provide coordination with 
Public Outreach Consultant provided by the City for notification of construction 
activities to the general public, if applicable. 
4. Provide all bypass pumping, piping, power, noise control, and odor control 
including materials, labor and equipment necessary to divert sanitary sewage flows 
around the rehabilitation construction area as necessary to complete the work. 
5. Perform cleaning of sanitary sewer pipe to remove all metallic pipe tuberculation, 
grease, scale, roots, debris, foreign protrusions and obstructions prior to cured-in 
place pipe (CIPP) lining. 
6. Perform Closed-Circuit Television (CCTV) investigation to confirm appropriate 
cleaning efforts and identify any pipe conditions that would prohibit cured-in-place 
pipe (CIPP) lining method of pipe rehabilitation. 
7. Provide all equipment, labor, and materials required to install CIPP liner into 
sanitary sewer pipes as indicated in the Contract Documents. 
8. Perform “pre” pipe rehabilitation and “post” pipe rehabilitation CCTV condition 
documentation. 
9. Provide all equipment, labor, and materials required to clean and repair sanitary 
sewer manholes as indicated in the Contract Documents.   
10. Coordinate work activities with adjacent businesses, public events and special

SECTION 01010 
SUMMARY OF WORK 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
01010 - 2 
October 25, 2024 
needs (e.g. medical and emergency response). 
11. Maintain access to private properties including sidewalks and driveways as 
necessary during the course of the work. Maintain sanitary sewer service to 
properties as necessary to prevent sewage backups into homes and businesses. 
 
1.02 
UTILITIES  
  
A. The Contractor shall field locate and verify the horizontal and vertical location of all 
pipe along with wet and dry utilities prior to conducting any excavation work.  
  
B. The Contractor is required to contact Arizona 811, formerly Blue Stake, at 811 at least 
two (2) working days prior to start of any excavation.  
  
C. Quarter Section maps of the City’s sanitary sewer collection system are available upon 
request from the City. It shall be the responsibility of the Contractor to coordinate and 
obtain copies of these maps. The Contractor shall not solely rely upon the information 
contained in the mapping and shall field verify for accuracy. 
 
1.03 
FLOW CHARACTERISTICS  
  
A. The project sanitary sewer collection system receives wastewater from residential, and 
commercial facilities within the City. The Contractor shall maintain all contributing 
flows for the duration of the project, and bypass flows around the work area described 
in the project as necessary to complete the work specified.    
 
B. The collection system may receive nuisance runoff water during storm events. Volumes 
of nuisance water are unpredictable. The Contractor shall be responsible to take 
appropriate precaution when rain events are pending. 
 
C. The Contractor shall be responsible for any/all monitoring of flows as necessary to size 
the bypass system to ensure against sanitary sewer overflows (SSO) of upstream 
sewers.    
 
D. The Contractor shall be responsible for maintaining uninterrupted sanitary sewer 
services in laterals within the segment affected by the manhole and pipe rehabilitation, 
and bypass pump flows if necessary, to ensure against detrimental surcharging of 
laterals and backup of raw sewage into residences and businesses.  
 
PART 2 - PRODUCTS  
(NOT USED)  
  
PART 3 - EXECUTION 
 (NOT USED) 
 
** END OF SECTION *

SECTION 01014 
WORK SEQUENCE 
_____________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01014 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01 
CONTINUITY OF FACILITY OPERATIONS  
  
Work under this Contract shall be planned, scheduled and performed so as to minimize 
disruption to the operation of existing business, facilities, surrounding residents and the 
traveling public. The Contractor shall provide all equipment and facilities (including 
piping, pumps, odor mitigation, and noise control along with standby power, pumps, 
equipment and appurtenances) necessary to maintain flow through and/or around existing 
facilities. Contractor shall be responsible for traffic control to redirect the flow of traffic 
through and/or around the work area, including pedestrian traffic. 
  
1.02 
PROJECT COMPLETION  
  
The project shall be completed within the contract time as outlined in the Construction 
Contract.  
 
1.03 
PROJECT CONSTRUCTION COORDINATION 
  
A. At the Pre-construction Meeting, the Contractor shall designate a Representative who 
will be on the job and available for communication at all times for the duration of the 
construction contract. The Contractor’s Representative shall be available 24 hours a 
day by mobile telephone, home telephone, or other means acceptable to the City or 
City’s Representative. The Contractor’s Representative shall be the contact person 
representing the Contractor and shall be capable of giving direct field orders as the need 
arises. Official job communication shall be conducted between Contractor’s 
Representative and the City.  
  
B. The Contractor shall obtain written approval from the City’s Representative 72 hours 
in advance of any change in the Contractor’s daily work schedule. Work performed at 
times other than the approved schedule must first be approved by the City’s 
Representative, except in case of emergency.  
  
C. The Contractor’s Representative shall attend construction progress meetings on a 
weekly basis or as scheduled by the City’s Representative.  Location of the meetings 
shall be determined by the City’s Representative. The Contractor shall present and 
distribute copies of a three-week look-ahead schedule, report on status of any resident 
concerns reported, any Traffic Control Plan updates, and upcoming construction 
activity coordination.  
 
D. The Contractor’s Representative shall be responsible for coordination of the work 
schedule. It shall be the responsibility of the Contractor to sequence work to resolve 
conflicts with ongoing adjacent construction (if any), and schedule work accordingly 
to minimize disruption. The City will not entertain Contractor claims for additional

SECTION 01014 
WORK SEQUENCE 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01014 - 2 
October 25, 2024 
compensation arising out of construction delays caused by adjacent construction work. 
City may at its sole discretion grant an extension of contract time due to unforeseen 
delays caused by adjacent construction activity conflicts. 
 
1.04 
SCHEDULING AND SEQUENCING CONSTRAINTS  
  
 
A. The Contractor shall CIPP line pipes and rehabilitate manholes identified in the 
Construction Documents. Once construction activities commence, the Contractor shall 
continue uninterrupted until all pipes and manholes identified are completed.  
B. No construction activities shall begin on-site until all required submittals are 
transmitted to the City or City’s Representative and returned stamped with “No 
Exceptions Taken” or “Make Corrections Noted”.  
C. The Contractor shall receive written approval from the property owner of equipment 
storage sites and/or corridors used for facility access (if any). Maps depicting 
locations of the equipment storage sites and copies of signed agreements shall be 
submitted to the City’s Representative prior to occupancy. 
D. Traffic control shall remain in effect as dictated by the approved Traffic Control Plan 
and Permit until all work is completed and inspected. Contractor shall maintain access 
to all private properties within the project area on a 24-hour basis unless written 
approval is otherwise obtained from property(s) owners for reduced access. Copies of 
all written approvals shall be provided to the City or City’s Representative prior to 
work commencing. Refer to Technical Specification Section 02100 – TRAFFIC 
CONTROL.  
E. Bypassing sewage flow and containment as required for rehabilitation of pipes is part 
of this contract. Refer to Technical Specification Section 02145 – DIVERSION OF 
SEWAGE FLOW AND DEWATERING for the bypass pumping requirements and 
restrictions.  
F. Odor control shall be provided at all times during the rehabilitation work. The odor 
control plan shall be submitted to the City’s Representative at the project progress 
meeting prior to commencement of work within the individual work area.  
G. Cleaning and CCTV of the pipe interior is required for all pipes scheduled to be CIPP 
lined. Time lapse between cleaning and CIPP lining shall be no greater than 30 calendar 
days and no sooner than 48 hours to identify the presence of obstructions or conditions 
that may impede/prevent/impact CIPP lining quality. Refer to Technical Specification 
Section 02146 - SEWER AND STRUCTURE CLEANING.  
Pipe shall be re-cleaned and CCTV to document existing condition just prior to pipe 
rehabilitation. Contractor shall inspect CCTV records prior to CIPP installation. 
Commencement of pipe rehabilitation constitutes Contractor’s acceptance of existing 
conditions for rehabilitation and warrants the quality of the pipe rehabilitation. 
H. The Contractor shall provide CCTV records after each pipe is taken out of service, 
dewatered and cleaned or cleared of obstructions for the City’s Representative to

SECTION 01014 
 
 
WORK SEQUENCE 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01014 - 3 
October 25, 2024 
review said records of the pipe interior. The Contractor shall notify the City or City’s 
Representative at least 48 hours prior to completion of the cleaning and CCTV video 
operation. Refer to Technical Specification Section 02147 - REMOTE CCTV 
INSPECTION OF EXISTING AND REHABILITATED SEWERS. 
I. The Contractor shall perform a detailed inspection of the work to confirm completion 
of all work items and conformance to the project Technical Specifications. Final 
inspection of the work will be carried out by the City or City’s Representative after 
receipt of the Contractor’s written request for final inspection.  
J. After receipt of the Contractor’s written notice of work completion, the City or City’s 
Representative will perform a detailed inspection and will create a punch list of 
omissions and defects observed. Punch list items shall be promptly corrected by the 
Contractor. The Contractor shall then schedule a time for the final inspection by the 
City or City’s Representative upon satisfactory completion of the punch list items. All 
costs associated with additional inspections after the final inspection, including the 
City’s Representative’s time and inspection costs, shall be the responsibility of the 
Contractor.  
 
1.05 
CONTRACTOR WORK HOURS  
  
A. The Contractor shall ensure adequate resources are available to complete all work 
within regular business hours per City of Glendale-Code of Ordinances Chapter 25, 
Part V.25-68 Construction of Buildings and Other Projects, unless an appropriate 
permit has been obtained beforehand from the City.  
 
B. Contractor shall be required to operate bypass pumping systems 24-hours per day. 
Work at night to minimize disruption to area residents or businesses may be required. 
It shall be the responsibility of the Contractor to apply for the necessary permits for the 
extended work hours. 
  
PART 2 - PRODUCTS  
(NOT USED) 
  
PART 3 - EXECUTION  
(NOT USED) 
 
 
 
 
 ** END OF SECTION **

SECTION 01014 
WORK SEQUENCE 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01014 - 4 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[This page intentionally left blank for double sided printing]

SECTION 01015  
CONTRACTORS USE OF PREMISES 
  
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
              01015 - 1 
October 25, 2024 
PART 1- GENERAL  
  
1.01 
OWNER’S RESPONSIBILITIES  
  
A. The City of Glendale operations personnel is responsible for operating the existing 
sewers and facilities throughout the execution of this Project.   
 
1.02 
CONTRACTOR’S RESPONSIBILITIES  
  
A. Except where the Contractor is bypassing flows, sewer pipes shall remain in operation 
throughout the performance of this Project. All coordination between the City’s 
operations personnel and the Contractor on all matters shall be through the City’s 
Representative unless otherwise approved in writing by the City.  
 
1.03 
USE AND OPERATION OF EXISTING FACILITIES 
 
A. The Contractor shall not interfere with the operation of existing sewer force mains and 
sanitary sewer pipes, except to bypass flows as necessary to perform the work. The 
Contractor shall use debris shields and exercise every precaution to ensure that debris 
and material from its operation does not enter the sewer. Any debris or blockage 
entering into the sewer as a result of the Contractor’s work shall be immediately 
removed and 5,000 linear feet of pipe downstream shall be cleaned at the Contractor’s 
expense. Any damages caused by or as a result of the debris entering the sewer shall be 
the responsibility of the Contractor.    
 
B. All costs, coordination, permits, and fees associated with the location of staging areas, 
material storage, equipment storage, and site trailer location (if applicable) shall be the 
responsibility of the Contractor. The Contractor shall submit copies of individual 
landowner agreements (if present) to the City. All disturbed areas shall comply with 
the dust control permit required by Maricopa County Air Quality Department as 
specified in Technical Specification Section 01062 – PERMITS AND EASEMENTS.  
 
1.04 
TRAFFIC:  
  
A. The Contractor shall comply with Technical Specification Section 02100 – TRAFFIC 
CONTROL. 
  
1.05 
DAMAGE TO EXISTING PROPERTY  
  
A. Contractor shall be responsible for any damage to existing structures, piping, work, 
materials, or equipment caused by its operations, and shall repair or replace any 
damaged structures, piping, work, materials or equipment, etc., to the satisfaction of 
the City, and at no additional cost to the City.

SECTION 01015  
CONTRACTORS USE OF PREMISES  
 
                                                            
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
              01015 - 2 
October 25, 2024 
B. Contractor shall protect all existing structures and property from damage.  
  
C. Contractor shall be responsible for all damage to streets, roads, curbs, sidewalks, 
walking trails, driveways, ditches, embankments, drainages, floodways, landscaping, 
or other public or private property, which may be caused by the work including 
transporting equipment, materials, or workers to or from the work. Contractor shall 
make satisfactory and acceptable arrangements with the agency having jurisdiction 
over the damaged property concerning its repair or replacement and/or as specified in 
these Technical Specifications.  
  
D. Contractor shall be responsible for any and all damage to private property as caused by 
the Contractor’s operations including but not limited to sewage spills/backups.  
 
E. Contractor shall be responsible to identify, locate and control all contributory flows, 
either mainline or lateral, that may detrimentally impact the proper CIPP lining of the 
sewer pipe or rehabilitation of manholes.  
 
1.06  RESIDENT SERVICES 
 
A. Contractor shall be responsible for maintaining general services provided to residents 
and businesses.  
 
B. Contractor shall be responsible for damage to businesses or residents if damage is 
caused by a backup of the sewer system, if that sewage backup is either intentional or 
unintentional. Contractor shall immediately clean and repair the damage, and the sewer 
system to proper working order. If not done in a timely manner, the City may elect to 
have another contractor perform cleaning and repairs and reduce compensation to the 
Contractor to cover these expenses. 
 
 
PART 2 - PRODUCTS  
NOT USED   
 
PART 3 - EXECUTION  
NOT USED  
 
 
 
 
 
 
 
** END OF SECTION **

SECTION 01060 
HEALTH AND SAFETY 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
              01060 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01 
HEALTH AND SAFETY REGULATIONS  
  
A. The Contractor shall exercise precaution at all times for the protection of persons 
(including employees) and property. The Contractor shall comply with the provisions 
of all applicable laws, pertaining to such protection including all federal, state and local 
occupational safety and health acts, codes, standards and regulations promulgated 
thereunder. Contractor shall have copies of, but not limited to, confined space entry 
permit on-site and available for review any time work activities are commencing.  
  
B. Contractor shall comply with the provisions of the Federal Occupational Safety and 
Health Act, as amended.  
 
C. Contractor shall comply with the provisions of the Maricopa County Air Quality 
Department.  
 
D. The Contractor shall provide and maintain in a neat, sanitary condition such 
accommodations for the use of the employees as may be necessary to comply with the 
requirements and regulations of the Arizona Department of Health Services and/or as 
specified by the Maricopa County Public Health Department, Sanitary Code.  
  
E. The Contractor shall provide all safeguards, safety devices and protective equipment 
and take any other needed actions reasonably necessary to protect the life and the health 
of employees on the job, the safety of the public, and to protect property in connection 
with the performance of the work covered by this contract.  
  
1.02 
SPECIAL CONSIDERATIONS  
  
A. GENERAL 
 
This Technical Specification Section describes certain minimum precautions the 
Contractor shall consider in developing its health and safety program. It supplements 
the regulatory requirements of Paragraph 1.01 and the requirements of the General 
Conditions. Sewers and appurtenant structures are considered confined spaces and are 
subject to federal, state, and local regulations governing confined space entry and safety 
procedures.   
  
B. INFECTIOUS DISEASES:  
  
Contractor should anticipate that a wide spectrum of disease-producing organisms will 
be present in the sewer. In addition to the requirements set forth in the regulations 
described in Paragraph 1.01 above, the Contractor shall provide the following as a 
minimum:

SECTION 01060 
HEALTH AND SAFETY 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
              01060 - 2 
October 25, 2024 
1. Instruction in appropriate disease-prevention mechanisms and personal sanitation 
practices for all workers and supervisors.  
  
2. A preventative inoculation program (tetanus/diphtheria, hepatitis, etc.) to all 
workers and supervisors.  
  
3. Clothing to protect against infection, including rubber boots with full sole and heel 
steel insert-liners, safety glasses or goggles, and gloves to all workers and 
supervisors.  
 
C. DANGEROUS GASES AND OXYGEN DEFICIENCY:  
  
  
The sewer pipe, sewer access manholes and junction structures are confined spaces, 
which mean they have a limited means of egress and are subject to the accumulation of 
dangerous gases or oxygen deficiency. Volatile petroleum products and common 
household hazardous materials may be present within the sewer. Explosive gases, such 
as methane generated from decomposing organic material, may be accumulated. Toxic 
gases, such as hydrogen sulfide, may be present in life-threatening concentrations.  
Significant oxygen depletion may occur. In addition, construction procedures may 
require combustion engine machinery to be located in or near the work site. Therefore, 
gaseous combustion by-products, such as carbon monoxide, may be present.    
  
In addition to the requirements set forth in the regulations described in Paragraph 1.01 
above, the Contractor shall provide the following:  
  
1. Portable atmospheric monitors that measure levels of oxygen, explosive gas 
(methane), carbon monoxide, and toxic gas (hydrogen sulfide). Monitors shall be 
properly calibrated and carefully maintained throughout the construction period.  
Monitors shall be used continuously while personnel are in confined spaces.  
  
D. TOXIC CHEMICALS:  
  
Toxic chemicals may be part of the construction process. The Contractor shall abide by 
all handling procedures recommended by the manufacturer when dealing with toxic 
chemicals.  
  
E. ASBESTOS-CEMENT PIPE:  
  
The Contractor shall abide by all asbestos-cement handling procedures as required by 
all local, state and federal regulatory agencies.  
 
1.03 
SUBMITTALS  
  
Contractor shall submit a Health and Safety Plan according to Technical Specification 
Section 01300 – SUBMITTALS. The City does not approve Contractor safety plans but 
can issue stop work orders to the contractor if an unsafe condition has been observed.

SECTION 01060 
 
 
HEALTH AND SAFETY 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
              01060 - 3 
October 25, 2024 
  
PART 2 - PRODUCTS  
  
2.01 
HEALTH AND SAFETY PLAN  
  
A. GENERAL  
  
The Contractor shall develop and maintain for the duration of the Contract three copies 
of a Health and Safety Plan that will effectively incorporate and implement all required 
health and safety precautions. At least one copy shall be located on the Contractor's 
work site.  
  
B. COMPLIANCE 
  
The Contractor shall appoint an on-site employee who is qualified, trained and 
authorized to supervise and enforce compliance with the Health and Safety Plan. The 
Contractor is responsible for ensuring that necessary gas monitoring, protective 
clothing, and other supplies and equipment as specified are available to implement this 
Plan.  
  
C. REVISIONS 
  
In the event that regulatory agencies or jurisdictions determine the Health and Safety 
Plan to be inadequate to protect employees and the public:  
  
1. The Contractor shall stop the work in progress until adequate safety measures are 
implemented.  
  
2. The Contractor shall modify the Plan to meet the requirements of said regulatory 
agencies, jurisdictions, and the City.  
  
3. The Contractor shall notify the City and the City’s Representative immediately 
when a notification of deficiency is issued by another agency and/or jurisdiction. 
 
4. The Contractor shall provide the City and City’s Representative with the revisions 
to the Plan within two (2) days of the notice of deficiency.  
 
D. MINIMUM CONSIDERATIONS  
  
The Health and Safety Plan shall, as a minimum, include the following considerations:  
  
1. Objective.  
  
2. Key personnel and responsibilities.  
  
3. Hazard analysis of the work activities and environment.

SECTION 01060 
HEALTH AND SAFETY 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
              01060 - 4 
October 25, 2024 
  
4. Training requirements, including contractor’s and sub-contractor’s authorized 
personnel and qualifications for work in confined spaces.  
  
5. Personal protective equipment.  
  
6. Confined Space Entry Plan. 
 
7. Fall protection plan and tie-off points. 
  
8. Site control measures.  
  
9. Work practices, decontamination procedures, and work limitations.  
  
10. Emergency procedures, including sewer evacuation plan, location of first aid, fire 
extinguishers, eyewash, drinking water, map showing route to nearest medical 
facility, list of key personnel who are currently certified in first aid/CPR.  
  
11. Job site cleanup, and spill containment and cleanup procedures.  
  
12. Telephone numbers:  
a. 24-hour number to contact Contractor's Representative.  
b. Emergency services. 
c. City’s Project Manager. 
d. City’s Representative.  
  
13. Documentation (training, injury or illness, respirator-fit tests, hazards notification 
log, etc.).  
 
PART 3 - EXECUTION  
(NOT USED) 
  
 
** END OF SECTION **

SECTION 01062 
PERMITS AND EASEMENTS 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
              01062 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01 
EASEMENTS  
  
Sewers and access manholes may be located in the City of Glendale right-of-way or utility 
easements. Contractor shall be responsible to obtain permits or permissions to access all 
applicable areas and to limit construction activities to within these areas. 
 
1.02 
PERMITS TO BE OBTAINED BY THE CONTRACTOR  
  
Contractor shall obtain any additional permits and access agreements required by the work 
and shall pay all costs thereof, including agency inspections. The Contractor shall comply 
with all applicable terms and conditions therein and provide copies to the City’s 
Representative before working in areas covered by those permits. The following permits, 
but not necessarily limited to the following, shall be obtained by the Contractor if 
applicable to the work:  
  
1) 
Occupational Safety and Health Association (OSHA): 
 
a) Confined Space Entry Permit. 
 
 
2) 
Arizona Department of Environmental Quality (ADEQ): 
 
a) Stormwater Pollution Prevention Plan (SWPPP). 
 
 
3) 
Maricopa County Air Quality Department: 
 
a) Dust Control Permit. 
 
 
4) 
City of Glendale:  
 
a) Righ-of-Way Permit. 
 
b) Traffic Control Permit. 
 
 
5) 
Arizona Department of Transportation: 
 
a) Encroachment Permit. 
 
 
6) 
Others: 
 
a) Debris Disposal Permit(s). 
 
b) as applicable. 
 
1.03 
POSTING  
  
Permits shall be posted (or available for review) at the site of the work at all times work 
is commencing. All permits shall be submitted to the City in accordance with Technical 
Specification Section 01300 – SUBMITTALS.

SECTION 01062 
PERMITS AND EASEMENTS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
              01062 - 2 
October 25, 2024 
PART 2 – PRODUCTS 
(NOT USED) 
  
PART 3 - EXECUTION 
(NOT USED) 
 
 
 
 
** END OF SECTION **

SECTION 01064 
INSPECTION AND TESTING 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
              01064 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01  INSPECTION AND TESTING OF MATERIALS  
  
All workmanship and materials shall be subject to inspection by the City or City’s 
Representative, who may select samples of materials in such a quantity as the City’s 
Representative may deem necessary to determine their qualities, as herein specified. Any 
samples taken shall be at the discretion of the City and shall be in addition to those required 
to be taken by the Contractor as specified in these Technical Specifications, manufacturer’s 
recommendations, and permits requiring test results. The City or City’s Representative will 
accept or reject the materials in accordance with the results of such trials or from test results 
submitted from an independent testing laboratory. All rejected materials shall be promptly 
replaced to the satisfaction of the City or City’s Representative. The Contractor shall assist 
the City or City’s Representative by providing access to the location where the work is in 
progress. The Contractor shall replace rejected work and materials and bear all costs for 
doing so.  
 
 
Non-rejection or non-inspection of materials does not constitute acceptance by the City or 
the City’s Representative. 
  
 
The City or City’s Representative inspection will be provided on an 8-hour per day, 5-day 
per week basis, excluding weekends and holidays. The Contractor shall not schedule any 
overtime work which requires inspection or material testing without written permission 
from the City or City’s Representative two (2) working days before the proposed overtime 
work. The City reserves the right to deny the requested overtime. If an overtime request is 
denied, the City may extend the contract time at no additional cost to the City.  
  
 
PART 2 - PRODUCTS  
(NOT USED) 
  
PART 3 - EXECUTION  
(NOT USED) 
 
 
** END OF SECTION **

SECTION 01064 
INSPECTION AND TESTING 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
              01064 - 2 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[This page intentionally left blank for double sided printing]

SECTION 01071  
STANDARD REFERENCES 
_ 
 
 
 
 
 
 
 
 
 
 
 
_ 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01071 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01  ABBREVIATIONS  
  
Wherever used in the Contract Documents, the following abbreviations will have the 
meanings listed:  
  
AAC  
Arizona Administrative Code  
 
1700 West Washington, 7th Floor  
 
Phoenix, AZ  85007-2808  
  
AASHTO  
American Association of State Highway and Transportation 
Officials  
 
444 North Capitol Street, N.W., Suite 249  
 
Washington, D.C. 20001  
  
ACI    
American Concrete Institute  
 
38800 Country Club Drive  
 
Farmington Hills, MI 48331-3439 
  
ADEQ  
Arizona Department of Environmental Quality  
 
1110 West Washington Street  
 
Phoenix, AZ 85007 
  
ADOT  
Arizona Department of Transportation  
 
206 South 17th Avenue  
 
Phoenix, AZ 85004  
  
ADWR  
Arizona Department of Water Resources  
 
3550 North Central Avenue, Suite 200  
 
Phoenix, AZ 85012 
 
  
AEIC  
Association of Edison Illuminating Companies  
 
600 North 18th Street  
 
Birmingham, AL 35203  
  
AISC 
American Institute of Steel Construction, Inc.  
 
130 East Randolph, Suite 2000 
 
Chicago, IL 60601 
 
AISI    
American Iron and Steel Institute  
 
25 Massachusetts Avenue, N.W., Suite 800  
 
Washington, D.C. 20001

SECTION 01071 
STANDARD REFERENCES 
 
 
 
 
 
 
 
 
 
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01071 - 2 
October 25, 2024 
Ameron  
Ameron International Protective Lining Products 
 
8000 Research Forest Drive 
 
Suite 115-118 
 
The Woodlands TX 77382 
  
ANSI  
American National Standards Institute, Inc.  
 
1899 L Street, N.W., 11th Floor  
 
Washington, D.C. 20036  
  
API    
American Petroleum Institute  
 
1220 L Street, N.W.  
 
Washington, D.C. 20005  
  
ASCE  
American Society of Civil Engineers  
 
1801 Alexander Bell Drive  
 
Reston, Virginia 20191  
  
ASCII  
American Standard Code for Information Interchange  
 
United States of America Standards Institute   
 
10 East 40th Street  
 
New York, NY 10016  
  
ASTM  
American Society for Testing and Materials  
 
100 Barr Harbor Drive 
 
P.O. Box C700 
 
West Conshohocken, PA 19428-2959 
 
AT & SFRR 
Atchison, Topeka and Santa Fe Railroad 
  
AWS  
American Welding Society  
 
8669 N.W. 36th Street, Suite 130  
 
Miami, FL 33166-6672 
  
AWWA  
American Water Works Association  
 
6666 West Quincy Avenue  
 
Denver, CO 80235  
  
BOCA    
Building Officials and Code Administrators  
 
7926 Halstead  
 
Homewood, IL 60430  
 
CFR  
Code of Federal Regulations  
 
Superintendent of Documents  
 
Government Printing Office  
 
Washington, D.C. 20402

SECTION 01071  
 
 
STANDARD REFERENCES 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01071 - 3 
October 25, 2024 
  
CMAA 
Crane Manufacturers Association of America, Inc.  
 
(Formerly called: Overhead Electrical Crane Institute) (OECI)  
 
8720 Red Oak Boulevard, Suite 201 
 
Charlotte, NC 28217-3992 
  
CRSI  
Concrete Reinforcing Steel Institute  
 
933 North Plum Grove Road  
 
Schaumburg, IL  60173-4758 
 
COG 
City of Glendale 
 
5850 W. Glendale Avenue 
 
Glendale, Arizona 85301 
  
EEI   
Edison Electric Institute  
 
701 Pennsylvania Avenue, N.W.  
 
Washington, D.C. 10016  
  
FEDSPEC  
Federal Specifications  
 
General Services Administration  
 
Specification and Consumer Information   
 
Distribution Branch  
 
Washington Navy Yard, Building 197   
 
Washington, DC 20407  
  
FEDSTDS  
Federal Standards  
 
(see FEDSPECS)  
 
FCDMC 
Flood Control District Maricopa County 
 
2801 West Durango Street 
 
Phoenix, AZ 85009 
  
IES    
Illuminating Engineering Society  
 
120 Wall Street, Floor 17  
 
New York, NY 10005-4001  
  
MAG  
Maricopa Association of Governments  
 
302 North 1st Avenue, Suite 300  
 
Phoenix, AZ 85003 
 
MCESD 
Maricopa County of Environmental Services Department 
 
1001 North Central Avenue, Suite 200 
Phoenix, AZ 85004 
 
NACE  
National Association of Corrosion Engineers

SECTION 01071 
STANDARD REFERENCES 
 
 
 
 
 
 
 
 
 
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01071 - 4 
October 25, 2024 
 
15835 Park Ten Place  
 
Houston, TX 77084  
  
NASSCO  
National Association of Sanitary Service Companies  
 
2470 Longstone Lane, Suite M 
 
Marriottsville, MD 21104  
  
NFPA  
National Fire Protection Association  
 
1 Batterymarch Park 
 
Quincy, MA 02169-7471 
 
NPDES  
National Pollutant Discharge Elimination System  
 
U.S. Environmental Protection Agency 
 
National Pollutant Discharge Elimination System Program  
 
Office of Water, Office of Wastewater Management 
 
1200 Pennsylvania Avenue, N.W. (Mail code 4203M)  
 
Washington, D.C. 20460  
  
OSHA   
Occupational Safety and Health Act 
 
U.S. Department of Labor 
 
Occupational Safety and Health Administration  
 
200 Constitution Avenue, N.W.  
 
Washington, D.C. 20210  
 
RID 
Roosevelt Irrigation District 
 
103 West Baseline Road 
 
Buckeye, AZ   85326 
   
SWPPP  
Storm water Pollution Prevention Plan 
 
Environmental Protection Agency, Region 9  
 
75 Hawthorne Street,  
 
San Francisco, CA  
  
UBC  
Uniform Building Code 
 
Published by ICBO  
  
UL  
Underwriters Laboratories Inc. 
 
207 East Ohio Street  
 
Chicago, IL 60611  
  
WABO  
Washington Association of Building Officers  
 
Post Office Box 7310  
 
Olympia, WA 98507

SECTION 01071  
 
 
STANDARD REFERENCES 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01071 - 5 
October 25, 2024 
PART 2 - PRODUCTS  
(NOT USED) 
 
  
PART 3 - EXECUTION  
(NOT USED) 
 
  
** END OF SECTION **

SECTION 01071 
STANDARD REFERENCES 
 
 
 
 
 
 
 
 
 
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01071 - 6 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page left intentionally blank for double sided printing ]

SECTION 01102 
CONTRACTORS HAZARDOUS MATERIALS  
MANAGEMENT PROGRAM 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01102 - 1 
October 25, 2024 
PART 1 - GENERAL  
 
1.01 
DESCRIPTION 
 
A. The Contractor shall Comply with all Federal, State, and local rules and regulations 
related to environmental protection and environmental safety including, but not limited 
to, the following: 
 
1. Title 29 Code of Federal Regulations Parts 1910, Occupational Safety and Health. 
 
2. Title 40 Code of Federal Regulations, Protection of Environment. 
 
3. Title 49 Code of Federal Regulations, Transportation. 
 
4. State Occupational Safety and Health Administration (OSHA). 
 
5. Arizona Department of Environmental Quality (ADEQ). 
 
6. Arizona Department of Water Resources (ADWR). 
 
7. Maricopa County Air Pollution Control Regulations. 
 
8. Maricopa County Air Quality Department Regulations. 
 
B. In order to ensure the City that the Contractor is complying with the intent of the 
regulations stated in Paragraph 1.01.A above, as they relate to the on-site use of 
hazardous materials, hazardous wastes and other substances similarly defined in those 
regulations, develop and maintain a Contractor’s Hazardous Materials Management 
Program that includes as a minimum, but is not limited to the requirements specified 
herein. The interests of the City are that accidental spills, site contamination, and injury 
of personnel on the site are avoided. The City will not enforce suspected violations of 
the rules and regulations referenced in Paragraph 1.01.A above, however the City will 
notify the Contractor of suspected violations. If in the opinion of the City, the 
Contractor fails to address the suspected violations in a timely and appropriate manner, 
the City will notify federal, state, or local regulatory agencies, report the suspected 
violations to them, and request that they inspect the Contractor’s operations. Any fines 
that may be levied against the City for violations committed on the site by the 
Contractor, as well as any costs associated with cleanup of materials, shall be paid by 
the Contractor or compensation to the Contractor shall be reduced by equal amount to 
reimburse the City. All documents required by the program shall be made available to 
the City’s Environmental Representative immediately, upon request.

SECTION 01102 
CONTRACTORS HAZARDOUS MATERIALS  
MANAGEMENT PROGRAM 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01102 - 2 
October 25, 2024 
C. Responsibility for any hazardous waste, as defined in any of the above listed 
regulations, and those generated by the Contractor, belongs to the Contractor. If the 
Contractor is going to generate, or has generated, a substance that qualifies as a 
hazardous waste, Contractor must obtain an Environmental Protection Agency (EPA) 
identification number, listing the Contractor’s name and construction site address as 
the generator of the hazardous waste. Responsibility for the identification, analysis, 
profiling, transport and disposal of hazardous wastes generated, belongs to the 
Contractor. The identification number can be obtained from ADEQ. This number shall 
be provided to the City’s Representative within five (5) days after the Notice to 
Proceed, or before any hazardous materials are brought onto the site. 
 
1.02 
HAZARDOUS MATERIALS PROGRAM REQUIREMENTS 
 
A. Within the regulations listed in Paragraph 1.01.A, above, terms such as hazardous 
material, hazardous wastes, and similar terms have varying definitions. To dispel 
confusion regarding what materials fall under the Program Requirements and for the 
purposes of this section, Hazardous Material is defined as “any material, whether solid, 
semi-solid, liquid, or gas, which, if not stored or used properly, may cause harm or 
injury to persons through inhalation, ingestion, absorption or injection, or which may 
negatively impact the environment through the use or discharge of the material on the 
ground, in the water (including groundwater), or to the air.” 
 
B. All chemicals brought onto the site must be approved by the City. Prior to bringing any 
chemical on site, request approval from the City’s Environmental Representative for 
each chemical the Contractor proposes to bring on site. At the time of request, the City’s 
Environmental Representative may request and receive from the Contractor, specific 
information associated with each chemical. The specific information may include, but 
is not limited to, SDS, manufacture, vendor, container size(s), number of containers, 
minimum and maximum volume of material intended to be stored on site, as well a 
description to the process or procedures in which any requested chemical is to be used. 
The City, within five (5) working day from receipt of the specific chemical information, 
will inform the Contractor as to whether the chemical has been approved for use on 
site. 
 
C. Maintain on site two notebooks containing (1) a chemical inventory, and (2) current 
(dated within the past two years) Safety Data Sheets (SDS) for all materials being used 
on site, whether or not they are defined as a Hazardous Material in Paragraph 1.02.A, 
above. One notebook shall be kept in the Contractor’s on-site office and the other shall 
be kept in a location specified by the City’s Environmental Representative. These 
notebooks must be kept up to date as materials are brought onto and removed from the 
site. Copies of SDS sheets for chemicals removed from the site shall be provided to the 
City’s Environmental Representative.

SECTION 01102 
CONTRACTORS HAZARDOUS MATERIALS  
 
 
MANAGEMENT PROGRAM 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01102 - 3 
October 25, 2024 
D. Develop an emergency/spill response plan, for each hazardous material or class/group 
of materials. As a minimum, the response plan must address the following: 
 
1. Provide a description of equipment on site available to contain or respond to an 
emergency/spill of the material. 
 
2. Notification procedures. 
 
3. Response coordination procedures between the Contractor, the City, and the City’s 
Representative. 
 
4. Provide a Site Plan showing the location of stored hazardous materials and location 
of spill containment/response equipment.  
 
5. Provide a description of the hazardous material handling and spill response training 
provided to the Contractor’s employees. 
 
E. In accordance with applicable Laws and Regulations, properly and safely store all 
hazardous materials, which shall include as a minimum, the following: 
 
1. A designated storage site for hazardous materials that includes secondary 
containment. The site must include barriers to prevent vehicles from colliding with 
the storage containers and offer protection from environmental factors such as 
weather. 
2. Signage in accordance with applicable Laws and Regulations, clearly identifying 
the hazardous materials storage site. 
3. All hazardous materials containers must bear the applicable Hazard Diamonds. 
 
F. Properly label all containers of consumable materials, whether or not they are classified 
as Hazardous Materials under this Section. The name of the Contractor or subcontractor 
shall be stenciled on any container containing a hazardous material and on any 
container over five-gallon capacity containing a non-hazardous material. Any container 
must have a label clearly identifying the contents. If any such unlabeled containers are 
discovered on the site, the City’s Environmental Representative will notify the 
Contractor. Responsibility to remove such containers belongs to the Contractor. 
Containers will be properly labeled or removed from the site within one (1) hour. Any 
containers that are filled from larger containers must also be properly labeled. 
 
G. The City encourages storage of hazardous materials off site until the materials are 
needed on site. 
 
H. Provide all documentation required herein available immediately upon request of the 
City’s Environmental Representative. The Contractor’s Safety Representative will 
meet at least monthly with the City’s Environmental Representative to review the

SECTION 01102 
CONTRACTORS HAZARDOUS MATERIALS  
MANAGEMENT PROGRAM 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01102 - 4 
October 25, 2024 
Contractor’s Hazardous Materials Management Program documents, procedures, and 
inspect the storage site and job site to ensure the requirements specified herein are being 
complied with. Also, provide the City’s Environmental Representative and the City’s 
Representative with copies of all permits obtained from environmental regulatory 
agencies. 
 
I. Provide documentation to the City’s Representative and the City’s Environmental 
Representative that the Contractor, subcontractors, or others hired by the Contractor 
making deliveries of hazardous Materials (as defined in Title 49 CFR) to the site are in 
compliance with Title 49 CFR 172.800 – 172.804, which requires each person who 
offers for transportation in commerce or transports in commerce one or more of the 
following hazardous materials, as defined by Title 49 CFR, must develop and adhere 
to a security plan for hazardous materials that conforms to the requirements of this 
subpart. 
 
PART 2 – PRODUCTS 
(NOT USED) 
 
PART 3 – EXECUTION  
(NOT USED) 
 
 
**END OF SECTION**

SECTION 01300 
SUBMITTALS 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01300 - 1 
October 25, 2024 
PART 1 - GENERAL  
 
1.01 
GENERAL  
  
Submittals covered by these requirements include manufacturers' information, shop 
drawings, test procedures, test results, samples, requests for substitutions, and 
miscellaneous work-related submittals. The Contractor shall furnish all specifications, 
descriptive data, certificates, samples, tests, methods, schedules, and manufacturer's 
installation and other instructions as specifically required in the contract documents to 
demonstrate fully that the materials to be furnished and the methods of work comply with 
the provisions and intent of the contract documents.  
  
1.02 
CONTRACTOR'S RESPONSIBILITIES  
  
The Contractor shall be responsible for the accuracy and completeness of the information 
contained in each submittal and shall assure that the material, equipment or method of work 
shall be as described in the submittal. The Contractor shall verify that all features of all 
products conform to the specified requirements. Submittal documents shall be clearly 
edited to indicate only those items which are being submitted for review. All extraneous 
materials shall be crossed out or otherwise obliterated. The Contractor shall ensure that 
there is no conflict with other submittals and notify the City’s Representative in each case 
where his submittal may affect the work of another Contractor or the City. The Contractor 
shall coordinate submittals among his subcontractors and suppliers.  
  
The Contractor shall coordinate submittals so that work will not be delayed. The Contractor 
shall coordinate and schedule different categories of submittals, so that one will not be 
delayed for lack of coordination with another. No extension of time will be allowed because 
of failure to properly schedule submittals. The Contractor shall not proceed with work 
relating to a submittal until the submittal process is complete. This requires that submittals 
for review and comment shall be returned to the Contractor stamped "No Exceptions 
Taken" or "Make Corrections Noted."  
  
The Contractor shall certify each submittal document by signing Form 01999-A Submittal 
Transmittal specified in Technical Specification Section 01999 – REFERENCE FORMS 
that the Contractor has reviewed the submittal, verified field conditions, and complied with 
the contract documents.  
  
The Contractor may authorize in writing a material or equipment supplier to deal directly 
with the City’s Representative or with the City with regard to a submittal. These dealings 
shall be limited to contract interpretations to clarify and expedite the work.

SECTION 01300 
SUBMITTALS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01300 - 2 
October 25, 2024 
1.03 
CATEGORIES OF SUBMITTALS  
  
A. GENERAL  
  
Submittals fall into two general categories; submittals for review and comment, and 
submittals, which are primarily for information only. Submittals, which are for 
information only, are typically specified in the Part 2 - PRODUCTS of the individual 
Technical Specification section.  
  
a. SUBMITTALS FOR REVIEW AND COMMENT: 
  
All submittals except where specified to be submitted as product data for 
information only shall be submitted by the Contractor to the City and/or City’s 
Representative for review and comment.  
  
b. SUBMITTALS (PRODUCT DATA) FOR INFORMATION ONLY  
  
Where specified, the Contractor shall furnish submittals (product data) to the City 
and/or City’s Representative for Information only.  
 
1.04 
TRANSMITTAL PROCEDURE  
  
A. GENERAL 
  
The City or City’s Representative will furnish the Contractor a list of numbers for 
anticipated submittals as specified in the Construction Documents. The list of 
submittals will be marked for review and comment and product data (submittals) for 
information only. The list is not intended to be an all-inclusive list of submittals 
required. Contractor shall coordinate additional submittals and corresponding submittal 
numbers with the City or City’s Representative. 
Unless otherwise specified, all submittals shall be accompanied by Submittal 
Transmittal Form 01999-A specified in Technical Specification Section 01999 – 
REFERENCE FORMS. A separate Transmittal Form shall be used for each specific 
item, class of material, and items specified in separate, discrete sections, for which the 
submittal is required.  Submittals for various items shall be made with a single form 
when the items taken together constitute a manufacturer's package or are so 
functionally related that expediency indicates checking or review of the group or 
package as a whole.  
A unique number, sequentially assigned, shall be noted on the transmittal form 
accompanying each item submitted. Original submittal numbers shall have the 
following format:  "XXX"; where "XXX" is the sequential number assigned by the City 
or City’s Representative. Re-submittals shall have the following format: "XXX-Y"; 
where "XXX" is the originally assigned submittal number and "Y" is a sequential letter 
assigned for re-submittals, e.g., A, B, or C being the 1st, 2nd, and 3rd re-submittals, 
respectively. Submittal 25B, for example, is the second re-submittal of submittal 25.

SECTION 01300 
 
 
SUBMITTALS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01300 - 3 
October 25, 2024 
Re-submittals shall include original information with all revisions. 
 
B. DEVIATION FROM CONTRACT  
  
1. The Contractor shall submit a copy of the specification section, with addendum 
updates included, and all referenced and applicable sections with addendum 
updates included, with each paragraph check-marked as follows: 
 
a. Marked to indicate specification compliance. Check marks (√) shall denote full 
compliance with a paragraph as a whole.   
 
b. Marked to indicate requested deviations from specification requirements.  If 
deviations from the specifications are indicated, and therefore requested by the 
Contractor, each deviation shall be underlined and denoted by a number in the 
margin to the right of the identified paragraph, referenced to a detailed written 
explanation of the reasons for requesting the deviation. The City shall be the 
final authority for determining acceptability of requested deviations. The 
remaining portions of the paragraph not underlined will signify compliance on 
the part of the Contractor with the specifications. Failure to include a copy of 
the marked-up specification sections, along with justification(s) for any 
requested deviations to the specification requirements, with the submittal shall 
be sufficient cause for rejection of the entire submittal with no further 
consideration. 
 
2. If the Contractor proposes to provide material, equipment, or method of work, 
which deviates from the Construction Documents, he shall indicate so under 
"Deviation" on Form 01999-A Submittal Transmittal accompanying the submittal 
copies. 
  
C. SUBMITTAL COMPLETENESS  
  
Submittals which do not have all the information required to be submitted, including 
deviations and Contractor’s signature, are not acceptable and will be returned without 
review. The Contractor will be charged an additional cost if a submittal requires three 
or more reviews. (See Sub-section: 1.07 THIRD AND SUBSEQUENT 
SUBMITTALS) 
 
1.05 
REVIEW PROCEDURE  
  
A. GENERAL 
  
Submittals are specified for those features and characteristics of materials, and methods 
of operation, which can be selected, based on the Contractor's judgment of their 
conformance to the specified requirements. Other features and characteristics are 
specified in a manner, which enables the Contractor to determine acceptable options 
without submittals. The review procedure is based on the Contractor's guarantee that

SECTION 01300 
SUBMITTALS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01300 - 4 
October 25, 2024 
all features and characteristics not requiring submittals conform as specified. Review 
shall not extend to means, methods, techniques, sequences or procedures of 
construction, or to verifying quantities, dimensions, weights or gages, or fabrication 
processes (except where specifically indicated or required by the contract documents) 
or to safety precautions or programs incident thereto. Review of a separate item, as 
such, will not indicate approval of the assembly in which the item functions.  
  
When the contract documents require a submittal, the Contractor shall submit the 
specified information as follows:  
  
1. Unless otherwise specified, one (1) electronic Copy (.pdf format) of all submitted 
information shall be transmitted with submittals for review and comment.  
 
2. Unless otherwise specified, one (1) electronic Copy (.pdf format) of all submitted 
information shall be transmitted with submittals (Product Data) for information 
only.  
 
B. SUBMITTALS FOR REVIEW AND COMMENT 
  
Unless otherwise specified, within ten (10) calendar days after receipt of a submittal 
for review and comment, the City and/or City’s Representative shall review the 
submittal and return one copy of the electronically marked-up original in PDF format.  
Shop drawing submittals that require markups shall be marked up in red by the City 
and/or City’s Representative. The City and/or City’s Representative will retain the 
original.   
 
The returned submittal shall indicate one of the following actions:  
  
1. If the review indicates that the material, equipment or work method complies with 
the contract documents, submittal copies will be marked "NO EXCEPTIONS 
TAKEN." In this event, the Contractor may begin to implement the work method 
or incorporate the material or equipment covered by the submittal.  
 
2. If the review indicates limited corrections are required, copies will be marked 
"MAKE CORRECTIONS NOTED." The Contractor may begin implementing the 
work method or incorporating the material and equipment covered by the submittal 
in accordance with the noted corrections. A corrected copy shall be resubmitted.  
 
3. If the review reveals that the submittal is insufficient or contains incorrect data, 
copies will be marked "AMEND AND RESUBMIT." Except at his own risk, the 
Contractor shall not undertake work covered by this submittal until it has been 
revised, resubmitted and returned marked either "NO EXCEPTIONS TAKEN" or 
"MAKE CORRECTIONS NOTED."  
 
4. If the review indicates that the material or work method does not comply with the 
contract documents, copies of the submittal will be marked "REJECTED - SEE

SECTION 01300 
 
 
SUBMITTALS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01300 - 5 
October 25, 2024 
REMARKS." Submittals with deviations, which have not been identified, clearly 
may be rejected. Except at his own risk, the Contractor shall not undertake the work 
covered by such submittals until a new submittal is made and returned marked 
either "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED."  
  
C. SUBMITTALS (PRODUCT DATA) FOR INFORMATION ONLY:  
  
Such information is not subject to submittal review procedures and shall be provided 
as part of the work under this contract and its acceptability determined under normal 
inspection procedures.  
  
1.06 
EFFECT OF REVIEW OF CONTRACTOR'S SUBMITTALS  
  
Review methods of work or information regarding materials the Contractor proposes to 
provide, shall not relieve the Contractor of his responsibility for errors therein and shall not 
be regarded as an assumption of risks or liability by the City’s Representative and/or the 
City, or by any officer or employee thereof, and the Contractor shall have no claim under 
the contract on account of the failure, or partial failure, of the method of work, material, or 
equipment so reviewed. A mark of "NO EXCEPTIONS TAKEN" or "MAKE 
CORRECTIONS NOTED" shall mean that the City has no objection to the Contractor, 
upon his own responsibility, using the plan or method of work proposed, or providing the 
materials proposed.  
 
1.07 
THIRD AND SUBSEQUENT SUBMITTALS  
  
The cost for third and subsequent submittals shall be borne by the Contractor. The cost of 
reviews for third and subsequent reviews shall be at a rate of $100 per review and shall be 
charged to the Contractor as a reduction in Contractor’s pay request.  
  
PART 2 - PRODUCTS  
(NOT USED) 
  
PART 3 - EXECUTION  
(NOT USED) 
 
**END OF SECTION**

SECTION 01300 
SUBMITTALS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01300 - 6 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[This page intentionally left blank for double sided printing]

SECTION 01310 
PROGRESS SCHEDULE 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01310 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01 
DESCRIPTION  
  
This Technical Specification section specifies requirements and procedures for the 
Contractor in preparing schedules. The purpose of the schedule shall be to ensure adequate 
planning and execution of the work by the Contractor, notification and coordination of 
construction activities with the general public, to establish the standard against which 
satisfactory completion of the project shall be judged, to assist the City or City’s 
Representative in monitoring progress and for the assessment of the impact of change 
orders on the Schedule.  
  
1.02 
SUBMITTAL PROCEDURES  
  
The Contractor shall submit a schedule to the City or City’s Representative within ten (10) 
calendar days of receiving Notice to Proceed and prior to Pre-construction meeting (if 
scheduled) with work identifying the duration of mobilization, anticipated time when work 
is to be performed, cleaning, pre-video, CIPP lining or rehabilitation activity sequence and 
duration, post video, and date of project completion. Schedule shall be transmitted to the 
City or City’s Representative per Technical Specification Section 01300 – SUBMITTALS.   
  
PART 2 - PRODUCTS  
  
2.01 
PROGRESS SCHEDULES  
  
A. Contractor shall provide a Schedule to the City and/or City’s Representative.  Schedule 
shall be updated weekly with anticipated pipes (if applicable) and/or structures (if 
applicable) to be rehabilitated. Schedule shall also list work completed to date.  
 
B. Schedule shall be prepared on computer software (such as Microsoft Project) that 
facilitates schedule updates and electronic distribution such as e-mailing.  
 
C. Special considerations, coordination requirements, etc., as encountered for certain 
pipes (if applicable) and structures (if applicable) shall be noted on schedule.  
 
D. Time for completion for each separate pipe segment (if applicable) and structure (if 
applicable) shall be shown on the schedule.  
 
E. The schedule duration of each activity shall be based on the work being performed 
during the normal work week with allowances made for legal holidays. The schedule 
shall include a critical path for each separate pipe segment (if applicable) and structure 
(if applicable).

SECTION 01310 
PROGRESS SCHEDULE 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01310 - 2 
October 25, 2024 
F. Dates imposed on the schedule by the Contractor shall not be binding on the City or 
City’s Representative. 
 
G. Failure to include elements of work required for the performance of this Project shall 
not excuse the Contractor from completing the work as described in the Construction 
Documents.  
 
H. Provide a list of the holidays and non-work days applicable to the schedule. 
  
I. Traffic Control concerns may necessitate work during nights, weekends, or holidays. 
 
J. Provide a schedule and narrative summary stating project status so the City and/or 
City’s Representative may use them as a basis for determining the Contractor’s 
compliance with the Technical Specification requirements regarding progress 
payments, contract time extensions, change order prices and impacts, and the overall 
progress of the work. Failure of the Contractor to comply with the requirements of this 
Technical Specification Section may delay the review and acceptance of the progress 
payment requests.  
 
PART 3 - EXECUTION  
  
3.01 
GENERAL  
 
The Contractor and the Contractor’s Field Superintendent shall attend regularly scheduled 
construction progress meetings with the City or City’s Representative and others invited 
by the City or City’s Representative.  
  
3.02 
UPDATES  
  
A. Requests for extensions in time resulting from changes issued by the City shall be 
accompanied by a Time Extension Request - Narrative Report explaining the impacts 
and costs associated with the extension if it were to be granted.  
 
B. If actual progress on the critical path items is observed to deviate from the schedule 
by ten (10) or more days behind, the Contractor shall update and submit a revised 
(updated) schedule. In the case of the work being behind schedule, the Contractor shall 
submit, along with the revised schedule, a written plan for completing the work within 
the milestone and contract times.  
 
 
** END OF SECTION **

SECTION 01380  
PHOTOGRAPHS AND VIDEO RECORDINGS  
 
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01380 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01  DESCRIPTION  
  
A. This section specifies digital color photographs and digital video recordings to be taken 
at the ground surface level by the Contractor before and after construction commences. 
These recordings shall clearly document site conditions prior to construction activities 
commencing and again following the completion of construction activities.  
  
1.02  PAYMENT  
  
A. Contractor shall pay costs for photography, video recordings and prints. Parties 
requiring additional photography, video recordings or prints shall invoice and pay 
photographer directly. 
  
1.03 
SUBMITTALS  
  
A. Contractor shall submit the following information for review per Technical 
Specification Section 01300 – SUBMITTALS at the pre-construction conference. 
  
1. Site condition color photographs and video with audio commentary taken prior to 
construction. 
 
PART 2 - PRODUCTS  
  
2.01  GENERAL  
  
A. The color photographs and audio-video recordings are intended for use as indisputable 
evidence in ascertaining the extent of any damage which may have occurred as a result 
of the Contractor's operations and are for the protection of the Contractor and the City, 
and may, at the City’s discretion, be a means of determining whether and to what extent 
damage, resulting from the Contractor's operations, occurred during the Contract work.  
 
B. PHOTOGRAPHS:  
  
Photographs shall be color digital (high resolution) .jpeg format stored on DVD or USB 
media. Submitted DVD media shall indicate on the front of each jewel protection case 
the date, name of Project, and City where the photographs were taken. Submitted USB 
media shall contain an identification tag along with a Readme Notepad file that 
contains the date, name of Project, and City where the photographs were taken. One 
(1) copy of each DVD or USB shall be delivered to the City.

SECTION 01380  
PHOTOGRAPHS AND VIDEO RECORDINGS  
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01380 - 2 
October 25, 2024 
C. VIDEO RECORDINGS: 
Video recordings shall be .mpeg format stored on DVD or USB media. Submitted DVD 
media shall indicate on the front of each jewel protection case the date, name of Project, 
and City where the videos were taken. Submitted USB media shall contain an 
identification tag along with a Readme Notepad file that contains the date, name of 
Project, and City where the videos were taken. The video recordings should contain an 
audio track, which narrates the progression of the video recording through the site. One 
(1) copy of each DVD or USB shall be delivered to the City. 
  
PART 3 - EXECUTION  
  
3.01  VIDEO / DVD  
  
A. Contractor shall perform video recordings of all areas where the Contractor anticipates 
construction activities to occur, including all staging, storing, working, parking and 
excavation areas. Easements and areas outside of paved roadways are of particular 
interest.  
  
B. After completion of construction and restoration, video recordings shall be taken from 
the same points, in the same direction as the pre-construction examination recording.  
  
3.02  CONSTRUCTION PHOTOGRAPHY  
  
A. Photographs shall be provided of items of special interest and/or special conditions 
during construction.  
  
**END OF SECTION**

SECTION 01400 
PUBLIC AWARENESS 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01400 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01 
DESCRIPTION  
  
The work under this item consists of informing adjacent property owners regarding the 
impact and schedule of construction work, attendance at public information meeting(s), 
responding to on-site public inquiries along with distribution of public information door 
hanger materials to adjacent property owners as needed, and coordination with the City’s 
Public Information Officer (PIO), Communications and Public Affairs (CAPA) department 
personnel, and City’s Public Outreach Consultant. 
 
The CAPA department shall review all materials for distribution to the public. The 
Contractor shall be responsible for developing and providing to the City the schedule 
outlining the work descriptions, start date, milestones, and duration of work that will be 
distributed to the public per Technical Specification 01310 – PROGRESS SCHEDULE.    
 
Construction information will be distributed to area residents and businesses by the City. 
The Contractor shall be responsible for coordination with the City’s Public Outreach 
Consultant. 
  
1.02 
SUBMITTALS  
  
The Contractor shall submit to the City and/or City’s Representative per Technical 
Specification Section 01300 - SUBMITTALS the following for approval: 
  
1. Schedule outlining construction start date and duration of construction within ten (10) 
days of the Notice to Proceed. 
 
2. Letter containing the name and contact phone number of the Contractor’s on-site 
Representative and stating that this person is duly authorized to act on behalf of the 
Contractor during public relation activities and/or construction problem resolution.  
 
3. The Company logo of the Contractor and any sub-contractors working on the project.  
Contractor shall give the City and/or subconsultant permission and sole discretion to 
reproduce logo on project related documents such as, but not limited to construction 
notices that are distributed to the general public. Company logo shall be provided in 
high resolution digital (.jpeg) format. 
 
1.03 
CONSTRUCTION NOTICES AND DOOR HANGERS  
  
A. The City shall notify properties potentially affected by construction activities by 
distributing a project notification flyer or other electronic, social media, or printed 
means prior to construction occurring.

SECTION 01400 
PUBLIC AWARENESS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01400 - 2 
October 25, 2024 
 
1.04 
NOTICE OF SERVICE INTERRUPTION  
  
The Contractor shall provide a list to the City and City’s Representative of sewer services 
that may be disrupted due to the rehabilitation operations or potential impact from 
construction activities no less than 72 hours prior to service interruption.   
 
1.05 
24-HOUR TELEPHONE HOTLINE  
  
A. The Contractor shall provide the name(s) and contact phone number of the Contractor’s 
on-site Representative who shall be responsible for replying to resident construction 
concerns, damage claims, resident complaints, etc. during construction activities.  
 
The Contractor shall be responsible for coordination with the CAPA department or 
their Public Outreach Consultant to obtain messages and respond accordingly. The 
Contractor shall provide written response back to the City as to the action undertaken 
for the resolution of the hotline complaint or concern within 24 hours. 
  
B. A log of telephone and/or on-site contacts of residential complaints shall be maintained 
by the Contractor. The Contractor shall immediately communicate to the City and 
City’s Representative any public issues concerning damage to private property, health 
concerns, nuisances and general complaints. The Hotline Log shall contain at the 
minimum the following information:  
  
Date of Communication. 
Time of Communication. 
Name of Person Receiving the Complaint. 
Contact Name. 
Contact Address. 
Contact Return Telephone Number. 
Description of Complaint or Concern. 
Description of Discussions. 
Description of Proposed Resolution. 
  
C. Hotline Log shall be submitted to City’s Representative within 24 hours of each new 
entry. Summary of all telephone contact shall be submitted to the City and City’s 
Representative at the next construction progress meeting.  
 
1.06 
WORK IN EASEMENTS  
  
A. Work may take place in right-of-way of streets and alleys, or in easements through 
private property. Access and working space may be limited in easements. Careful 
attention to access and private property protection is required in easements.   
 
B. Contractor shall NOT attempt to contact the property owner prior to entering an 
easement. City of Glendale personnel shall be responsible to inform the property owner

SECTION 01400 
 
 
PUBLIC AWARENESS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01400 - 3 
October 25, 2024 
of the details of the work. 
  
C. Contractor shall take surface feature pre-construction videos of easement areas or areas 
potentially impacted by construction activities according to Technical Specification 
Section 01380 – PHOTOGRAPHS AND VIDEO RECORDINGS before beginning 
work. The purpose of these videos is to document existing surface features and 
conditions prior to bringing any equipment into the area or performing any work. 
 
1.07  ON-SITE SUPERINTENDENT  
   
The Contractor shall have a Representative familiar with the work on-site during project 
work hours and shall be available to answer questions received from the public on a 24-
hour basis and assist the public with access needs.   
 
 
PART 2 - PRODUCTS  
 
2.01 
PUBLIC NOTIFICATION 
 
Information provided to the general public shall be determined and produced by the City 
or the City’s Public Outreach Consultant.  Project notification will be distributed by the 
City through printed flyer, door hanger, or other electronic and social media platforms.  
 
 
PART 3 - EXECUTION  
(NOT USED) 
 
** END OF SECTION **

SECTION 01400 
PUBLIC AWARENESS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01400 - 4 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[This page intentionally left blank for double sided printing]

SECTION 01550  
CONTRACTORS UTILITIES 
  
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01550 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01 
DESCRIPTION  
  
A. This section specifies the facilities, utilities, and security the Contractor is required to 
furnish and maintain during construction.  
 
B. Copies of any Contract Documents shall be kept at the work site and available for use 
at all times.  
  
PART 2 - PRODUCTS  
  
2.01  POWER  
  
A. Contractor shall use battery, pneumatic, or hydraulic power for all interior sewer pipe 
work. This limitation is not necessary for work on the surface or for sewer pipe 
illumination.  
  
2.02 
LIGHTING AND ILLUMINATION  
  
A. As necessary, the Contractor shall provide low voltage lighting and illumination in the 
sewer pipe interior, in accordance with the guidelines published in Practice for 
Industrial Lighting, ANSI/IES RP-7-2017. Lighting used by the Contractor on the 
surface shall be placed and directed to avoid nuisance to traffic or local residences. 
Light shields may be required to limit light pollution into adjacent residences or 
businesses. 
  
2.03  TELEPHONE  
  
A. Contractor shall provide and maintain telephone service at the construction site and the 
telephone shall be manned by the Contractor or Contractor’s Representative 24 hours 
per day. Contractor or Contractor’s Representative manning the telephone service shall 
be fluent in written and verbal English as well as Spanish languages. Cellular telephone 
service is acceptable as a substitute for telephone service. These telephone and labor 
costs shall be paid by the Contractor.  
  
2.04  WATER  
  
A. All water for testing, flushing, cleaning and construction activities shall be furnished 
and paid for by the Contractor. Water may be available upon request to the City for 
connecting to the City’s water distribution system. Connection may be approved by the 
City with appropriate backflow prevention and metering devices installed by the 
Contractor according to City requirements. Authorization to receive water may be 
rescinded by the City upon written notice to the Contractor at any time and for any 
reason.

SECTION 01550  
CONTRACTORS UTILITIES  
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01550 - 2 
October 25, 2024 
 
The City shall charge the Contractor for water used in performing the above functions 
in accordance with the City’s established rate schedule. At Contractor’s expense, an 
approved water meter and backflow prevention device, meeting the requirements of 
ANSI A40.6, latest revision, shall be installed in each and every connection to the 
City’s water supply. The Contractor shall be required to meter all water used.  
  
2.05  DEBRIS DISPOSAL  
  
A. Contractor shall make provisions for legal, off-site debris disposal. Contractor shall be 
responsible to obtain and submit to the City a written letter of acceptance, signed by an 
authorized representative of the agency and/or authorized party accepting debris.  
Disposal of debris shall not occur until City has reviewed and accepted the disposal 
site. Contractor shall pay all fees and charges for debris disposal. Contractor shall be 
responsible for all permits and fees according to Technical Specification Section 01062 
– PERMITS AND EASEMENTS, subsection 1.02 Permits to be Obtained by the 
Contractor for transport to the disposal site. 
 
B. Contractor shall make provisions for proper disposal of hazardous materials, such as 
asbestos, hazardous chemicals, etc. with appropriate documentation and chain of 
authority for such disposal. 
  
2.06 
BYPASS PUMPS 
 
A. Contractor shall provide and maintain a sanitary sewer bypass pumping system to 
divert flow around the work area according to Technical Specification Section 02145 
– DIVERSION OF SEWAGE FLOW AND DEWATERING. Contractor shall be 
responsible for all operation, maintenance and monitoring of bypass pumping and 
discharge piping system. 
 
PART 3 - EXECUTION  
  
NOT USED  
   
  
  
**END OF SECTION**

SECTION 01560  
ENVIRONMENTAL CONTROLS  
  
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01560 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01 
DESCRIPTION  
  
A. Provide and maintain methods, equipment, and temporary construction, as necessary 
to provide controls over environmental conditions at the construction site and adjacent 
areas.  Remove physical evidence of temporary facilities at completion of work.  
  
1.02 
TRANSPORTATION ROUTES  
  
A. The Contractor shall select its transportation routes for hauling materials, equipment, 
or imported products based on the existing condition of the pipelines and impacts on 
local traffic. Transportation routes shall be documented in a traffic control plan on a 
case by case basis.  
  
1.03 
TRAFFIC CONTROL  
  
A. All streets, traffic ways, and sidewalks shall be kept open in a safe manner for the 
passage of traffic and pedestrians during the construction period unless otherwise 
approved by the City.  
 
B. When required to cross, obstruct or close a street, traffic way, or sidewalk for a short 
duration that is approved by the City, the Contractor shall provide and maintain suitable 
bridges, detours or other approved temporary means for the accommodation of 
vehicular and pedestrian traffic. Closings shall be for the shortest time practical, and 
passage shall be restored immediately after completion of construction.  
 
C. Contractor shall give the City 24 hours advance notice of his proposed operations 
within any public rights-of-way and temporary roadway closings. All proposed 
roadway closings shall be submitted in the Traffic Control Plan and approved prior to 
commencement of operations.   
 
D. Contractor shall provide signs, signals, barricades, flares, lights and all other 
equipment, service and personnel required to regulate and protect all traffic and warn 
of hazards in accordance with MAG specifications. All such work shall conform to 
requirements of the City or authority having jurisdiction. Remove temporary 
equipment and facilities when no longer required and restore grounds to original 
condition.  
 
E. As specified in Technical Specification Section 02100 – TRAFFIC CONTROL, the 
Contractor shall provide a Traffic Control Plan and implement traffic control around 
all work as part of the contract.  
 
F. Qualified and suitably equipped flaggers shall be used to assist all construction 
equipment and vehicle access to and from the construction site.

SECTION 01560 
ENVIRONMENTAL CONTROLS 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01560 - 2 
October 25, 2024 
1.04 
RELEASE OF HOT WATER 
 
A. Contractor shall not release heated water into the sanitary sewer system directly 
upstream of any wastewater reclamation facility. Contractor shall be responsible to 
obtain written authorization from the facility operator receiving the sanitary sewer 
flow. Authorization, if given, shall state the maximum discharge temperature of the 
water. Contractor shall submit Authorization to Release letter to the City according to 
Technical Specification Section 01300 – SUBMITTALS. 
 
B. Contractor shall be responsible to cool process water to a temperature below levels 
required by the facility operator or find alternative hot water disposal methods and/or 
location at no additional cost to the City. 
 
C. Contractor shall be responsible for and pay all damages caused by an unauthorized 
release of heated water into the headworks of the treatment facility. 
 
1.05 
SEWAGE SPILL CONTROL  
  
A. A spill is defined as any uncontrolled release of raw sewage outside of the intended 
sanitary sewer collection system. Raw sewage releases shall not be allowed to occur 
and are not permitted. The Contractor shall be responsible for all consequences and 
damages caused by the overflow, backup, or spill due to the Contractor's work 
activities.  
 
B. Contractor shall give both verbal and written notification to the City immediately in 
the event of any sewage release, overflow, backup, or spill.  
 
C. Contractor shall complete and submit to the City the Confidential Spill Report form 
found in Technical Specification Section 01999 – REFERENCE FORMS within 2 
hours of any spill. 
 
1.06 
EMERGENCY SPILL RESPONSE PLAN  
 
A. The Contractor shall be responsible to develop, submit for approval and follow an 
emergency spill response plan. Plan shall be well communicated to all personnel in the 
event an emergency should occur, it can be handled in the safest and most efficient 
manner possible.  
 
B. The primary responsibility for all Contractor personnel is to respond to sewer spills as 
quickly as possible.  
 
C. Emergency telephone list is part of this procedure and will be kept up-to-date at all 
times.  
 
D. Follow Standard Procedure List.

SECTION 01560 
 
 
ENVIRONMENTAL CONTROLS 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01560 - 3 
October 25, 2024 
E. Fill out attached Confidential Spill Reporting Form.  See Technical Specification 
Section 01999 - REFERENCE FORMS.  
 
F. Contractor shall develop an Emergency Spill Response Phone List containing, but not 
limited to the following: 
 
(name) ____  (Contractors Field Superintendent)  
(___) __ - ____ 
(name) ____  (Engineer’s Field  Representative)   
(___) __ - ____ 
(name) ____  (City’s Construction Project Manager)(___) __ - ____ 
(name) ____  (Engineer's Project Manager)  
(___) __ - ____ 
 
Submit list to City according to Technical Specification Section 01300 – SUBMITTALS.   
 
List shall remain current at all times. Any proposed changes shall be provided to the City 
a minimum of 24 hours in advance of the change or within 1 hour if the change is due to 
an emergency. 
  
1.07 
STANDARD REPORTING PROCEDURES  
  
A. HANDLING EMERGENCIES  
 
1. Medical emergency, fire, or explosion, call 911 immediately.  Do not call 911 to 
report a wastewater spill. 
 
B. OBSERVATION 
 
1. Contractor shall obtain enough information to make an initial assessment of the 
situation without endangering themselves.  
 
C. PROTOCOL FOR NOTIFICATION OF SPILL  
 
1. Contractor’s Field Superintendent:  
Contractor’s field personnel shall verbally notify the Contractor’s Field 
Superintendent. 
Field 
Superintendent 
shall 
promptly 
notify 
City 
Representatives immediately, always less than one (1) hour from the time of 
being made aware of the spill. Document all calls and conversations.  
 
D. REPORT 
 
As soon as possible, but no later than 24 hours following discovery of the spill, the 
Contractor shall complete the Form 01999-C Confidential Spill Reporting, reference 
Technical Specification Section 01999 – REFERENCE FORMS. The Contractor shall 
take photographs at all stages of the incident to include in the report. Submit copies of 
all documentation to City per Technical Specification Section 01300 – SUBMITTALS 
except as herein modified. Spill reports shall be hand carried to the City’s 
Representative as soon as complete.

SECTION 01560 
ENVIRONMENTAL CONTROLS 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01560 - 4 
October 25, 2024 
  
E. SUBMITTAL 
 
The Contractor shall verify that City has received a copy of completed Form 01999-C 
Confidential Spill Reporting and supporting documentation and submitted copy of said 
report to the City’s Representative in a timely manner. Provide all reports and report 
discrepancies to the City’s Representative and retain one (1) copy in the Project File 
located at Contractor’s office.  
 
1.08 
SANITARY SEWAGE SPILL/BACKUP  
  
A. If a sanitary sewage spill/backup occurs into a lateral and a citizen or business sustains 
property damage, the following procedure is to be adhered to:  
  
1. The initial responsibility of the Contractor is to locate and eliminate the cause of 
the backup as soon as possible. As part of cleaning the backup, Contractor crews 
are to determine the cause and source (if possible) of the backup. Contractor will 
obtain an emergency clean-up service and relocate the residents, if necessary, to 
minimize health risks. Contractor shall be responsible for all costs and coordination 
efforts associated with the sewer backup and cleanup including but not limited to:  
 
a. Relocation of residents, businesses, and schools 
b. Temporary housing of displaced residents 
c. Clean-up and sanitizing costs 
d. Replacement of damaged personal items 
e. Relocation of residents back into the residence 
 
 
2. Determine the extent of the property damage (photographs are recommended).  A 
report (Incident Report), with the photos must be provided to the  Contractor’s 
designated Safety Officer. The Safety Officer will forward the information to the 
Contractor’s corporate liability insurance carrier. Information compiled should 
include:  
 
a. Time call was received  
b. Time the crew arrived at the site  
c. Time work was completed 
d. Cause of stoppage/source of backup sewage (if possible) and location of 
stoppage causing the backup 
e. Name of property owner/tenant and address of affected property  
f. Extent of damage  
g. Action taken  
  
3. Contractor-authorized personnel will also assist and pay all costs for obtaining and 
coordinating a sub-contractor to perform restoration work and will work with the 
selected sub-contractor to equitably restore the premises to its pre-loss condition.

SECTION 01560 
 
 
ENVIRONMENTAL CONTROLS 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01560 - 5 
October 25, 2024 
4. The Contractor’s Superintendent shall notify the City of the stoppage in the sanitary 
sewer pipe.  
  
5. Notify City in the event of any spills. 
 
6. The City of Glendale shall notify Arizona Department of Environmental Quality 
(ADEQ) only as it pertains to Arizona State Law Requirements.  
 
1.09 
SURCHARGING  
  
A. Upon notification or discovery that a surcharge condition exists, crews shall respond 
immediately to the area with proper equipment and manpower to reduce the surcharge. 
If, due to limited capacity of the sewers, the surcharge cannot be reduced, any spill 
which occurs shall be properly cleaned. Waste products are to be disposed of in 
accordance with state and federal laws.  
 
Contractor shall be responsible for obtaining City’s known areas or sections of sanitary 
sewer pipes that are subject to surcharging capacity situations. These instructions will 
remain in effect until the problem is resolved. These areas or sections of concern will 
be monitored throughout the bypass or slip lining operations, and in the event of an 
emergency, City shall be notified by the Contractor immediately for response. 
Response of City crews shall not relieve the Contractor for project responsibilities or 
liabilities.  
  
A Confidential Spill Reporting Form must be completed by the Contractor and 
distributed to the required parties according to Section 1.05. Distribution of said 
Confidential Spill Reporting Form must take place, preferably by fax or electronic mail, 
within one (1) day of the occurrence.  
 
PART 2 - PRODUCTS  
(NOT USED)  
 
PART 3 - EXECUTION  
  
3.01  SITE MAINTENANCE  
  
A. Contractor shall keep the work site, staging areas, storage and parking area, 
Contractor's facilities clean and free from rubbish and debris. Materials and equipment 
shall be promptly removed from the site when they are no longer necessary. Upon 
completion of the work and before final acceptance, the work site shall be cleared of 
equipment, unused materials, and rubbish to present a clean and neat appearance in 
conformance with the preconstruction condition of the site.    
 
B. Contractor shall not store equipment or materials anywhere other than locations 
approved by the City. Property surrounding the work site shall be completely free of 
all debris and rubbish at all times.

SECTION 01560 
ENVIRONMENTAL CONTROLS 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01560 - 6 
October 25, 2024 
3.02  CLEAN-UP 
  
A. Waste material of any kind will not be permitted to remain on the site of the work or 
on adjacent streets. Immediately, upon such materials becoming unfit for use in the 
work, they shall be collected, carried off the site and legally disposed of by the 
Contractor. The Contractor shall be responsible for obtaining necessary permits or 
approval for the Contractor's disposal site. 
 
B. The Contractor shall keep all buildings and areas occupied by the Contractor clear of 
all refuse, rubbish and debris that may accumulate from any source and shall keep them 
in a neat condition to the satisfaction of the City.  
 
C. In the event that waste material, refuse, debris and/or rubbish are not so removed from 
the work area by the Contractor, the City reserves the right to have the waste material, 
refuse, debris and/or rubbish removed and the expense of the removal and disposal 
charged to the Contractor. 
 
D. Paints, solvents, and other construction materials shall be handled with care to prevent 
entry of contaminants into storm drains, surface waters, or soils.  
  
3.03.  BARRIERS 
  
A. A barrier shall be provided around all unattended excavations and open structures.  The 
barrier shall enclose the area and prevent unauthorized access.  
  
3.04  STREET CLEANING 
  
A. Contractor shall be responsible for preventing dirt, dust, and sediments from escaping 
from trucks departing the project site, by covering dusty loads, washing truck tires 
before leaving the site, or other reasonable methods. 
 
B. When working trucks and/or other equipment on paved streets and roadways, the 
Contractor will be required to clean said streets as soon as possible, but no later than at 
the conclusion of each day's operations or 24-hour period and at such interim periods 
as required by the City. 
 
C. All streets in the construction area used by Contractor's trucks or any other equipment 
hauling material to and from the area, whether within the Contract limits or adjacent 
thereto, shall be kept clean by the Contractor and shall be continuously serviced by the 
Contractor's use of water trucks to control dust. 
 
D. Cleaning and dust control shall be as specified in MAG Section 104.1.4 “Cleanup and 
Dust Control” and shall be at the Contractor's expense.  
 
E. Any violation of the requirements shall be sufficient grounds for the City to order the 
streets in question cleaned by others and the cost to be paid by the Contractor.

SECTION 01560 
 
 
ENVIRONMENTAL CONTROLS 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01560 - 7 
October 25, 2024 
 
F. No solid materials or soils may be flushed into storm drains or in the sanitary sewers 
or wastewater facilities.  
 
G. Contractor shall use a power pick-up broom as part of the dust control effort.  
  
3.05  AIR POLLUTION CONTROL  
  
A. GENERAL  
  
The Contractor shall not discharge smoke, dust, and other contaminants into the 
atmosphere that violate the regulations of any legally constituted authority. The 
Contractor shall maintain construction vehicles and equipment in good repair. 
Equipment exhaust emissions that are determined to be excessive by the City shall 
cause the equipment to be repaired or replaced.  
  
B. Contractor shall also minimize dust nuisance by cleaning, sweeping, and sprinkling 
with water, or other means. The use of water, in amounts, which result in mud on public 
streets, is not acceptable as a substitute for sweeping or other methods. Equipment for 
this operation shall be on the job site or available at all times.    
 
3.06  ODOR 
  
A. The Contractor shall employ methods and procedures that mitigate the generation and 
discharge of objectionable odors to the surface environment at all times.  
  
3.07  ODOR CONTROL 
  
A. Contractor shall be prepared to add approved chemicals to the wastewater flow 
upstream of bypass pumping or slip lining operations to reduce odor. Costs for 
chemical odor control dosing shall be as negotiated and approved by the City prior to 
use. The Contractor shall make his own determination of flow characteristic for 
required dosing.   
  
The Contractor shall add the chemicals from a location upstream that will allow 10 to 
15 minutes reaction time before the flow enters the work area. The chemical dosing 
shall reduce odors generated from the wastewater stream to a level acceptable to the 
City. If this is not accomplished by adding chemicals only, an additional control may 
be required. 
  
3.08  NOISE CONTROL  
  
A. Contractor shall perform all work in compliance with OSHA standards and in no case 
will noise levels be permitted which would interfere with the work of the City or others. 
Noise levels shall be in accordance with City noise ordinance.

SECTION 01560 
ENVIRONMENTAL CONTROLS 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01560 - 8 
October 25, 2024 
B. If pumping operations and/or power generation occur after normal work hours as stated 
in the Technical Specification Section 02145 – DIVERSION OF SEWAGE FLOWS 
AND DEWATERING, subsection 2.01A. Contractor shall utilize sound attenuated 
bypass pumps with a maximum decibel rating of 70 db at a distance of 50 feet. 
 
C. Each internal combustion engine, used for any purpose on the job or related to the job, 
shall be equipped with a muffler of a type recommended by the manufacturer for 
residential use. No internal combustion engine shall be operated on the project without 
said muffler.  
 
D. Noisy portable equipment, such as generators, pumps, or compressors, shall be located 
as far away from sensitive noise receptor areas as practical. Sensitive noise receptors 
are defined as occupied buildings with windows or doors facing the site. Noise barriers 
shall be constructed around noisy, stationary, construction equipment such as 
compressors, pumps, or generators that have to be utilized at locations near (within 
100 feet of) sensitive noise receptors as defined above.  
 
E. Idling equipment not actively utilized for extended periods of time shall be shut off.  
  
3.09  TREE AND PLANT PROTECTION  
  
A. If a tree or any landscaped vegetation is damaged or destroyed by construction, or any 
action of the Contractor, the Contractor shall replace the damaged tree or plant with a 
healthy one of the same species. The replacement tree or plant shall be of the same size 
as the damaged tree or plant and will be placed at the existing grade. The Contractor 
shall bear all expenses required to clear and grub the damaged tree or plant and to 
establish the replacement tree or plant. The replacement tree or plant shall be installed 
per City Standard Landscaping Specifications and Details and guaranteed healthy for 
1 year after final completion. The Contractor shall be responsible for any tree or plant 
that the Contractor had replaced that is deemed unhealthy during that year.  
 
B. All landscaped areas and other surface improvements which are damaged by actions of 
the Contractor shall be restored to their original condition at the Contractor's expense.  
When the impact is to private property, the property owner shall confirm acceptance to 
original condition 
  
3.10  SURFACE WATER CONTROL  
  
A. Contractor shall conform to the regulations and requirements of legally authorized 
surface water management agencies. The Contractor is responsible to provide and 
maintain any temporary pumping, drainage structures, or other means to manage or 
control nuisance surface water.  
 
B. The Contractor shall be responsible for keeping any open excavations and other areas 
free from water as required to permit continuous progress of, or to prevent damage to, 
its own work or work of others. The Contractor shall cover exposed excavated areas

SECTION 01560 
 
 
ENVIRONMENTAL CONTROLS 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01560 - 9 
October 25, 2024 
and spoil piles when runoff from rain is or would be likely to cause turbid waters to 
enter local waterways. The Contractor shall suspend work in the rain, if such work 
cannot be performed without causing turbid runoff.  
  
3.11  STORM SEWER  
  
A. Contractor shall not discharge any wastewater, potable water used for testing, or 
cleaning, or any chemical or waste materials from the construction operation into the 
storm sewer system.  
  
3.12 
SANITARY SEWER  
  
A. Contractor shall not dispose of chemical or any waste materials from the construction 
operations into the sanitary sewer system.  
  
** END OF SECTION **

SECTION 01560 
ENVIRONMENTAL CONTROLS 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01560 - 10 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[This page intentionally left blank for double sided printing]

SECTION 01700  
RESTORATION OF IMPROVEMENTS  
  
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01700 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01  GENERAL  
  
This section specifies restoration of improvements of the Contractor's work area, staging 
area, storage area, and parking area.  
  
1.02  STRUCTURES  
  
Contractor shall remove such existing structures as may be necessary for the performance 
of the work and shall rebuild the structures thus removed, with the specified requirements, 
in as good a condition as found. The Contractor shall also repair existing structures that 
workers damage as a result of the work under this Project at no additional cost to the City. 
  
1.03 
ROADS AND STREETS  
  
Unless otherwise specified, roads and streets in which the surface is removed, broken, or 
damaged, or in which the ground has caved or settled during or as a result of the work 
under this Project, shall be resurfaced and/or repaved and brought back to the original grade 
and section or City Standard section, whichever is greater, at the Contractor’s expense. The 
Contractor shall document in video the entire road or street area to be used for the work 
and parking area as specified in Technical Specification Section 01380 – PHOTOGRAPHS 
AND VIDEO RECORDINGS. Copies of the DVD or USB storage device shall be 
submitted to the City prior to starting the work. Once construction starts, Contractor 
assumes responsibility for road condition and repair.   
 
Roadways used by the Contractor shall be cleaned and repaired if damaged. Before 
resurfacing and/or repaving material is placed, edges of pavements shall be trimmed back 
far enough to provide clean, solid, vertical faces, and shall be free of loose material. Streets, 
sidewalks, and other City, County, or State-owned facilities impacted by construction 
activities shall be replaced or repaired in accordance with current City and MAG 
requirements.  
  
1.04  CULTIVATED AREAS AND OTHER SURFACE IMPROVEMENTS  
  
A. Cultivated or planted areas, other unpaved areas, and other surface improvements 
which are damaged by actions of the Contractor shall be restored to their original 
condition. In addition to City inspection, the Contractor shall document in video the 
entire area to be used as the work area, staging area, storage area, and parking area as 
specified in Technical Specification Section 01380 – PHOTOGRAPHS AND VIDEO 
RECORDINGS.  
 
B. Contractor shall be responsible for coordination of all irrigation piping and facilities 
located within cultivated areas with appropriate jurisdictional agency. Contractor shall 
protect the work area(s) from uncontrolled irrigation waters that impact the work or

SECTION 01700 
RESTORATION OF IMPROVEMENTS 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01700 - 2 
October 25, 2024 
work area(s).   City will not entertain damage claims as a result of irrigation water. 
 
C. Repair of irrigation facilities damaged by construction activities shall be the 
responsibility of the Contractor.  Irrigation schedules shall be maintained to sustain 
vegetation health.  Any sod, vegetation, or foliage damaged due through insufficient 
water as a result of construction activities shall be replaced in kind and size to the 
satisfaction of the City by the Contractor at no additional cost to the City.   
 
D. Existing guard posts, barricades, and fences shall be protected and replaced if damaged. 
 
1.05  PROTECTION OF EXISTING INSTALLATIONS  
  
A. Contractor shall protect all existing operating facilities and structures from damage. 
However, if damage occurs, the Contractor shall immediately correct or replace 
existing equipment, materials, or systems that are damaged as a result of its operations 
to the satisfaction of the City.  
   
PART 2 - PRODUCTS  
(NOT USED)  
  
 PART 3 - EXECUTION  
  
3.01  RESTORATION ACCEPTANCE  
  
A. The Contractor shall restore the area to existing condition of the Contractor’s work 
area, staging area, storage area, and parking area as documented in the photographs and 
video recordings.  
 
B. The City shall determine if and when restoration of the site is acceptable following on-
site inspection and review of the pre-construction and post-construction recordings as 
specified in Technical Specification Section 01380 – PHOTOGRAPHS AND VIDEO 
RECORDINGS.   
  
   
** END OF SECTION **

SECTION 01999 
REFERENCE FORMS 
______________________________________________________ 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01999 - 1 
October 25, 2024 
PART 1 - GENERAL  
 
1.01 
REQUIRED FORMS  
  
The forms listed below and included in this section are referenced from other Technical 
Specification sections of the contract documents:  
  
Form No.  
Title 
 
 
 
  
01999- A  
Submittal Transmittal  
  
01999- B  
Request for Information  
  
01999- C  
Confidential Spill Reporting  
 
01999- D 
Chain of Custody 
 
1.02 
SCOPE  
  
The Contractor shall be responsible for the documentation forms for tests and evaluations 
required of the contract that do not have specific forms identified.  Contractor generated 
forms shall follow the format established on Form 01999-A Submittal Transmittal 
contained herein.  
  
  
PART 2 - PRODUCTS  
(NOT USED) 
  
  
PART 3 - EXECUTION  
(NOT USED)

SECTION 01999 
REFERENCE FORMS 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01999 - 2 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double sided printing ]

SECTION 01999 
 
 
REFERENCE FORMS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01999 - 3 
October 25, 2024 
 
FORM 01999-A         SUBMITTAL TRANSMITTAL  
 
 
Submittal Description:    
 
 
 
 
               Submittal No:    
       
  
 
 
 
 
 
 
 
 Spec Section:    
 
  
Routing  
Sent  
Received  
OWNER:               
Contractor  
  
  
PROJECT NUMBER AND NAME:  
Engineer  
  
  
  
Contractor  
  
  
CONTRACTOR:  
  
  
  
  
 
  
We are sending you    
Attached    
 
Under separate cover via         
 ˜ Submittals for review and comment  
 ˜ Product data for information only  
 
Remarks:     
 
  
Item  
Copies  
Date  
Section 
No.  
Description  
Review 
action
a 
Reviewer 
initials  
Review comments 
attached  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
 
aNote:  NET = No exceptions taken; MCN = Make corrections noted; A&R = Amend and resubmit; R = Rejected  
Attach additional sheets if necessary.  
  
Contractor:  Certify either A or B:  
  
 A. We have verified that the material or equipment contained in this submittal meets all the requirements, including 
coordination with all related work specified (no exceptions).  
  
 B. We have verified that the material or equipment contained in this submittal meets all the requirements specified 
except for the attached deviations.  
No. 
  
Deviation 
  
  
                
  
  
                
  
  
               
  
  
  
  
 
Certified by:  ______________________________________________________________  
 Contractor's Signature

SECTION 01999 
REFERENCE FORMS 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01999 - 4 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double sided printing ]

SECTION 01999 
 
 
REFERENCE FORMS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01999 - 5 
October 25, 2024 
 
FORM 01999-B       REQUEST FOR INFORMATION  
  
RFI NO.     
 
 
 
OWNER:  
___________________  
ROUTING  
  
SENT  
  
RECEIVED  
PROJECT 
NAME:  
 
  
_________________ 
  
Contractor  
 
 
________              _______________ 
PROJECT 
NUMBER: 
 
 
City 
Representative 
 
 
 
 
 
CONTRACTOR 
  
 
 
 
 
  
  
  
  
 
 
 
 
RFI TITLE:  
  
  
  
    
  
  
  
  
  
  
  
  
REFERENCES:  
DRAWING NO:  
  
LOCATION:  
  
  
SPEC. SECTION:  
  
    PAGE:    
  
OTHERS:  
  
  
  
  
  
  
  
    
  
  
The following information is requested as described below or in the attachments:  
  
  
  
  
  
  
  
  
By:  
  
  
  
  
  
Date:    
  
 
The following information is provided as described below or in the attachments:  
  
  
  
  
  
  
  
  
 
By:  
  
 
Date:

SECTION 01999 
REFERENCE FORMS 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01999 - 6 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double sided printing ]

SECTION 01999 
 
 
REFERENCE FORMS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01999 - 7 
October 25, 2024 
FORM 01999-C   CONFIDENTIAL SPILL REPORTING  
  
  
INSTRUCTIONS:  The Contractor shall ensure that appropriate on-site personnel complete 
this form.  The form shall be completed immediately upon discovery of a sanitary sewer spill 
or release by the individual who first made the discovery.  
 
  
First at the Scene (name):  
  
1. Facility name and address/location/intersection (or major cross streets): 
 
 _____________________________________________________________________________ 
   
2. Is/was there a fire or explosion or other release (except for sewage release) outside the facility?    
 
      Yes           No   
 
If yes, immediately contact the Fire Department (911) for assistance, initiate appropriate 
facility response procedures, and then continue with this form.  
  
3. Personal injuries and extent, if any: _______________________________________________ 
 
  
4. Date and time of initial call or complaint:___________________________________________ 
 
  
5. Date and time of spill found or confirmed:__________________________________________ 
 
  
6. Date spill reporting completed:___________________________________________________ 
 
  
7. Date and time spill occurred or started, if known:_____________________________________  
 
  
8. What was spilled?  Describe completely.  List chemical names/wastewater if known.  
 
______________________________________________________________________________ 
  
 9. How much was spilled?  Use units such as gallons or pounds, etc._______________________ 
  
10. Where and how did the spill occur?  Include a description of the container or vessel from which 
the spill occurred.  Attach diagram or map, if available.  
 
______________________________________________________________________________

SECTION 01999 
REFERENCE FORMS 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01999 - 8 
October 25, 2024 
  
11. Where did the spilled material go?  Check all that apply.  
  
 drywell  
 dry wash  
 canal  
 riverbed  
 private property  
retention basin  
 sanitary sewer  
secondary 
containment  
 storm  drain  
city street  
Air (vapors or 
odors)  
other (specify 
below)  
______________________________________________________________________ 
______________________________________________________________________ 
______________________________________________________________________ 
______________________________________________________________________ 
______________________________________________________________________ 
 
12. How far did the spill travel?  Describe the path the spill took to its final destination.   
 
______________________________________________________________________________  
 
13. Was the spill stopped or contained?  Describe how and by whom.  
 
______________________________________________________________________________ 
  
14. How long did the spill last? _____________________________________________________ 
  
 
15. Who found the spill?  Use the back of this form if necessary.  
  
Name_________________ Title_____________________ Phone________________  
  
a. ____________________        _____________________           ________________ 
 
b.____________________         _____________________           ________________  
 
 
16. Who was notified of the spill?  List names and identify how notification was made (phone call, 
fax, etc.  Use the back of this form if necessary).  
 
Name Department/Division/Agency       Date/Time Notified   Method of Notification  
 
a.___________________________        _______________     ___________________  
  
b.___________________________        _______________     ___________________

SECTION 01999 
 
 
REFERENCE FORMS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01999 - 9 
October 25, 2024 
Printed name and signature of person who completed this form:  
  
 
 
Printed Name_______________________Title___________________Phone__________ 
 
 
 
Signature_____________________________                      Date____________________

SECTION 01999 
REFERENCE FORMS 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01999 - 10 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double sided printing ]

SECTION 01999 
 
 
REFERENCE FORMS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01999 - 11 
October 25, 2024 
FORM 01999-D      CHAIN OF CUSTODY 
 
PROJECT NUMBER AND NAME: 
CITY: 
 
 
 
 
 
 
OWNERS REPRESENTATIVE: 
 
COMPANY NAME: 
ADDRESS 
 
 
CONTACT PHONE NUMBER: 
CONTACT NAME: 
 
 
CONTRACTOR: 
 
COMPANY NAME: 
 
ADDRESS 
 
 
 
CONTACT PHONE NUMBER: 
 
CONTACT NAME: 
 
 
TESTING LABORATORY: 
 
LAB  NAME: 
 
ADDRESS 
 
 
 
CONTACT PHONE NUMBER: 
 
FAX NUMBER 
 
CONTACT NAME: 
 
 
 
 
Pipe Segment No. 
 
Date Sample Taken: 
 
 
Pipe Diameter 
 
Sample Number: 
 
 
Liner Design Thickness: 
 
Quarter Section No. 
 
 
Resign Type: 
 
Upstream Manhole No. 
 
 
Downstream Manhole No. 
 
 
SAMPLE TAKEN BY: 
SIGNATURE: 
 
 
DATE 
 
PRINT NAME: 
 
ENGINEER, RECEIVED BY: 
SIGNATURE: 
 
 
DATE 
 
PRINT NAME: 
 
LABORATORY RECIEVED BY: 
SIGNATURE: 
 
 
DATE 
 
PRINT NAME: 
 
TEST RESULTS, RECEIVED BY: 
SIGNATURE: 
 
 
DATE 
 
PRINT NAME: 
 
** END OF SECTION **

SECTION 01999 
REFERENCE FORMS 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 01999 - 12 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double sided printing ]

SECTION 02100  
TRAFFIC CONTROL  
 
  
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02100 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01  DESCRIPTION  
  
Traffic control during construction shall be provided in accordance with the requirements 
of the 2015 City of Glendale Engineering Design and Construction Standards, MAG 
Uniform Standard Specifications for Public Works Construction Section 401 - Traffic 
Control, and the Manual on Uniform Traffic Control Devices (MUTCD) (latest edition).  
  
1.02  TRAFFIC REGULATIONS  
  
A. A traffic control plan (TCP) must be submitted for review and approval by the City 
for arterial, collector, and local streets impacted by construction operations.   
 
B. A traffic control plan (TCP) must be submitted for review and approval by the Arizona 
Department of Transportation (ADOT) for areas within ADOT right-of-way impacted 
by construction operations.   
 
C. All traffic and/or traffic control devices on this project shall be provided, maintained 
and/or controlled as specified section 1.01. 
  
D. Traffic/Pedestrian control shall comply with the requirements of Section 1.01, or any 
special conditions required by the City. 
 
E. The submitter/designer of the TCP shall be IMSA or ATSSA certified.   
 
F. Permission to restrict City streets, sidewalks and alleys (street closure permits) shall 
be requested as specified in Chapter 24, Article III of the City of Glendale Code of 
Ordinances. 
  
G. All traffic on this project shall be regulated as specified in Chapter 24, Article III of 
the City of Glendale Code of Ordinances. 
  
H. No deviation to the “Special Traffic Regulations” will be allowed or implemented 
unless submitted to the City for review and approval two (2) weeks prior to proposed 
work. 
 
I. 
Variable Message Boards (VMB) are required per City requirements. 
 
J. 
Law enforcement officers may be required within 300 feet of a signalized intersection.  
Officers may be required for non-signalized construction areas at the discretion of the 
City. 
 
K. A minimum of three (3) working days, (72 hours), advance notice is required for TCP

SECTION 02100 
TRAFFIC CONTROL 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02100 - 2 
October 25, 2024 
review prior to construction starting. Additional time may be required for review and 
approval and shall be determined during the pre-construction meeting. 
 
1.03  TRAFFIC CONTROL / ACCESS   
 
A. Contractor shall be responsible to present traffic control plans at the regularly 
scheduled construction progress meeting for review as outlined in Technical 
Specification Section 01014 – Work Sequence, subsection 1.04.C. Uninterrupted 
access to commercial businesses and residences shall be maintained at all times. 
Contractor shall be responsible to adjust work schedule to minimize disruption to 
normal operation of businesses.  
 
B. Contractor shall be responsible to coordinate traffic control plans and inform the 
project’s public relations representative of any potential impacts to commercial 
businesses or residents. Contractor shall adjust work activities and schedules to 
minimize disruptions to the City, residents, and traveling public. City reserves the right 
to request the Contractor move his operations or modify work plans and schedules to 
minimize disruptions to commercial business or residents at no cost to the City.  
 
1.04  TRAFFIC CONTROL PLAN DISTRIBUTION  
 
A. Copy of approved TCP’s shall be submitted to the City and City’s Representative prior 
to start of work.  
 
B. Copy of approved TCP shall be on-site and available for review at all times work 
activities are commencing. Failure to have approved TPC on-site while work is 
commencing will be grounds for rejection and non-payment of work being performed.  
  
PART 2 - PRODUCTS  
(NOT USED)  
  
PART 3 - EXECUTION  
(NOT USED) 
 
** END OF SECTION **

SECTION 02145 
DIVERSION OF SEWAGE FLOW  
AND DEWATERING 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02145 - 1 
October 25, 2024 
PART 1 – GENERAL 
 
1.01 
DESCRIPTION 
 
A. SCOPE: 
 
This Technical Specification Section describes requirements for temporary bypassing 
and dewatering of sewers during sanitary sewer pipe and access manhole rehabilitation, 
if required.  
 
B. REQUIREMENTS: 
 
1. Contractor shall provide all coordination, labor, materials, equipment and 
supervision to temporarily bypass flow around the Contractor’s work in accordance 
with the Contractor’s specific needs of the rehabilitation method being utilized and 
dewater the pipelines in preparation for cleaning and rehabilitation.   
 
2. The actual design of the bypass system shall be the responsibility of the Contractor 
and shall be submitted to the City and City’s Representative to review for general 
conformance to project objectives. Means and methods of accomplishing the 
bypassing shall be the responsibility of the Contractor. 
 
3. Contractor shall use fused High-Density Polyethylene (HDPE) piping to convey 
flow around the project area. The use of quick connect pipe collars is not an 
approved material or method for use in the City.  
 
4. The Contractor shall have the entire bypassing system in place and successfully 
pressure tested with potable water at a minimum of 1.5 times the maximum 
operating pressure of the system before bypassing any sewage. 
 
5. The Contractor shall notify the City 48 hours prior to shutting down or bypassing 
any pipeline. The bypass system equipment and existing flows shall be 
continuously monitored. 
 
6. It is the Contractor’s responsibility to arrange all necessary access and temporary 
construction agreements with all affected parties for the Contractor’s proposed 
location of the bypass pumping system. 
 
7. Contractor is responsible for immediate and proper cleanup as per Technical 
Specification Section 01560 – ENVIRONMENTAL CONTROLS should any 
sewage spill occur. Regardless of amount, the Contractor shall pay for all damages 
and fines incurred as a result of a spill.

SECTION 02145 
DIVERSION OF SEWAGE FLOW  
AND DEWATERING 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02145 - 2 
October 25, 2024 
 
C. EXPERIENCE: 
 
Contractor shall utilize staff and/or a subcontractor that has been directly responsible 
for completion of a rehabilitation project that required the bypass pumping of sewage 
flows in excess of 1.0 mgd. 
 
1.02 
SUBMITTALS 
 
A. At the pre-construction meeting the Contractor shall submit, in accordance with 
Technical Specification Section 01300 - SUBMITTALS, drawings and complete 
design data showing methods and equipment the Contractor proposes to utilize in sewer 
bypassing for review by the City. The submittal shall include the following 
information: 
 
1. Drawings indicating the scheme and location of temporary sewer plugs and bypass 
discharge pipes. The drawings shall also show the method and location for 
suctioning and discharging the bypass pipes. 
 
2. Capacities of pumps, prime movers, and standby equipment at Net Positive Suction 
Head (NPSH) with pumps at existing ground surface or proposed depressed pump 
elevation. 
 
3. Design calculations verifying adequacy of the capacity of the pumping system and 
selected equipment, The Contractor shall have a professional civil engineer, 
registered in the State of Arizona, design and professionally seal bypassing 
pumping plan and calculations. 
 
4. Standby power source. 
 
5. Staffing plan. 
 
1.03 
EMERGENCY PLAN 
 
A. Diversion of sewage into adjacent sewers (if applicable or proposed) 
 
1. Drawings and/or design calculations verifying available flow capacity of sewer 
receiving the bypassed sewage.  
 
2. CCTV showing the structural and internal condition of the sewer receiving the bypassed 
sewage.

SECTION 02145 
DIVERSION OF SEWAGE FLOW  
 
 
AND DEWATERING 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02145 - 3 
October 25, 2024 
1.04 
JOB CONDITIONS 
 
A. AVAILABLE FLOW DATA: 
 
There is no current flow data available. The Contractor shall be responsible for any/all 
monitoring of flows as necessary to properly size the bypass system to ensure against 
sanitary sewer overflows (SSO) of upstream sewers.  
 
B. PROTECTION: 
 
No bypassing to the ground surface, receiving waters, storm drains, or bypassing 
which results in soil or groundwater contamination or any potential health hazards 
shall be permitted. 
 
C. SCHEDULING: 
 
The bypassing system shall operate continuously and shall not be shut down between 
shifts, on holidays or weekends, or during work stoppages without written permission 
from the City. The bypass system shall have attendants monitoring 24-hours a day 
whose only duty is to maintain the bypass pumping system until the bypassing of that 
specific pipeline is no longer required. 
 
D. SERVICE LATERALS: 
 
Sanitary sewers to be bypassed may have service laterals connected to adjacent users. 
The Contractor shall verify the locations of these laterals and any other service laterals 
not shown on the Drawings.  
 
PART 2 – PRODUCTS 
 
2.01 
MATERIALS 
 
A. Contractor shall provide temporary pumps, conduits, and other equipment to bypass 
sewer flow around the Contractor’s work area as required during CCTV inspection, 
cleaning, and rehabilitation activities. Contractor shall furnish all necessary labor and 
supervision to set up, operate and remove the pumping and bypass piping system. 
Sound attenuated pumps shall be provided for the bypass pumping. The sound 
attenuated pumps and/or power generators shall be capable of achieving an operating 
noise level of 70 decibels or less, measured at a distance of 50 feet. Contractor shall be 
responsible to provide and install sound attenuation devices, methods, and/or systems 
to maintain noise levels below stated decibels. Sound measurements shall be made and 
recorded by the Contractor in accordance with ANSI/ASA S12.50-2002. Pumps and 
bypass pipes shall be of adequate capacity and size to handle the required capacity.  
 
1. Pumping: Contractor shall provide adequate size pump(s) to accommodate 150 
percent of the maximum instantaneous flow. The Contractor shall determine the 
required flow capacity.

SECTION 02145 
DIVERSION OF SEWAGE FLOW  
AND DEWATERING 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02145 - 4 
October 25, 2024 
 
2. Contractor shall provide 100 percent redundant bypass pumping capability when 
only one pump is required to accommodate the flow. When multiple pumps are 
required to accommodate the bypass flows, the Contractor shall provide a 
minimum of 50 percent additional number of pumps. 
 
3. Contractor shall provide fused (HDPE) piping to convey flow around the project 
area. HDPE pipe shall be used outside of spill containment area.  
 
4. Contractor shall provide a full-time operator/inspector with full responsibility for 
the bypass pumping operation. 
 
5. In no case shall the Contractor allow any sewage to surcharge and backup into 
homes or businesses, or in any way overflow into the environment. If the bypass 
pumping capacity is insufficient to prevent surcharge and/or overflow at any time, 
the Contractor shall pull the line plugs irrespective of the status of the application 
or rehabilitation process. 
 
B. Contractor shall maintain on site, sufficient equipment and materials to ensure 
continuous and successful operation of the bypass and dewatering systems. The 
standby equipment shall be installed, fueled/powered and fully operational at all times 
including all pumps, support equipment being in-place. The Contractor shall maintain 
on site a sufficient number of valves, tees, elbows, connections, tools, sewer plugs, 
piping, and other parts or system hardware to ensure immediate repair or modification 
of any part of the system as necessary. 
 
C. All pumps, generators and other fueled equipment shall be placed in a containment 
barrier to protect against gasoline, oil, and hydraulic fluid spills. 
 
PART 3 - EXECUTION  
  
3.01 
PROTECTION  
  
In areas where flows are bypassed, all bypass flow shall be discharged as described above 
or approved by the City or City’s Representative. No bypassing to the ground surface, 
receiving waters, storm drains, or bypassing which results in groundwater contamination 
or potential health hazards shall be permitted.  
 
3.02 
DAMAGES  
  
The Contractor shall repair, without cost to the City, any damage that may result from his 
negligence, inadequate or improper installation, maintenance and operation of bypassing 
system, including mechanical or electrical failures.  
 
 
** END OF SECTION **

SECTION 02148 
CIPP LINING OF EXISTING SEWERS 
______________________________________________________  
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01 
DESCRIPTION  
  
A. SCOPE 
  
This Technical Specification Section specifies the Cured-In-Place-Pipe (CIPP) 
rehabilitation lining, sets acceptable material and experience parameters, defines 
minimum performance requirements for the finished, installed product and details 
testing requirements for the completed product. 
 
B. REQUIREMENTS 
  
The Contractor shall provide and install a resin impregnated flexible tube (liner) with 
an interior plastic coating wearing surface into pipes identified for CIPP lining in 
accordance with American Society for Testing and Materials ASTM F1216 for the 
inversion installation method or ASTM F1743 for the pulled-in-place installation 
method, or ASTM F2019 for pulled-in-place (Glass Reinforced Plastic – liner) with 
resin cured by exposure to heated water, steam or UV light.  When cured, the CIPP 
lining shall be continuous and tight fitting. 
 
1.02 
CLIMATIC CONDITIONS 
 
The Contractor is made aware that the Work may occur during the summer months with 
temperatures exceeding 115 degrees F. The Contractor shall be prepared for these 
conditions and alter installation procedures or provide protection from detrimental 
exposure to adverse temperature or sunlight consistent with the materials proposed for use.  
 
Severe thunderstorms could occur that may increase volume of flow present within the 
sewer system.  The Contractor shall be prepared for these conditions and alter his 
installation procedures and/or provide bypass pumping capabilities accordingly. 
Contractor shall be responsible for review of the weather forecast prior to commencement 
of liner installation that restricts or impedes the flow capacity of sewer pipe being 
rehabilitated. When the anticipated weather conditions are such that the resulting sewer 
flow may exceed upstream sanitary system storage volume or the capacity of the bypass 
pumping system or otherwise adversely affect the liner installation then the City’s 
Representative shall be informed and the installation shall be delayed until favorable 
weather is forecast. 
 
1.03 
EXPERIENCE RECORD OF THE CONTRACTOR 
 
The Contractor shall provide to the satisfaction of the City, written documentation from 
the CIPP lining manufacturer that the Contractor’s personnel have been adequately 
informed and trained in the installation procedures of CIPP liner process proposed.  Such

SECTION 02148 
CIPP LINING OF EXISTING SEWERS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 2 
October 25, 2024 
written documentation shall describe manufacturer’s procedures for installers, training 
program and, if applicable, licensing policies.  
 
The Contractor shall have an experienced representative on-site that has been responsible 
for the successful installation of a minimum of 5,000 linear feet of CIPP liner installation 
of similar diameter in the United States utilizing the installation materials and techniques 
proposed. 
 
1.04 
REFERENCES  
  
This Technical Specification Section contains references to the following documents.  
They are a part of this section as specified and modified.  In case of conflict between the 
requirements of this section and those of the listed documents, the requirements of this 
section shall prevail.  
 
AASHTO Loading  
American Association of State Highway and 
Transportation Officials - Anticipated external 
load to be placed on the pipe. 
 
ASTM F412 
Definitions of Terms Relating to Plastic Piping 
Systems. 
 
ASTM F1216 
(including Appendix 
XI) 
Standard practice for rehabilitation of existing 
pipelines and conduits by the inversion and 
curing of a resin-impregnated tube. 
 
ASTM F1743 
 
 
 
 
 
 
ASTM F2019 
Standard Practice for Rehabilitation of Existing 
Pipelines and Conduits by Pulled-in-Place 
Installation of Cured-in-Place Thermosetting 
Resin Pipe (CIPP). 
 
Standard Practice for Rehabilitation of Existing 
Pipelines and Conduits by the Pulled in Place 
Installation of Glass Reinforced Plastic (GRP) 
Cured-in-Place 
Thermosetting 
Resin 
Pipe 
(CIPP) 
 
ASTM C581 
Standard Practice for Determining Chemical 
Resistance of thermosetting resins used in glass 
fiber reinforced structures, intended for liquid 
service.

SECTION 02148 
 
 
CIPP LINING OF EXISTING SEWERS 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 3 
October 25, 2024 
 
ASTM D543 
Test Method for resistance of plastics to 
chemical reagents. 
 
ASTM D578 
Standard Specification for Glass Fiber Strand 
ASTM D790 
Test Method(s) for flexural properties of 
unreinforced 
and 
reinforced 
plastics 
and 
electrical insulating materials. 
 
ASTM D883 
Definitions and Terms Relating to Plastics. 
 
ASTM D1600 
Abbreviations, Acronyms, and Codes for Terms 
Relating to Plastics. 
 
ASTM D2990 
Standard 
Test 
Methods 
for 
Tensile, 
Compressive, and Flexural Creep and Creep-
Rupture of Plastics. 
 
ASTM D 1682 
Test Method for Breaking Load and Elongation 
of Textile Fabrics. 
 
ASTM D1784 
 
 
 
ASTM D 5813 
Standard Specification for Rigid Poly (Vinyl 
Chloride) (PVC) Compounds and Chlorinated 
Poly (Vinyl Chloride) (CPVC) Compounds 
 
Specification for Cured-in-Place Thermosetting 
Resin Sewer Pipe APS Standard – Water 
tightness standard for cured-in-place thermo-
setting resin pipe Porosity Test protocol. 
 
ASTM  D3039 / 
D3039M 
Test Method for Tensile Properties of Polymer 
Matrix Composite Material 
 
ASTM D 3567 
Practice for Determining Dimensions of 
Reinforced Thermosetting Resin Pipe (RTRP) 
and Fittings 
 
ASTM E797 
Practice for Measuring Thickness by Manual 
Ultrasonic Pulse-Echo Contact Method. 
 
NASSCO Standard 
Recommended 
Specifications 
for 
Sewer 
Collection System Rehabilitation. 
1.05 
SUBMITTALS

SECTION 02148 
CIPP LINING OF EXISTING SEWERS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 4 
October 25, 2024 
  
The following submittals shall be provided in accordance with Technical Specification 
Section 01300 – SUBMITTALS:  
  
1. Shop drawings which detail short and long term properties (providing all supporting 
test data) of all component materials, construction and recommendations for material 
storage, sunlight control (if applicable), temperature control (if applicable), and CIPP 
liner handling constraints. 
 
2. Representative cured liner sample (1-foot in length) for each diameter size of the same 
resin and felt/fiberglass liner proposed for the project depicting all material 
components, depicting the final quality of workmanship that can be expected on this 
project. 
 
3. Structural calculations of each CIPP diameter size that is proposed for use in pipes up 
to a bury depth of 15-feet using parameters stated in paragraph 2.04 along with 
calculations for each individual liner in the project with a bury depth greater than 15-
feet. CIPP liner calculations shall be stamped by a Professional Engineer in the State 
of Arizona. 
 
4. 10,000-hour third party, 50-year Flexural Creep Modulus test data.  Test shall be in 
accordance with ASTM D-2990 at 10,000 hours.  If approved 10,000 hour tests are not 
available, Contractor shall use a minimum 50% reduction (50% retention) of Flexural 
Modulus of Elasticity (per ASTM F1216, ASTM F1743, ASTM F2019, ASTM F1867) 
for all design calculations.  
 
5. Independent laboratory test reports of CIPP sample(s) and tests as specified in 
Technical Specification Section 02148 , paragraph 1.06 (A). 
 
6. Remote visual inspection video and reports as specified in Technical Specification 
Section 02148 , paragraph 3.01 (C), 
  
7. Liner manufacturer’s recommended installation procedures per ASTM F1216, ASTM 
F1743 or ASTM F2019, or ASTM F1867, Recommendations for material storage, 
temperature and sunlight control, CIPP liner handling, insertion, curing, trimming and 
finishing.   
 
8. CIPP liner manufacturer’s recommended maximum pulling force that can be applied 
to the liner (if winched-in method employed) and/or maximum inflation pressure (if 
inversion method, UV cure method, or PVC pipe installation method is employed). 
 
9. CIPP liner manufacturer’s proposed rate of cure temperature change (heating and 
cooling) and the target temperature and duration for cure of resin along with the 
maximum rate and target temperature for cool down prior to the termination of the cure 
process. 
10. CIPP liner manufacturer’s proposed exposure time to ultraviolet (UV) light and

SECTION 02148 
 
 
CIPP LINING OF EXISTING SEWERS 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 5 
October 25, 2024 
recommended travel speed of UV light train for wattage of light bulbs used (if 
applicable to material(s) proposed). 
 
11. Certification obtained within the previous six (6) months of the Contractor UV Light 
bulbs wattage output (if applicable to material(s) proposed).  
 
12. Certification showing the Contractor is currently licensed by the appropriate licensor 
to perform CIPP installation.  Certification shall be given to the City’s Representative 
before any materials are delivered to the job site.  
 
13. A certified affidavit, signed by an officer of the installation Company, shall be provided 
stating that the on-site superintendent has received proper training in the 
manufacturer’s recommendations for CIPP liner installation methods and procedures. 
  
14. Certification stating CIPP tube has been manufactured in accordance with ASTM 
F1216, ASTM F2019, ASTM F1871, ASTM F1867, ASTM D1784 and resin ASTM 
D5813 is suitable for its intended use.  
 
15. Test results for chemical resistance performed on a previously prepared sample of the 
finished product proposed for this project.  Contractor shall submit a certified affidavit, 
signed by an officer of the company, stating that the resin the tests apply to and the 
resin submitted for this project are the same.  
 
16. Contractor shall submit method of measuring defects and an outline of specific repair 
or replacement procedures as recommended by the tube manufacturer for potential 
defects removal that may occur in the installed CIPP.  Potential defects within the CIPP 
that cannot be repaired shall be clearly defined by the Contractor based on the 
manufacture’s recommendations, accompanied by a proposal for compensation to the 
City.  
  
17. Manhole connection (liner termination) detail and material proposed to seal any annular 
space between the liner and host pipe. 
 
18. Warranty information and certificates. 
 
19. Material safety data sheets for all hazardous chemicals used or expected to be on-site.  
At a minimum, sheets for the resin, catalyst, cleaners and repair agents should be 
submitted.  
 
20. Proposed equipment and fiber optic cable for monitoring the CIPP liner wall 
temperature during cure along the entire length being installed.  
 
 
 
1.06 
CIPP LINER QUALITY ASSURANCE

SECTION 02148 
CIPP LINING OF EXISTING SEWERS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 6 
October 25, 2024 
  
A. LABORATORY TEST SAMPLE: 
  
1. Sample should be cut from a section of cured CIPP at an intermediate manhole or 
at the termination point that has been inverted through a similar diameter pipe or 
other restraining system which will be held in place by a suitable heat sink, such as 
sandbags per ASTM F1216 or ASTM F1743 or ASTM F2019. 
 
2. CIPP liner samples taken shall be sent to an independent laboratory within three (3) 
days of collection for quality control testing.  Samples are to be signed by the City’s 
Representative and accompanied by a completed Chain of Custody form, included 
in Technical Specification Section 01999 -REFERENCE FORMS – FORM 01331-
D.  Results of laboratory testing shall be submitted directly to the City’s 
Representative within three (3) working days of receipt by the Contractor. 
 
3. Samples taken for testing shall be individually labeled and logged to record the 
following: 
 
a. City name. 
b. City’s project number and project title. 
c. Unique sample number. 
d. Pipe segment number as noted on Design Drawings or Pipe Rehabilitation List. 
e. Date and time sample was taken. 
f. Name of Contractor. 
g. Date, location and name of person by whom the sample was taken. 
 
Updated copies of the test log shall be submitted to the City Representative at the 
regularly scheduled construction progress meeting.  
 
4. SAMPLE TESTING.  The cured sample shall be tested by an independent testing 
laboratory approved by the City’s Representative.  Final payment will not be 
made until acceptable test results are received by the City’s Representative.  The 
Contractor shall be responsible for any deviation from the specified physical 
properties and those evaluated through testing.  Failure to meet the specified 
physical properties will result in the CIPP liner being considered defective work 
which will be handled in accordance with MAG Section 106.  The Contractor 
shall be responsible for all costs associated with the testing of the liner physical 
properties and repair of any defective work.  
 
5. SAMPLING FREQUENCY:  The above-stated sampling shall be performed for 
each manufacturing lot of CIPP liner materials (per diameter size).  A sample shall 
be taken every 3,000 lineal feet or one semi-trailer load of liner whichever is less. 
City’s Representative reserves the right to request the Contractor to perform one 
(1) additional test for every 3,000 lineal feet or one semi-trailer load of liner 
whichever is less.  
6. Grounds for rejection of installed CIPP liner include, but not limited to the

SECTION 02148 
 
 
CIPP LINING OF EXISTING SEWERS 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 7 
October 25, 2024 
following: 
 
a. CIPP sample sent to laboratory that is missing City’s Representative signature. 
 
b. CIPP samples missing the Chain of Custody form. 
 
c. Chain of Custody form missing information or signatures of all those who 
handled or processed the sample, including the signature of the City’s 
Representative and the laboratory Manager responsible for performing the 
quality control testing. 
 
d. Laboratory test results not meeting minimum Technical Specification 
requirements. 
 
B. LABELING  
  
Each liner tube shall be labeled by the liner manufacturer with a permanent unique 
identification number that is referenced in accompanying documentation.  
Documentation shall include the following: 
 
1. Liner manufacturer’s name, 
2. Location of the liner manufacturer,  
3. Felt supplier, 
4. Resin supplier, 
5. Date of resin impregnation into felt liner, 
6. Unique identification number of liner, 
7. Resin identification number,  
8. Resin weight – lbs/ft,  
9. Manufactured liner length both resin impregnated felt “wet” and dry felt “dry” 
10. Liner thickness,  
11. Liner diameter.  
  
1.07 
WARRANTY  
  
The work performed under this Project shall be warranted to be free from defects in 
material and workmanship for a period of two (2) years from the date of Final Acceptance.  
The City’s Representative, while not acting as quality control agent for the Contractor, 
shall be allowed to view and document any portion of this contract, including but not 
limited to verifying type and quantities of resin used at any point during this work. If the 
City’s Representative determines that the process/material/installation has failed during the 
warranty period, the Contractor shall perform any and all repairs, including ancillary costs 
associated with repair at no additional cost to the City. 
 
The warranty period of any part of the Work repaired or replaced under the provisions of 
the warranty will be extended for one (1) additional year. 
 PART 2 - PRODUCTS

SECTION 02148 
CIPP LINING OF EXISTING SEWERS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 8 
October 25, 2024 
  
2.01 
GENERAL  
  
A. All materials and installation procedures provided by the Contractor for use in the CIPP 
installation process shall be equal to or exceed the requirements of ASTM F1216, 
ASTM F1743 and ASTM F2019 and ASTM D2990. 
  
B. Contractor shall be responsible for control of all material and process variables to 
provide a finished CIPP possessing the minimum properties specified in ASTM F1216 
and ASTM 5813 and/or supplemented herein.  
 
2.02 
COMPONENT PROPERTIES  
 
A.  MATERIAL 
 
a. FELT LINER  
The liner tube shall consist of one or more layers of flexible needled felt or an 
equivalent non-woven and/or woven material meeting ASTM 1216 Section 5 or 
ASTM F1743 Section 5.2.1 and capable of carrying resin, withstanding installation 
pressures and curing temperatures, and is compatible with the resin system used.   
 
a. FIBERGLASS LINER  
The liner tube shall consist of one or more layers of flexible fiberglass or an 
equivalent woven material meeting ASTM D2990 and ASTM D5813 and capable 
of carrying resin, withstanding installation pressures and curing temperatures and 
is compatible with the resin system used.   
 
The fiberglass liner shall include an exterior and interior film that protects and 
contains the resin used in the liner.  The exterior film shall be provided with an 
ultraviolet (UV) light blocker foil. 
 
B. RESIN  
 
The resin system to be used shall be manufactured by an approved company selected 
by the CIPP process manufacturer.  Only corrosion resistant polyester or vinyl ester 
resins shall be used. 
 
The resin used shall produce a properly cured-in-place pipe system, which will be 
resistant to abrasion caused by solids, grit, and/or sand.  The cured-in-place pipe system 
shall also be resistant to corrosion due to acids and gases such as sulfuric acid, carbonic 
acid, hydrogen sulfide, methane, and carbon monoxide.  The cured-in-place pipe 
system utilized shall withstand the corrosive effect of the existing residential, 
commercial, and industrial effluents, liquids and/or gases. 
 
The chemical corrosion resistance of the actual resin system used by the Contractor 
shall be tested by the resin manufacturer in accordance with ASTM F1216, D543, or

SECTION 02148 
 
 
CIPP LINING OF EXISTING SEWERS 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 9 
October 25, 2024 
C581 as applicable.  Exposure to the chemical solutions listed below shall result in a 
loss of not more than twenty percent (20%) of the initial physical properties when tested 
in accordance with ASTM C581. 
 
C.  CHEMICAL RESISTANCE  
  
The chemical resistance tests should be completed in accordance with Test Method 
ASTM D 543.  Exposure should be for a minimum of one month at 73.4 degrees F.  
During this period, the CIPP test specimens should lose no more than 20 percent of 
their initial flexural strength and flexural modulus when tested in accordance with 
Section 8 of ASTM F1216 when subjected to the following solutions:  
 
 
Chemical 
Solution 
 
Concentration (%) 
Tap Water (pH 6-9) 
100 
Nitric Acid 
5 
Phosphoric Acid 
10 
Sulfuric Acid 
10 
Gasoline 
100 
Vegetable Oil 
100 
Detergent 
0.1 
Soap 
0.1 
 
The Contractor shall be responsible for all costs associated with the chemical resistance 
tests.  Proof of meeting these requirements shall be provided to the City’s 
Representative for approval at least seven (7) days prior to commencement of work.  
 
D. LINER TUBE 
  
1. The liner tube shall be fabricated to a size that, when installed, will fit the internal 
circumference of the existing sanitary sewer main without any annular space 
between liner and walls of host pipe.  Allowances shall be made for circumferential 
stretching due to insertion of liner and deterioration of host pipe walls. 
 
2. The minimum liner tube length shall be that deemed necessary by the Contractor to 
effectively and continuously span the distance from the inlet to the outlet of the 
respective manholes, unless otherwise specified.  The Contractor shall verify the 
lengths in the field before impregnation and installation of the tube.  Individual 
insertion runs may be made over one or more manhole sections as determined in 
the field by the Contractor.  
3. Measure the overall elongation of the fabric tube after pull-in completion and report 
to the City’s Representative.

SECTION 02148 
CIPP LINING OF EXISTING SEWERS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 10 
October 25, 2024 
 
4. Contractor shall utilize a dynamometer or load cell per ASTM F1743 Section 6.4.1 
or other approved method to monitor winch or cable pulling force.   
 
5. Prior to insertion, the liner tube shall be free of all visible tears, holes, cuts, foreign 
materials, and other defects.  
 
6. The physical properties quoted in Technical Specification 02148 – paragraph 2.03 
applies to CIPP manufactured polyester, vinyl-ester, or epoxy resin.  Resins shall 
be tinted for visibility and provide positive indication of adequate liner wet-out.  
Resins should be appropriate for conditions encountered.  
 
E. DIMENSIONS  
  
1. The Contractor shall make allowances in determining the felt tube length and 
circumference for stretch during installation and shrinkage during curing.  The 
Contractor shall verify the lengths in the field before the felt tube is cut and 
impregnated.  Individual installation runs may include one or more manhole-to-
manhole sections as approved by the City’s Representative.  
 
2. The diameter of the host pipe may be larger than the nominal inside diameter due 
to corrosion of the existing host pipe.  It is the Contractor’s responsibility to 
determine the required diameter of the liner.  
 
3. “Minimum Design” thickness is defined as the CIPP calculated thickness according 
to ASTM F1216 or ASTM F1743 or ASTM D2990 as applicable, using design 
criteria then rounded up to next manufactured increment.  Calculations of liner 
thickness shall be submitted to the City or City’s Representative according to 
Technical Specification Technical Specification Section 01300 – Submittals prior 
to installation.  
 
Unless otherwise specified to provide for excess resin migration, the gap thickness 
of the wetting out equipment shall be sized to allow an excess of 5 to 10 percent 
resin to pass during impregnation. The measurement of installed dry cured liner 
thickness shall be determined at a minimum of three locations cut from a CIPP 
restrained liner sample, minus the thickness of any plastic coatings or CIPP layers 
not included in the structural design of the CIPP, using a method of measurement 
accurate to the nearest 0.005-mm. 
 
2.03 
FINISHED AND CURED CIPP LINER PROPERTIES 
 
The physical properties of the cured CIPP shall have minimum initial test values as given 
in Table 1 of ASTM F1216 (and supplemented below in Table 1) for polyester and vinyl 
ester, resins.  Properties for these or any other enhanced resins shall be substantiated with 
test data.

SECTION 02148 
 
 
CIPP LINING OF EXISTING SEWERS 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 11 
October 25, 2024 
Table 1:  Standard Materials 
Test Property 
Test Value 
Felt Liner 
Test Value 
Fiberglass Liner  
Test Method 
Flexural strength 
4,500 psi 
6,500 psi 
ASTM D790 
Flexural modulus 
300,000 psi 
725,000 psi 
ASTM D790 
50-year flexural creep 
modulus 
150,000 psi 
362,500 psi 
ASTM D2990 
 
2.04 
DESIGN CRITERIA 
 
A. The liner thickness shall be designed in accordance with the procedures of ASTM F 
1216, Appendix XI, ASTM D2990 and these Technical Specifications.  All material 
properties used in design calculations shall be long-term (time-corrected) values.  
Contractor shall familiarize himself with site conditions when preparing liner design. 
 
B. The following parameters shall be assumed for the liner design: 
 
1. Modulus of soil reaction, E's = 1,000 psi (fully deteriorated) 
2. Unit weight of soil = 140 pcf 
3. The minimum ovality shall be 2.0 percent 
4. Groundwater to ground surface elevation 
5. AASHTO HS20 Traffic loads 
6. Safety Factor = 2.0 
7. Pipe depth at invert 
 
2.05 
PAYMENT PENALTY / REDUCTION 
 
A penalty will be assessed by the City to the Contractor for payment on all installed CIPP 
liners that do not meet or exceed the minimum CIPP wall thickness requirements as stated 
in Technical Specification Section 02148 - paragraph 2.02.E.3.  Payment to the Contractor 
will be reduced on Contractor’s unit price per foot payment for the total length of CIPP 
liner installed as measured from center of upstream manhole to center of downstream 
manhole.   Payment/reduction shall be based on the following Table 2 – Payment Penalty 
/ Reduction: 
 
TABLE 2 - PAYMENT PENALTY / REDUCTION 
Payment Penalty 
(see note 1) 
Installed Dry Cured Liner Thickness Below             
Minimum Design (mm) 
0% 
0% up to and including 5% 
10% 
Greater than 5% up to and including10% 
20% 
Greater than 10% up to and including 20% 
Rejected 
Greater than 20% 
Note 1 – Reduction in payment assessed in Contractor’s pay request to City 
2.06 
CIPP TERMINATION POINTS  
  
The Contractor shall provide CIPP liner terminations.  If the CIPP fails to make a tight seal

SECTION 02148 
CIPP LINING OF EXISTING SEWERS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 12 
October 25, 2024 
at the manhole walls, the Contractor shall seal the liner/manhole interface with material 
consisting of a resin mixture compatible with the liner/resin system or approved equivalent.  
The sealing system shall be applied in accordance with manufacturer specifications and 
approved by the City’s Representative.  
 
2.07 
CURE TEMPERATURE MONITORING 
 
The Contractor shall provide equipment and fiber optic cable for monitoring the CIPP liner 
wall temperature during cure along the entire length being installed. Sensor technology 
shall be as manufactured by Zia Systems LLC of Galloway, Ohio Vortex Technology 
Group LLC of Houston, Texas or approved equal. 
 
Temperature sensor cable shall be placed between the host pipe and the CIPP liner in the 
bottom of the host pipe (invert) throughout the reach to record the heating and cooling that 
takes place on the outside of the CIPP liner. The sensors shall be spaced apart no greater 
than 10-feet. The monitoring of these sensors shall be by a computer which can record the 
temperatures at this interface throughout the processing of the CIPP liner utilizing a 
tamper-proof database.  
 
Prior to installing the CIPP liner in the host pipe, the temperature monitoring system’s 
function shall be confirmed by hooking it up to the computer and seeing that the sensors 
are reporting ambient temperatures. No more than two (2) sensors in sequence can be found 
faulty during this test. If three (3) or more sensors in sequence are discovered faulty, a new 
sensor array shall be pulled into the host pipe replacing the previously installed array; and 
the new array shall be again tested for its proper function. 
 
As a secondary backup system, the Contractor shall monitor the temperature of the CIPP 
liner wall to verify manufacturer recommended curing temperature has been achieved. 
Temperature sensors shall be placed at the upstream and downstream ends of the reach 
being lined.  Additionally, sensors shall be strategically placed at points where a significant 
heat sink is likely to occur. The temperatures at these interfaces shall be monitored by the 
Contractor throughout the curing of the CIPP liner. 
 
The Contractor shall submit a written repair plan in the event CIPP liner manufacture 
recommended temperature is not attained or continuously maintained in a portion of the 
liner. 
 
PART 3 - EXECUTION  
  
3.01 
PREPARATORY PROCEDURES  
 
A. SET-UP 
 
Prior to CIPP installation all necessary traffic control measures shall be put into place 
per Technical Specification Section 02100 – Traffic Control, and the bypass diversion

SECTION 02148 
 
 
CIPP LINING OF EXISTING SEWERS 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 13 
October 25, 2024 
pumping system, including back-up pumps, shall be tested and running per Technical 
Specification Section 02145 – Diversion of Sewage Flow and Dewatering.   
 
Every effort should be made to protect the environment from any contamination from 
sanitary sewer.  
 
B. SEWER CLEANING 
  
Prior to CIPP tube installation, the Contractor shall clean the existing sewer in 
accordance with Technical Specification Section 02760 – SEWER PIPE AND SEWER 
STRUCTURE CLEANING.  The Contractor shall clear the existing sewer of 
obstructions such as solids that will prevent or hinder CIPP liner installation.   The 
Contractor shall utilize a spinning nozzle as to ensure that the host pipe is free from 
any residual sediment prior to lining.  A time lapse no greater than 30 calendar days 
shall be allowed between initial host pipe cleaning and liner installation. 
 
C. SEWER BYPASSING AND DEWATERING 
 
The Contractor shall be responsible for bypassing flow around their work and 
dewatering sanitary sewer pipes in accordance with the requirements of Section 02145 
– Diversion of Sewage Flow and Dewatering.  
 
D. CCTV INSPECTION 
  
The interior of the sewer shall be inspected in accordance with Technical Specification 
Section 02761 – REMOTE CCTV INSPECTION OF EXISTING AND 
REHABILITATED SEWERS to determine the location of conditions, which may 
prevent proper installation of CIPP.   
 
The Contractor shall furnish the cleaning CCTV and report to the City’s Representative 
for host pipe segments that the Contractor determines existing conditions may impact 
the final operation of the lined pipe, either grade or condition. If existing host pipe 
defects or voids exist, the Contractor shall repair or replace that section of the host pipe.  
 
The Contractor shall not line over any offset that is greater than 5% of the lined pipe 
internal diameter without first notifying the City’s Representative.   
 
E. CIPP LINER DIAMETER VERIFICATION 
  
The internal diameter of the existing host pipe may be larger (or smaller) than their 
nominal size.  It is the Contractor's responsibility to measure the actual inside diameter 
of the sewer to determine the appropriate size of CIPP liner to use.  
 INSTALLATION METHODS 
 
A. GENERAL

SECTION 02148 
CIPP LINING OF EXISTING SEWERS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 14 
October 25, 2024 
  
The Contractor shall designate the location where the CIPP felt tube would be 
impregnated with resin ("wet-out").  Locations shall be subject to approval by the City’s 
Representative and applicable local agencies.  The Contractor shall allow the City 
and/or City’s Representative to inspect the materials and "wet-out" procedure.  
 
If the “wet-out” location is not at the project site, the impregnated CIPP tube shall be 
transported to the site under controlled environmental conditions.  Transport vehicles 
shall include a tamper resistant, sealed temperature-recording device which records the 
temperature of the liner at all time after leaving the wet-out site.  The Contractor shall 
decide when to transport the impregnated CIPP tube to the site and when to commence 
insertion with respect to weather conditions.  
 
The Contractor is responsible for obtaining construction/ fire hydrant meters from City 
of Tempe and for paying all applicable deposit, fees and water usage fees according to 
revised City Code Section 49.  
 
B. PRE-INSTALLATION 
 
Prior to installation of the liner, the following activities are required to be completed: 
 
1. Receipt and approval of pre-installation submittals by the City’s Representative. 
 
2. Verification of pipe condition and any obstructions by video inspection. 
 
3. Verification of existing laterals and location of services by flowing water, dye test, 
or visually with a pan and tilt head camera or other means. 
 
4. Cleaning of sewer main (recorded on video). 
 
5. Perform required point repairs at pipe locations that would prevent or hinder proper 
CIPP liner.  The Contractor shall obtain the approval of the point repairs from the 
City’s Representative prior to proceeding with the liner installation.  The Contractor 
assumes all responsibility of liner quality once installation begins if prior written 
notification is not received and acknowledged by the City’s Representative. 
 
6. The Contractor is to ensure liner tube is free of all visible tears, holes, cuts, foreign 
materials, and other defects. 
 
C. HANDLING 
  
The Contractor shall exercise adequate care during transportation, handling and 
installation to ensure the CIPP material is not torn, cut, or otherwise damaged.  If any 
part or parts of the CIPP material becomes torn, cut or otherwise damaged before or 
during insertion, it shall be repaired or replaced in accordance with the manufacturer’s 
recommendations and approval by the City’s Representative before proceeding further;

SECTION 02148 
 
 
CIPP LINING OF EXISTING SEWERS 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 15 
October 25, 2024 
and at the Contractor's expense.  
  
D. INSTALLATION PROCESS 
  
No CIPP installations will be undertaken in weather conditions that could jeopardize 
the installation of the CIPP, or be detrimental to the long-term performance of the CIPP.  
The liner will be installed by the inversion tube method or winching method as follows.   
 
1. INVERSION METHOD:  The tube shall be impregnated with a liquid 
thermosetting resin and lowered into the insertion pit through an inversion tube.  
The inversion tube will then be inverted into the existing sewer by air pressure 
which will push the tube through the host pipe inside out, while pressing the resin 
impregnated side firmly against the inside walls of the host pipe.  The smooth 
coated side of the liner shall become the new interior surface of the host pipe.  After 
the tube is inverted through the host pipe section, the Contractor shall cure the liner 
by introducing steam or a combination of compressed air and steam to initiate the 
curing process.  
  
2. WINCHING METHOD: The wet out liner shall be inserted through the upstream 
manhole and pulled through the section through the use of a power winch attached 
to the end of the liner with an appropriate pulling head.   
 
A monitoring device shall be provided to measure the pulling force.  Should the 
pulling force exceed the manufacture recommendations, the tube shall be rejected, 
removed and replaced.  Maximum manufacturer’s pulling force shall be submitted 
according to Technical Specification Section 01300 – Submittals. 
  
If anticipated drag forces exceed manufacture’s maximum recommended pulling 
force, a plastic slip sheet may be installed flush on the invert of the host pipe when 
installing fiberglass liner to minimize liner damage and reduce tension during pull-
in as per ASTM F1743 or ASTM F2019 Section 6.2.1. Slip sheet shall terminate a 
minimum of one (1) foot from pipe liner termination so as not to interfere with liner 
termination end seal performance. If lubricants are utilized to further reduce drag 
forces, they shall be food grade quality and submitted for approval per Section 
01300 – Submittals. 
 
Rollers shall be installed in the upstream and downstream manholes to guide the 
liner into and out of the host pipe and to guard against chafing of the crowns at the 
entry and exit.  
  
The sewer invert throughout the section to be lined shall be covered with a 
polyethylene foil or other suitable material to facilitate threading of the liner and 
reduce the risk of damage to the liner material.  The CIPP shall be formed with a 
polyurethane, polyethylene, or polypropylene coating on its interior surface.

SECTION 02148 
CIPP LINING OF EXISTING SEWERS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 16 
October 25, 2024 
During insertion of the resin impregnated tube into the host pipe, the maximum 
allowable longitudinal elongation, or stretch, of the liner tube shall be 5% per 
ASTM F1743 Section 6.4.2.  The longitudinal stretch of the tube shall be gauged 
by comparing the fully inserted tube to the actual length of host pipe being 
rehabilitated.  Contractor shall field measure within the interior of the pipe the 
actual host pipe length and submit to the City’s Representative.  
  
The Contractor shall use a flexible and impermeable calibration hose to inflate the 
tube.  The calibration hose may or may not remain in the complete installation.  Any 
dry tube or inflation hose material that enters the existing pipe that has not been 
previously impregnated with resin under controlled conditions cannot be included 
in the structural wall of the CIPP.  The nominal thickness of this material shall be 
deducted from the field sample thickness measured in order to verify that the 
minimum specified wall thickness is achieved.  Hose material remaining in the 
installation shall be compatible with the resin system used, shall bond permanently 
with the tube, and shall be translucent to facilitate post installation inspection.  Hose 
materials which are to be removed after curing shall be of non-bondable material.  
  
The Contractor shall introduce air, water or steam into the liner and expand with 
pressure inflating and pressing the liner material in a tight fit against the inner walls 
of the host pipe producing dimples at lateral and side connections and flared ends 
at manholes.   
 
All hoses/pipes used for introducing water, air, and/or steam shall be ramped during 
the inversion and curing process to allow for the ease of vehicular and pedestrian 
traffic.   
 
All hoses/pipes shall be color-coded for identification to prevent the use of 
hoses/pipes used for water conveyance are not used for wastewater conveyance or 
vice versa.  
 
E. CURING 
  
1. FELT LINER 
 
The curing process shall be per ASTM F1216 or ASTM F1743 or similar approach 
recommended by the manufacturer and approved by the City’s Representative, to 
ensure that the liner design physical properties are attained.  Circulation water shall be 
cool down to at least 100 degrees F before releasing the hydrostatic head. 
  
The rate of temperature rise and fall during heating and cooling shall not exceed 2 
degrees F per minute or manufacturer’s recommendation.  Contractor shall submit per 
Technical Specification Section 01300 – SUBMITTALS the manufacturer 
recommendation for temperature control requirements during heat–up, cure, 
recommended cure temperature, and length of time at recommended cure temperature,

SECTION 02148 
 
 
CIPP LINING OF EXISTING SEWERS 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 17 
October 25, 2024 
and maximum rate of cool down of temperature.  
  
2. FIBERGLASS LINER 
 
The fiberglass liner shall be cured with UV light sources (i.e., light train). When 
inserting the curing equipment (light train) into the liner, care should be taken not to 
damage the inner film material.  The liner shall be held at a constant inner air pressure 
during the curing process. 
 
Contractor shall submit manufacturer’s maximum air pressure to be exerted and 
maximum rate of inflation, recommended incremental inflation pressure points with 
corresponding hold time durations according to Section 01300 – Submittals. 
 
The UV light sources or light train should be assembled according to the 
manufacturer’s recommendations for the liner diameter.  For the liner to achieve the 
required water tightness and specified mechanical properties, the following parameters 
must be controlled during the entire curing process.  A record of the curing parameters 
over each segment of the entire length of the liner shall be submitted per Section 01300 
- Submittals, to the Owner’s Representative to demonstrate that the entire liner is cured 
properly.   
 
The recorded cure data shall include: 
a. Curing speed 
b. Number of light sources working and wattage of each bulb  
c. Inner liner air pressure 
d. Exothermic (curing) temperatures  
e. Date and time 
f. Length of liner installed. 
 
Record of the curing parameters shall be accomplished using a computer and database 
that are tamper proof.  During the curing process, infrared sensors shall be used to 
record curing data that shall be submitted to the Owner’s Representative with a post-
installation CIPP CCTV inspection on DVD / USB according to Section 01300 – 
Submittals. 
 
The required parameters for curing speed, inner air pressure and wattage are defined in 
the UV curing protocol issued by the resin manufacturer.  The optimal curing speed, or 
travel speed of the energized UV light train, shall be determined for each length of liner 
based on liner diameter, liner thickness, and exothermic reaction temperature. Required 
parameters shall be submitted to the Owner’s Representative according to Section 
01300 – Submittals, prior to installation.  The UV light train shall be capable of curing 
the fiberglass liner at a curing rate of up to 10 LF (linear feet) per minute. 
 
The fiberglass liner shall be monitored and inspected prior to and during the curing 
process.  Once the light train is inserted into the pipe, prior to curing, the liner shall be

SECTION 02148 
CIPP LINING OF EXISTING SEWERS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 18 
October 25, 2024 
inspected by the Contractor using a CCTV camera.  During the curing process, infrared 
sensors shall record the exothermic curing temperatures on a tamper proof computer 
file.  In addition, visual observation using CCTV shall be conducted during the curing 
process.  A printout of the recorded data and a copy of the CCTV data shall be a part 
of the post installation submittal or as-built information to be submitted to the Owner’s 
Representative. 
 
F. CURE TEMPERATURE MONITORING 
 
The Contractor shall monitor the temperature of the CIPP liner wall to verify and 
document manufacturer recommended curing temperature has been achieved. 
Temperature monitoring system shall be placed between the host pipe and the liner in 
the bottom of the host pipe (invert) to record the heating and cooling that takes place 
on the outside of the liner. The Contractor shall install and monitor temperature during 
the curing process with system/equipment as follows: 
 
1. CIPP Liner in Pipe 15-inch Diameter and Larger: Fiber optic cable along the entire 
length of CIPP liner in addition to point temperature sensors installed at the 
upstream, downstream, and intermediate (if present) access manholes. The 
monitoring shall be by a computer which can record the temperatures at this 
interface throughout the processing of the CIPP utilizing a tamper-proof database.  
 
Prior to installing the CIPP liner in the host pipe, the temperature monitoring 
system’s function shall be confirmed by hooking it up to the computer and seeing 
that the sensors are reporting ambient temperatures. No more than two sensors in 
sequence can be found faulty during this test. If three or more sensors in sequence 
are discovered faulty, a new sensor array shall be pulled into the host pipe replacing 
the previously installed array; and the new array shall be again tested for its proper 
function. 
 
3.02 
FINISHED PRODUCT  
  
A. FINISH 
  
The finished CIPP shall be continuous over the entire length of an installation run.  
  
B. OUTER FILM / INNER FILM (Fiberglass Liner) 
 
The outer film that has been manufactured to control resin loss, liner thickness, and 
contamination of the resin by water or other contaminants, shall remain in-place after 
UV curing of the liner has been completed.  The inner film shall be removed after the 
curing of the liner is complete. 
C. MANHOLE CONNECTION  
  
The Contractor shall provide and install a watertight hydrophilic end seal between the

SECTION 02148 
 
 
CIPP LINING OF EXISTING SEWERS 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 19 
October 25, 2024 
existing host pipe and liner pipe at the manhole connection. Liner shall extend through 
the end seal and terminate into the interior of the manhole two (2) inches and trimmed 
square. 
  
D. INSPECTION 
  
The Contractor shall inspect the CIPP after installation.  The inspection will be 
performed and recorded using remote visual television inspection equipment in 
accordance with Technical Specification Section 02761 – REMOTE CCTV 
INSPECTION OF EXISTING AND REHABILITATED SEWERS. If defects exist 
within the liner, the Contractor shall repair or replace that section of liner at no 
additional cost to the City.  Methods of repair shall be proposed by the Contractor and 
submitted to the City’s Representative for review and approval prior to initiating repair 
work. City Representative shall be notified a minimum of 24 hours prior to performing 
repair work. 
 
The Contractor shall resubmit a final video showing a post inspection after the liner 
issues have been addressed and approved. 
  
E. REPAIR OF DEFECTS 
 
Defects such as foreign inclusions, dry spots, pinholes, delamination, seam separation 
and wrinkling beyond the specification allowances or as determined by the City’s 
Representative as affecting the integrity or structural stability of the CIPP pipe, or as 
adversely affecting the hydraulic capacity of the CIPP lined pipe are unacceptable and 
shall be repaired or replaced at the Contractor's expense. 
 
1. Wrinkles in the finished lined pipe which cause a backwater of one (1) inch or more 
or reduce the hydraulic capacity of the lined pipe (wrinkle height that exceed 5 
percent of the lined pipe internal diameter) are unacceptable and shall be removed 
and/or repaired by the Contractor at no additional cost to the City.   
 
2. Voids or annular space that exists between a wrinkle and the host pipe shall be 
repaired or pipe section replaced and relined by the Contractor at no additional cost 
to the City.  Methods of repair shall be proposed by the Contractor and submitted 
to the City’s Representative for review and approval prior to initiating work.  
 
3. Separations of CIPP liner seam in the finish lined pipe are unacceptable and shall 
be removed or repaired by the Contractor at no additional cost to the City.  If a 
separation of a liner seam exists, the Contractor shall remove the CIPP liner or 
replace that section of pipe.  Methods of repair shall be proposed by the Contractor 
and submitted to the City’s Representative for approval.  
 
4. Poke holes, gouges, scrapes, or damage to the liner created during mechanical 
operation of equipment including but not limited to the hydro-jetter or lateral cutter

SECTION 02148 
CIPP LINING OF EXISTING SEWERS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
 02148 - 20 
October 25, 2024 
shall be repaired as per approved method at no additional cost to the Owner. 
 
3.03 
CLEANUP  
  
Following inspection, the Contractor shall clean up the entire project area.  The Contractor 
shall dispose of all excess material and debris not incorporated into the permanent 
installation off site.  
 
 
 
 
** END OF SECTION **

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 1 
October 25, 2024 
SECTION 02720 
FIBER REINFORCED POLYMER (FRP) 
 
PART 1 – GENERAL 
1.01 
DESCRIPTION 
This Technical Specification is intended to provide guidelines and performance 
requirements for the rehabilitation of structures and gravity sewers using internally and 
externally bonded fiber reinforced polymer (FRP) composite systems. The rehabilitation 
system described herein shall include a glass fiber reinforced polymer (GFRP) as the main 
reinforcement system. The FRP can also include layers of other materials to increase 
stiffness of the FRP composite system in a cost-effective manner. The additional materials 
used to increase the stiffness of the FRP system may be proprietary to the FRP material 
supplier. Any materials used for the FRP system shall be subject to the approval of the 
Engineer. 
 
A. SCOPE: 
The work includes furnishing of all materials, labor, equipment, and services for the 
supply, installation, and finish of structural strengthening and/or rehabilitation using a 
FRP system. 
The Contractor shall be licensed in the State of Arizona and shall include all 
engineering, labor, materials, tools, equipment, appliances, and services required to 
design, deliver, furnish all items necessary for the proper execution and completion of 
the work as shown in the Contract Documents, as specified herein and/or as required 
by job conditions. A detailed design of the FRP system for the specific site conditions 
shall be included with the installation of the FRP system by the FRP installer selected 
by the Contractor. All items not shown or specified, but which are necessary for the 
proper execution and completion of the Work, shall be provided by the Contractor. 
 
The extent of the FRP composite system applied to shall be as defined herein and as 
shown on the Design Drawings. 
 
The Contractor shall cooperate and coordinate with all other trades in executing the 
work described in the Contract Documents. 
 
The Contractor shall deliver finished product(s) including all materials, labor, 
equipment, and services necessary for product installation, all quality controls and 
material samples required for performance tests, final inspection, and warranty work, 
all as specified in these Contract Documents and at the quantities of each component 
to complete the work. 
 
The prices submitted by the Contractor shall include all costs of permits, labor, 
equipment, and materials for the various items necessary for rehabilitation materials 
and processes in accordance with these Technical Specifications complete and in place,

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 2 
October 25, 2024 
SECTION 02720 
FIBER REINFORCED POLYMER (FRP) 
 
 
 
including all items of work not specifically identified herein which are required to 
make the product perform as intended. All Contractor costs to deliver the final product 
shall be included in the respective lump sum and/or unit price bid items depicted in the 
Proposal. 
 
It shall be the responsibility of the Contractor to monitor the weather and make 
necessary adjustments in means and methods while work is being conducted. 
1.02 
SAFETY REQUIREMENTS: 
The Contractor shall conform to all work safety and health requirements of pertinent 
regulatory agencies and/or shown in Technical Specification Section 01060 – HEALTH 
AND SAFETY and shall secure the site for working conditions in compliance with the 
same. The Contractor shall perform existing material testing as required by regulatory 
regulation requirements and provide/install/maintain such signs and/or other devices as 
are necessary for safety at the work site. 
 
Sewers and appurtenant structures are considered confined spaces and are subject to 
federal, state, and local regulations governing confined space entry and safety procedures. 
The Contractor shall obtain all necessary permits required to enter and work in confined 
spaces. 
1.03 
NOTIFICATION: 
It shall be the Contractor’s responsibility to notify businesses and the public per Technical 
Specification Section 01400 – PUBLIC AWARENESS. The Contractor shall notify all 
utility companies involved whenever a utility is to be cut, tapped, moved, or in any way 
disturbed from its original placement. Sufficient notice shall be given to the utility 
company so that its users can be informed of any disruption of service. Such notice shall 
be given no less than 48 hours in advance. 
 
It is the Contractor’s responsibility to inform the City of construction activities which may 
lead to interruption in pedestrian or vehicular traffic or sewer service. The Contractor shall 
provide 72-hour notice prior to construction to verify all applicable businesses and 
residents have been alerted. 
1.04 
QUALITY CONTROL 
A. REFERENCES: 
 
Reference 
Title 
 
ACI—American Concrete Institute 
 
117-90 
Specifications for Tolerances for Concrete Construction and 
Materials, and Commentary.

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 3 
October 25, 2024 
SECTION 02720 
                                                                   FIBER REINFORCED POLYMER (FRP) 
224.1R-07 
Causes, Evaluation, and Repair of Cracks in Concrete 
Structures. 
 
224R-01 
Control of Cracking in Concrete Structures. 
 
440R-07 
State-of-the-Art Report on Fiber Reinforced Plastic 
Reinforcement for Concrete Structures. 
 
503R-93 
Use of Epoxy Compounds with Concrete. 
503.4-R92 
Standard Specifications for Repairing Concrete with Epoxy 
Mortars. 
 
503.6R-97 
Guide for the Application of Epoxy and Latex Adhesives for 
Bonding Freshly Mixed and Hardened Concretes. 
 
546R-04 
Concrete Repair Guide. 
 
ASTM- American Society for Testing and Materials 
 
D3039 
Test Method for Tensile Properties of Polymer Matrix 
Composite Materials 
 
D3418 
Test Method for Transition Temperatures of Polymers by 
Differential Scanning Calorimetry. 
 
D5687 
Guide for Preparation of Flat Composite Panels with 
Processing Guidelines for Specimen Preparation. 
 
D7565 
Standard Test Method for Determining Tensile Properties of 
Fiber Reinforced Polymer Matrix Composites Used for 
Strengthening of Civil Structures. 
 
D7290 
Standard Practice for Evaluating Material Property 
Characteristic Values for Polymeric Composites for Civil 
Engineering Structural Applications. 
 
D638 
Standard Test Method for Tensile Properties of Plastics. 
D695 
Standard Test Method for Compressive Properties of Rigid 
Plastics. 
 
D790 
Standard Test Methods for Flexural Properties of 
Unreinforced and Reinforced Plastics and Electrical 
Insulating Materials.

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 4 
October 25, 2024 
SECTION 02720 
FIBER REINFORCED POLYMER (FRP) 
 
 
 
D543 
Standard Practices for Evaluating the Resistance of Plastics 
to Chemical Reagents. 
NACE International 
 
SSPC-SP12 / NACE 5 
Surface Preparation and Cleaning of Steel and Other Hard 
Materials by High- and Ultra High- Pressure Water Jetting 
Prior to Recoating. 
 
SSPC-SP13 / NACE 6 
Surface Preparation of Concrete. 
 
ICRI- International Concrete Repair Institute 
No. 03732 
Selecting and Specifying Concrete Surface Preparation for 
Sealers, Coatings, and Polymer Overlays. 
No. 03733 
Guide for Selecting and Specifying Materials for Repairs of 
Concrete Surfaces. 
1.05 
CERTIFIED INSTALLER 
The Contractor must be trained and certified by the FRP material supplier and approved 
by the City and City’s Representative for installation of the FRP system. A training 
outline for the certification program shall be submitted to the City or City’s 
Representative for review. The Contractor shall provide evidence that the on-site 
Superintendent responsible for supervision of the FRP installation crew has received the 
FRP material supplier’s training. 
 
The certified installer of the FRP system shall show experience in the installation of the 
proposed rehabilitation method for all jobs within the last five (5) years. Information 
provided shall include a description of the job, the location of the job, the value of the 
job, the Owner name, and the Owner contact person for the job including name, title, 
address, and phone number. 
The Contractor shall appoint a Quality Assurance Manager who will be on-site full- 
time during FRP installation to take full responsibility for the quality of the work. The 
Quality Assurance Manager shall be fully certified by the FRP material supplier. 
1.06 
SURFACE PREPARATION 
The Contractor shall perform surface preparation per Technical Specification Section 
02146 – SEWER PIPE AND SEWER STRUCTURE CLEANING 
1.07 
PERFORMANCE WORK STATEMENT (PWS) 
A Performance Work Statement (PWS) shall be submitted by the Contractor for the 
approval of City and City’s Representative. The PWS shall include submittals consisting 
of Design Drawings, sketches, FRP material supplier’s literature, catalog descriptions, or 
other descriptions in sufficient detail to allow a decision for submittal acceptance.

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 5 
October 25, 2024 
 
        
    SECTION 02720 
                                                        FIBER REINFORCED POLYMER (FRP) 
One (1) electronic copy of submittal(s) shall be provided to the City and City’s 
Representative at minimum of thirty (30) days before a submittal response is required or 
as per the submittal requirements under Section 4.7.3 of General Conditions, whichever is 
less. 
 
1.08 
SUBMITTALS: 
The Contractor shall submit the following information to the City or City’s Representative 
in accordance with Technical Specification Section 01300 – SUBMITTALS. 
 
A. Performance work statement (PWS). 
 
B. Certifications of applicator with written consent from the FRP material supplier that 
the Contractor has been trained in proper application of FRP material supplier’s 
systems. 
 
C. Physical and mechanical properties shall be provided of each proposed FRP system 
and other components, including test results conducted per the ASTM standards as 
applicable to the project. Physical properties shall, at the minimum include: 
a. Laminate density, Laminate Shore D hardness (ASTM D2240). 
b. Corrosion resistance (ASTM D543). 
c. Fully cured resin water absorption (ASTM D570). 
d. Glass transition temperature (ASTM E1640). 
e. Fabric ply thickness, resin cure times. 
f. Volatile organic compound (VOC) of laminate materials (ASTM D2369). 
g. FRP fabric roll dimensions range. 
 
Mechanical properties shall, at the minimum include: 
 
a. Minimum ultimate and characteristic design tensile strength. 
b. Elongation percent. 
c. Tensile modulus of the laminate in fiber direction (per ASTM D3039. 
D7290, respectively). 
d. Minimum design laminate thickness per layer. 
 
D. FRP material supplier’s Safety Data Sheets (SDS) for all materials brought on-site. 
 
E. Product Data Sheets (PDS) for the components of the FRP system. 
 
F. Safety Plan in compliance with local, state, and federal requirements. 
 
G. Detailed installation plan describing all work items. 
 
H. FRP material supplier test data.

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 6 
October 25, 2024 
SECTION 02720 
FIBER REINFORCED POLYMER (FRP) 
 
 
 
I. FRP system design engineer’s qualifications and the criteria incorporated into the 
design. Design calculations submitted shall be sealed by a professional Structural 
Engineer registered in the State of Arizona. 
J. Product installation procedure. 
 
K. QA/QC plan including field sampling and testing. 
 
L. FRP Design Drawings and Technical Specifications. 
 
M. Documentation of Contractor’s Experience: Contractor shall provide references for 
all jobs within the last five (5) years that were either completed or under 
construction using the proposed rehabilitation method and materials. 
N. Qualifications, certifications / training received of installer including experience on 
similar projects. 
O. Submit FRP material supplier’s published product and installation literature and 
published quality control testing criteria data for the proposed FRP system. 
P. Submit independent test report showing that the physical properties of the proposed 
materials meet the requirements of these Technical Specifications and will meet or 
exceed the physical properties given in the FRP material supplier’s published literature 
submitted as required by Part 2 – PRODUCTS. 
Q. Submit a report of the proposed installation process and procedures as directed by the 
FRP system to be used. The report shall include information specific to the installation 
instructions and any unique site condition(s) that must be taken into consideration 
including surface preparation, environmental limitations such as humidity, surface 
temperature, set times, access coordination, installation timing and identification and 
any coordination requirements/requests from the City or City’s Representative. 
 
R. Shop Drawings: The Contractor shall provide shop drawings of proposed materials for 
approval prior to ordering. Shop drawings shall depict: 
 
1. All measurements made by the Contractor to verify critical dimensions. 
 
2. Material(s) proposed for construction. 
 
3. Critical dimensions, jointing, overlap, and connections, necessity for fasteners, and 
anchors with sizes, spacing, and location if proposed, connections, attachments, and 
openings. 
 
4. Color(s). 
S. Documentation of the control checks for materials used in the fabrications and each 
part of the fabrication materials including resin and fabric(s).

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 7 
October 25, 2024 
SECTION 02720 
                                                                   FIBER REINFORCED POLYMER (FRP) 
T. Warranty: Contractor shall submit warranty documents signed by an officer of the 
company and notarized stating the terms and conditions of the warranty identified in 
Paragraph 1.12 – WARRANTY. 
U. Any item the Contractor proposes to utilize as an “or equal” to that proposed in the 
Contract Documents. 
1.09 
SUBSTITUTIONS 
Any item the Contractor proposes to substitute for a specified item as an “or equal” must 
be submitted per Technical Specification Section 01300 – SUBMITTALS and approved 
by the City or City’s Representative prior to the start of construction activities. 
Substitutions or deviations not approved by the City or City’s Representative shall risk 
rejection and replacement at no additional cost to the City. 
1. For any proposed design change or deviation from these Technical Specifications. 
 
2. For anything in these Technical Specifications found to conflict with applicable codes 
and ordinances. 
 
3. For anything not understood by the Contractor. 
1.10 
QUALITY ASSURANCE/QUALITY CONTROL 
 
A. EXAMINATION: Each component part shall be examined by the Contractor for 
dimensional requirements, soundness, and workmanship in accordance with ASTM 
C478. 
 
B. COMPOSITION CONTROL: The FRP installer shall control and document the fiber 
to resin ratio content for each part of the installation. Documentation of the control 
checks shall be maintained by the Contractor and FRP installer. Proper content shall 
be shown by fiber to resin ratio usage rate checks, in accordance with the FRP material 
supplier’s recommended material composition. 
 
C. TESTING RECORDS: Records of all testing shall be submitted in accordance with 
Technical Specification Section 01300 – SUBMITTALS. 
1.11 
INSPECTION POINTS 
 
The Contractor shall keep the City or City’s Representative informed of milestone 
progress for the following items: 
 
1. Completion of removal of unsound material and pressure wash cleaning. 
2. Completion of leveling/seal material placement and surface preparation prior to FRP 
placement. 
3. Completion of FRP placement. 
4. Completion of FRP protective coating.

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 8 
October 25, 2024 
SECTION 02720 
FIBER REINFORCED POLYMER (FRP) 
 
 
1.12 
WARRANTY 
The Contractor shall replace promptly and at no expense to the City, any FRP system 
materials which fail during the warranty period. A failure is defined as blistering, cracking, 
embrittlement, softening, peeling, pitting, or adhesion failure to the substrate. Warranty 
work shall include all ancillary items including, but not limited to permits, traffic control, 
exposure, flow control, labor, equipment, bypass pumping, third party quality control 
inspection and all other work required to complete the repair/replacement work. Any 
testing performed during construction, including but not limited to, spark testing and 
adhesion testing, shall not in any way modify this Warranty or relieve the Contractor from 
its responsibility to repair or replace a failed FRP system. Mechanical damage due to 
maintenance operations or ancillary work on the FRP system by others is excluded from 
this Warranty. Warranty and durations are described below: 
 
A. Project Warranty: The Contractor shall warrant all materials and workmanship 
performed under this contract for a period of five (5) years from the date of final 
acceptance of the project and Letter of Acceptance by the City or as stated in the project 
Contract Documents whichever is longer. 
 
B. Materials Warranty: The FRP system installed shall be free of defects that will affect 
the long-term life and operation of the system. The Contractor shall warrant in writing 
all materials provided under this contract for a period of five (5) years from the date of 
final acceptance of the project and Letter of Acceptance by the City. 
C. Design Life: Material(s) shall provide a design life of a minimum of fifty (50) years 
against deterioration from H2S corrosion and typical chemicals found in municipal 
sanitary sewage. 
PART 2 – PRODUCTS 
 
2.01 
ACCEPTABLE FRP MATERIAL SUPPLIERS & COMPOSITE STRENGTHENING 
SYSTEM 
A. General 
The Materials for the FRP system must be suitably qualified, compliant with industry 
standards and properties provided herein, and supplied by a reputable FRP material 
supplier approved by the City or City’s Representative. Before the materials are ordered 
or work is performed, the Contractor must identify which materials are proposed to be 
utilized and from which FRP material supplier(s) Contractor proposes to obtain the 
materials. 
Quality Control Testing and Certification: FRP material supplier shall certify that all 
material(s) provided conforms to the project specification or provide a proposed 
substitution per paragraph 1.09. The quality control test results for all proposed 
materials shall be submitted per Technical Specification Section 01300 – 
SUBMITTALS. 
 
Labeling, packaging, and storage shall include any health hazard warnings, precautions 
for handling and recommended first aid procedures in case of contact.

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 9 
October 25, 2024 
SECTION 02720 
                                                                   FIBER REINFORCED POLYMER (FRP) 
PART 2 – PRODUCTS 
 
2.02 
ACCEPTABLE FRP MATERIAL SUPPLIERS & COMPOSITE STRENGTHENING 
SYSTEM 
A. General 
The Materials for the FRP system must be suitably qualified, compliant with industry 
standards and properties provided herein, and supplied by a reputable FRP material 
supplier approved by the City or City’s Representative. Before the materials are ordered 
or work is performed, the Contractor must identify which materials are proposed to be 
utilized and from which FRP material supplier(s) Contractor proposes to obtain the 
materials. 
Quality Control Testing and Certification: FRP material supplier shall certify that all 
material(s) provided conforms to the project specification or provide a proposed 
substitution per paragraph 1.09. The quality control test results for all proposed 
materials shall be submitted per Technical Specification Section 01300 – 
SUBMITTALS. 
 
Labeling, packaging, and storage shall include any health hazard warnings, precautions 
for handling and recommended first aid procedures in case of contact. 
All materials used shall conform to the project Technical Specifications and other 
specifications referenced within and subject to the approval of the City or City’s 
Representative. 
B. Design Loads 
The FRP system shall be designed for the following loads as they apply for the specific site 
conditions: 
1. Earth load (a long-term loading). 
2. External pressure from ground water to ground surface elevation. 
(a long-term loading). 
3. Live load (a short-term loading). 
4. Internal working pressure (a long-term loading, where applicable) 
5. Water weight (a long-term loading) 
6. Host pipe weight (a long-term loading) 
7. Wind loads (if applicable) 
8. Seismic (if applicable) 
2.03 
GLASS FABRIC 
A. Glass fabric layers may be used where loading conditions allow. 
B. A glass fabric layer shall be used to create a dielectric barrier if the host pipe is conducive to 
electricity (steel, iron, etc.). The minimum dielectric constant (κ) shall be 4 (ASTM D150) 
for the dielectric barrier. Glass fabric shall have the minimum physical and mechanical 
properties shown in the table:

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 10 
October 25, 2024 
SECTION 02720 
FIBER REINFORCED POLYMER (FRP) 
 
 
 
Longitudinal (0°) Direction: 
Weight (Fabric Only) 
20 oz/yd2 
(670 g/m2) 
27 oz/yd2 
(904 g/m2) 
20 oz/yd2 
(670 g/m2) 
Fiber Orientation 
Uniaxial 
Uniaxial 
Biaxial 
Tensile Strength 
63.7 ksi 
(439 MPa) 
85.2 ksi 
(587 MPa) 
20 ksi 
(138 MPa) 
Tensile Modulus 
2,940 ksi 
(20,270 MPa) 
3,980 ksi 
(27,440 MPa) 
1,500 ksi 
(10,342 MPa) 
Ultimate Elongation 
2.20% 
2.30% 
2.10% 
Breaking Force 
2,365 lb./in. 
(4,140 N/cm) 
3,490 lb./in. 
(6,110 N/cm) 
1,120 lb./in. 
(1,961 N/cm) 
Transverse (90°) Direction: 
Tensile Strength 
N/A 
N/A 
20 ksi 
(138 MPa) 
Tensile Modulus 
N/A 
N/A 
1,500 ksi 
(10,342 MPa) 
Ultimate Elongation 
N/A 
N/A 
2.10% 
Breaking Force 
N/A 
N/A 
1,120 lb./in. 
(1,961 N/cm) 
Ply Thickness 
.037 in 
N/A 
0.040 in. 
(1.0 mm) 
 
2.04 
ALTERNATIVE FABRICS 
Alternative fabrics can be used for improved ring stiffness. Such materials can be proprietary and 
are subject to approval. Proposed alternative fabrics shall be submitted per Technical 
Specification Section 01300 – SUBMITTALS. Although revealing the chemical composition of 
alternative systems is at the discretion of the FRP material supplier, the physical and mechanical 
properties of such materials and the overall system are subject to the review and approval process. 
2.05 
SATURATING RESIN – POLYMER 
A. Fabrics shall be saturated with a two component, high strength, and low viscosity 
structural epoxy or other resin system as listed in Section 2.05 paragraph D. The resin 
shall have low viscosity and long pot life, with a fast cure time designed for high 
volume saturation of heavy reinforcement fabrics using a saturation machine or hand 
tools as per project requirements to saturate the fabric thoroughly and uniformly. 
 
1. The resin system shall be resistant to service environment conditions, including but 
not limited to moisture, corrosive gases, elevated temperature, and chemicals in 
the fluid flowing inside the municipal sanitary sewer host pipe. 
 
2. The resin system shall be resistant to service environment conditions, including but 
not limited to moisture, corrosive gases, elevated temperature, and chemicals in 
the fluid flowing inside the municipal sanitary sewer host pipe.

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 11 
October 25, 2024 
SECTION 02720 
                                                                   FIBER REINFORCED POLYMER (FRP) 
 
 
3. The resin system shall not be diluted with any organic solvents such as a thinner. 
4. The resin system shall not be used outside of the FRP material supplier’s specified 
pot life. 
 
5. The resin system shall not be applied on cold or frozen surfaces. 
 
6. Only moisture tolerant resins shall be allowed to be applied on wet surfaces. 
 
7. The temperature and moisture range for application shall be within the FRP 
material supplier’s specified values. 
B. Primer: For systems requiring a primer, the primer shall have sufficiently low viscosity 
to penetrate the concrete substrate and provide an adhesive bond for the thickened resin 
applied. 
 
C. Thickened Resin: A thickened resin system, which consists of the saturating resin and 
fumed silica (or similar), or the specified tack coat, both supplied by the FRP material 
supplier as premixed or mixed at the site according to the FRP material supplier’s 
recommended procedure, shall be used to provide a smooth surface for the application 
of the FRP laminate. The thickened resin system shall be used to fill in surface voids 
and even out the concrete substrate. It is permissible to use a thin coat of thickened 
epoxy between laminae to enhance adhesion. 
 
Saturating Resins: Saturating resins shall be 100% solids formulation with low odor conforming 
to the minimum physical and mechanical properties as shown in the table below. 
 
Epoxy Resin Properties 
Color – Part “A” is pigmented syrup, Part “B” is amber liquid. 
Viscosity Mixed at 770 F (250 C) 
1,500 – 1,600 cps 
Pot Life at 770 F (250 C) 
3 – 4 h (thin film set time) 
Cure time (>55 °F) 
24 h 
Density at 392 ⁰F (200 ⁰C) 
Part A: 70.5 lb./ft3 (1.13 kg/L) 
Part B: 62.4 lb./ ft3 (1.00 kg/L) 
Tensile Strength (ASTM D638) 
Tensile Modulus (ASTM D638) 
7,150 psi (49 MPa) 
289,000 psi (1,992 MPa) 
Flexural Strength (ASTM D790) 
Flexural Modulus (ASTM D790) 
11,140 psi (77 MPa) 
252,400 psi (1,740 MPa) 
Compressive 
Strength 
(ASTM 
D695) 
Compressive Modulus (ASTM D695) 
13,000 psi (90 MPa) 
350,000 psi (240 MPa) 
Water Absorption (% gain) in 24 hours 
< 1% 
Expansion Coefficient [-37.40 – 40.10 ⁰C] 
Expansion Coefficient [1,200 – 2,220 ⁰C] 
78 ×10-6 m/m ⁰C 
151.8 ×10-6 m/m ⁰C

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 12 
October 25, 2024 
SECTION 02720 
FIBER REINFORCED POLYMER (FRP) 
 
 
Saturating Resins: Saturating resins shall be 100% solids formulation with low odor conforming 
to the minimum physical and mechanical properties as shown in the table below. 
 
Epoxy Resin Properties 
Color – Part “A” is pigmented syrup, Part “B” is amber liquid. 
Viscosity Mixed at 770 F (250 C) 
1,500 – 1,600 cps 
Pot Life at 770 F (250 C) 
3 – 4 h (thin film set time) 
Cure time (>55 °F) 
24 h 
Density at 392 ⁰F (200 ⁰C) 
Part A: 70.5 lb./ft3 (1.13 kg/L) 
Part B: 62.4 lb./ ft3 (1.00 kg/L) 
Tensile Strength (ASTM D638) 
Tensile Modulus (ASTM D638) 
7,150 psi (49 MPa) 
289,000 psi (1,992 MPa) 
Flexural Strength (ASTM D790) 
Flexural Modulus (ASTM D790) 
11,140 psi (77 MPa) 
252,400 psi (1,740 MPa) 
Compressive 
Strength 
(ASTM 
D695) 
Compressive Modulus (ASTM D695) 
13,000 psi (90 MPa) 
350,000 psi (240 MPa) 
Water Absorption (% gain) in 24 hours 
< 1% 
Expansion Coefficient [-37.40 – 40.10 ⁰C] 
Expansion Coefficient [1,200 – 2,220 ⁰C] 
78 ×10-6 m/m ⁰C 
151.8 ×10-6 m/m ⁰C 
2.06 
OTHER MATERIALS 
The Contractor shall provide compatible primer, filler and other materials recommended 
by the FRP material supplier as needed for the proper installation of the surface bonded 
FRP system. Vinyl ester resins can be used to saturate the FRP fabrics as an alternative to 
epoxy as requested per paragraph 1.09 – SUBSTITUTIONS. The vinyl ester (or epoxy) 
resins shall have the minimum physical and mechanical properties as provided in the 
Table below. It should be noted that use of vinyl ester resins will require additional safety 
measures when applied in confined space due to styrene or other monomer emissions. 
Cure times of vinyl ester resins vary in a wide range, and if the project requires faster cure 
times than those provided by the FRP material supplier in ambient temperature, then 
heating of resin during application should be considered commensurate with the FRP 
material supplier’s curing schedule.

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 13 
October 25, 2024 
SECTION 02720 
                                                                   FIBER REINFORCED POLYMER (FRP) 
 
 
 
Sample Epoxy or Vinyl Ester Resin Properties Table 
Viscosity (ISO 2555) 
200 – 250 cps 
Gel Time 
30 min 
Density 
62.4 lb./ ft3 (1.00 kg/L) 
Tensile Strength (ASTM D638) 
Tensile Modulus (ASTM D638) 
12,800 psi (88 MPa) 
460,000 psi (3.2 GPa) 
Flexural Strength (ASTM D790) 
Flexural Modulus (ASTM D790) 
22,000 psi (153 MPa) 
500,000 psi (3.5 GPa) 
Compressive Strength (ASTM D695) 
17,600 psi (121 MPa) 
Water Absorption (% gain) in 24 hours 
< 1% 
Expansion Coefficient [-37.40 – 40.10 ⁰C] 
Expansion Coefficient [1,200 – 2,220 ⁰C] 
78 ×10-6 m/m ⁰C 
151.8 ×10-6 m/m ⁰C 
 
PART 3 – EXECUTION 
3.01 
GENERAL PROCEDURES 
The design of the FRP reinforcement shall conform to the design provisions given for the 
project and applicable standards. 
3.02 
INSTALLATION BY THE WET LAYUP METHOD 
The Contractor may propose installation techniques and design improvements to meet the 
project goals and design requirements outlined in the Design Drawings and Technical 
Specifications. Such proposed changes shall be submitted as part of the Performance 
Work Statement (PWS) per paragraph 1.07. 
A. Surface Preparation 
The Contractor shall prepare the surface receiving FRP per Technical Specification 
Section 02146 – SEWER PIPE AND SEWER STRUCTURE CLEANING including 
the following: 
 
1. The Contractor shall expose and inspect the pipe and manholes to be rehabilitated 
with the FRP system. Inspection shall verify the existing conditions of the concrete. 
 
All proposed repairs and restoration technique submittals shall be approved prior 
to surface preparation.

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 14 
October 25, 2024 
SECTION 02720 
FIBER REINFORCED POLYMER (FRP) 
 
 
 
The Contractor shall examine the existing conditions to identify potential 
obstructions and constraints, shall verify dimensions, geometry, and access 
locations. 
 
An adhesive bond with adequate strength shall be provided between the first layer 
of the FRP system and substrate. Surface preparation shall also promote continuous 
intimate contact between the FRP system and substrate by providing a clean, and 
smooth surface. 
 
2. Surface Grinding/Blasting: All irregularities, unevenness, and sharp protrusions in 
the surface profile shall be mechanically ground away to a smooth surface with 
CSP 3/CSP 2 surface profile for substrate. Disk grinders or other similar devices 
shall be used to remove previously applied coatings, stain, paint, or any other 
surface substance that may affect the bond. Voids or depressions with diameters 
larger than 1 ½ in. or depths greater than 1/8 in., when measured from a 12-in. 
straight edge placed on the surface, shall be filled according to Section 3.02 
paragraphs A.4. 
3. Crack Injection: In case of host pipe having deep cracks and fractures to an extent 
that it imposes a risk of failure of the substrate during FRP application, these cracks 
and fractures shall be filled, and the host pipe shall be pre-strengthened by crack 
injection. Where crack injection is necessary, internal, or external cracks at a width 
specified by the Engineer shall be filled using pressure injection of epoxy. The FRP 
system shall be installed no earlier than 12 hours after crack injection. Any surface 
roughness caused by injection shall be removed as per Section 3.02 paragraph A.2. 
 
4. Surface Profiling: After surface grinding, if necessary, any remaining unevenness 
in the surface greater than that specified in Section 3.02 paragraph A.2, fins, 
protrusions, voids, bug holes, depressions, eroded or un surfaces shall be filled 
and smoothened over by using putty made of epoxy resin mortar or polymer 
cement mortar. 
 
5. Surface Cleaning: Substrate concrete and finished surface of concrete shall be 
cleaned prior to application of the FRP system. Cleaning shall remove any dust, 
laitance, grease, oil, curing compounds, wax, stains, coatings (as necessary), 
surface lubricants, foreign particles, weathered or deteriorated concrete layers, or any 
other bond-inhibiting material. If power wash is used, the surface shall be allowed 
to dry thoroughly before installing the FRP system. If grit blast media is used, the 
surface shall be cleaned of expended media and all loose materials before 
installing the FRP system. The clean surface shall be protected against 
redeposition of any bond-inhibiting materials. 
 
B. Installation 
This section specifies general installation procedures for the wet lay-up of the FRP 
system composed of FRP laminae. The Contractor shall submit a site-specific

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 15 
October 25, 2024 
 
SECTION 02720 
                                                                   FIBER REINFORCED POLYMER (FRP) 
installation procedure in the PWS, which shall, at the minimum, include the following 
measures. 
 
1. Environmental Conditions: Environmental conditions for installation shall be 
examined before and during installation of the FRP system to ensure conformity to 
the Contract Documents and FRP Material Supplier’s recommendations. Primers, 
putty, saturating resins, or adhesives shall not be applied on cold, frozen, damp, or 
wet surfaces, unless the resin is moisture tolerant. Ambient, concrete, and steel 
surface temperatures shall be within 45-95 °F (7-35 °C). Moisture level on all 
contact surfaces shall be less than 10 percent at the time of installation of the FRP 
system, as evaluated according to ACI 503R-93. Moisture restrictions may be 
waived for resins that have been formulated for wet applications. Work areas 
identified as confined space require an entry permit in accordance with OSHA 
regulations. The Contractor is responsible for the training of all personnel, air 
testing, safety equipment and complying with the requirements of OSHA. A 
detailed Safety Plan shall be submitted by the Contractor as part of the Technical 
Specification Section 01300 – SUBMITTALS. 
2. Moisture Vapor Transmission: Application of bonded FRP systems shall not 
proceed if any moisture vapor transmission is present. Concrete dryness is 
necessary when using elevated temperature cure. Any bubble that develops from 
moisture vapor transmission can effectively be injected with the same adhesive 
material used for the FRP system following the procedure specified in Section 3.02 
paragraph A.3. 
 
3. Applications in Inclement Weather: When inclement weather does not allow 
installation of the FRP system, as specified in Section 3.02 paragraph B.1, auxiliary 
measures may be employed to correct the conditions. An auxiliary heat source may 
be used in cold weather to raise the ambient and concrete surface temperatures to 
acceptable levels during product application and cure duration, as recommended 
by the FRP material supplier, but not higher than the glass transition temperature 
(Tg) of the primer or saturating resin. Pressurized air, with an effective oil 
separator, may be used to dry the surface dampness. 
4. Equipment: The Contractor shall provide all necessary equipment in sufficient 
quantities and clean operating conditions for continuous uninterrupted FRP system 
installation. 
 
5. Mixing of Resin Components: All resin components, including the main agent and 
hardener, shall be mixed at the proper temperature using the appropriate weight 
ratio and for a duration specified by the FRP material supplier until thorough 
mixing with uniform color and consistency is achieved. The resins shall not be 
diluted with any organic solvents such as a thinner. Electrically powered mixing 
blades can be used for mixing. Resin shall be mixed in quantities sufficiently small 
to ensure that it can be used within its pot life. Any mixed resin that exceeds its pot 
life or begins to generate heat or shows signs of increased viscosity shall not be

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 16 
October 25, 2024 
SECTION 02720 
FIBER REINFORCED POLYMER (FRP) 
 
 
 
used and shall be disposed of according to the SDS. The mixing of some resins may 
be accompanied by noxious fumes. Precautions must be taken regarding the resin’s 
impact on the environment, including emission of volatile organic compounds. If 
flammable resins are used, explosion proof electrical motors or air driven motors 
shall be used for mixing and installation of the materials. 
 
6. Primer and Putty: When necessary, apply one (1) or two (2) coats of primer on the 
substrate surface to penetrate its open pores. Putty, if used, shall be applied as soon 
as the primer becomes tack free or is not sticky to the fingers. Putty shall be applied 
within seven (7) days after primer application; otherwise, the primer- coated surface 
shall be roughened with sandpaper or a similar tool. The resulting surface shall be 
cleaned according to Section 3.02 paragraph A.5 before applying the putty. Apply 
a minimum of 40-mil (1 mm) thick coat of putty in one (1) layer, and smooth over 
the surface to fill in any small voids, cracks, or uneven areas. Any swelling on the 
surface after applying the putty shall be corrected to meet surface profile as 
specified in Section 3.02 paragraph A.4. The surfaces of primer and putty shall be 
protected from dust, moisture, and any other contaminants before applying the FRP 
system. 
7. Saturant: Saturant is the term for the engineered resin used to impregnate FRP 
fabrics and turn them into laminae upon cure. The saturant used in a FRP system 
shall have sufficiently low viscosity to ensure full impregnation of the fiber sheets 
prior to curing. To maintain proper viscosity of the saturant, the ambient and 
substrate surface temperatures must be within the range specified in Section 3.02 
paragraph B.1. Any mixed saturant that exceeds its pot life shall be disposed of 
according to Section 3.05. 
 
8. Applying Fiber Sheet and Saturant: The fabric shall be uniformly saturated with 
the saturant using the saturating machine or hand saturated, where site conditions 
are not favorable for using the machine. The fabric shall be cut to the length 
specified in the Contract Documents and shall be installed in place and gently 
pressed onto the wet putty. Any entrapped air between the fiber sheet and the 
surface shall be released or rolled along the sheet in the direction parallel to the 
fibers while allowing the resin to impregnate the fibers and achieve intimate contact 
with the substrate. Rolling perpendicular to the fiber direction is not permitted. In 
bi- directional fabrics, rolling shall be initially in the fill (transverse) direction end 
to end and then in the warp (longitudinal) direction. 
 
9. Multiple-Fiber Plies: Subsequent layers of fabric (if called for in the design), shall 
be properly saturated with saturant and applied on top of the first sheet of fabric 
with no interruption. The amount of resin overcoat for intermediate plies shall 
factor in overcoat for the applied ply and undercoat for the next ply. Follow the 
PWS and approved shop and Design Drawings for the fiber orientation and ply 
stacking sequence. Each ply and core fabric shall be applied before the onset of 
complete gelation of the previous layer. The number of plies that can be applied in 
a single day shall be based on the FRP material supplier’s recommendation When

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 17 
October 25, 2024 
SECTION 02720 
                                                                   FIBER REINFORCED POLYMER (FRP) 
 
previous layers are cured, interlayer surface preparation, such as light sanding and 
filling with putty, may be required, as specified in Section 3.02 paragraph B.6. 
 
10. Overlapping: Lap joints shall be constructed over a minimum of one (1) CFRP or 
GFRP laminate. The lap joint layer shall not be the top laminate. The length of the 
lap splice shall be as specified by the Contract Documents but must be a minimum 
of 6-inches (152 mm) long. Staggering of lap splices on multiple plies and adjacent 
strips shall be required unless permitted by Contract Documents. 
 
11. Alignment of FRP Materials: The fiber plies shall be aligned on the host pipe 
according to the Contract Documents. Any deviation in the alignment more than 5 
degrees (approximately 1 in./ft) is not acceptable and shall be grounds for rejection. 
Once installed, the fibers shall be free of kinks, folds, and waviness. 
12. Termination Points: The termination points of the FRP system shall be installed 
such that water is not allowed to seep in between the surface and the FRP system. 
The FRP system shall be sealed properly at the termination points by applying 
epoxy sealant. In locations where flow velocities are high or in pressurized 
conduits, elastomeric internal joint seals with compressed steel bands shall be used 
at the termination points, with the appropriate approved details included in the 
Design Drawings. 
 
13. Curing: The FRP system shall be allowed to cure for the minimum amount of time 
specified per the FRP material supplier’s requirements. Field modification of resin 
chemistry for rapid curing shall not be allowed. An elevated cure temperature may 
be used if rapid curing is necessary. The cure of installed plies shall be monitored 
before placing subsequent plies. In case of any curing irregularity, installation of 
subsequent plies shall be halted. Protect the FRP system while curing. 
 
14. Protective Coating and Finishing: It is permissible to use a protective coating for 
abrasion resistance and improved flow conditions. The protective coating shall be 
either thickened epoxy, with or without a pigment added to facilitate inspection, or 
another resin as agreed between the City or City’s Representative and Contractor. 
The protective coating shall be compatible with exposure conditions including 
corrosive gases, moisture, abrasive chemicals in sewage, salt water, and physical 
abrasion due to debris and silt in sewers. Applicability of the topcoat to the FRP 
system in abrasive environments shall be verified by testing (ASTM D4060). 
 
15. Protective Coating Field Application: Surface preparation shall be as 
recommended by the FRP material supplier. Solvent wipes shall not be used to 
clean the FRP surface unless approved by the FRP material supplier. If abrasive 
cleaning is necessary, air pressure shall be limited to avoid any damage to fibers. 
Ambient and surface temperatures shall be within the range specified in Section 
3.02 paragraph B.1, prior to applying the protective coating.

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 18 
October 25, 2024 
SECTION 02720 
FIBER REINFORCED POLYMER (FRP) 
 
 
 
3.03 
INSPECTION & QUALITY ASSURANCE 
 
The Contractor shall coordinate with and accommodate the needs of the City or City’s 
representative Quality Assurance inspector. The Contractor shall provide a specific 
quality assurance (QA) plan for the tests identified. The Contractor shall provide its own 
onsite inspector for Quality Control (QC). 
 
The project specific QA/QC plan shall be included in the PWS submittal that includes: 
 
A. Inspection of Materials: The FRP material supplier’s certifications for all delivered 
and stored FRP components shall be inspected for conformity to the Contract 
Documents before starting the project. Materials testing shall be conducted on samples 
as detailed in the PWS. Any material that does not meet the requirements of the 
Contract Documents or PWS will be rejected. Additional inspection measures may be 
taken during the installation process at the discretion of the City or City’s 
representative. 
 
B. Daily Inspection: Daily inspection shall include date and time of repair; relative 
humidity; general weather conditions; surface dryness per ACI 503.4-92; surface 
preparation and surface profile using ICRI surface profile chips; qualitative description 
of surface cleanliness; type of auxiliary heat source, if any; widths of cracks not injected 
with epoxy; fiber or procured laminate batch numbers and their locations in the 
structure; batch numbers, mixture ratios, mixing times, and qualitative descriptions of 
the appearance of all mixed resins, primers, putties, saturants, adhesives, and coatings; 
observations of the progress of the cure of resins; conformance with installation 
procedures; adhesion test results of bond strength, failure mode, and location; FRP 
properties from tests of field sample panels or witness panels, if required; location and 
size of any delamination’s or air voids; lot number, manufacturer and expiration date 
of applied materials, and the general progress of work. 
 
C. Inspection for Fiber Orientation: Fiber or ply orientation, fiber kinks, and waviness 
shall be examined by visual inspection for conformity to the Contract Documents. 
Tolerances will follow Sections 3.02 and 3.03. Any nonconforming FRP repair area 
shall be removed and repaired as per Section 3.04 – Repair of Defective Work. 
D. Inspection for Debonding: After at least 24 hours from initial installation of the resin, 
a visual inspection of the surface shall be performed for any swelling, bubbles, voids, 
or delamination. If an air pocket is suspected, an acoustic tap test shall be carried out 
with a hard object to identify delaminated areas by sound, with at least one strike per 
one (1) foot2. Delamination defects smaller than 0.5-inch in diameter shall require no 
corrective action, unless as specified in Section 3.04 paragraph A. Delamination 
defects larger than 0.5-inch but smaller than 2-inch in diameter will be repaired as per 
Section 3.04 paragraph B. Delamination defects larger than 2-inch but smaller than 6-
inch in diameter, and with a frequency of less than five (5) per 10 foot2 of surface 
area, shall be repaired as per Section 3.04 paragraph C. Larger delamination defects 
shall be repaired as per Section 3.04 paragraph D.

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 19 
October 25, 2024 
SECTION 02720 
                                                                   FIBER REINFORCED POLYMER (FRP) 
 
E. Inspection for Cure of Resin: If specified in the Contract Documents, the relative cure 
of resin in FRP systems shall be examined by visual inspection or by third party 
laboratory testing of resin-cup samples using ASTM D3418. Follow recommendations 
of the resin FRP material supplier for acceptance criteria. If the cure of resin is found 
unacceptable, the entire area shall be marked and repaired as per Section 3.04. 
 
F. Tests: Specimens from the installed FRP system or samples representative thereof, 
shall be tested at the request of the City, City’s Representative, for tensile, compressive, 
and adhesive strengths. A minimum of 2 witness panels per day shall be obtained on 
the days the FRP system is installed at the project site. 
Adhesion test: Refer to ASTM D7234 for adhesion to concrete. To validate the 
adequacy of the surface preparation and the adhesion strength of the FRP system, the 
Contractor shall perform random adhesion tests on the prepared concrete substrate of 
pipe segments adjacent to repair pipes as directed by the Engineer and witnessed by the 
City’s Representative. The City’s Representative should designate the areas for trial 
adhesion tests prior to the surface preparation activities. These areas shall be cleaned, 
prepared, and covered with two-ply FRP system test patches with minimum dimensions 
of 1-foot x 1-foot for adhesion test to concrete substrate. The patch shall consist of two 
orthogonal plies of FRP laminae. One (1) adhesion test shall be performed on each test 
patch. The remaining adhesion test patches shall be finish coated and remain in place 
for future testing purposes as needed. The Contractor shall log the location of the 
adhesion test and report the test results to the City or City’s Representative. 
 
Tensile strength test (ASTMD3039): Depending on the composition of the FRP system 
used for a particular application, test panels shall be field fabricated using two (2) FRP 
system layers of glass fiber fabric, any core (3D) fabric, resins and saturation equipment 
used in the application. Tensile test panels shall be approximately 12-inch by 12-inch. 
The test panel shall be prepared on a smooth flat surface overlaid with plastic 
(polyethylene or vinyl) sheeting. Saturating resin shall be used to prime the surface, 
followed by the saturated system, and finally topped with more saturating resin. A 
cover of plastic sheeting shall be placed over the panel and the panel squeegeed to 
remove any bubbles and other surface irregularities to ensure a smooth flat surface. The 
panel shall be labeled with time, date, and sample panel number, fabric lot numbers, 
and resin batch numbers, and stored in an environment representative of the surface 
being repaired condition to cure until collected for lab testing. 
 
The test lab shall perform a minimum of five (5) tensile tests with the fibers oriented 
in the strong direction for each tensile test panel in accordance with ASTM D3039, and 
report certified tests results for tensile strength, tensile modulus, related specimen 
dimensions, and percent elongation. For projects where multiple test panels with the 
same fabric batch are prepared, it is permissible to perform three (3) tension tests per 
panel instead of five (5) tests per panel, subject to review and approval by the Engineer. 
 
The FRP system will be unacceptable if the average tensile strength per unit width is 
below that specified in the Contract Documents.

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 20 
October 25, 2024 
SECTION 02720 
FIBER REINFORCED POLYMER (FRP) 
 
 
 
Holiday “Spark” Testing: The Contractor shall furnish services of a trained operator 
in holiday detection devices until final acceptance of the FRP system. Devices shall 
be tested and operated in the presence of the City or City’s Representative. The 
Contractor shall perform holiday testing on all FRP surfaces in the presence of the 
City or City’s Representative. The Contractor shall be responsible to repair defective 
areas and retest the FRP system as necessary at no additional cost to the City. 
 
3.04 
REPAIR OF DEFECTS 
 
This section specifies the conditions and types of defects that require repair and the 
acceptable methods of repair. Defects are of different types and may be generally classified 
as aesthetic, short-term critical, or long-term critical. Repair procedure depends on the type, 
size, and extent of defects. Repair procedures indicated below are exemplary, and the actual 
procedure specific to each project shall be submitted as a part of the PWS. 
A. Repair of Protective Coating: 
Defects in protective coating can be of three (3) types: small hairline cracks, blistering, 
and peeling. In all cases, the moisture content of the substrate should be below 0.05% 
before applying a new coating. Prior to any repair of protective coating, the FRP system 
shall be examined visually or otherwise to ensure that no defect exists within or on the 
surface. 
Defects in FRP, if found, shall be repaired as described below. If protective coating appears 
to show small areas with cracks, the local surface shall be lightly sanded. Then a new 
coating with the appropriate primer shall be applied according to the FRP material 
supplier’s recommendations. At the minimum, the coating shall be applied over an area 
extending 1-inch on either side of the defect. If the protective coating shows signs of 
blistering, the entire area of blisters as well as the surrounding area to a distance of at least 
12-inches shall be carefully scraped clean. In no case should a blistered surface be recoated 
without complete removal of the existing coating. The area shall be wiped clean and dried 
thoroughly. Once dry, the area can be recoated after application of the primer coat if 
required by the FRP material supplier. If the surface shows signs of excessive peeling, the 
entire coating shall be scraped off and the surface lightly sanded, wiped clean, and 
thoroughly dried before applying a new coat according to the FRP material supplier’s 
recommendations. 
B. Epoxy Injection of Small Defects: 
Small entrapped voids or surface discontinuities no larger than 0.5-inch in diameter shall 
not be considered defects and require no corrective action unless they occur next to edges 
or when there are more than five (5) such defects in an area of ten (10) foot2. Small defects 
of size between 0.5-inch and 2-inches in diameter shall be repaired using low-pressure 
epoxy injection if the defect is local and does not extend through the complete thickness of 
the FRP system.

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 21 
October 25, 2024 
SECTION 02720 
                                                                   FIBER REINFORCED POLYMER (FRP) 
 
C. Patching of Minor Damage: 
Minor defects are those with diameters between 2-inches and 6-inches and a frequency of 
less than five (5) per unit surface area of 10 foot2. The area surrounding the defects to an 
extent of at least 1-inch on all sides shall be carefully removed. The area shall be wiped 
clean and thoroughly dried. The area shall then be patched by adding an FRP patch 
extending at least 1-inch on all sides of the removed area. 
D. Replacement of Large Defects: 
Defects larger than 6-inches in diameter shall be carefully marked and scarfed out 
extending to a minimum of 1-inch on all sides. Scarfing shall be progressing through the 
layers of the FRP system until past the defective area. The substrate shall be appropriately 
prepared, and primer reapplied after ensuring that the surface is clean and dry. Application 
of an FRP patch system shall extend a minimum of 6-inches on all sides of the scarfed area. 
Once cured, the protective coating shall be applied over the entire area. 
3.05 
STORAGE, HANDLING, AND DISPOSAL 
 
A. Storage Requirements: All components of the FRP system must be delivered and 
stored in the original factory-sealed, unopened packaging or in containers with proper 
labels identifying the FRP material supplier, brand name, system identification number, 
manufacture date, and expiration date. Catalysts and initiators should be stored 
separately. All components must be protected from dust, moisture, chemicals, direct 
sunlight, physical damage, fire, and temperatures outside the range specified in the 
system data sheets. Any component that has been stored in a condition different from 
that stated above must be disposed of, as specified in Section 3.05 paragraph G. 
 
B. Shelf Life: All components of the FRP system, especially resins and adhesives, that 
have been stored longer than the shelf life specified on the system data sheet shall not 
be used and must be disposed of, as specified in Section 3.05 paragraph G. 
 
C. Handling: All components of the FRP system, especially fiber sheets, must be handled 
with care according to the FRP material supplier recommendations to protect them 
from damage and to avoid misalignment or breakage of the fibers by pulling, 
separating, or wrinkling them or by folding the sheets. After cutting, sheets shall be 
either stacked dry with separators or at a radius no tighter than 12-inches or as 
recommended by the FRP material supplier. 
 
D. Safety Hazards: All components of the FRP system, especially resins and adhesives, 
must be handled with care to avoid safety hazards, including but not limited to skin 
irritation and sensitization, and breathing vapors and dust. Mixing resins shall be 
monitored to avoid fuming and inflammable vapors, fire hazards, or violent boiling. 
The Contractor is responsible for ensuring that all components of the FRP system at all 
stages of work conform to the local, state, and federal environmental and worker’s 
safety laws and regulations. The Contractor is advised that a forced ventilator system

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 22 
October 25, 2024 
SECTION 02720 
FIBER REINFORCED POLYMER (FRP)                                                    
 
 
may be required inside enclosed sections and that provision for ventilation, if any, shall 
be included in the cost of the work. Refer to the Safety Plan as specified in Section 3.02 
paragraph B-1 for details. 
 
E. Safety Data Sheets: The SDS for all components of the FRP system shall be accessible 
to all at the project site. Specific handling hazards and disposal instructions shall be 
specified in the SDS section entitled Personnel and Workplace Protection. The 
Contractor is responsible for providing the proper means of protection for safety of the 
personnel and the workplace. 
The Contractor shall inform the personnel of the dangers of inhaling fumes of primer, 
putty, or resin and shall take all necessary precautions against injury to personnel. The 
resin mixing area shall be well vented to the outside. Refer to the Safety Plan as 
specified in Section 3.02 paragraph B-1 for details. 
 
F. Clean-Up: The Contractor is responsible for the cleanup of the equipment and the 
project site from hazardous and aesthetically undesirable FRP components using 
appropriate solvents, as stated in the safety data sheet. 
 
G. Disposal: Any component of the FRP system that has exceeded its shelf life or pot life 
or has not been properly stored, and any unused or excess material that is deemed waste 
shall be disposed of in a manner amiable to the protection of the environment and 
consistent with the SDS. 
 
3.06 
PROJECT CLOSE-OUT AND MAINTENANCE 
 
Documentation of the work: The City requires documentation of the work to be prepared 
and submitted to the City or City’s Representative by the Contractor on completion of the 
work according to Technical Specification Section 01300 - SUBMITTALS. The 
documentation shall include the following: 
 
1. Information on the products and installation method used. 
2. Pre- and post-inspection results. 
3. Test results. 
4. Any changes or deviations from the Contract Documents and possible corrective 
work. 
 
A. Verification/Basis for Rejection: Materials not complying with the requirements of 
this Technical Specification shall be rejected at the discretion of the City or City’s 
Representative. Repairs, replacements, and retesting shall be accomplished in 
accordance with the Contract Documents at no additional cost to the City.

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 23 
October 25, 2024 
SECTION 02720 
                                                                   FIBER REINFORCED POLYMER (FRP) 
 
B. Affidavit of Compliance: The City requires an affidavit from the FRP material supplier 
or Contractor, as applicable, that the material provided, or the installation performed 
complies with the applicable requirements of the Technical Specifications provided 
herein and delivered to the City or City’s Representative according to Technical 
Specification Section 01300 - SUBMITTALS. 
 
3.07 
PROTECTION OF SITE: 
 
Except as otherwise provided herein, the Contractor shall protect from damage all fences, 
structures, sidewalks, utilities, trees, shrubbery, lawns, etc., during the progress of this 
work. All debris and unused materials shall be removed immediately upon completion of 
the work. The site shall be restored as nearly as possible to its original condition, including 
the replacement, at the Contractor's sole expense, of any facility or landscaping which has 
been destroyed or damaged beyond restoration. 
 
3.01 
UTILITIES: 
 
The Contractor shall arrange for and provide any required utilities at the Contractor’s sole 
cost and expense. This includes but is not limited to water, power for operating any 
equipment along with personnel sanitation facilities. 
 
3.02 
CLEANING AND PREPARATION 
 
A. The Contractor shall be responsible for all cleaning and surface preparation. The 
Contractor shall notify the City’s Representative of any irregularity, which may 
interfere with the proper installation. 
3.03 
ACCEPTANCE 
 
As a condition precedent to Final Acceptance of the work, Contractor shall certify the 
proper installation and testing of material provided under this section. Certification shall 
warrant that materials and installation are free of defects and/or workmanship and suitable 
for trouble-free operation under the conditions set forth in these Technical Specifications. 
 
 
** END OF SECTION **

City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02720 - 24 
October 25, 2024 
SECTION 02720 
FIBER REINFORCED POLYMER (FRP) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[This page intentionally left blank for double sided printing]

SECTION 02760  
SEWER PIPE AND SEWER STRUCTURE CLEANING  
 
 
______________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02760 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01  DESCRIPTION  
  
A. SCOPE:  
  
This section specifies the requirements for cleaning of sanitary sewer pipes and 
manhole structures prior to remote visual inspection and pipe / manhole 
rehabilitation.  
  
B. REQUIREMENTS:  
  
The work to be done consists of furnishing all labor, materials, and equipment 
to remove loose or detached PVC liner, accumulated sediments and debris 
down to sound, solid structural material. The Contractor shall grit blast or hydro 
blast with a minimum 1000 PSI water pressure for duration sufficient to clean 
to lining manufacturer’s recommendations. 
 
The Contractor shall remove obstructions, deteriorated or loose PVC linings, 
existing sediment, debris, roots, scale, encrustations, and grease accumulations 
from the sanitary sewer pipes and sewer structures to be inspected and/or 
rehabilitated and adequately prepare the surfaces for CIPP liner installation, 
manhole inserts and/or grout repair.  All materials dislodged during cleaning 
and surface preparation shall be removed from the pipe and manhole work area 
and delivered to an approved disposal site.  
  
1.02  SUBMITTALS  
  
A. The following submittal shall be provided in accordance with Technical 
Specification Section 01300 - SUBMITTALS:  
  
1. A letter report identifying the methods the Contractor anticipates employing 
to remove loose/detached linings, sediment, debris, grease, scale, 
encrustations, and roots throughout the sanitary sewer pipe to be 
rehabilitated and in the sanitary sewer structures to be repaired or coated.  
The letter report shall include a detailed explanation of the surface 
preparation process and a schedule of activities and references where the 
Contractor has used the identified cleaning method successfully in the past.   
 
PART 2 - MATERIALS  
  
2.01  CHEMICAL ADDITIVES  
  
A. No chemicals shall be used without written approval of the City.  In no case

SECTION 02760 
SEWER PIPE AND SEWER STRUCTURE CLEANING 
 
 
______________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02760 - 2 
October 25, 2024 
shall any chemical additive be used which might be considered hazardous or 
might be considered detrimental to organisms or equipment of a wastewater 
treatment plant, or detrimental to old or new pipe materials.    
  
A Safety Data Sheet (SDS) shall be posted onsite with a copy supplied to the 
City for all chemicals anticipated to be used in the project or brought on-site.  
   
 
PART 3 - EXECUTION  
  
3.01  GENERAL  
  
The Contractor shall at all times conduct work so as to prevent any detrimental 
sewage blockage and minimize surcharging in the sewer manholes or connecting 
sanitary sewer system.  Damage to existing facilities as a result of the Contractor's 
work shall be promptly repaired in kind at the Contractor's expense.  
  
3.02  SEWER BYPASSING AND DEWATERING  
  
Sewer flow shall be bypassed or temporarily plugged during the cleaning of the 
sewers as specified in Technical Specification Section 02145 – DIVERSION OF 
SEWAGE FLOW AND DEWATERING. 
  
3.03  CLEANING  
  
Cleaning shall remove all loose or hanging lining and/or coatings previously 
applied, sediment, rocks, debris, roots, grease accumulations and obstructions from 
the manhole and pipe to be rehabilitated. Cleaning of the interior surfaces shall 
remove all grease, scale, encrustation, and any other material from the surface that 
may impede lining installation.  Multiple passes with cleaning equipment may be 
required at no additional cost to the City.  
 
Sediment, material or debris from cleaning operations larger than U.S. #8 sieve 
shall not be deposited downstream in the sewer main.  Sedimentation deposited 
downstream shall be removed at no cost to the City.    
 
The Contractor shall be thoroughly familiar with all phases of structure cleaning to 
ensure that surface preparation is adequate for lining installation without causing a 
health hazard or damage to the sanitary sewage system, and public and private 
properties.  
  
The Contractor shall clean the pipe and manhole so that there is no visible residue, 
rocks, debris, roots, grease accumulation and/or obstructions.  The Contractor shall 
clean the structure adequately for proper installation of the sewer rehabilitation 
method proposed.

SECTION 02760 
                               SEWER PIPE AND SEWER STRUCTURE CLEANING 
 
______________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02760 - 3 
October 25, 2024 
 
Man entry into the interior of the pipe and/or manhole may be required to remove 
loose, hanging or deteriorated material that may impact the rehabilitation.   
  
3.04  DISPOSAL OF SEDIMENTS  
  
The Contractor shall be responsible for transporting and disposing, including all 
disposal fees, of any sediments and material removed from the sewer or structures 
per 
Technical 
Specification 
SECTION 
01560 
– 
ENVIRONMENTAL 
CONTROLS.  
  
All sediment and debris removed from the sewer shall be disposed off-site in a 
lawful manner.  Hauling containers shall be watertight.  On-site stockpiling of 
removed material is not acceptable or allowed.  
  
The Contractor is responsible for obtaining all necessary permits, fees, and 
approval from all regulatory agencies required to perform the work, including 
transport of sediments.  Off-site disposal of all material removed from the sewer 
shall be the Contractor's responsibility.  
  
Copies of all disposal receipts shall be submitted to the City.  
  
  
  
** END OF SECTION **

SECTION 02760 
SEWER PIPE AND SEWER STRUCTURE CLEANING 
 
 
______________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02760 - 4 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double-sided printing ]

SECTION 02761 
REMOTE CCTV INSPECTION   
OF EXISTING AND REHABILITATED SEWERS  
  
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02761 - 1 
October 25, 2024 
PART 1 - GENERAL  
  
1.01 
DESCRIPTION  
  
A. This Technical Specification defines the requirements for internal remote CCTV 
inspection of the interior of existing sanitary sewer pipe prior to (pre-video) and after 
rehabilitation (post-video) construction activities. Post video documentation shall be 
utilized to assist in determination of work acceptance and final payment.  
 
The Contractor shall inspect the sewer interior using a camera or process capable of 
producing a color 360-degree digital image of the pipe interior for permanent record 
and documentation of inspection with audio annotation, date and location information, 
and title information.  
 
The Contractor shall be responsible for identifying and documenting existing defects 
present within the pipe that were previously underwater and out of sight during the 
Drawings development. CCTV will also be utilized to document the final condition of 
the rehabilitated pipe showing the size and location of the repair along with capturing 
the written signature of the quality control inspector directly on the repair to signify its 
acceptance.  
 
The Contractor shall utilize remotely operated equipment to record digital video 
footage and collect data to determine the condition of the pipes.  The Contractor shall 
document the findings and bring to the attention of the City those locations with issues  
that may adversely impact the final grade of the new liner.   The Contractor shall repeat 
the investigation following CIPP liner installation to document the final pipe grade as 
evidence of proper installation and payment of work. 
 
1.02 
QUALIFIATIONS AND EXPERIENCE 
 
The Contractor shall utilize a National Association of Sewer Service Companies 
(NASSCO) certified technician to operate the CCTV camera to document the interior 
sewer pipe condition and repairs performed. 
 
1.03 
SUBMITTALS  
 
Contractor shall submit the following information for review per Technical Specification 
Section 01300 – SUBMITTALS: re-write so it makes more sense 
  
1. The Contractor shall submit the camera operator’s name and current NASSCO 
Pipeline Assessment Certification Program (PACP) certification number. Any 
camera operator personnel change will require an updated name and certification

SECTION 02761 
REMOTE CCTV INSPECTION 
OF EXISTING AND REHABILITATED SEWERS 
  
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02761 - 2 
October 25, 2024 
number submitted for approval prior to work being completed by that individual.  
 
2. The Contractor shall submit an example of the camera operator’s work consisting 
of one remote visual inspection record in digital format of the operator’s previous 
sewer inspection work complete with audio commentary and inspection log(s). The 
submitted record shall show sewers that are of the same diameter as the sewers in 
this project. The record and inspection logs will be reviewed to determine if the 
quality of the images, technique, and procedures are acceptable and if defect repairs 
are properly identified and documented. Samples shall be with the same camera, 
lighting equipment, and data handling procedures proposed for this work.  
 
3. The Contractor shall be responsible for modifications to their equipment and/or 
inspection procedures to achieve report material of acceptable quality. No CIPP 
lining installation work shall commence prior to approval of the camera format 
material by the City or City’s Representative. Once accepted, the report material 
shall serve as a standard for the remaining work.  
 
4. Digital Video Disk (DVD) records or other approved format shall include labels 
containing project titles, dates, including the City and Contractor company names. 
Contractor shall maintain a copy of all inspection documentation (video, databases, and 
logs) for the duration of the work and warranty period.  
 
5. The final video shall be submitted to the City or City’s Representative within ten (10) 
working days from the time the video was created.  
 
6. The Contractor shall submit written inspection logs and video procedures according to 
NASSCO PACP for pipes inspected. 
 
PART 2 - PRODUCTS  
  
2.01 
MATERIALS  
  
A. TELEVISION INSPECTION CAMERA(S) 
  
1. Camera(s) shall be intrinsically safe and shall be operative in 100 percent humidity 
conditions. Lighting intensity shall be remote controlled and shall be adjusted to 
minimize reflective glare. Lighting and camera quality shall provide a clear, 
focused picture of the entire inside periphery of the sewer. Camera shall have tilt 
and zoom capabilities to view 90 degrees to the pipe centerline for the entire 360 
degrees of the pipe circumference. Camera and associated equipment shall support 
the minimum of 768H x 494V pixels and 470H TVL NTSC resolution. 
 
2. The Contractor shall utilize equipment that allows for video to be performed within 
conditions noted in the specification. Contractor’s equipment shall be sized to fit

SECTION 02761 
REMOTE CCTV INSPECTION 
OF EXISTING AND REHABILITATED SEWERS 
  
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02761 - 3 
October 25, 2024 
within sewer segments. Any scrapes or damages to the manholes and pipe resulting 
from equipment used shall be addressed and corrected at the Contractor’s expense.  
 
B. DATA STORAGE DEVICES 
  
Video recordings of all sewer pipe inspections shall be copied to Digital Video Disk 
(DVD) disks or portable external hard drive compatible with the latest version of 
Microsoft Windows operating system. The audio portion of the composite video shall 
be sufficiently free from electrical interference and background noise to provide 
complete intelligibility of the oral report. Video recording shall be MPEG I and shall 
comply with ISO/IEC 11172 MPEG I specifications. The inspection image files 
(pictures) shall have the ability to be exported to Industry Standard Formats, including 
JPEG, BMP, and TIFF formats, and shall be capable of transfer between DVD and 
external hard drive. A copy of the video recordings shall be consolidated into 
subdirectories according to quarter section number and unique pipe segment numbering 
system as provided by the City.  
  
C. FOOTAGE COUNTER 
  
A footage counter device, which measures the distance traveled by the camera in the 
sewer, shall be accurate to plus or minus 2 feet in 1,000 feet. Footage counter record 
shall be measured and documented from the pipe/manhole interface. 
 
D. VIDEO TITLING 
  
Video equipment software shall include genlocking capabilities to the extent that 
computer generated data, (i.e., footage, date, size, address and location, etc.) as 
determined by the City or City’s Representative can be overlaid onto video, and both 
indicated on the television monitor and permanently recorded on the inspection video. 
Title page of reach recording shall contain the camera operator name and certification 
number. Absence of the certification number in the recording title page or video 
investigation recording completed by a non-certified video operator shall be grounds 
for rejection of video documentation recording. Costs to recreate the investigation 
video documentation by a certified video operator shall be the responsibility of the 
Contractor.  
  
 
PART 3 - EXECUTION  
  
3.01 
INSPECTION METHODS  
 
The Contractor shall inspect the sewer interior using a camera or process capable of 
producing a color image for permanent record and documentation of inspection in digital 
format (mpeg or jpeg) with audio location and date information, and data title information.

SECTION 02761 
REMOTE CCTV INSPECTION 
OF EXISTING AND REHABILITATED SEWERS 
  
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02761 - 4 
October 25, 2024 
 
Pre-video and post-video inspections shall be conducted in the same direction along the 
pipe.  
 
A. SCHEDULE 
 
The Pre-video remote visual inspection shall be performed after cleaning the sewer to be 
rehabilitated as specified in Technical Specification Section 02760 – SEWER PIPE AND 
SEWER STRUCTURE CLEANING and prior to rehabilitation of the pipe. The Contractor 
shall be responsible for conducting Post-video inspection after the rehabilitation of the 
sewer pipes has been completed.  
 
The Contractor shall submit post-video of segments within ten (10) working days from the 
date of pipe rehabilitation completion. The Contractor shall also submit hard copy post-
video inspection logs. 
 
B. VERBAL COMMENTARY 
 
The Contractor shall audio record narrative on the remote visual inspection the location, 
upstream and downstream control points, date, and time of the inspection.  
 
C. ACCESS 
 
The City or City’s Representative shall have full access to observe the monitor and all 
other operations at all times. The system of cabling employed to transport the camera 
and transmit its signal shall not obstruct the camera's view.  
 
D. INSPECTION RATE 
  
The camera shall traverse through the sewer from upstream manhole to downstream 
manhole. Maximum rate of travel shall be 30 feet per minute when recording analog 
images. Camera advancement shall be stopped at each joint to obtain a 360-degree view 
and at each repair location. 
  
E. IMAGE PERSPECTIVE 
  
1. The camera image shall be down the center axis of the pipe when the camera is in 
motion. The Contractor is required to provide a 360-degree view of the pipe 
interior. Points of interest shall also be documented and shall include, but not be 
limited to, defects, encrustations, mineral deposits, debris, sediment, pipe repair and 
any location determined not to be clean or part of proper pipe rehabilitation.  
 
2. Video recording of the pipe interior shall include a 360-degree view of the pipe to 
manhole connection at each upstream and downstream manhole location.

SECTION 02761 
REMOTE CCTV INSPECTION 
OF EXISTING AND REHABILITATED SEWERS 
  
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02761 - 5 
October 25, 2024 
 
F. SEWER IDENTIFICATION 
  
All inspection documentation shall include the sewer location identified by City of 
Glendale GIS, quarter section and manhole numbers.  
  
G. QUALITY CONTROL 
  
The City or City’s Representative will review DVDs or portable external hard drive to 
ensure compliance with the requirements listed in this Contract Documents. If any 
portion of the rehabilitation work is determined not acceptable, the unacceptable work 
shall be repaired or replaced, whichever the City or City’s Representative deems 
appropriate, and re-inspected and documented at no additional cost to the City.  
 
Final video documentation of the pipe interior following CIPP lining shall be one 
continuous recording documenting the entire length of the pipe segment, from manhole 
to manhole. If any portion of the pipe or lateral required additional repair, the entire 
length of pipe, including laterals (if present) must be recreated to produce a final 
construction record of the entire pipe length. Each repair location shall be documented 
in images of the entire circumference of the edge weld strip repair. No additional cost 
to the City will be allowed for video recreation. 
 
H. AS-BUILT LOG 
 
The Contractor shall document in Microsoft Excel format, the station, clock position 
location, and size of all PVC repairs made within the pipe. Log spreadsheet shall be 
submitted to the Owner for permanent record of repairs. 
 
 
 
** END OF SECTION **

SECTION 02761 
REMOTE CCTV INSPECTION 
OF EXISTING AND REHABILITATED SEWERS 
  
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
02761 - 6 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double-sided printing ]

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 1 
October 25, 2024 
PART 1 - GENERAL 
 
1.01 
DESCRIPTION 
 
A. SCOPE 
 
This section specifies the coating system used for the rehabilitation of municipal 
sanitary sewer manholes and structures to provide protection against chemical or gas 
corrosion. The coating shall yield a hard, durable, chemical resistant coating and 
provide a water and gas tight seal to concrete and other components within existing 
sanitary sewer collection system infrastructure. 
 
B. DEFINITIONS 
 
1) In this Technical Specification, the words “coating” (or “coatings”) and “lining” 
(or “linings” or “liner”) are used interchangeably. Similarly, “to coat” is used 
interchangeably with “to line” (or other variations of these words).  
 
2) In this Technical Specification, unless otherwise specifically noted, the word 
“manhole” shall mean “sewer structure” and shall encompass sewer manholes, 
sewer structures, sewer vaults, and other structures contained within the sanitary 
sewer system. It also encompasses sewer pipes (or portions thereof) that are located 
within the sewer structure but does not include sewer pipes (or portions thereof) 
that are located outside of the limits of the structure.  
 
3) In this Technical Specification, “existing manholes” shall mean those manholes 
that are (or were) not constructed as part of this project work. “Rehabilitating” 
existing manholes and "applying corrosion protective coating" to those manholes 
shall include the following activities:  
 
a. Cleaning and preparation of the surface to coating manufacture’s recommended 
standards and removing corroded/deteriorated materials from the manhole, and 
otherwise preparing the manhole for one of the approved coating systems. 
  
b. Testing of the prepared surface to coating manufacturer’s standards prior to 
applying an approved coating system. 
 
c. Applying one of the approved coating systems, as specified herein.  
 
d. Testing the finished surface coating, as required herein.  
 
e. Other related activities, as noted herein.

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 2 
October 25, 2024 
Where required by the Contract Documents, existing manholes shall be rehabilitated 
and an approved, or equal, corrosion protective coating applied to their interior 
surfaces, as specified herein.  
 
The approved coating system (as specified herein) shall be applied to exposed brick, 
concrete, grout, mortar, and cementitious surfaces or portions thereof that are not PVC 
lined within the manhole including pipe-to-throat transitions, throat, bench, risers, 
cones, chimney, adjusting rings, etc as indicated in the plans. 
 
1.02 
QUALITY ASSURANCE 
 
A. REFERENCES 
 
This section contains references to the following documents. They are a part of this 
section as specified and modified. In case of conflict between the requirements of this 
section and those of the listed documents, the requirements of this section shall prevail. 
 
Reference 
Title 
 
ASTM C109 
Standard Test Method for Compressive Strength of 
Hydraulic Cement Mortars (Using 2-in. or [50-mm] Cube 
Specimens)  
 
ASTM D638 
Standard Test Method for Tensile Properties of Plastics 
 
ASTM D2240 
Standard Test Method for Rubber Property – Durometer 
Hardness 
 
ASTM D4138 
Standard Practices for Measurement of Dry Film 
Thickness of Protective Coating Systems by Destructive, 
Cross-Sectioning Means 
 
ASTM D4258 
Standard Practice for Surface Cleaning Concrete for 
Coating 
 
ASTM D4262 
Standard Test Method for pH of Chemically Cleaned or 
Etched Concrete Surfaces 
 
ASTM D4414 
Standard Practice for Measurement of Wet Film Thickness 
 
ASTM D4541 
Standard Test Method for Pull-off Strength of Coatings 
using Portable Adhesion Testers (Metallic Substrate) 
 
ASTM D4787 
Standard Practice for Continuity Verification of Liquid or 
Sheet Linings Applied to Concrete Substrates

SECTION 09710 
 
 
CONCRETE AND MASONRY COATING 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 3 
October 25, 2024 
ASTM D5162 
Standard Practice for Discontinuity (Holiday) Testing of 
Nonconductive Protective Coating on Metallic Substrates 
 
ASTM D7234 
Standard Test Method for Pull-off Adhesion Strength of 
coatings on Concrete Using Portable Pull-Off Adhesion 
Testers 
 
OSHA – ADOSH 
Occupational Safety and Health Association - Arizona 
Division of Occupational Safety and Health (ADOSH) 
 
NACE 
National Association of Corrosion Engineers Published 
Standards 
 
ACI 503.1 -503.4 
Four Epoxy Specifications 
 
 
B. STANDARDIZATION 
 
Materials and supplies provided shall be the standard products of manufacturers. 
Materials in each coating system shall be the products of a single manufacturer or 
proven to be compatible.  
 
C. INSPECTION 
 
All work shall be performed in presence of the  City or City’s Representative, unless 
the City has granted prior approval to perform work in their absence. The Contractor 
shall provide testing as approved by the City. Cost of this testing shall be the 
responsibility of the Contractor. Inspection by the City or waiver of inspection in any 
particular portion of work shall not relieve the Contractor of responsibility to perform 
work in accordance with this Technical Specification.  
 
a. Safety Equipment: Scaffolding and/or tri-pod safety equipment shall be erected and 
moved by the Contractor to locations to facilitate inspection by the City or City’s 
City or City’s Representative. The Contractor shall be responsible to provide 
equipment and conditions according to OSHA safety standards for the City or 
City’s Representative to enter into confined space for inspection purposes. The 
Contractor shall provide additional illumination and/or fresh air upon the City’s 
requests.  
 
b. Surface pH Testing: The Contractor shall furnish services of a trained operator in 
surface pH testing, equipment and chemicals until acceptance of prepared surface. 
Surface pH testing shall be performed in the presence of the City or City’s 
Representative. The Contractor shall perform pH testing on all surfaces prior to 
application of coating. The Contractor shall be responsible to perform additional 
surface cleaning/washing per Technical Specification Section 02760 - SEWER 
PIPE AND SEWER STRUCTURE CLEANING as necessary to obtain pH 
readings acceptable to coating manufacturer’s requirements.

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 4 
October 25, 2024 
 
c. Adhesion “Pull” Testing: The Contractor shall furnish until final acceptance of 
coatings, inspection devices in good working condition for the verification of 
adhesion of any substrate material to the existing concrete. The Contractor shall 
furnish services of trained operator in pull test devices until final acceptance of 
coatings. Pull test devices shall be tested in the presence of the City or City’s 
Representative. The Contractor shall perform pull test in the presence of the City 
or City’s Representative. 
 
Pull testing and repair of the coating test areas shall be performed prior to spark 
testing. The Contractor shall be responsible to repair test areas and retest coating as 
necessary at no additional cost to the City.  
 
The Contractor shall conduct thickness measurements of coating retained on the 
destructive pull strength dolly. Measurements of thickness of applied protective 
coatings in the presence of the City or City’s Representative. Pull strength dolly 
shall be submitted to the City following thickness measurements as a permanent 
record of coating thicknesses. 
 
d. Holiday “Spark” Testing: The Contractor shall furnish services of a trained operator 
in holiday detection devices until final acceptance of coatings. Holiday detection 
devices shall be tested and operated in the presence of the City or City’s 
Representative. The Contractor shall perform holiday test on all coated surfaces in 
the presence of the City or City’s Representative. The Contractor shall be 
responsible to repair defective areas and retest coating as necessary at no additional 
cost to the City. 
 
D. SUMMARY REPORT 
 
Surface pH, pull strength, and coating thickness measurements shall be documented 
and reported in a Summary Report produced by the Contractor and submitted to the 
City. The report shall be presented after completion of underlayment, top coating 
operations, and shall state number of manufacturer’s product units used and total square 
footage of surface area covered. City shall have option of requiring the Contractor to 
document number of units (coating materials) on hand before and after coating of each 
structure operations to verify actual minimum coating thickness applied. All coating 
thicknesses not meeting required minimums shall be removed and/or re-coated per 
manufacturer’s recommendations and project Technical Specifications.  
 
E. INSPECTION MILESTONES 
 
The Contractor shall keep City informed of his progress on rehabilitation of each 
structure. At each manhole, the City may inspect the work at the completion of each of 
the milestones listed below before the Contractor shall commerce work on the next 
milestone:

SECTION 09710 
 
 
CONCRETE AND MASONRY COATING 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 5 
October 25, 2024 
1. Completion of the cleaning and surface preparation activities required by these 
Technical Specifications. 
 
2. Completion of all void-filling activities and underlayment application, prior to 
surface coating application, with the associated adhesion testing of the 
underlayment layer. 
 
3. pH of surface following cleaning and void filling underlayment activities, prior to 
surface coating application. 
 
4. Completion of the surface coating installation prior to testing. 
 
5. Adhesion/bond testing of the finished coating system as required by these Technical 
Specifications. 
 
6. Spark testing of the final surface coating as required by these Technical 
Specifications. 
 
7. Following final clean-up and inspection, the Contractor shall prepare a table in 
Microsoft Excel format and summit digitally the results of testing that include at a 
minimum the manhole number, pull test locations with corresponding test results, 
and spark test pass/fail results. 
 
F. QUALITY CONTROL TESTING 
 
The Contractor shall submit the following test results to the City: 
 
1. pH Testing: pH of surface shall be tested per ASTM D4262 and reported. 
 
2. Adhesion Testing: Adhesion of the coating to the concrete substrate shall be tested 
per ASTM D7234, and the mode of failure shall be such that the substrate fails 
before the coating separates from the substrate.” 
 
3. Holiday Testing: Holiday “spark” testing shall be employed to identify holidays, 
defects, and substandard coating thickness. 
 
4. Coating Thickness Test: Coating thickness testing shall be performed by pull test 
destructive testing methods and direct measurement of coating thickness to verify 
cured coating meets the minimum dry mil thickness. 
 
5. Surface Hardness Test: Coating Hardness shall be performed per ASTM D2240 
and reported. 
 
6. Chemical Resistance Testing: The following chemical resistance tests shall be 
performed in accordance with the Standard Specifications for Public Works 
Construction 2018 Edition, Section 210-2.3.3 and ASTM D638. The samples shall

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 6 
October 25, 2024 
be tested for weight change, tensile strength and elongation after exposure for a 
period of 28, 56, 84 and 112 days in the following chemical solutions/volume 
concentration percentage: Sulfuric Acid/20%, Sodium Hydroxide/5%, Ammonium 
Hydroxide/5%, Nitric Acid/1%, Ferric Chloride/1%, Soap/0.1%, Detergent/0.1%, 
Bacteriological (BOD)/≥700ppm, and Bleach/1%. After exposure to the chemical 
solutions for the specified days of immersion, specimens shall exhibit zero (0) 
weight loss, spalling, cracking or blistering. Any changes to appearance such as 
color and texture shall be noted. After exposure to the chemical solutions for the 
specified test intervals, the physical properties to be determined after each test 
period are tensile strength (psi) and elongation (%) in accordance with ASTM 
D638. All test specimen tensile strength results shall be greater than or equal to the 
initial tensile strength prior to any chemical exposure. 
 
1.03 
CERTIFIED APPLICATOR 
 
The Contractor applying coating shall be a contractor licensed in the state of the specified 
project location. The coating system shall be applied by an applicator certified within the 
prior two (2) years by the coating and underlayment material system manufacturer as 
properly trained for applying the manufacturer’s coating and underlayment products. 
Underlayment products include repair materials, grouts, fillers, primers, etc. A training 
outline for the certification program undergone by the applicators shall be submitted to the 
City, for review. The Contractor shall provide evidence that the personnel performing the 
product application received the manufacturer's training for certification. 
 
The Contractor shall appoint a Quality Assurance Manager who shall take full 
responsibility for the oversight of the quality of the work. The Quality Assurance Manager 
shall be fully certified and have a minimum of five (5) years of application experience with 
the particular coating system. 
 
Applicator(s) shall be fully certified by the product manufacturer and have a minimum of 
two (2) years of application experience with the particular coating system. 
 
1.04 
DELIVERY AND STORAGE 
 
Materials shall be delivered to the job site in their original, unopened containers. Each 
container shall bear the manufacturer's name, coating type, batch number, date of 
manufacture, storage life, and special directions. 
 
Materials shall be stored in enclosed structures and shall be protected from weather and 
excessive heat or cold. Flammable materials shall be stored in accordance with state and 
local codes. Materials exceeding storage life recommended by the manufacturer or visibly 
deviate from normal appearance or texture shall not be used, physically marked in Orange 
paint on the container as being REJECTED and physically removed from the project site 
so as not to be inadvertently incorporated into future work.

SECTION 09710 
 
 
CONCRETE AND MASONRY COATING 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 7 
October 25, 2024 
1.05 
WARRANTY 
 
A. A non-prorated written (but not bonded) warranty to cover workmanship and materials 
against coating failure shall be provided for the entire coating system, including all 
repair material, defect fillers, primers, intermediate (if applicable), and finish coats. 
The minimum duration of the warranty shall be five (5) years following final 
acceptance of the project. The product and the installation shall both be covered by the 
Contractor’s warranty. The Contractor shall be responsible for administration, 
performance and all ancillary costs associated with implementation of the warrantee. 
The warranty shall be delivered to the City prior to and as a condition of final 
acceptance and final payment for this project. 
 
B. Inspection shall be conducted during the eleventh/fifty ninth months (FOR 12/60 
MONTH WARRANTY ITEMS) following completion of all coating work. The 
Contractor and representative of coating manufacturer shall attend inspection. 
Defective work shall be repaired in accordance with these Technical Specifications and 
satisfaction of the City within one (1) month of written notification. The City may, by 
written notice to the Contractor, reschedule warranty inspection to another date within 
one-year correction period, or may cancel warranty inspection altogether. If warranty 
inspection is not held, the Contractor is not relieved of the responsibilities stated under 
Contract Documents. 
 
C. This warranty shall state that the coating(s) will not fail for a minimum period of five 
(5) years. Coating failure is defined as blistering, cracking, embrittlement, or softening, 
or failure to adhere to the substrate. The warranty shall also apply to any repair 
materials, primers, or other products used in the application. If any repair or 
replacement is necessary within the warranty period, a new five (5) year warranty 
period shall start at the date that the manhole is placed back into service following 
repairs. 
 
D. By executing this contract, the Contractor certifies and agrees that any testing 
performed during construction (e.g., spark testing, adhesion testing and/or other 
testing) shall not in any way modify the warranty, nor relieve the Contractor for 
responding to defects during the warranty period. 
 
E. The Contractors responsibility to provide the Warranty is considered incidental to the 
work and is, therefore, a non-pay item. 
 
F. The Contractor and coating system Manufacturer shall within one (1) month of written 
notice thereof, repair defects in materials or workmanship that may develop during said 
warranty period(s). 
 
G. The costs for ancillary items associated with coating repair includes, but not limited to, 
permitting costs, bypass pumping, traffic control and third party quality control 
inspection shall be the Contractor’s responsibility and are to be included in and 
incidental to the cost(s) of warrantee repairs.

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 8 
October 25, 2024 
1.06 
SUBMITTALS 
 
A. Before materials are delivered to the job site, the Contractor shall provide the following 
information in accordance with Technical Specification Section 01300 - 
SUBMITTALS: 
 
1. Name(s) and qualifications of all proposed applicator(s) per paragraph 1.03, along 
with Certification of Applicator(s) and outline of training undertaken for the 
certification program. 
 
2. Schedule identifying sequence and dates the Contractor will be working on each 
structure. When the Contractor is prepared to start work at a structure, they shall 
inform the City of their schedule of milestone inspection points for that structure. 
Failure to provide notification of any milestone inspection point is grounds for 
rejection and non-payment of all work performed within the structure.  
 
3. Current Arizona Contractor's license or equivalent (specifically for the 
rehabilitation of concrete manholes/structures). If the manhole(s) to be rehabilitated 
is (are) brick, then the license or equivalent shall state for the rehabilitation of 
concrete and brick manholes. 
 
4. Safety Data Sheet (SDS) for the grout, filler, primer and finish coating, the 
Contractor proposes to use. 
 
5. For the filler and finish coating, the Contractor shall provide the manufacturer's 
technical literature and application instructions, which shall include the following: 
 
a. Surface preparation recommendations and limitation(s) of any existing 
subsurface materials for adherence bonding concerns. 
b. Primer type, where required. 
c. Limitations for surface preparation methods and/or products. 
d. Maximum mil thickness per coat. 
e. Mixing and proportioning requirements (as applicable). 
f. Minimum and maximum curing time between coats (if applicable), including 
atmospheric temperature and humidity limits for each. 
g. Curing time before submergence in flowing liquid. 
h. Thinners (if allowed) that are acceptable with coating material. 
i. Environmental requirements for application and worker safety, including 
ventilation, humidity, and temperature ranges. 
j. Allowable application methods. 
k. Maximum allowable surface moisture content. 
l. Allowable surface pH range. 
m. Required storage conditions and maximum storage life. 
n. Sample of finished product showing final color.

SECTION 09710 
 
 
CONCRETE AND MASONRY COATING 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 9 
October 25, 2024 
6. List of materials proposed to be used under this section and manufacturer's 
technical literature and data for each material. 
 
7. A letter or manufacturer’s technical literature and product data identifying the 
procedures recommended for repair of defect(s) that may be found in each proposed 
material. 
 
8. Written certification from the materials manufacturer that the surface material is 
compatible with proposed material, the surface has been prepared to acceptable 
standards, and the applied coating has been installed according to material 
manufacturer’s recommendations.  
 
9. Minimum pull force reading that is anticipated for proposed pull test equipment 
and size of dolly for passing test. 
 
10. Testing Summary Report per paragraph 1.02 D.  
 
11. Written warranty per paragraph 1.05. 
 
12. The Contractor shall provide procedures and products proposed for use to repair 
deteriorated steel reinforcement bars (if present). 
 
13. The Contractor shall provide procedures and products proposed for use around 
utility penetrations (if present). 
 
PART 2 – PRODUCTS 
 
2.01 
MANHOLE COATINGS 
 
Materials shall be delivered to the site in factory sealed and labeled containers. Date of 
manufacture shall be labeled on each container. Materials shall be handled and stored 
according to the strictest requirements of the manufacturer and in accordance with all local, 
state, and federal laws and regulations.  
 
1. Coating systems shall be compatible with the preparation methods as specified herein. 
Any limitations or deviations requested by the manufacturer shall be approved in 
writing by the City, prior to surface preparation. The Contractor shall provide all labor, 
materials and equipment as necessary at no additional cost to the City for any deviations 
of surface preparation required by the coating materials manufacturer. 
 
2. Epoxy based coating shall be applied within eight (8) months of their date of 
manufacture (unless the manufacturer’s requirements are more stringent), or otherwise 
approved in writing by the City.

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 10 
October 25, 2024 
3. Thicknesses specified herein is the minimum dry thickness required and do not include 
the primer or underlayment thickness, unless otherwise noted. Provide greater 
thickness where recommended by the product manufacturer. 
 
4. Sealant or Primer, if required, shall be as recommended by the manufacturer for each 
installation. 
 
5. Defect filler and repair materials shall be as recommended by the manufacturer for each 
installation. All materials shall be identified. 
 
6. Manhole infiltration control material shall be as recommended by the manufacturer 
for each installation, and shall be covered under the same warranty as the rest of the 
coating system. 
 
2.02 
APPROVED CORROSION PROTECTIVE COATING SYSTEMS FOR EXISTING 
MANHOLES 
 
Manhole coating materials shall be one of the approved products listed in this paragraph. 
Manhole coating system proposed shall be compatible with any existing manhole epoxy 
coating present or removed down to coating manufacturer acceptable substrate at no 
additional cost to the City. The approved corrosion protective coating systems shall be as 
listed below.  
 
• Sauereisen Sewergard Lining No. 210 with Sauereisen Underlayment No. F-120, as 
manufactured by Sauereisen Cements, Pittsburgh, PA. The underlayment shall be used 
to repair and reprofile corroded areas of manhole surfaces. Manhole surfaces shall be 
cleaned and prepared in accordance with the manufacturer’s recommendations and 
coating system specification sheets (COATSPEC) in Technical Specification Section 
3.22 prior to application. 
 
• Sewer Shield 150 Epoxy Lining as manufactured by Environmental Coatings, Mesa, 
Arizona. The underlayment shall be used to repair and re-profile corroded areas of 
manhole surfaces. Manhole surfaces shall be cleaned and prepared in accordance with 
the manufacturer’s recommendations and coating system specification sheets 
(COATSPEC) in Technical Specification Section 3.19 prior to application. 
 
• Raven 405 Epoxy Lining with calcium aluminate cement underlayment, as 
manufactured by Raven Lining Systems, Tulsa, Oklahoma. The underlayment shall be 
used to repair and reprofile corroded areas of manhole surfaces. Manhole surfaces shall 
be cleaned and prepared in accordance with the manufacturer’s recommendations and 
coating system specification sheets (COATSPEC) in Technical Specification Section 
3.22 prior to application. 
 
The underlayment material and the surface coating material installed in any one manhole 
shall be from the same coating system.

SECTION 09710 
 
 
CONCRETE AND MASONRY COATING 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 11 
October 25, 2024 
2.03 
CORROSION INHIBITOR FOR REINFORCING STEEL 
 
Reinforcing steel, exposed by corrosion or during surface preparation operations, shall be 
treated with a water-based epoxy resin, anti-corrosion coating and bonding agent such as 
Armatec 110 EpoCem, manufactured by the Sika Corporation, or approved equal. The 
Contractor shall be responsible to verify that the corrosion inhibitor product is compatible 
with proposed coating system materials. 
 
2.04 
BONDING COMPOUNDS 
 
All surfaces where new concrete contacts existing concrete shall be coated with a bonding 
compound as recommended by the manufacturer of the concrete repair material. 
 
2.05 
BENCH REPAIR 
 
Acid-resistant non-shrink grout mortar shall be used for bench restoration. The grout 
mortar shall be applied to a depth of at least ¾-inches on the bench. The finish surface shall 
be hand-troweled smooth to finish the bench and channel. 
 
2.06 
UNDERLAYMENT FOR STRUCTURE WALL REPAIR 
 
Where the manhole wall substrate material is exposed and/or deteriorated, the surface shall 
be abraded down to solid concrete. Where the abraded material is equal to or greater than 
0.25 inches from the original profile, the substrate shall be restored back to original profile. 
 
Manhole wall repair (if necessary) shall be provided for manhole walls for re-profiling 
back to original manhole dimensions with a product as recommended by underlayment and 
coating manufacturer. Voids that extend beyond the exterior manhole wall shall be brought 
to the attention of the City for approved repair procedures.  Costs for exterior manhole wall 
repair shall be considered a changed condition with costs for repairs negotiated and agreed 
upon prior to proceeding with the work. Failure to obtain prior approval of repair costs 
eliminates any claims by the Contractor for additional compensation for added work to 
repair the manhole. 
 
PART 3 - EXECUTION 
 
3.01 
HAZARDOUS LOCATIONS 
 
The City may wish to enter the manhole under the Contractor’s safety program to perform 
observations and/or perform additional testing. The Contractor shall provide the necessary 
safety equipment, monitoring, and safe working atmosphere to allow the City or City’s 
Representative to safely enter the manhole, at no additional cost to the City. 
 
The Contractor is responsible for safety of the job site, including the responsibility to 
enforce and enact the provisions of the Contractor’s Confined Space Entry program and 
the responsibilities to monitor the atmosphere within the structures and provide a safe

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 12 
October 25, 2024 
working atmosphere and environment.  These safety measures shall be at no additional cost 
to the City. The City shall not be responsible for safety or for safety monitoring of the job 
site. 
 
3.02 
SEWAGE FLOW AND DIVERSION 
 
The Contractor shall be aware that the existing manholes included in this project are active, 
functioning manholes. The Contractor shall be required to coordinate the minimization of 
existing sewer flow and corresponding water level within the manhole through upstream 
diversion as much as possible per Technical Specification Section 02145 – DIVERSION 
OF SEWAGE FLOW AND DEWATERING when rehabilitating the lower sections of the 
manhole. 
 
Manholes designated for rehabilitation that are contiguous to pipe rehabilitation activities 
shall be performed while flow is diverted and manhole is dewatered.  
 
3.03 
MANHOLE PREPARATION AND CLEANING 
 
Surface preparations for each type of surface shall be in accordance with manufacturer’s 
recommendations or the specific requirements of the coating specification sheet 
(COATSPEC). 
 
The Contractor shall inspect all surfaces specified to receive a coating system prior to 
surface preparation. The Contractor shall notify City, of any noticeable disparity in the 
surfaces, which may interfere with the proper preparation, or application of the coating 
system. 
 
The entire manhole interior including frame, chimney, walls, bench and throat shall be 
cleaned prior to rehabilitation using abrasive blasting and/or hydro jet cleaned per 
Technical Specification Section 02760 – SEWER PIPE AND SEWER STRUCTURE 
CLEANING. The Contractor shall remove all manhole steps present within the interior or 
as directed and any voids repaired.  
 
The Contractor shall use manhole debris shields or other approved method to prevent debris 
from entering the live sewers. Discharge of removed sediment and debris into the 
interceptor pipe is prohibited. The Contractor shall remove and legally dispose of dislodged 
debris offsite. All hauling equipment shall be watertight to prevent spillage during 
transport. The Contractor will be responsible for interceptor pipe cleaning, removal of all 
sediments to an approved waste facility, and all costs incurred if debris is observed to be 
discharged into the interceptor sewer. 
 
3.04 
DEFECT REPAIR 
 
A. All surface defects including tie holes, any honeycombing or otherwise defective 
concrete or brick shall be repaired. All voids, holes, and rough or irregular surfaces 
shall be filled/repaired.

SECTION 09710 
 
 
CONCRETE AND MASONRY COATING 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 13 
October 25, 2024 
 
B. The Contractor shall use the fill/repair material recommended by the coating 
manufacturer, to repair or fill all defects. Areas to be patched shall be cleaned. Minor 
honeycombed or otherwise defective areas shall be removed to solid concrete. The 
edges of the cut shall be perpendicular to the surface of the concrete. Patches on 
exposed surfaces shall be finished to match the adjoining surfaces after they have set. 
Finishes shall be equal in workmanship, texture and general appearance to that of the 
adjacent material.  
 
C. Deteriorated or honeycombed concrete which exposes the reinforcing steel or with 
defects that affect the structural strength shall be repaired. Any exposed reinforcing 
steel shall be mechanically cleaned and coated in accordance with paragraph 3.08. The 
proposed repair method shall be approved by the City. 
 
D. Extend all existing control and expansion joints through any patch or repair area. 
 
3.05 
STRUCTURAL REINFORCING REPAIR 
 
Structural repairs shall include splicing new reinforcing steel to existing reinforcing steel 
and providing additional reinforcing steel to reestablish the original structural integrity and 
existing loading capacity. Provide 3/8-inch diameter anchor bolts as needed to support 
reinforcing steel. 
 
3.06 
REINFORCING STEEL TREATMENT 
 
Where corrosion or surface preparation activities have exposed reinforcing steel the 
following procedure shall be used: 
 
1. If half the diameter of the reinforcing steel, or more, is exposed, chip out behind 
the reinforcing steel a minimum of 1-inch for placement of grout or polymer 
concrete. 
 
2. Determine cross sectional area loss of reinforcing steel. 
 
3. Where reinforcing steel cross sectional area loss exceeds 15% of the original 
reinforcing steel, perform structural repair as directed by the City. 
 
4. Abrasive blast all exposed reinforcing steel surfaces to remove all contaminants 
and corrosion products. 
 
5. Clean exposed reinforcing steel with stiff brush or grit blast equipment per 
Technical Specification Section 02760 – SEWER PIPE AND SEWER 
STRUCTURE CLEANING. 
 
6. Apply a 20 mil (wet) coat of corrosion inhibitor to all surfaces of the clean, exposed 
reinforcing steel with a stiff brush or spray equipment. Allow 2 to 3 hours for

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 14 
October 25, 2024 
coating to cure or until surface is tack-free. 
 
7. Apply a second 20 mil (wet) coat of corrosion inhibitor and allow for 2-hour to 3-
hour cure prior to placement of polymer mortar, cementitious mortar, or grout. 
 
3.07 
REPAIR MANHOLE BENCH AND NON-MAIN CHANNEL(S) 
 
The Contractor shall repair manhole bench and non-main channel(s) with acid-resistant 
mortar. The grout mortar shall be applied to a depth of at least ¾-inches on the bench. The 
finish surface shall be hand-troweled smooth to finish the bench and channel. Manhole 
bench shall be sloped a minimum ½-inch per foot to the edge of the throat. Minimum 
mortar thickness shall be ¾-inch. 
 
3.08 
CHIMNEY REPAIR 
 
Brick chimneys shall be repaired through re-pointing or replacement as necessary to ensure 
structural integrity. 
 
3.09 
MANHOLE FRAME AND COVER AND ADJUSTING RINGS REPLACEMENT 
 
Manhole frames and covers shall be replaced as indicated in the Contract Documents. The 
Contractor shall perform work in accordance with MAG Standard Details 420, 422, and 
424. The frames and covers shall be Product Numbers 2230Z (Frame) and 2230A (Cover), 
as manufactured by East Jordan Iron Works, or approved equal. The covers shall contain 
the City of Glendale official logo and the words “City of Glendale Sanitary Sewer” as 
shown on City of Glendale Standard Detail G-704. The frames and covers shall have a 
nominal opening diameter of 30-inches.  
 
Adjusting rings shall be replaced as necessary to raise the lid to surface grade and slope. 
Grade rings shall be per Technical Specification SECTION 13133 – POLYPROPYLENE 
GRADE ADJUSTMENT RINGS. If concrete adjusting rings are used, they shall receive 
the same corrosion-resistant coating system as the rest of the concrete in the manhole. 
 
3.10 
PREPARATION 
 
A. GENERAL 
 
Surfaces to be coated shall be clean and dry according to Technical Specification 
Section 02760 – SEWER PIPE AND SEWER STRUCTURE CLEANING. 
 
B. DETAILED SURFACE PREPARATION 
 
Surface preparations for each type of surface shall be in accordance with the specific 
requirements of the coating specification sheet (COATSPEC).

SECTION 09710 
 
 
CONCRETE AND MASONRY COATING 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 15 
October 25, 2024 
C. CIPP SURFACE PREPARATION 
 
CIPP liner shall be abraded clean to 80 grit surface finish roughness. 
 
3.11 
COATINGS  
 
A. GENERAL 
 
Coating products shall not be used until the City has inspected the materials and the 
coating manufacturer's technical representative has instructed the Contractor and City 
in the recommended procedures for surface preparation, mixing and application of the 
coating. 
 
 
B. COATING SYSTEMS 
 
Field coats shall consist of one or more finish coats to build up the coating to the 
specified mil thickness. Unless otherwise specified, finish coats shall not be applied 
until other work in the area is complete and until all previous coats have been inspected. 
 
The Contractor shall employ whatever means necessary (e.g., humidity control, 
temperature control, additional abrasive blasting, hydro jet cleaning, mechanical 
surface preparation, etc.) to ensure strong adhesion of the surface coating layer(s), to 
any underlying and overlying layers and proper curing of the surface coating layer(s). 
If the surface coating is applied in two or more layers, the time between applications of 
the various layers shall be controlled to ensure proper bond between layers. 
 
C. COATING REQUIREMENTS 
 
The approved surface coating shall be mixed in a clean, dry mixing container. 
Compound that has begun to set shall not be recovered by adding additional liquid but 
shall be discarded. 
 
All items of equipment, or parts and surfaces of equipment, which are immersed when 
in service, with the exception of pumps shall have all surface preparation and coating 
work performed in the field. 
 
3.12 
COATING APPLICATION 
 
A. WORKMANSHIP 
 
Coated surfaces shall be free from runs, drops, ridges, waves, laps, and trowel marks. 
Coats shall be applied so as to produce an even film of uniform thickness completely 
coating corners and crevices.

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 16 
October 25, 2024 
The Contractor's equipment shall be designed for application of the materials specified. 
The coating shall be applied using a trowel suitable for obtaining the proper thickness 
and surface characteristics as recommended by the coating manufacturer.  
 
Each coat shall be applied evenly and sharply cut to line. Care shall be exercised to 
avoid over-coating or spattering on surfaces not to be coated. All over-coating or 
spattering shall be removed. 
 
For all coatings, trowel marks and other surface irregularities shall be removed by using 
a short nap mohair paint roller. The short nap mohair shall be dampened with water. 
Excess water shall be shaken off prior to use. 
 
B. ATMOSPHERIC CONDITIONS 
 
Coatings shall be applied only to surfaces that are dry, and only under conditions of 
evaporation rather than condensation. Coatings shall not be applied during rainy, misty 
weather, or to surfaces upon which there is frost or moisture condensation. During 
damp weather, when the temperature of the surface to be coated is within 10 degrees 
Fahrenheit (F) of the dew point, the surfaces shall be heated to prevent moisture 
condensation thereon. During coating, and for a period of at least eight (8) hours after 
the coating has been applied, the temperature of the surfaces to be coated, the coated 
surfaces, and the atmosphere in contact shall be maintained at or above 40 degrees F 
and 10 degrees F above the dew point. When applied, coating shall be approximately 
the same temperature as that of the surface on which it is applied, but not greater than 
the maximum allowable coating installation temperature as specified by the 
manufacturer. Fans or heaters shall be used inside enclosed areas where conditions 
causing condensation are present.  
 
Structures shall be continuously ventilated to prevent condensation. The Contractor 
shall be responsible for providing, installing, maintaining and removal of all safety 
apparatus safeguarding open structure being ventilated.  
 
Contractor shall confirm ambient temperature and humidity of the manhole interior and 
the surface temperature and moisture content of the surface, and the temperature of 
coating materials that is to be applied are within the manufacture’s recommended 
ranges. 
 
C. SURFACE CONDITIONS 
 
The Contractor shall remove excess water from the surface using compressed air 
equipment with oil-trapping filters, or other means to produce surface-dry conditions, 
or as recommended by the coating manufacturer. Suitable heaters shall also be used as 
needed to produce the surface-dry condition. The surface shall be vacuumed to ensure 
that loose particles are not present. The Contractor shall evaluate the moisture content 
in accordance with the requirements of ACI 503-1 – 503.4 standard specification 
applicable to the application prior to the installation of any coatings.

SECTION 09710 
 
 
CONCRETE AND MASONRY COATING 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 17 
October 25, 2024 
 
D. PROTECTION OF COATED SURFACES 
 
Items which have been coated shall not be handled, worked on, or otherwise disturbed, 
until the coating is completely dry and hard. Do not allow flowing water, chemicals or 
other liquids on the approved, applied coating for a minimum of four (4) hours after 
installation or longer as recommended by the coating manufacturer. 
 
E. THICKNESS AND CONTINUITY 
 
Coating system thickness is the total thickness of protective coats. 
 
The surface area covered for various types of surfaces and thickness per coat shall not 
exceed those recommended by the manufacturer. Coatings shall be applied as a 
minimum to the mil thickness specified, in layers if necessary, as recommended by the 
coating manufacturer and in accordance with these Technical Specifications and 
project requirements. 
 
In testing for continuity of coating about welds, projections (such as bolts and nuts,) 
and crevices, the City will determine the minimum conductivity for smooth areas of 
like coating where the mil thickness has been accepted.  This conductivity shall then 
be taken as the minimum required for these rough or irregular areas. Pinholes and 
holidays shall be repaired and recoated to the required coverage. 
 
F. SAFETY AND VENTILATION REQUIREMENTS 
 
Requirements for safety and ventilation shall be in accordance with manufacturer’s 
recommendations. 
 
3.13 
ADHESION / BOND TESTING 
 
A. GENERAL 
 
1. After proper cure the Contractor shall perform an adhesion test in accordance with 
ASTM D7234 in accordance with manufacturer’s recommended procedures to 
demonstrate that the specified field coatings adhere to the substrate. Costs 
associated with adhesion testing are considered to be incidental to the unit price 
cost of coating. 
 
2. Where unacceptable test results are obtained, the Contractor shall be responsible 
for removing and reapplying the specified coatings at no additional expense to the 
City.

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 18 
October 25, 2024 
B. FREQUENCY OF TESTING 
 
After the approved coating has been applied to all specified surfaces and has adequately 
cured (as determined by the manufacturer, but no more than 4 days), the Contractor 
shall test the finished coating system for adequate adhesion between the underlying 
substrate and the coating system and between the various layers of the coating system. 
Said test shall be performed in-place and in accordance with ASTM Standard D-7234 
and the requirements as dictated in the remainder of this section. 
 
1. Adhesion testing shall be performed at two different stages of the work: 
  
a. Underlayment Adhesion Testing: Underlying substrate shall be tested before 
the surface coating layer(s) are applied; 
 
b. Finish Coating System Adhesion Testing: After the surface coating layer(s) 
have been applied, the adhesion of all applied layers in the coating system to 
one another and to the underlying substrate shall be tested. The Contractor shall 
perform adhesion tests on 30% of the manholes coated, or at least one (1) 
manhole if 30% of the manholes coated is equal to less than one (1). 
 
2. Adhesion tests shall be required at a minimum of one (1) underlayment adhesion 
test and one (1) finished coating system adhesion test per manhole tested.  
 
3. Specific test locations within each manhole shall be selected by the City or City’s 
Representative. The City or City’s Representative shall be present to observe all 
adhesion testing.  
 
4. The need to repeat an adhesion test due to an error in the performance of the 
adhesion testing (e.g., a dolly coming off prematurely) or due to a failure in the 
coating system before the required full test pressure is applied (i.e., a "not pass" test 
result) shall not count as an additional test for the purposes of determining 
compliance with the minimum number of tests required per Item No. 1, but shall 
rather be denominated a "repeat test".  
 
5. Adhesion testing of the underlayment layer shall conform to the following:  
 
a. After the underlayment layer has cured for a minimum of 4 hours but before the 
surface coating has been applied over the underlayment layer, the Contractor 
shall test the underlayment layer for proper adhesion to the underlying 
substrate.  
 
b. The Contractor shall perform the adhesion testing in-place and in accordance 
with ASTM Standard D-7234 and the requirements as dictated in the remainder 
of this section.

SECTION 09710 
 
 
CONCRETE AND MASONRY COATING 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 19 
October 25, 2024 
6. The adhesion/bond testing is in addition to the spark testing discussed in paragraph 
3.14. 
 
C. ADHESION TEST EQUIPMENT 
 
The remaining paragraphs of this section apply to both the adhesion testing of the 
underlayment layer and the adhesion testing of the finished coating system:  
 
The Contractor shall perform the adhesion testing discussed in this section using a 
DeFelsko Positest Pull-off Adhesion Tester Model AT-A or AT-M with 50mm dolly 
accessory kit or City Approved Equal, to be provided by the Contractor. The Contractor 
shall be responsible to purchase and provide enough 50 mm diameter dollies (as sold 
by DeFelsko) and adhesive for the dollies to perform all of the required tests.  
 
The Contractor shall provide the equipment and tools to core drill around the test dolly 
location to score the applied coating to a depth of the substrate material that bond 
strength is being verified as described in paragraph 2.16 - D.  
 
The Contractor shall provide proof that the pull-off adhesion tester has been calibrated 
within the last twelve (12) months.  
 
D. ADHESION TEST PROCEDURES 
 
Adhesion testing shall be conducted after the coating system has cured per 
manufacturer instruction and tested in accordance with ASTM D2240 and in 
accordance with ASTM D4541 (for metal) or ASTM D-7234 (for concrete). Adhesion 
shall be completed per ASTM or as described as follows: 
 
1. The Contractor shall first adhere the test dolly to the surface of the manhole at the 
test location selected by the City. The Contractor may lightly sand the coating 
surface with sandpaper at the test location to improve dolly adhesion. After the 
adhesive has set, the Contractor shall test the dolly for adhesion to the surface of 
the manhole by pulling on it by hand. If the dolly comes off, the Contractor shall 
re-adhere the dolly, using different glue if necessary. After the dolly is properly set, 
the Contractor shall then score the manhole surface (using a circle-cutting "hole 
saw" type drill bit that leaves the center of the drill area intact) around the perimeter 
of the dolly. The drill bit shall penetrate through the layers to be tested, but shall 
not penetrate more than 1/8-inch into the underlying substrate. The diameter of the 
drilled circle shall match (1/8-inch +/-) the diameter of the test dolly. Use of a sharp 
and properly sized cutting instrument is required. 
 
2. The adhesion testing machine shall then be attached to the dolly and each test 
location shall be tested to a minimum pulling strength of 200 psi (defined herein as 
the pulling force divided by the test sample cross-sectional area perpendicular to 
the applied force).

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 20 
October 25, 2024 
3. If delamination or any other failure occurs between or within any of the coating 
system layers and/or the underlying concrete substrate prior to the application of 
the full pulling pressure of 200 psi, the test shall be classified as “not pass”. 
However, if the dolly comes off the surface of the coating and no other delamination 
or failure occurs between or within any of the coating system layers and/or the 
underlying concrete substrate, the test will not be classified as a "failure" or "not 
pass", but the test shall be repeated at no additional cost to the City. The loading 
duration rate up to the full pulling pressure of 200 psi shall be consistently applied 
such that the test last a minimum of 7 seconds. 
 
The test can be discontinued if the testing pressure reaches 200 psi and no 
delamination or other failure has occurred within or between any of the coating 
system layers and/or the underlying concrete substrate, which test would be judged 
a “pass”. If delamination or other failure occurs within the underlying substrate, but 
only when the applied pulling pressure is in excess of 200 psi, the test shall also be 
judged to be a “pass”. To avoid damaging the test equipment, do not continue the 
test beyond 500 psi.  
 
4. For tests that are classified as “not pass”, the City will require additional testing. In 
the event of a “not pass”, three (3) additional tests shall be performed. Location of 
tests shall be at the discretion of the City. If any one (1) of the three (3) additional 
tests is found to be “not pass”, the coating shall be determined as defective and 
remedial action required.  
 
Remedial action will include removal of the entire coating system (or whatever 
components of it that have been installed in the manhole to that point) from the 
entire manhole, re-cleaning of the manhole, re-application of the coating system to 
all required surfaces and re-testing. Said retesting and remedial action shall be at 
no additional cost to the City.  
 
5. After the adhesion tests have been performed, the Contractor shall mechanically 
grind down the test locations to the underlying substrate and re-apply the 
underlayment and/or coating system (whatever has been installed up to that point 
in the manhole) in accordance with these provisions to patch the area. Said repair 
work shall be at no additional cost to the City. The Contractor shall not use acetone, 
MEK or other chemicals to dissolve the underlayment or coating system as a 
substitute for mechanical grinding down of the test area.  
 
3.14 
HIGH VOLTAGE SPARK TEST 
 
A. DEFINITION – HOLIDAY: Holidays are defined as pinholes and voids in non-
conductive coating that allow electrical current to pass through the protective coating 
to the base material. 
 
B. After the protective coating has set hard to the touch it shall be inspected with high-
voltage holiday detection wire brush wand style equipment. Surface shall first be dried,

SECTION 09710 
 
 
CONCRETE AND MASONRY COATING 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 21 
October 25, 2024 
an induced holiday shall then be made on to the coated concrete surface and shall serve 
to determine the minimum/maximum voltage to be used to test the coating for holidays 
at that particular area. The spark tester shall be initially set at 100 volts per 1 mil (25 
microns) of film thickness applied but may be adjusted as necessary to detect the 
induced holiday (refer to NACE RPO188-99 or ASTM D5162).  
 
In testing for continuity of coating about welds, projections (such as bolts and nuts), 
and crevices, the City will determine the minimum conductivity for smooth areas of 
like coating where the mil thickness has been accepted. This conductivity shall then be 
taken as the minimum required for these rough or irregular areas. Pinholes and holidays 
shall be repaired and recoated to the required coverage. 
 
Whereas adhesion testing is required at two (2) stages of the project work in each 
manhole, spark testing is required only on the fully installed coating system. 
 
1. After the approved coating has been applied to all specified surfaces, the Contractor 
shall spark test the coated surfaces in accordance with ASTM D4787. The 
Contractor shall provide all equipment and materials necessary to perform said 
testing, which equipment and materials shall remain the property of the Contractor.  
 
2. Testing shall be performed with a wire brush-type test wand (the squeegee-type is 
not acceptable) with a minimum test voltage of 100 volts per mil (where 1 mil = 
1/1000-inch) of finished surface coat thickness. For example, a minimum of 12,500 
volts shall be used for a surface coat thickness of 1/8-inch (125 mils). The 
Contractor shall use a grounding rod, or other means to establish ground for the 
spark testing equipment.  
 
3. As a test of the proper functioning of the spark testing equipment, the City may 
require the Contractor to drill a hole through the coating system into the underlying 
concrete substrate and to demonstrate to the City that the spark testing equipment 
can "find" the hole. The Contractor shall then patch and repair the hole at no 
additional cost to the City. At the City discretion, one such quality control test may 
be required for each manhole. Unless otherwise determined by the City, any 
adjustments to the spark testing methodology (e.g., adjusting the grounding 
method, increasing the test voltage, etc.) required to "find" the known holiday 
(hole) shall remain in effect for the remainder of the spark testing of that manhole.  
 
4. The entire surface of the manhole shall then be spark tested. Any imperfections 
found in the coating system shall be ground down and refilled. Use of a chemical 
solvent such as acetone or MEK in lieu of mechanical grinding down the area shall 
not be permitted. Repaired areas shall be re-tested. Said testing, repairs and re-
testing shall continue until all portions of the manhole pass the spark test as 
specified herein.  
 
5. The Contractor shall perform repairs and re-testing at no additional cost to the City. 
All detected holidays shall be marked and repaired by abrading the coating surface.

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 22 
October 25, 2024 
After abrading and cleaning, additional protective coating material shall be hand 
applied to the repair area. All touch-up/repair procedures shall follow the protective 
coating manufacturer's recommendations. 
 
6. The City or City’s Representative shall be notified and present to observe testing 
and retesting. In addition, the Contractor shall provide certification for each 
manhole stating that the coating is free of holes or other imperfections.  
 
3.15 
UNDERLAYMENT DEFECT REPAIR 
 
A. All surface defects in the underlayment including cracks, tie holds, minor 
honeycombing or otherwise defective concrete, shall be repaired. All voids, holes, 
rough or irregular concrete shall be cleaned with abrasive blasting and hydro jet 
cleaning to sound material and filled. 
 
B. The Contractor shall use the repair and fill material recommended by the coating 
manufacturer to repair or fill all defects. Areas to be patched shall be cleaned. Minor 
honeycombed or otherwise defective areas shall be cut out to solid concrete to a depth 
of at least 1-inch. The edges of the cut shall be perpendicular to the surface of the 
concrete. Patches on exposed surfaces shall be finished to match the adjoining surfaces 
after they have set. Finishes shall be equal in workmanship, texture and general 
appearance to that of the adjacent concrete. Concrete with honeycombing which 
exposes the reinforcing steel or with defects, which affect the structural strength, shall 
be corrected. 
 
3.16 
REPAIRS OF COATING SYSTEMS 
 
All pinholes, uncured coating, blisters, surface imperfections and damage to the coating 
resulting from the adhesion test shall be prepared to a point 1-inch minimum beyond the 
limits of the damaged area. Pinhole defects shall be primed and recoated with the same 
coating system to a minimum additional thickness of 30 mils unless otherwise specified by 
the coating manufacturer and/or City.  
 
Blisters, uncured coating and surface imperfections shall be completely removed and the 
areas recoated with appropriate coating material to 1-inch minimum beyond the repair area 
at a minimum dry film thickness of 125 mils or design coating thickness whichever is 
greater. The damage resulting from the adhesion test shall be repaired by recoating with 
appropriate lining material to 1-inch beyond the repair area at 150 mils or design coating 
thickness whichever is greater. Additional spark testing shall be completed after repairs are 
completed. 
 
3.17 
INSPECTIONS 
 
A. The Contractor shall notify City or City’s Representative of impending completion of 
surface repairs, re-profiling, and prior to application of epoxy coating.

SECTION 09710 
 
 
CONCRETE AND MASONRY COATING 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 23 
October 25, 2024 
B. The notifications shall be given a minimum 24-hours in advance of completion of the 
surface repairs and re-profiling, and 24-hours in advance of application of the epoxy 
coating and any testing, including spark testing, adhesion testing, and dry film thickness 
testing. 
 
C. Failure to provide notification at these designated times/work stages may prevent the 
acceptance of the work by the City. 
 
3.18 
CLEANUP 
 
Upon completion of coating, the Contractor shall remove surplus materials, protective 
coverings, and accumulated rubbish, and thoroughly clean all surfaces and repair any 
overspray or other coating-related damage. 
 
Any spilled or over sprayed material must be cleaned-up prior to curing. After curing has 
occurred, clean-up may be accomplished by chipping hydro jet cleaning and/or abrasive 
blasting. All discarded materials shall be disposed of properly. Clean-up and disposal of 
discarded material shall be at no additional cost to the City. 
 
Surfaces damaged by clean-up procedures shall be cleaned, repaired and refurbished to 
original condition.

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 24 
October 25, 2024 
3.19 
A. COATING SYSTEM SPECIFICATION SHEETS (COATSPEC) 
 
Surfaces shall be coated in accordance with the COATSPEC to the system thickness 
specified. 
 
Coating System 
Identification: 
Sewer Shield 150 
 
Surface: 
Concrete/Masonry 
 
Minimum Surface  
Preparation: 
Abrasive Blasting and Hydro Blasting 
 
Concrete Surface  
Profile Acceptable  
Range: 
ICRI CSP 3-4 
 
Concrete: 
Except as otherwise specified, loose concrete, form oils, 
surface hardeners, curing compounds, and laitance shall be 
removed from surfaces by abrasive and hydro blasting. 
Voids and cracks shall be repaired as specified in Technical 
Specification Section 09710, paragraph 3.06 and as 
indicated by the underlayment defect repair paragraph. After 
grit abrasion blasting, the concrete should be high pressure 
washed to remove oil, grease, and other contaminants. All 
active hydrostatic leaks must be stopped by use of a water 
stop, waterproofing, or urethane grout. 
 
Concrete must be structurally sound, dry or damp, free of 
grease, oils, coatings, dust, curing compounds and other 
contaminants. Surface laitance must be removed. The 
preferred method of surface preparation is abrasive blasting 
or shotblasting. For oil contaminated surfaces use of steam 
cleaning in conjunction with strong emulsifying detergent 
may be considered. Rinse thoroughly with potable water. 
After cleaning, remove defective concrete, honeycombs, 
cavities, joint crack voids and other defects by routing to 
sound material. Smooth, precast and formed concrete 
surfaces must be cleaned, roughened and made absorptive 
by abrasive blasting or shotblasting. If it is not possible to 
abrasive blast or shotblast, consider acid etching with a 15% 
Hydrochloric acid solution. After etching pressure wash or 
flush the surface with copious amounts of water to neutralize 
the surface. Care must be taken to ensure that all salts and 
residue from the reaction have been removed. The pH of the 
surface should be checked as per ASTM D4262 following 
acid etching. Following surface preparation, the cleaned

SECTION 09710 
 
 
CONCRETE AND MASONRY COATING 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 25 
October 25, 2024 
surface should pull concrete when tested with an Elcometer 
or similar pull tester (ASTM D4541). Before application of 
the lining system, use the “Visqueen test” (ASTM D4263) 
to evaluate moisture level in concrete. 
Epoxy Coating 
Compatibility: 
Except as otherwise specified, any existing coating that is 
incompatible with proposed epoxy coating as recommended 
by the proposed coating manufacturer’s recommendation for 
proper bonding purposes, shall be removed from surfaces by 
abrasive and hydro blasting and chipping if required.  
 
Underlayment: 
C-120 Cement Underlayment and Patching Material shall be 
used to fill holes and undulations in concrete surface found 
or created during the cleaning process. Sufficient material 
shall be used to build the concrete surface back to original 
dimensions prior to protective coating or lining installation. 
Holes and any other defects up to 2-inches deep shall be 
filled with C-120 calcium aluminate cement (manufactured 
by Environmental Coatings) or approved equal to restore 
structural integrity. If the defects are larger than 2-inches 
deep a high-early, cement fill compatible with these 
Technical Specifications and recommended by the 
manufacturer 
shall 
be 
used. 
Loose 
or 
splattered 
underlayment shall be removed by scraping and chipping. 
The C-120 and high early cement fill shall be applied as 
recommended by the manufacturer. 
 
Application: 
Underlayment shall dry a minimum of 5 hours at 70 degree 
F in an atmospheric environment with humidity below 
manufacturer’s recommended levels prior to application of 
the protective coating Sewer Shield 100 or as recommended 
by the manufacturer. 
 
Coating shall be applied as recommended by the 
manufacturer, provided the coating as applied complies with 
prevailing air pollution control regulations. 
 
Drying time between coats shall be as recommended by 
coating manufacturer. 
Design Coating  
Thickness: 
250 mils dry thickness. 
 
Coatings: 
Coats at manufacturer's recommended dry thickness per coat 
to the specified total system thickness. 
 
Color 
ivory white – or approved color

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 26 
October 25, 2024 
3.20     B. COATING SYSTEM SPECIFICATION SHEETS (COATSPEC) 
 
Surfaces shall be coated in accordance with the COATSPEC to the system thickness 
specified. 
 
Coating System 
Identification: 
Sauereisen Sewergard Lining No. 210 
 
Surface: 
Concrete/Masonry 
 
Minimum Surface  
Preparation: 
Abrasive Blasting and Hydro Blasting 
 
Concrete Surface 
Profile Acceptable 
Range: 
ICRI CSP 3-4 
 
Concrete: 
Except as otherwise specified, loose concrete, form oils, 
surface hardeners, curing compounds, and laitance shall be 
removed from surfaces by abrasive and hydro blasting. 
Voids and cracks shall be repaired as specified in Technical 
Specification Section 09710 paragraph 3.06 and as indicated 
by the underlayment defect repair paragraph. After grit 
abrasion blasting, the concrete should be high pressure 
washed to remove oil, grease, and other contaminants. All 
active hydrostatic leaks must be stopped by use of a water 
stop, waterproofing, or urethane grout. 
Epoxy Coating 
Compatibility: 
Except as otherwise specified, any existing coating that is 
incompatible with proposed epoxy coating as recommended 
by the proposed coating manufacturer’s recommendation for 
proper bonding purposes, shall be removed from surfaces by 
abrasive and hydro blasting and chipping if required.  
 
Underlayment: 
Sauereisen Restokrete Substrate Resurfacer No. F-120 shall 
be used to fill holes and undulations in concrete surface 
found or created during the cleaning process. Sufficient 
material shall be used to build the concrete surface back to 
original dimensions prior to protective coating or lining 
installation. Holes and any defects up to 2-inches deep shall 
be filled with as manufactured by Sauereisen Cements, 
Pittsburgh, PA or approved equal to restore structural 
integrity. If the defects are larger than 2-inches deep a high-
early cement fill compatible with these Technical 
Specifications and recommended by the manufacturer shall 
be used. Loose or splattered underlayment shall be removed

SECTION 09710 
 
 
CONCRETE AND MASONRY COATING 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 27 
October 25, 2024 
by scraping and chipping. The Sauereisen No. F-120 and 
high early cement fill shall be applied as recommended by 
the manufacturer. 
 
Application: 
Underlayment shall dry a minimum of 5 hours at 70 degree 
F in an atmospheric environment with humidity below 
manufacturer’s recommended levels prior to application of 
the protective coating Sewergard No. 210 or as 
recommended by the manufacturer. Underlayment must be 
cured by means of fog spray, wet burlap, or appropriate 
Sauereisen curing compound. The Contractor shall follow 
coating manufacturer’s requirements for bonding the coating 
systems to the installed sewer liner. 
 
Coating shall be applied as recommended by the 
manufacturer, provided the coating as applied complies with 
prevailing air pollution control regulations. Only one coat 
should be applied to obtain the system thickness. The 
Contractor shall follow costing manufacturer’s requirements 
for bonding the coating system to the installed liner. 
 
Drying time between coats shall be as recommended by 
coating manufacturer. 
Design Coating  
Thickness: 
250 mils dry thickness. 
 
Coatings: 
Coats at manufacturer's recommended dry thickness per coat 
to the specified total system thickness. 
 
Color 
Ivory white – or approved color

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 28 
October 25, 2024 
3.21 – C. COATING SYSTEM SPECIFICATION SHEETS (COATSPEC) 
 
Surfaces shall be coated in accordance with the COATSPEC to the system thickness 
specified. 
 
Coating System 
Identification: 
Raven 405 Epoxy Lining 
 
Surface: 
Concrete/Masonry 
 
Minimum Surface  
Preparation: 
Abrasive Blasting and Hydro Blasting 
 
Concrete Surface 
Profile Acceptable 
Range:  
 
 
ICRI CSP 3-4 
 
Concrete: 
Except as otherwise specified, loose concrete, form oils, 
surface hardeners, curing compounds, and laitance shall be 
removed from surfaces by abrasive and hydro blasting. 
Voids and cracks shall be repaired as specified in Technical 
Specification Section 09710 paragraph 3.06 and as indicated 
by the underlayment defect repair paragraph. After grit 
abrasion blasting, the concrete should be high pressure 
washed to remove oil, grease, and other contaminants. All 
active hydrostatic leaks must be stopped by use of a water 
stop, waterproofing, or urethane grout. 
Epoxy Coating 
Compatibility: 
Except as otherwise specified, any existing coating that is 
incompatible with proposed epoxy coating as recommended 
by the proposed coating manufacturer’s recommendation for 
proper bonding purposes, shall be removed from surfaces by 
abrasive and hydro blasting and chipping if required.

SECTION 09710 
 
 
CONCRETE AND MASONRY COATING 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 29 
October 25, 2024 
 
Underlayment: 
Underlayment 
with 
calcium 
aluminate 
cement 
as 
recommended by Raven 405 manufacturer shall be used to 
fill holes and undulations in concrete surface found or 
created during the cleaning process. Sufficient material shall 
be used to build the concrete surface back to original 
dimensions prior to protective coating or lining installation. 
Holes and any other defects up to 2-inches deep shall be 
filled with calcium aluminate cement (as manufactured by 
Raven Lining Systems, Tulsa, Oklahoma) or approved equal 
to restore structural integrity. If the defects are larger than 2-
inches deep a high-early cement fill compatible with these 
Technical Specifications and recommended by the 
manufacturer 
shall 
be 
used. 
Loose 
or 
splattered 
underlayment shall be removed by scraping and chipping. 
The calcium aluminate cement and high early cement fill 
shall be applied as recommended by the manufacturer. 
 
Application: 
Underlayment shall dry a minimum of 5 hours at 70-degree 
Fahrenheit in an atmospheric environment with humidity 
below manufacturer’s recommended levels prior to 
application of the protective coating Raven 405 or as 
recommended by the manufacturer. 
 
Coating shall be applied as recommended by the 
manufacturer, provided the coating as applied complies with 
prevailing air pollution control regulations. Only one coat 
should be applied to obtain the system thickness. The 
Contractor shall follow coating manufacturer’s requirements 
for bonding the coating system to the installed liner. 
 
Design Coating  
Thickness: 
250 mils dry thickness. 
 
Coatings: 
Coats at manufacturer's recommended dry thickness per coat 
to the specified total system thickness. 
 
Color 
ivory white – or approved color 
 
 
** END OF SECTION **

SECTION 09710 
CONCRETE AND MASONRY COATING 
 
 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
09710 - 30 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double-sided printing ]

SECTION 13128 
FIBERGLASS REINFORCED MANHOLE INSERT 
_ 
 
 
 
 
 
 
_ 
 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 1 
October 25, 2024 
PART 1 – GENERAL 
 
1.01 
DESCRIPTION 
 
This Technical Specification section specifies the requirements for installing a chemically 
inert structural composite material insert within an existing sanitary sewer access manhole. 
The work to be done under this Contract consists of furnishing all labor, materials, and 
equipment to install a composite manhole insert.  
 
A. SCOPE: 
 
This Technical Specification covers all work necessary to furnish and install a structural 
manhole insert. The Contractor shall be licensed in the State of Arizona. The Contractor 
shall deliver a finished insert product(s) including all materials, labor, equipment, and 
services necessary for product installation, all quality controls and samples for performance 
of required material tests, final inspection and warranty work.   Anticipated work to be 
provided also includes removal and replacement of ring and cover, excavation of existing 
manhole cone including removal and offsite disposal, manhole interior cleaning, insert 
installation and grouting of annular space, along with removal and replacement of any 
interior piping and equipment. 
 
The work shall be for the renewal of sanitary sewer manholes that shall be accomplished 
by the installation of a number of components either individually or together with other 
components. These may include acid resistant non-shrink grout to structurally rebuild the 
manhole bench and or throat section back to original dimensions and apply polymer grout 
to provide chemical resistance for the specified service life.  
 
Several manhole components such as existing frame and cover will typically be removed 
and/or reinstalled if in good condition or replaced with new components. Any steps present 
within the manhole will be removed and not replaced.  The Contractor is responsible for 
extension and proper reconnection of any sewer and/or utility piping present within the 
manhole including all seals and/or mechanical devices to properly restore original service 
and capabilities unless otherwise directed.  Contractor is responsible for accurate and 
complete manhole rehabilitation as specified. 
 
1.02 
SAFETY REQUIREMENTS:   
 
The Contractor shall conform to all work safety and health requirements of pertinent 
regulatory agencies and/or shown in Technical Specification Section 01060 – HEALTH 
AND SAFETY and shall secure the site for working conditions in compliance with the 
same. The Contractor shall perform existing material testing as required by regulatory 
regulation requirements and erect such signs and other devices as are necessary and be 
responsible for safety at the work site. Sewer flow will be present during installation, the 
Contractor shall consider the exposed existing manhole as a confined space.

SECTION 13128 
FIBERGLASS REINFORCED MANHOLE INSERT 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 2 
October 25, 2024 
 
1.03 
NOTIFICATION:   
 
It shall be the Contractor's responsibility to notify all utility companies involved whenever 
a utility is to be cut, tapped, moved, or in any way disturbed from its original placement. 
Sufficient notice shall be given to the utility company so that its users can be informed of 
any disruption of service. Such notice shall be given no less than 48 hours in advance. 
 
It is the Contractor's responsibility to inform the City of construction activities which may 
lead to interruption in sewer service.  The Contractor shall provide 72 hour notice prior to 
construction in order for the City to alert all applicable residents. 
 
1.04 
QUALITY CONTROL 
 
A. REFERENCES: 
 
Reference 
Title 
 
ASTM C33  
Specification for Concrete Aggregates 
 
ASTM C273 
Standard Test Method for Shear Properties of Sandwich 
Core Materials  
 
ASTM C581 
Practices for Determining Chemical Resistance of Chemical 
Thermosetting Resins Used in Glass-Fiber Reinforced 
Structures Intended for Liquid Service. 
 
ASTM C582 
Plastic Laminate 
 
ASTM D543 
Test Method for Resistance of Plastics to Chemical Reagents 
 
ASTM D638 
Standard Test Method for Tensile Properties of Plastics 
 
ASTM D695 
Standard Test Methods for Compressive Properties of Rigid 
Plastics 
 
ASTM D790 
Standard Test Methods for Flexural Properties of 
Unreinforced and Reinforced Plastics and Electrical 
Insulating Materials 
 
ASTM D1244 
Standard Test Method for Concrete Sewer Manholes by the 
Negative Air Pressure (Vacuum) Test Prior to Backfill  
 
ASTM D1622 
Standard Test Method for Apparent Density of Rigid 
Cellular Plastics

SECTION 13128 
 
 
 
    
FIBERGLASS REINFORCED MANHOLE INSERT 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 3 
October 25, 2024 
ASTM D1623 
Standard Test Method for Tensile and Tensile Adhesion 
Properties of Rigid Cellular Plastics  
 
ASTM D2412 
Test Method for Determination of External Loading 
Characteristics of Plastic Pipe by Parallel Plate Loading 
 
ASTM D2583 
Standard Test Method for Indentation Hardness of Rigid 
Plastics by Means of a Barcol Impressor 
 
ASTM D2842  
Standard Test Method for Water Absorption of Rigid 
Cellular Plastics 
 
ASTM D3753 
Standard Specification for Glass-Fiber Reinforced Polyester 
Manholes 
 
ASTM G20 
Standard Test Method for Chemical Resistance of Pipeline 
Coatings 
 
AASHTO HS-20 
Standard Specification for Highway Bridges Codes - Axle 
Loading 
 
AWWA C950 
Glass-Fiber Reinforced Thermosetting Resin Pressure Pipe 
 
1.05 
CERTIFIED INSTALLER 
 
The composite insert shall be installed by a Contractor certified by the insert 
manufacturer. A training outline for the certification program shall be submitted to the 
City for review. The Contractor shall provide evidence that the on-site Superintendent 
that is responsible for supervision of the crew performing the installation and has 
received the manufacturer's training. 
 
The Contractor shall appoint a Quality Assurance Manager who will be on-site full-
time during manhole bench preparation, insert installation, annular space grouting, 
and backfill to take full responsibility for the quality of the work.  The Quality 
Assurance Manager shall be fully certified by the insert manufacturer. 
 
1.06 
SUBMITTALS: 
 
Contractor shall submit the following information to the City’s Representative in 
accordance with Technical Specification Section 01300 - SUBMITTALS. 
 
A. Insert Manufacturer’s Qualifications: The manufacturer of the manhole insert shall 
show experience in the manufacture of proposed insert for more than five (5) years. 
 
B. Documentation of Contractor’s Experience: Contractor shall provide references for all 
jobs within the last two (2) years that were either completed or under construction using 
the proposed rehabilitation method.

SECTION 13128 
FIBERGLASS REINFORCED MANHOLE INSERT 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 4 
October 25, 2024 
C. Installer’s Qualifications: The installer of the manhole insert shall show experience in 
the installation of the proposed inserts for more than five (5) years. References shall be 
provided for a minimum of five (5) jobs.  Information provided shall include a 
description of the job, the location of the job, the value of the job, the Owner name, and 
the Owner contact person for the job including name, title, address, and phone number.   
The total jobs submitted shall show that at least 1,000 vertical feet of the product 
installed by the installation Contractor.  
 
D. Submit manufacturer’s published product and installation literature and published 
quality control testing criteria data for the proposed manhole insert system. 
 
E. Submit Test Reports: The manufacturer shall design, fabricate and certify that the 
manhole insert conforms to ASTM D-3753 - Standard Specification for Glass-Fiber 
Reinforced Polyester Manholes and the requirements of this Technical Specification. 
 
F. Submit independent test report showing that the physical properties of the proposed 
insert meet the requirements of these Technical Specifications and will meet or exceed 
the physical properties given in the manufacturer’s published literature submitted as 
required by Part 2 – PRODUCTS. 
 
G. Submit a report outlining the proposed installation process and procedures as directed 
by the insert manufacturer to be used. The report shall include information specific to 
the installation instructions and any unique site condition(s) that must be taken into 
consideration including grout curing operations and procedures, annular space grout 
type requirements and lift limitations, access coordination, installation timing and 
identification and any coordination requirements/requests from the City or others. 
 
H. Shop Drawings:  Contractor shall provide shop drawings of proposed materials for 
approval prior to ordering.  Shop drawings shall depict: 
 
1. All measurements made by the Contractor to verify manhole critical dimensions 
including but not limited to depth and diameter along with any pipe penetrations or 
equipment hanger requirements.   
2. Material(s) proposed for construction. 
3. Critical dimensions, jointing and connections, fasteners and anchors with sizes, 
spacing, and location, connections, attachments, and openings. 
4. Anticipated grade adjustment ring(s) and height. 
 
I. Contractor to provide design detail for manhole bench conditions with insufficient 
circumferential bearing area to support the manhole insert. Modifications shall be per 
manufacturer’s recommendations.  
 
J. Documentation of the control checks of fiberglass, epoxy or polyester resin content 
for materials used in each part of insert fabrication.

SECTION 13128 
 
 
 
    
FIBERGLASS REINFORCED MANHOLE INSERT 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 5 
October 25, 2024 
K. Approved maximum depth of annular space grout per lift as calculated by the insert 
manufacturer structural engineer. 
 
L. Warranty:  Contractor shall submit warranty documents signed by an Officer of the 
Company and notarized stating the terms and conditions of the warranty identified in 
Paragraph 1.10 – WARRANTY. 
 
M. Any item the Contractor proposes to utilize as an "or equal" to that proposed in the 
Contract Documents. 
 
1.07 
SUBSTITUTIONS 
 
Any item the Contractor proposes to substitute for a specified item as an "or equal" must 
be made in writing, received and approved by the City or City’s Representative prior to the 
start of construction activities. Substitutions or deviations installed and not approved by 
the City shall risk rejection and replacement at no additional cost to the City. 
 
1. For any proposed design change or deviation from these Technical Specifications, 
2. For anything in these Technical Specifications found to conflict with applicable codes 
and ordinances, 
3. For anything not understood by the Contractor. 
4. One (1) electronic copy of submittal(s) shall be provided to the City at least two (2) 
weeks before a determination is required.   
5. Submittals may be drawings, sketches, manufacturer's literature, catalog descriptions, 
or other descriptions in sufficient detail to allow a decision. The submittal shall indicate 
the amount to be added to or deducted from the bid price should the submittal be 
accepted. 
 
1.08 
QUALITY ASSURANCE/QUALITY CONTROL 
 
A. EXAMINATION: Each insert component part shall be examined by the Contractor for 
dimensional requirements, soundness, and workmanship in accordance with 
manufacturer’s specifications.  
 
B. COMPOSITION CONTROL: Manufacturer shall control the fiberglass, epoxy or 
polyester resin content for each part of manhole fabrication. Documentation of the 
control checks shall be maintained by the manufacturer.  Proper fiberglass content may 
be shown by glass usage checks or glass and resin application rate checks, in 
accordance with the material composition test in ASTM D-3753 and ASTM D-2584. 
 
C. TESTING RECORDS:  Records of all testing shall be kept and copies of test results 
shall be submitted to the City or City’s Representative in accordance with Paragraph 
1.06 - SUBMITTALS.

SECTION 13128 
FIBERGLASS REINFORCED MANHOLE INSERT 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 6 
October 25, 2024 
1.09 
INSPECTION POINTS 
 
Contractor shall keep the City or City’s Representative informed of milestone 
progress on each insert location for the following items: 
 
1. Start of excavation to remove the cone, chimney, frame and cover. 
2. Completion of removal of unsound material and manhole pressure wash cleaning. 
3. Completion of bench cleaning and preparation (if any). 
4. Completion of leveling/seal grout placement prior to insert placement. 
5. Prior to annular space grouting. 
6. Completion of bench protective coating. 
7. Completion of backfill placement. 
 
1.10 
WARRANTY 
 
The Contractor shall replace promptly and at no expense to the City, any materials which 
fails during the warranty period.  Warranty work shall include all ancillary items including, 
but not limited to permits, traffic control, and flow control required to compete the 
repair/replacement work.   Warranty and durations are described below: 
 
A. Project Warranty: The Contractor shall warrant all materials and workmanship 
performed under this contract for a period of one (1) year from the date of formal 
acceptance or as stated in the project Contract Documents whichever is longer. 
 
B. Materials Warranty: The manhole insert shall be free of defects that will affect the long 
term life and operation of the manhole.  The Contractor shall warrant in writing all 
materials provided and work performed under this contract for a period of five (5) years 
from the date of formal acceptance.   
 
C. Insert: Insert material(s) shall be tested for a design life of a minimum of fifty (50) 
years against deterioration from H2S corrosion and typical chemicals found in 
municipal sanitary sewage. 
 
 
PART 2 – PRODUCTS 
 
2.01 
COMPOSITE MATERIAL LINER INSERT 
 
A structural insert shall be installed into the interior of existing deteriorated sanitary sewer 
manhole that meet or exceed ASTM D 3753 - Standard Specification for Glass-Fiber 
Reinforced Polyester Manholes.  Approved insert manufacturer: 
 
1) Sewer Shield Composite Insert: Manufactured by Joseph Painting Company, Inc. 
(JPCI), 4702 E. Virginia Street, Mesa, AZ 85215 
2) Approved equal

SECTION 13128 
 
 
 
    
FIBERGLASS REINFORCED MANHOLE INSERT 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 7 
October 25, 2024 
2.02 
MATERIAL and DESIGN 
 
This section is to provide minimum design calculations and testing requirements for a 
barrel section and cone together. There are some Technical Specifications that shall differ 
between the cone and the barrel that shall be described in separate sections. 
 
A. The design of the insert shall be prepared and professionally sealed by an Engineer 
licensed in the State of Arizona. The insert shall meet or exceed the requirements of 
buried manholes up to 40 feet deep without the use or reliance upon external or internal 
structural stiffeners. The design shall not allow infiltration of ground water. 
 
B. Insert shall be designed and tested to withstand AASHTO HS-20 loading with no structural 
strength derived from the existing manhole structure or installation of external or internal 
structural stiffeners. 
 
C. Material of the insert shall be consistent throughout the structure consisting of resin 
material including reinforcement that is inert to corrosion from sewer gasses. Epoxy 
shall be 100% solids, solvent free, low odor emitting, environmentally friendly, and 
impervious to chemicals. Reinforcement shall be made with fiberglass. 
 
D. The resins used shall be unsaturated, supplier certified commercial grade polyester 
resins.  Mixing lots of resin from different manufacturers or “odd-lotting” of resins 
shall not be permitted.  Quality assurance records on the resin shall be maintained. Non-
pigmented resin is required to allow for light or “sand” color of interior surface in order 
to facilitate ease of inspection from ground surface. UV inhibitors shall be added 
directly to resins to prevent degradation. 
 
E. The Fiberglass Reinforced Manhole Insert shall have the following minimum strengths:  
1. Tensile Strength (psi):  
18,000 
2. Flexural Strength (psi):  
26,000 
 
F. Load Rating: The complete manhole shall have a minimum dynamic load rating of 
16,000 pounds. When tested in accordance with ASTM 3753, 8.4 (note 1). To establish 
this rating the complete manhole shall not leak, crack, or suffer other damage when 
load tested to 40,000 pounds and shall not deflect vertically downward more than 0.25-
inches at the point of load application when loaded to 24,000 pounds. 
 
 
G. The use of a multi-piece insert must be approved by the City prior to ordering.  If 
allowed, joints shall be of bell and spigot configuration. Joints every 5 feet shall be 
sealed with a material consistent with the chemical resistance of the composite manhole 
sections and shall not affect the warranty.  All joints shall be waterproofed and shall 
not allow infiltration.

SECTION 13128 
FIBERGLASS REINFORCED MANHOLE INSERT 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 8 
October 25, 2024 
2.03 
THIRD PARTY TESTING 
 
The manufacturer shall have testing of the manhole insert performed by an independent 
test laboratory. Testing shall be performed in accordance with ASTM D-3753 and this 
Technical Specification. Where there are conflicts between the requirements of the ASTM 
and this Technical Specification, this Technical Specification shall supersede. The 
Manufacturer shall submit the results of third-party testing, as specified below, and in 
accordance with Technical Specification Section 01330 - SUBMITTALS. 
1. LOAD RATING: The insert shall have an AASHTO HS-20 load rating.  When 
tested in accordance with ASTM D-3753 the insert shall have a maximum vertically 
deflection of 0.25-inches at the point of load application when loaded to 24,000 
pounds; and shall not leak, crack, or suffer other damage when load tested to 40,000 
pounds. 
 
2. CHEMICAL RESISTANCE TESTING: The following chemical resistance tests 
shall be performed in accordance with ASTM D-3753: 
a. Separate test specimens shall be subjected to the following four reagents: 
1. A 10 percent solution of sulfuric acid and tested in accordance with ASTM 
C-581 and ASTM D 3753. 
2. Grease, as defined by Standard Methods for the Examination of Water & 
Wastewater, Sections 2530C – Floatables, and 5520 - Oil and Grease 
3. Deionized water (pH of 5 to 6) 
4. A 10 percent (by weight) detergent in water solution 
 
a. The manufacturer shall provide the testing laboratory a representative product 
sample large enough whereby the laboratory will prepare appropriate test 
specimens for required testing. Each specimen shall be large enough to allow a 
minimum of three individual flexural test samples. Seal cut edges with the resin 
used in the resin-rich surfaces. 
 
b. All testing to be performed for a total of 12 months for each test specimen. 
Intermittent observations shall be made for each test specimen after one (1), 
three (3), six (6), and twelve (12) months immersions in each test medium. The 
test report shall note the condition and appearance of each sample after each 
test period. 
 
c. A "control" test specimen shall be maintained for comparison of immersed 
specimens throughout testing. 
 
For this Technical Specification, acid concentration in terms of "percent" is defined 
as weight of solute per volume of solution. A sulfuric acid concentration of 10 
percent contains 100 grams of sulfuric acid per liter of acid solution. Estimated pH 
value for 10 percent sulfuric acid solution is 1.0.

SECTION 13128 
 
 
 
    
FIBERGLASS REINFORCED MANHOLE INSERT 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 9 
October 25, 2024 
After exposure to the solutions, specimens shall exhibit zero (0) weight loss, 
spalling, cracking or blistering. Any changes to appearance such as color and 
texture shall be noted. 
 
2. MATERIAL PROPERTY TESTING: Manufacturer to provide results of testing 
performed in accordance with ASTM D-3753, without modification, for the 
following material properties: 
 
a. STIFFNESS: The insert shall have the minimum pipe-stiffness values shown in 
the table below, when tested in accordance with ASTM D-3753. Stiffness for 
other manhole lengths can be interpolated between values.  
PIPE STIFFNESS VALUES 
Manhole Length 
(feet) 
PSI 
6 
0.72 
12 
1.26 
20 
2.01 
25 
3.02 
35 
5.24 
 
2.04 
CONE DESIGN SPECIFICATIONS 
 
Cones shall be concentric for all manhole diameters. The cone section must provide a 
flat shoulder bearing surface on which a chimney consisting of adjustment grade rings 
may be supported. 
 
2.05 
CHIMNEY CONSTRUCTION:   
 
The chimney shall be constructed on the flat shoulder bearing surface of the cone using 
grade adjustment rings, unless otherwise approved by the City. The chimney shall be 
built to support the cast iron frame and cover adjusted to final surrounding grade.  The 
height of chimney shall be 18-inches minimum to three (3) feet maximum.   
 
2.06 
STANDARD CITY CAST IRON FRAME AND COVER: 
 
The cast iron frame and cover shall be supported by the chimney and shall not be installed 
directly on the cone.  Contractor shall inform City if existing frame and/or cover is worn 
or damaged and shall obtain approval prior to replacing frame and cover.

SECTION 13128 
FIBERGLASS REINFORCED MANHOLE INSERT 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 10 
October 25, 2024 
2.07 
MANHOLE B E N C H / BOTTOM:   
 
Resin and fiberglass reinforced manhole bottoms shall not be allowed unless otherwise 
approved by City or City's Representative. If allowed they shall meet the requirement of 
this Technical Specification.  Stiffeners shall be of non-corrosive materials encapsulated 
in fiberglass. FRP encapsulated wood or lumber will not be permitted. 
 
2.08 
GROUTS:  
 
 
All grouts applied to the manhole interior shall be acid resistant quick-setting non-
shrink epoxy grouts, approved by the insert manufacturer and compatible with the 
polymer protective coating material and tested in accordance with ASTM C579 – 
Standard Test Methods for Compressive Strength of Chemical-Resistant Mortars, 
Grouts, Monolithic Surfacing, and Polymer Concretes.  
 
2.09 
MARKING AND IDENTIFICATION: 
 
A. Manhole insert shall be marked on both the interior and exterior with the following 
information: 
 
1. Manufacturer’s Company Name identification.  
2. Date of Manufacture.               
3. Manhole wall thickness. 
4. Installation assist marks. 
 
2.10 
DELIVERY, STORAGE AND HANDLING 
 
Contractor shall be responsible for any damage resulting from improper storage and/or 
handing.  Damaged materials shall be replaced at no additional cost to the City. 
 
A. Materials shall be handled in accordance with MAG 106. 
 
B. Store all products according to manufacturer’s recommendations until installation.  Protect 
from construction traffic and damage. 
 
C. During the loading, unloading, and storage, care should be taken to ensure that the manhole 
insert is not dropped or otherwise damaged. 
 
D. The manhole insert should be stored on a smooth surface free of sharp objects.  
 
E. Nylon or fabric slings should be used in conjunction with a spreader bar to lift or move the 
manhole insert.  
 
F.  UNDER NO CIRCUMSTANCES SHOULD CABLES OR CHAINS BE USED. 
 
G. If the manhole insert is stored horizontally, the manhole insert should be placed in such 
a way as to avoid damage and braced.

SECTION 13128 
 
 
 
    
FIBERGLASS REINFORCED MANHOLE INSERT 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 11 
October 25, 2024 
PART 3 – EXECUTION 
 
3.01 
PROTECTION OF SITE:  
 
Except as otherwise provided herein, the Contractor shall protect from damage all fences, 
structures, sidewalks, utilities, trees, shrubbery, lawns, etc., during the progress of this 
work. All debris and unused materials shall be removed immediately upon completion of 
the work. The site shall be restored as nearly as possible to its original condition, including 
the replacement, at the Contractor's sole expense, of any facility or landscaping which has 
been destroyed or damaged beyond restoration. 
 
3.02 
UTILITIES:   
  
Unless otherwise indicated in Technical Specification Section 01550 – CONTRACTOR’S 
UTILITIES, the Contractor shall arrange for and provide any required utilities at his sole 
cost and expense.  This includes but is not limited to water for compaction or testing, power 
for operating any equipment along with personnel sanitation facilities. 
 
3.03 
CLEANING AND PREPARATION 
 
A. The Contractor shall be responsible for all existing manhole cleaning and surface 
preparation according to Technical Specification Section 02760 – SEWER AND 
SEWER STRUCTURE CLEANING.  The Contractor shall notify the City of any 
irregularity, which may interfere with the proper installation of the manhole insert.   
 
3.04 
COMPOSITE INSERT 
 
A. The manhole insert installed shall bond to or fit sufficiently tight atop the existing 
manhole bench so as to eliminate water leakage into the manhole or allow water or 
vapors to leak out of the manhole through pinholes or other defects. If infiltration or 
exfiltration leakage occurs, the Contractor shall seal these areas to stop all leakage 
using a material compatible with the insert material installed and as specified by the 
manufacturer. If leakage continues to occur, the Contractor shall remove and replace 
the insert at no additional cost to the City. All repair materials shall have the same 
estimated life expectancy as the insert installed. Final approval of the installation will 
be based on meeting the acceptance test requirements for each insert installed. 
 
B. All existing manhole interior piping shall be removed prior to insert installation and 
bench protective coating application.  Interior piping shall be reinstalled per project 
Design Drawings or as required by these contract Technical Specifications. 
 
C. Flow from existing active service connections entering the manhole shall be plugged 
or diverted through by-pass pumping operation, if the flow affects proper installation. 
 
D. Testing and warranty inspections shall be witnessed by the City or the City’s 
Representative. Any defects found shall be repaired by the Contractor.

SECTION 13128 
FIBERGLASS REINFORCED MANHOLE INSERT 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 12 
October 25, 2024 
E. Compensation for all work required for providing test samples and independent 
laboratory testing shall be included in the in the Bid Proposal cost of the item contained. 
 
3.05 
INSTALLATION: 
 
A. The Contractor shall install the manhole insert in accordance to approved 
manufacturer’s techniques. 
 
B. The insert shall be centered inside the existing manhole base or as otherwise 
approved. 
 
C. Contractor shall use an acid resistant polymer grout around circumference of the bench 
prior to lowering insert into position.  The insert base section shall be installed into 
fresh grout to evenly support the weight of the insert and establish a gas 
tight seal.  The polymer grout shall be compatible with insert material and approved 
for use by the insert manufacturer and compatible with the bench protective coating 
material. The bottom seal shall also prevent loss of annular space grout material 
installed between the outside of the insert and the interior wall of the existing 
manhole. 
 
D. After placement of insert, Contractor shall complete installation of the 
protective coating of the manhole bench. As a minimum, Contractor shall raise 
manhole bench to the same elevation as the crown of the pipe as directed or shown in 
project Design Drawings. Manhole bench shall be sloped a minimum ¼-inch per foot 
to the channel. Minimum repair grout thickness shall be ¾-inch.   
 
E. Where insert is installed using multiple barrel sections in lieu of a single piece barrel, 
apply a non-shrink epoxy putty or butyl mastic sealant approved by the manufacturer, 
to the joint of each barrel or cone section. Wipe excess material from the inside seam 
to provide a smooth finish. 
 
F. Replace all existing manhole connections with the same inside diameter pipe. Sewer 
main and lateral connections in the existing manholes shall be extended through the 
insert with sealed watertight connections. Seal all penetrations through the insert with 
an acid resistant non-shrink polymer grout. Installation shall be in accordance with 
Manufacturer's written instructions utilizing installation equipment approved for use 
by the Manufacturer. 
 
G. Fill the annular space between the insert and the existing manhole wall with a Portland 
cement and sand grout mixture or a hydrophilic grout. The grout backfill shall be 
placed in a maximum 12-inch lifts or as approved by the insert manufacturer 
structural engineer.  Manufacturer’s approved maximum lift shall be submitted 
to the City per Technical Specification Section 01300 – SUBMITTALS.  Grout 
shall cure to provide a minimum compressive strength of 100 psi. The grout shall be 
consolidated without damage to the insert or connecting pipes.

SECTION 13128 
 
 
 
    
FIBERGLASS REINFORCED MANHOLE INSERT 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 13 
October 25, 2024 
H. Install the cone section (if applicable). after grouting the top bell section  
 
3.06 
CONE BACKFILL MATERIAL 
 
Contractor shall backfill around the manhole cone and chimney with sand, crushed stone, 
pea gravel or aggregate base course (ABC) per MAG Section 701, unless directed 
otherwise and approved by the Engineer.  The material chosen shall be free of large lumps 
or clods, which shall not readily break down under compaction. 
 
Backfill shall be placed in layers of not more than twelve (12) loose measure inches and 
mechanically tamped to 95 percent Standard Proctor Density, unless otherwise approved 
by the City or City’s Representative. Flooding or water jet compaction shall not be 
permitted. Backfill shall be placed in such a manner as to prevent any wedging action 
against the manhole structure. 
 
Contractor shall install grade rings and adjust height to surrounding elevation and slope.  
Pour a concrete collar around the manhole ring and cover after setting the proper height. 
 
All damaged pavements shall be removed and replaced in kind with new pavement. In 
landscaped areas the surface shall be restored in kind. Any damaged irrigation facilities 
shall be repaired. 
 
3.07 
GROUTING: 
 
Annular space grouting shall be done in accordance with manufacturer's requirements and 
as described in "Installation" procedures, and should meet the following minimum 
requirements: 
 
 
Test Type 
Results 
Test Method 
Density 
4 lbs. 
ASTM D-1622 
Water Absorption 
(volume confined) 
<1% 
ASTM D-2842 
Shear Strength 
17.10 PSI 
ASTM C-273 
Tensile Strength 
29.30 PSI 
ASTM D-1623 
Elongation 
44% 
ASTM D-1623 
Viscosity 
@ 500 CPS 
 
Chemical Emersion 
Testing 
Excellent results 
ASTM G20-88 
 
The system should also use an accelerator to quicken the reaction time (30 minutes) where 
needed.  All physical properties shall be expected to be detailed in submittals showing that 
they meet these Technical Specifications.

SECTION 13128 
FIBERGLASS REINFORCED MANHOLE INSERT 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 14 
October 25, 2024 
3.08 
MANHOLE BENCH and CHANNEL RESTORATION 
 
Manhole bench and channel shall be cleaned and coated as follows: 
 
A. The manhole invert and bench shall be grit blasted to produce a profile, followed by 
high pressure water blasting to remove any lose debris and adjust pH acidity to Neutral. 
 
B. Manhole bench shall be rebuilt with non-shrink acid resistant grout as necessary to 
restore original dimensions in preparation for structural foundation of insert. 
 
C. A polymer grout should then be applied according to Technical Specification 09710 – 
CONCRETE AND MASONRY COATING to the circumference of the bench to create 
a level bearing area and seal of the first insert barrel section installation. 
 
D. After the manhole insert has been installed and base rebuilt, the entire bench and 
channel shall be coated with a protective polymer grout according to Technical 
Specification 09710 – CONCRETE AND MASONRY COATING to ensure the 
exposed manhole base/throat/channel have the similar acid resistance as the remainder 
of the rehabilitated manhole. 
 
3.09 
LATERALS AND CONNECTIONS: 
 
Sewer main and lateral connections present in the existing manholes shall be extended 
through the insert wall with sealed watertight connections. Existing pipe diameters shall be 
maintained.  Penetration installation shall be in accordance with insert manufacturer's 
written instructions utilizing installation equipment approved for use by the manufacturer.  
Penetrations cut through the insert wall shall be made with tools capable of cutting circular 
shapes.  Use of a carbide blade chop saw or other tools that cut a straight edge shaped is 
strictly prohibited. Penetrations through the insert shall be sealed with a material approved 
by the insert manufacturer.  
 
3.10 
PROTECTIVE BENCH COATING TESTING 
 
Contractor shall perform spark test and pull test on applied coatings per Technical 
Specification Section 09710 – CONCRETE AND MASONRY COATING. 
 
3.11 
ACCEPTANCE 
 
As a condition precedent to Final Acceptance of the work, Contractor shall certify the 
proper installation and testing of material provided under this section. Certification shall 
warrant that materials and installation are free of defects and/or workmanship and suitable 
for trouble-free operation under the conditions set forth in these Technical Specifications.

SECTION 13128 
 
 
 
    
FIBERGLASS REINFORCED MANHOLE INSERT 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 15 
October 25, 2024 
3.12 
RECORD DRAWINGS:  
 
Prior to final payment, the Contractor shall provide a complete set of redlined Design 
Drawings showing the project as constructed including manhole insert depth, diameter, 
along with location and diameter of any insert penetrations and interior piping 
configurations.  A spreadsheet and/or Design Drawings shall include all information 
required elsewhere in these Technical Specifications as well as any changes. 
 
 
** END OF SECTION **

SECTION 13128 
FIBERGLASS REINFORCED MANHOLE INSERT 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13128 - 16 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double sided printing ]

SECTION 13130 
POLYMER CONCRETE MANHOLE INSERT 
______________________________________________________  
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13130 - 1 
October 25, 2024 
PART 1 – GENERAL 
 
1.01 
DESCRIPTION 
 
The purpose for this Technical Specification is to provide guidance for the rehabilitation 
of sanitary sewer access manholes using a fully structural insert capable of supporting loads 
without the addition of internal or external stiffeners and manufactured out of materials 
that are chemically inert from chemicals and corrosive gasses typically found in a 
municipal sanitary sewer system.   The insert shall be comprised of barrel and cone 
segments as a single or multi piece monolithic designed unit constructed and installed in a 
manner consistent with acceptable manufacturing and construction techniques and 
practices. 
 
A. SCOPE: 
 
This Technical Specification covers all work necessary to furnish and install a 
structural manhole insert. The Contractor shall be licensed in the State of Arizona. The 
Contractor shall deliver finished insert product(s) including all materials, labor, 
equipment, and services necessary for product installation, all quality controls and 
material samples required for performance tests, final inspection and warranty work, 
all as specified in these Contract Documents and at the quantities of each component 
contained in the Bid Proposal.   Anticipated work to be provided also includes all traffic 
control, bypass pumping diversion and/or temporary restriction of sewage flows (as 
necessary) for durations to complete the work, removal and reinstallation of any grade 
rings along with ring and cover, excavation of existing manhole cone including 
removal, transport and offsite disposal of materials, manhole interior cleaning, any 
manhole bench modifications and placement of  insert base support/seal grout along 
with grouting of insert exterior annular space.  Work also included removal and 
replacement of any interior piping and equipment and reconnection of any lateral pipe 
connections as necessary to reinstate normal sewer service. 
 
The work shall be for the renewal of sanitary sewer manholes that shall be 
accomplished by the installation of a number of components either individually or 
together with other components. These may include acid resistant non-shrink grout to 
structurally rebuild the manhole bench and throat section (if present) back to original 
dimensions and the application of a protective polymer coating at a minimum thickness 
to all exposed concrete/grout to establish chemical resistance.  
 
Any steps present within the manhole shall be removed flush with the manhole interior 
wall.  The Contractor is responsible for extension and proper reconnection of any sewer 
and/or utility piping present within the manhole including all seals and/or mechanical 
hangers and devices to properly restore original service and capabilities.

SECTION 13130 
POLYMER CONCRETE MANHOLE INSERT 
 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13130 - 2 
October 25, 2024 
Contractor is responsible for accurate and complete manhole rehabilitation as specified.  
The prices submitted by the Contractor shall include all costs of permits, labor, 
equipment and materials for the various bid items necessary for furnishing and 
installing the manhole rehabilitation materials and processes in accordance with these 
Technical Specifications complete and in place, including all items of work not 
specifically mentioned herein which are required to make the product perform as 
intended.  All Contractor costs to deliver the final product shall be included in the 
respective lump sum and/or unit price bid items depicted in the Bid Proposal. 
 
1.02 
SAFETY REQUIREMENTS:   
 
The Contractor shall conform to all work safety and health requirements of pertinent 
regulatory agencies and/or shown in Technical Specification Section 01060 – HEALTH 
AND SAFETY and shall secure the site for working conditions in compliance with the 
same. The Contractor shall perform existing material testing as required by regulatory 
regulation requirements, and provide/install/maintain and be responsible such signs and/or 
other devices as are necessary for safety at the work site. 
 
1.03 
NOTIFICATION:   
 
It shall be the Contractor's responsibility to notify all utility companies involved whenever 
a utility is to be cut, tapped, moved, or in any way disturbed from its original placement. 
Sufficient notice shall be given to the utility company so that its users can be informed of 
any disruption of service. Such notice shall be given no less than 48 hours in advance. 
 
It is the Contractor's responsibility to inform the City of construction activities which may 
lead to interruption in sewer service.  The Contractor shall provide 72 hour notice prior to 
construction in order for the City to alert all applicable residents. 
 
1.04 
QUALITY CONTROL 
 
A. REFERENCES: 
 
Reference 
Title 
 
ASTM C478  
Standard Specification for Precast Reinforced Concrete 
Manholes Sections (Structural intent only) 
 
ASTM C478 
Standard Specification for Circular Precast Reinforced 
Concrete Manhole Sections 
 
ASTM C497 
Test Methods for Concrete Pipe, Manhole Sections, or Tile 
 
ASTM C579  
Standard Test Methods for Compressive Strength of 
Chemical-Resistant Mortars, Grouts, Monolithic Surfacings, 
and Polymer Concretes

SECTION 13130 
 
 
 
 
 
POLYMER CONCRETE MANHOLE INSERT 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13130 - 3 
October 25, 2024 
 
ASTM C587 
Standard Practice for Minimum Structural Design Loading 
for Underground Utility Structure 
 
ASTM C923 
Standard Specification for Resilient Connectors between 
Reinforced Concrete Manhole Structures, Pipes, and 
Laterals 
 
ASTM C990  
Standard Specification for Joints for Concrete Pipe, 
Manholes, and Precast Box Sections Using Preformed 
Flexible Joint Sealants 
 
ASTM D1244 
Standard Test Method for Concrete Sewer Manholes by the 
Negative Air Pressure (Vacuum) Test Prior to Backfill  
 
ASTM D2584 
Test Method for Ignition Loss of Cured Reinforced Resins 
 
ASTM D6783  
Standard Specification for Polymer Concrete Pipe (material 
mix design) 
 
ASTM G20 
Standard Test Method for Chemical Resistance of Pipeline 
Coatings 
 
AASHTO HS-20 
Standard Specification for Highway Bridges Codes - Axle 
Loading 
 
AASHTO HL 93  
(LRFD) Bridge Design and Axial Load Specifications 
 
1.05 
CERTIFIED INSTALLER 
 
The insert shall be installed by a Contractor certified by the insert manufacturer. A 
training outline for the certification program shall be submitted to the City for review. 
The Contractor shall provide evidence that the on-site Superintendent responsible for 
supervision of the insert installation crew has received the manufacturer's training. 
 
The Contractor shall appoint a Quality Assurance Manager who will be on-site full 
time during manhole bench preparation, insert installation, annular space grouting, 
and backfill to take full responsibility for the quality of the work.  The Quality 
Assurance Manager shall be fully certified. 
 
1.06 
SUBMITTALS: 
 
Contractor shall submit information to the City or City’s Representative in accordance with 
Technical Specification Section 01300 - SUBMITTALS. 
 
A. Insert Manufacturer’s Qualifications: The manufacturer of the manhole insert shall 
show experience in the manufacture of proposed insert for more than five (5) years.

SECTION 13130 
POLYMER CONCRETE MANHOLE INSERT 
 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13130 - 4 
October 25, 2024 
B. Documentation of Contractor’s Experience: Contractor shall provide references for all 
jobs within the last two (2) years that were either completed or under construction using 
the proposed rehabilitation method.   
 
C. Installer’s Qualifications: The installer of the manhole insert shall show experience in 
the installation of the proposed inserts for more than five (5) years. References shall be 
provided for a minimum of five (5) jobs.  Information provided shall include a 
description of the job, the location of the job, the value of the job, the Owner name, and 
the Owner contact person for the job including name, title, address, and phone number.   
The total jobs submitted shall show that at least 1,000 vertical feet of the product 
installed by the installation Contractor.  
 
D. Submit Manufacturer’s published product and installation literature and published 
quality control testing criteria data for the proposed manhole insert system. 
 
E. Submit Test Reports: The manufacturer shall design, fabricate and certify that the 
manhole insert conforms to ASTM C478 - Standard Specification for Precast 
Reinforced Concrete Manholes Sections and the requirements of this Technical 
Specification. 
 
F. Submit independent test report showing that the physical properties of the proposed 
insert meet the requirements of these Technical Specifications and will meet or exceed 
the physical properties given in the manufacturer’s published literature submitted as 
required by Part 2 – PRODUCTS. 
 
G. Submit a report outlining the proposed installation process and procedures as directed 
by the insert manufacturer to be used. The report shall include information specific to 
the installation instructions and any unique site condition(s) that must be taken into 
consideration including grout curing operations and procedures, annular space grout 
type requirements and lift limitations, access coordination, installation timing and 
identification and any coordination requirements/requests from the City or others. 
 
H. Shop Drawings:  Contractor shall provide shop drawings of proposed materials for 
approval prior to ordering.  Shop drawings shall depict: 
 
1. All measurements made by the Contractor to verify manhole critical dimensions 
including but not limited to depth and diameter along with any pipe penetrations or 
equipment hanger requirements.   
2. Material(s) proposed for construction. 
3. Critical dimensions, jointing and connections, fasteners and anchors with sizes, 
spacing, and location, connections, attachments, and openings. 
4. Anticipated grade adjustment ring(s) and height. 
5. Color(s).

SECTION 13130 
 
 
 
 
 
POLYMER CONCRETE MANHOLE INSERT 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13130 - 5 
October 25, 2024 
I. Contractor to provide design detail for manhole bench conditions with insufficient 
circumferential bearing area to support the manhole insert. Modifications shall be per 
manufacturer’s recommendations.  
 
J. Documentation of the control checks for materials used in the fabrications each part 
of insert fabrication including resin and aggregate content. 
 
K. Approved maximum depth of annular space grout per lift as calculated by the insert 
manufacturer structural engineer. 
 
L. Warranty:  Contractor shall submit warranty documents signed by an officer of the 
company and notarized stating the terms and conditions of the warranty identified in 
Paragraph 1.10 – WARRANTY. 
 
M. Any item the Contractor proposes to utilize as an "or equal" to that proposed in the 
Contract Documents. 
 
1.07 
SUBSTITUTIONS 
 
Any item the Contractor proposes to substitute for a specified item as an "or equal" must 
be made in writing, received and approved by the City or City’s Representative prior to the 
start of construction activities. Substitutions or deviations not approved by the City shall 
risk rejection and replacement at no additional cost to the City. 
 
1. For any proposed design change or deviation from these Technical Specifications, 
2. For anything in these Technical Specifications found to conflict with applicable codes 
and ordinances, 
3. For anything not understood by the Contractor. 
4. One (1) electronic copy of submittal(s) shall be provided to the City at least two (2) 
weeks before a determination is required.   
5. Submittals may be drawings, sketches, manufacturer's literature, catalog descriptions, 
or other descriptions in sufficient detail to allow a decision. The submittal shall indicate 
the amount to be added to or deducted from the bid price should the submittal be 
accepted. 
 
1.08 
QUALITY ASSURANCE/QUALITY CONTROL 
 
A. EXAMINATION: Each insert component part shall be examined by the Contractor for 
dimensional requirements, soundness, and workmanship in accordance with ASTM 
C478. 
 
B. COMPOSITION CONTROL: Manufacturer shall control and document the resin and 
aggregate content for each part of manhole fabrication. Documentation of the control 
checks shall be maintained by the manufacturer.  Proper content may be shown by 
resin and aggregate usage rate checks, in accordance with the manufacturer’s 
recommended material composition.

SECTION 13130 
POLYMER CONCRETE MANHOLE INSERT 
 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13130 - 6 
October 25, 2024 
C. TESTING RECORDS:  Records of all testing shall be kept and copies of test results 
shall be submitted in accordance with Paragraph 1.06 - SUBMITTALS. 
 
1.09 
INSPECTION POINTS 
 
Contractor shall keep the City or City’s Representative informed of milestone 
progress on each insert location for the following items: 
 
1. Start of excavation to remove the cone, chimney, frame and cover. 
2. Completion of removal of unsound material and manhole pressure wash cleaning. 
3. Completion of bench cleaning and preparation (if any). 
4. Completion of leveling/seal grout placement prior to insert placement. 
5. Prior to annular space grouting. 
6. Completion of bench protective coating. 
7. Completion of backfill placement. 
 
1.10 
WARRANTY 
 
The Contractor shall replace promptly and at no expense to the City, any materials which 
fails during the warranty period.  Warranty work shall include all ancillary items including, 
but not limited to permits, traffic control, and flow control required to compete the 
repair/replacement work.   Warranty and durations are described below: 
 
A. Project Warranty: The Contractor shall warrant all materials and workmanship 
performed under this contract for a period of one (1) year from the date of formal 
acceptance or as stated in the project Contract Documents whichever is longer. 
 
B. Materials Warranty: The manhole insert shall be free of defects that will affect the long 
term life and operation of the manhole.  The Contractor shall warrant in writing all 
materials provided under this contract for a period of five (5) years from the date of 
formal acceptance.   
 
C. Insert: Insert material(s) shall be tested for a design life of a minimum of fifty (50) 
years against deterioration from H2S corrosion and typical chemicals found in 
municipal sanitary sewage. 
 
 
PART 2 – PRODUCTS 
 
2.01 
POLYMER CONCRETE INSERT 
 
A structural insert shall be installed into the interior of existing deteriorated sanitary sewer 
manhole that meet or exceed the structural requirements as stated in ASTM C478 Standard 
Specification for Circular Precast Reinforced Concrete Manhole Sections.  Approved insert 
manufacturers:

SECTION 13130 
 
 
 
 
 
POLYMER CONCRETE MANHOLE INSERT 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13130 - 7 
October 25, 2024 
1) Armorock™ : Manufactured by Armorock, 3555 21st Street, Boulder City, NV 89005  
(702) 479-1772 
2) Rock HardTMscp Manufactured by P3 Polymers, 885 S. State Rd 57, P.O. Box 494, 
Washington, IN 47501 (812) 674-2051 
3) Approved Equal. 
 
2.02 
MATERIAL and DESIGN 
 
This section is to provide minimum design calculations and testing requirements for a 
barrel section and cone together.  There are some Technical Specifications that shall differ 
between the cone and the barrel that shall be described in separate sections. 
 
A. The design of the insert shall be prepared and professionally sealed by an Engineer 
licensed in the State of Arizona. The insert shall meet or exceed the requirements of 
buried manholes up to 40 feet deep without the use or reliance upon external or internal 
structural stiffeners. The design shall not allow infiltration of ground water. 
 
B. Insert shall be designed and tested to withstand AASHTO HS-20 loading with no 
structural strength derived from the existing manhole structure or installation of 
external or internal structural stiffeners. 
 
C. Material of the insert shall be consistent throughout the structure consisting of resin 
and aggregate material, including reinforcement that is inert to corrosion from sewer 
gasses per ASTM D6783 - Standard Specification for Polymer Concrete Pipe (material 
mix design). Epoxy shall be 100% solids, solvent free, low odor emitting, 
environmentally friendly, and impervious to chemicals. Manufacture shall determine 
the need for and type of reinforcement including that for safety and lifting 
requirements. Reinforcement, if determined necessary, shall be made of non-ferrous 
material. 
 
D. The resins used shall be unsaturated, supplier certified commercial grade resins.  
Mixing lots of resin from different manufacturers or “odd-lotting” of resins shall not 
be permitted.  Quality-assurance records on the resin shall be maintained. Interior 
surface shall be light in color in order to facilitate ease of inspection from ground 
surface. 
 
E. Load Rating: The complete manhole shall have a minimum dynamic load rating of 
16,000 pounds. To establish this rating the complete manhole shall not leak, crack, or 
suffer other damage when load tested to 40,000 pounds. 
 
F. The use of a multi-piece insert must be approved by the City prior to ordering.  If 
allowed, joints shall be of bell and spigot configuration. Joints every 5 feet shall be 
sealed with a material consistent with the chemical resistance of the manhole sections 
per ASTM C990 - Standard Specification for Joints for Concrete Pipe, Manholes, and 
Precast Box Sections Using Preformed Flexible Joint Sealants and shall not affect the 
warranty.  All joints shall be water proofed and shall not allow infiltration.

SECTION 13130 
POLYMER CONCRETE MANHOLE INSERT 
 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13130 - 8 
October 25, 2024 
2.03 
THIRD PARTY TESTING 
 
The Manufacturer shall have testing of the manhole insert materials performed by an 
independent test laboratory. Where there are conflicts between the requirements of the 
ASTM and this Technical Specification, this Technical Specification shall supersede. The 
Manufacturer shall submit the results of third-party testing, as specified below, and in 
accordance with Technical Specification Section 01300 - SUBMITTALS. 
1. LOAD RATING: The insert shall have an AASHTO HS-20 load rating. 
 
2. CHEMICAL RESISTANCE TESTING: The following chemical resistance tests 
shall be performed in accordance with ASTM G20 - Standard Test Method for 
Chemical Resistance of Pipeline Coatings.  After exposure to the solutions, 
specimens shall exhibit zero (0) weight loss, spalling, cracking or blistering. Any 
changes to appearance such as color and texture shall be noted. 
 
2.04 
BARREL DESIGN SPECIFICATIONS: 
 
The barrel section of the polymer concrete insert shall meet general design specifications 
as noted in Paragraph 2.02 - Material and Design. 
 
Dimensions:  Barrel sections of the manhole insert shall be designed to maximize the 
diameter of the existing manhole interior. 
 
2.05 
CONE DESIGN SPECIFICATIONS: 
 
The cone section of the insert shall meet general design specifications as noted in Paragraph 
2.02 - Material and Design.   Cones shall be concentric for all manhole diameters.  The 
cone section must provide a bearing flat shoulder surface on which a chimney consisting 
of adjustment grade rings may be supported. 
 
Dimensions:  Cone sections of the manhole insert shall be a designed according to MAG 
Standard Detail 520.   
 
2.06 
CHIMNEY CONSTRUCTION:   
 
The chimney shall be constructed on the flat shoulder bearing surface of the cone using 
grade adjustment rings. The chimney shall be built to support the cast iron frame and 
cover adjusted to final surrounding grade.  Height of the chimney shall be according to 
MAG Standard Detail 420-1.   
 
2.07 
STANDARD CITY CAST IRON FRAME AND COVER: 
 
The cast iron frame and cover shall be supported by the chimney and shall not be installed 
directly on the cone.  Contractor shall inform City if existing frame and/or cover is worn 
or damaged and shall obtain approval prior to replacing frame and cover.

SECTION 13130 
 
 
 
 
 
POLYMER CONCRETE MANHOLE INSERT 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13130 - 9 
October 25, 2024 
2.08 
GROUTS:  
 
 
All grout or concrete applied to the manhole interior shall be acid resistant quick-setting 
non-shrink epoxy grouts, approved by the insert manufacturer and compatible with the 
polymer protective coating material and tested in accordance with ASTM C579 - Standard 
Test Methods for Compressive Strength of Chemical-Resistant Mortars, Grouts, 
Monolithic Surfacings, and Polymer Concretes. 
 
2.09 
MARKING AND IDENTIFICATION: 
 
A. Manhole insert shall be marked on both the interior and exterior with the following 
information: 
 
1. Manufacturer’s Company Name identification.  
2. Date of Manufacture.               
3. Manhole wall thickness. 
4. Installation assist marks. 
 
2.10 
DELIVERY, STORAGE AND HANDLING 
 
Contractor shall be responsible for any damage resulting from improper storage and/or 
handing.  Damaged materials shall be replaced at no additional cost to the City. 
 
A. Materials shall be handled in accordance with MAG 106. 
 
B. Store all products according to manufacturer’s recommendations until installation.  Protect 
from construction traffic and damage. 
 
C. During the loading, unloading, and storage, care should be taken to ensure that the manhole 
insert is not dropped or otherwise damaged. 
 
D. The manhole insert should be stored on a smooth surface free of sharp objects.  
 
E. Nylon or fabric slings should be used in conjunction with a spreader bar to lift or move the 
manhole.  
 
F.  UNDER NO CIRCUMSTANCES SHOULD CABLES OR CHAINS BE USED. 
 
G. If the manhole insert is stored horizontally, the manhole insert should be placed in such 
a way as to avoid damage and braced. 
 
PART 3 – EXECUTION 
 
3.01 
PROTECTION OF SITE:  
 
Except as otherwise provided herein, the Contractor shall protect from damage all fences, 
structures, sidewalks, utilities, trees, shrubbery, lawns, etc., during the progress of this

SECTION 13130 
POLYMER CONCRETE MANHOLE INSERT 
 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13130 - 10 
October 25, 2024 
work. All debris and unused materials shall be removed immediately upon completion of 
the work. The site shall be restored as nearly as possible to its original condition, including 
the replacement, at the Contractor's sole expense, of any facility or landscaping which has 
been destroyed or damaged beyond restoration. 
 
3.02 
UTILITIES:   
  
Unless otherwise indicated in Technical Specification Section 01550 – CONTRACTOR’S 
UTILITIES, the Contractor shall arrange for and provide any required utilities at his sole 
cost and expense.  This includes but is not limited to water for compaction or testing, power 
for operating any equipment along with personnel sanitation facilities. 
 
3.03 
CLEANING AND PREPARATION 
 
A. The Contractor shall be responsible for all existing manhole cleaning and surface 
preparation according to Technical Specification Section 02760 – SEWER AND 
SEWER STRUCTURE CLEANING.  The Contractor shall notify the City of any 
irregularity, which may interfere with the proper installation of the manhole insert.   
 
3.04 
COMPOSITE INSERT 
 
A. The manhole insert installed shall bond to or fit sufficiently tight to the existing 
manhole so as to eliminate water leakage into the manhole or allow water or vapors to 
leak out of the manhole through pinholes or other defects. If infiltration or exfiltration 
leakage occurs, the Contractor shall seal these areas to stop all leakage using a material 
compatible with the insert material installed and as specified by the manufacturer. If 
leakage continues to occur, the Contractor shall remove and replace the insert at no 
additional cost to the City. All repair materials shall have the same estimated life 
expectancy as the insert installed. Final approval of the installation will be based on 
meeting the acceptance test requirements for each insert installed. 
 
B. All existing manhole interior piping shall be removed prior to insert installation and 
bench protective coating application.  Interior piping shall be reinstalled per project 
Design Drawings or as required by these contract Technical Specifications. 
 
C. Flow from existing active service connections entering the manhole shall be plugged 
or diverted through by-passed pumping operation, if the flow affects proper installation. 
 
D. Testing and warranty inspections shall be witnessed by the City or the City’s 
Representative. Any defects found shall be repaired by the Contractor. 
 
E. Compensation for all work required for providing test samples and independent 
laboratory testing shall be included in the in the Bid Proposal cost of the item contained.

SECTION 13130 
 
 
 
 
 
POLYMER CONCRETE MANHOLE INSERT 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13130 - 11 
October 25, 2024 
3.05 
INSTALLATION: 
 
A. The Contractor shall install the manhole insert in accordance to approved 
manufacturer’s techniques. 
 
B. The insert shall be centered inside the existing manhole or as otherwise approved. 
 
C. Contractor shall use an acid resistant polymer grout around circumference of the bench 
prior to lowering insert into position.  The insert base section shall be installed into 
fresh grout to evenly support the weight of the insert and establish a gas 
tight seal.  The polymer grout shall be compatible with insert material and approved 
for use by the insert manufacturer and compatible with the bench protective coating 
material. The bottom seal shall also prevent loss of annular space grout material 
installed between the outside of the insert and the interior wall of the existing 
manhole. 
 
D. After placement of insert, Contractor shall complete installation of the 
protective coating of the manhole bench. As a minimum, Contractor shall raise 
manhole bench to the same elevation as the crown of the pipe as directed or shown in 
project Design Drawings. Manhole bench shall be sloped a minimum ¼-inch per foot 
to the channel. Minimum repair grout thickness shall be ¾-inch.   
 
E. Where insert is installed using multiple barrel sections in lieu of a single piece barrel, 
apply a non-shrink epoxy putty or butyl mastic sealant approved by the manufacturer, 
to the joint of each barrel or cone section. Wipe excess material from the inside seam 
to provide a smooth finish. 
 
F. Replace all existing manhole connections with the same inside diameter pipe. Sewer 
main and lateral connections in the existing manholes shall be extended through the 
insert with sealed watertight connections. Seal all penetrations through the insert with 
an acid resistant non-shrink polymer grout. Installation shall be in accordance with 
Manufacturer's written instructions utilizing installation equipment approved for use 
by the Manufacturer. 
 
G. Fill the annular space between the insert and the existing manhole wall with a Portland 
cement and sand grout mixture or a hydrophilic grout. The grout backfill shall be 
placed in a maximum 12-inch lifts or as approved by the insert manufacturer 
structural engineer.  Manufacturer’s approved maximum lift shall be submitted 
to the City per Technical Specification Section 01300 – SUBMITTALS.  Grout 
shall cure to provide a minimum compressive strength of 100 psi. The grout shall be 
consolidated without damage to the insert or connecting pipes. 
 
H. Install the cone section (if applicable). after grouting the top bell section

SECTION 13130 
POLYMER CONCRETE MANHOLE INSERT 
 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13130 - 12 
October 25, 2024 
3.06 
CONE BACKFILL MATERIAL 
 
Contractor shall backfill around the manhole cone and chimney with sand, crushed stone, 
pea gravel or aggregate base course (ABC) per MAG Section 701, unless directed 
otherwise and approved by the Engineer.  The material chosen shall be free of large lumps 
or clods, which shall not readily break down under compaction. 
 
Backfill shall be placed in layers of not more than twelve (12) loose measure inches and 
mechanically tamped to 95 percent Standard Proctor Density, unless otherwise approved 
by the City or City’s Representative. Flooding or water jet compaction shall not be 
permitted. Backfill shall be placed in such a manner as to prevent any wedging action 
against the manhole structure. 
 
Contractor shall install grade rings and adjust height to surrounding elevation and slope.  
Pour a concrete collar around the manhole ring and cover after setting the proper height. 
 
All damaged pavement shall be removed and replaced in kind with new pavement. In 
landscaped areas the surface shall be restored in kind. Any damaged irrigation facilities 
shall be repaired. 
 
3.07 
GROUTING: 
 
Annular space grouting shall be done in accordance with manufacturer's requirements and 
as described in "Installation" procedures, and should meet the following minimum 
requirements: 
 
Test Type 
Results 
Test Method 
Density 
4 lbs. 
ASTM D-1622 
Water Absorption 
(volume confined) 
<1% 
ASTM D-2842 
Shear Strength 
17.10 PSI 
ASTM C-273 
Tensile Strength 
29.30 PSI 
ASTM D-1623 
Elongation 
44% 
ASTM D-1623 
Viscosity 
@ 500 CPS 
 
Chemical Emersion 
Testing 
Excellent results 
ASTM G20-88 
 
The system should also use an accelerator to quicken the reaction time (30 minutes) where 
needed.  All physical properties shall be expected to be detailed in submittals showing that 
they meet these Technical Specifications.

SECTION 13130 
 
 
 
 
 
POLYMER CONCRETE MANHOLE INSERT 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13130 - 13 
October 25, 2024 
3.08 
MANHOLE BENCH and CHANNEL RESTORATION 
 
Manhole bench and channel shall be cleaned and coated as follows: 
 
A. The manhole bench shall be grit blasted down to solid/sound substrate, followed by 
high pressure water blasting to remove any lose debris and adjust pH acidity to Neutral. 
Debris shields shall be used to prevent any dislodged material from entering the sewer 
system as per Technical Specification Section 02760 – SEWER PIPE AND SEWER 
STRUCTURE CLEANING. 
 
B. Manhole bench shall be rebuilt with non-shrink acid resistant grout as necessary to 
restore original dimensions in preparation for structural foundation of insert. 
 
C. A polymer grout should then be applied to the circumference of the bench as necessary 
to manhole insert manufacturer’s recommended dimensions for structural foundation 
of insert to create a level bearing area and seal of the first insert barrel section 
installation. 
 
D. Manhole channel shall be rebuilt with acid resistant polymer coating, as necessary, to 
dimensions consistent with existing incoming and outgoing pipe grades 
 
E. After the manhole insert has been installed and base rebuilt, the entire bench and 
channel shall be coated with a protective polymer concrete coating to ensure the 
exposed manhole base/throat/channel have the similar acid resistance as the remainder 
of the rehabilitated manhole. 
 
3.09 
LATERALS AND CONNECTIONS: 
 
Sewer main and lateral connections present in the existing manholes shall be extended 
through the insert wall with sealed watertight connections. Existing pipe diameters shall be 
maintained.  Penetration installation shall be in accordance with insert manufacturer's 
written instructions utilizing installation equipment approved for use by the manufacturer.  
Penetrations cut through the insert wall shall be made with tools capable of cutting circular 
shapes.  Use of a carbide blade chop saw or other tools that cut a straight edge shaped is 
strictly prohibited. Penetrations through the insert shall be sealed with an approved non 
shrink, acid resistant polymer grout material approved by the insert manufacture.  
 
3.10 
PROTECTIVE BENCH COATING TESTING 
 
Contractor shall perform spark test and pull test on applied coatings per Technical 
Specification Section 09710 – CONCRETE AND MASONRY COATINGS.   
 
3.11 
ACCEPTANCE 
 
As a condition precedent to Final Acceptance of the work, Contractor shall certify the 
proper installation and testing of material provided under this section. Certification shall

SECTION 13130 
POLYMER CONCRETE MANHOLE INSERT 
 
 
 
 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13130 - 14 
October 25, 2024 
warrant that materials and installation are free of defects and/or workmanship and suitable 
for trouble-free operation under the conditions set forth in these Technical Specifications. 
 
3.12 
RECORD DRAWINGS:  
 
Prior to final payment, the Contractor shall provide a complete set of redlined Design 
Drawings showing the project as constructed including manhole insert depth, diameter, 
along with location and diameter of any insert penetrations and interior piping 
configurations.  A spreadsheet and/or Design Drawings shall include all information 
required elsewhere in these Technical Specifications as well as any changes. 
 
 
 
 
 
 
 
 
 
** END OF SECTION **

SECTION 13133 
POLYPROPYLENE GRADE  
                                                                  ADJUSTING RINGS 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13133 - 1 
October 25, 2024 
PART 1 - GENERAL 
 
1.01 
SCOPE 
 
This Technical Specification defines the materials required for the adjustment of grade of 
manhole structures to surrounding area finish final grade elevation or as shown on the 
project Design Drawings. 
 
1.02 
WORK REQUIRED 
 
Grade adjustment rings meeting the requirements of this section shall be used to adjust and 
support the frame and cover to the final elevation on all project manholes. 
 
1.03 
SYSTEM DESCRIPTION 
 
A. Design Requirements – The grade adjustment rings shall be designed to allow final 
adjustment of the frame and cover to the surrounding grade.  The rings shall also be 
designed to accommodate flat or sloping surfaces to within ¼-inch (one quarter inch) 
of the final elevation.  The grade adjustment system shall have a minimum 50 (fifty) 
year design life. 
 
B. Performance Requirements – The grade adjustment rings shall be capable of supporting 
the minimum requirements of AASHTO H-20 and HS-20, be UV stable and be resistant 
to chemicals and corrosion commonly associated with the sanitary sewer environments. 
 
1.04 
SUBMITTALS 
 
The following submittal shall be provided in accordance with Technical Specification 
Section 01300 – SUBMITTALS: 
 
1. Test Report:  A test report from an approved third-party testing agency showing the 
grade adjustment rings meets the minimum requirements of ASSHTO H-20 and HS-
20. 
 
2. Certification: The manufacturer of the grade adjustment rings shall provide 
certification to the City stating that the product meets the design life and material 
requirements of this specification. 
 
1.05 
REFERENCES  
  
 
This Technical Specification Section contains references to the following documents.  
They are a part of this section as specified and modified.  In case of conflict between the 
requirements of this section and those of the listed documents, the requirements of this 
section shall prevail.

SECTION 13133 
POLYPROPYLENE  
GRADE ADJUSTING RINGS 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13133 - 2 
October 25, 2024 
AASHTO Loading  
American Association of State Highway and 
Transportation Officials. 
 
ASTM D3575 
 
Standard Test Methods for Flexible Cellular 
Materials Made From Olefin Polymers. 
 
ASTM C920 
Standard Specification for Elastomeric Joint 
Sealants 
 
PART 2 – PRODUCTS 
 
 
2.01 
MANHOLE GRADE ADJUSTMENT RING 
 
Manhole grade adjustment rings shall consist of a variety of heights (thicknesses), 
diameters and shapes all conforming to the following requirements: 
 
A. The grade adjustment rings shall be manufactured from expanded polypropylene 
(EPP), black, meeting ASTM D3575.  The rings shall be manufactured using a high 
compression molding process to produce a finished density of a minimum of 120 g/l 
((7.5 pcf). 
 
B. “Grade” adjustment rings may contain either an upper and lower keyway (tongue and 
groove) for vertical alignment and/or an adhesive trench on the underside with a flat 
top. 
 
C. “Finish” or “Flat” rings may either have a keyway (groove) on the underside for vertical 
alignment and/or an adhesive trench with a flat upper surface.  These rings shall be 
available in heights (thicknesses) which will allow final adjustment of the frame and 
cover or grate to within ¼” (one quarter inch) of the specified final elevation. 
 
“Finish” rings may also have a keyway on the upper surface of the inner diameter to 
facilitate installation of an “Angle” ring. 
 
D. “Angle” rings may either have an upper and lower keyway (tongue and groove) for 
vertical alignment and/or an adhesive trench on the underside.  When required, the 
“Angle” ring or rings shall allow final adjustment of the frame and cover or grate to 
within ¼” (one quarter inch) of the specified final elevation. 
 
2.02 
APPROVED MANUFACTURER  
 
1. Cretex Specialty Products Inc., N16 W23390 Stone Ridge Dr A, Waukesha, WI 53186 
PRO-RING™  
2. Approved equal

SECTION 13133 
 
POLYPROPYLENE  
 
 
GRADE ADJUSTING RINGS 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble  
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13133 - 3 
October 25, 2024 
2.03 
EQUIPMENT 
 
The contractor shall have the required tools and equipment necessary to facilitate proper 
installation of the grade adjustment rings. 
 
2.04 
ADHESIVE/SEALANT 
 
A. Any adhesive or sealant used for watertight installation of the manhole grade 
adjustment rings shall be M-1 Structural Adhesive/Sealant or equal meeting ASTM C-
920, Type S, Grade NS, Class 25, Uses NT, T, M, G, A and O  
 
B. Other adhesives or sealants may only be used with grade ring manufacturer written 
authorization and City approval. 
 
 
PART 3 - EXECUTION 
 
3.01 
INSTALLATION 
A. Installation and surface preparation shall be in accordance with the grade ring 
manufacturer’s instructions. 
 
B. The joint between the first grade ring and top of the manhole shall be sealed using an 
adhesive/sealant meeting the requirements of paragraph 2.04. 
 
C. The remaining joints between all manhole adjustment rings and the frame and cover 
or grate shall be sealed using an adhesive/sealant meeting the requirements of Section 
2.04. 
 
D. No other materials shall be used in the construction of the grade adjustment area 
beyond those specified above.  Prohibited materials include, but are not limited to 
wood or wood shims of any kind, concrete, brick, block, stones, etc. 
 
 
 
 
 
 
** END OF SECTION **

SECTION 13133 
POLYPROPYLENE  
GRADE ADJUSTING RINGS 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
Contract No.: 202104.01 
13133 - 4 
October 25, 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double sided printing ]

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
EXHIBIT F 
Statement of All Clarifications and Assumptions (if any) 
 
(2 pages - To be Incorporated by Amendment) 
 
SEE ATTACHED

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
T H I S P A G E I S B L A N K

ROC089744   |   BFCONTRACTING.COM   |   11011 North 23rd Avenue   |   Phoenix, AZ 85029 
P: 623.582.1170   |   F: 623.582.3761 
 
Exhibit F: Clarification & Assumptions 
ARROWHEAD PHASE 1.1 
COG PROJECT NUMBER: 202104 
GMP-001 
 
 
1. Mobilization/Demobilization for this GMP-001 is a onetime round trip for personnel, equipment, 
and supplies. Project delays that result in demobilization of personnel and/or equipment are not 
included, and any additional costs incurred are a change in scope.   
2. No temporary signals are included in GMP and if required they will be reimbursed through Project 
Contingency.  
3. Any costs associated with Permits, Paving Permit/Fees, Waterline and Trench Permit/Fees and 
Haul Permit/Fees are not included in the GMP, except for the dust control permit fee. 
4. Dust Control permit is included in the mobilization item of the GMP. 
5. Costs associated with City and/or ADOT permit and plan review fees, Quality Assurance 
(QA) (i.e. City/ADOT inspection and testing) costs, impact fees, and utility company fees, 
water meters/meter installations except for construction water, and/or any other fees not 
specifically identified within this GMP, are not anticipated and, if required, shall be 
reimbursed through Project Contingency.  
6. This GMP does not include costs for the remediation of hazardous waste materials. 
7. Traffic Control Allowance includes anticipated costs for traffic control labor and equipment 
for setup and teardown, barricade device rental, sandbags, and flags with dowels. Traffic 
control item will be cost reimbursable with appropriate backup documentation plus 
applicable mark-ups, insurance, bond, and taxes per the contract.  
8. Excludes any costs associated with blasting or hydraulic breakers of any kind. 
9. Project schedule is estimated at a 3 month duration, thus Indirect/General Conditions costs were 
estimated at 3 months for this GMP and will be billed monthly. 
10. Includes a Project Contingency to cover material escalation costs related to aggregates,  
asphalt, pipeline, CIPP liner materials as compared to the vendor/supplier quote. This will 
be cost reimbursable with appropriate back-up documentation showing the cost impacts on 
the project from GMP to construction plus applicable mark-ups, insurance, bond, and taxes 
per the contract.  
11. Excludes costs for repair of pre-existing damage to any private and public roadways used to 
access this project. If required, costs to be reimbursed from Project Contingency. 
12. GMP assumes access can be granted to CMAR for suitable staging and installation of the sewer 
replacements and rehabilitation efforts at the various sections of right of way (ROW). 
13. GMP excludes costs for utility relocation. If any utility relocations are required, CMAR shall be 
reimbursed through Project Contingency. 
14. Costs for Private Irrigation or any other unmarked utility damaged and/or relocated as part of this 
project to be compensated out of Project Contingency line items. 
15. CMAR expectation is to close sidewalks and bike paths in the construction zone and route 
pedestrians to the nearest ADA compliant crossing and detour pedestrians to the opposite of 
the roadway around the work zone.  
Date: 1/28/2025

ROC089744   |   BFCONTRACTING.COM   |   11011 North 23rd Avenue   |   Phoenix, AZ 85029 
P: 623.582.1170   |   F: 623.582.3761 
 
 
 
16. Survey/GIS Allowance includes costs to record asset data directly associated with the 
rehabilitation scope of work and incorporating that data into the GIS system.  
17. Off-Duty Officer Allowance will be utilized for Off-Duty Officers as designated by the City 
of Glendale traffic department and will be cost reimbursable with appropriate backup plus 
applicable mark-up, insurance, bond, and taxes.  
18. Allowances are only anticipated/estimated costs and overruns of the Allowances will be 
compensated through Project Contingency.  
19. All specialty asphalt, concrete, and/or paver unless expressed explicitly on the plans would 
be compensated through Project Contingency. 
20. Unit Price Contract Administration:  This GMP will be administered as a Measured 
Quantity/Unit Price, Guaranteed Not‐to‐Exceed Contract. The Schedules of Values is 
defined by the individual work/pay items plus fee structure, and markups. Final contract 
price/payout will be based on field measured, final completed quantities at the approved unit 
prices, approved allowance and/or contingency utilization, and approved change orders. It 
is understood that these City approved prices including mark‐ups are the “Cost of the Work”.  
The mark‐up structure on the Schedule of Values will apply to Change Orders and/or Extra 
Work, allowances, and contingencies. Pay Item under‐runs and/or unused items shall fall to 
Project contingency for the duration of the project. Quantity over‐runs shall be paid at the 
unit price established in the Schedule of Values for the pay item and shall be paid from 
Contingency or Change Orders. 
21. Any additional point repairs or SLC seals/tops hats not identified on the plans that are 
deemed required shall be reimbursed via Project Contingency. 
22. GMP assumes that the 42” and 21” sewer will be bypassed during project across the SR101 
at Union Hills Road into the Arrowhead plant to accommodate the work.  
23. B&F crews will need 24-hour access to the Arrowhead Plant during the project to 
accommodate the work.  
24. CMAR GMP is based on full 8-hour street restrictions allowing 8 full hours of work to be 
performed on site by CMAR crews.  
25. CMAR GMP has basic best practices for Odor control which consists of tarping and covering the 
suction and discharge points. Any additional odor control required via chemical injection or 
mobile odor scrubbers will be compensated through the Odor control allowance once approved 
by the City or City designated representative.  
26. Allowance for additional rehabilitation is to be utilized for any additional work that was not 
identified on the plan and/or additional bypass time as designated by the City or City designated 
representative.  
27. Allowance for landscaping is to restore any landscaping post rehabilitation of the sewer system.  
28. Asphalt paving for the ADOT ROW assumes a 50’ section will be replaced based on previous 
project.

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
EXHIBIT G 
Schedule of Major Milestones 
 
(1 page - To be Incorporated by Amendment) 
 
SEE ATTACHED

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
T H I S P A G E I S B L A N K

ID
Task 
Mode
Task Name
Duration
1
Arrowhead Sewer Lines Phase 1.1
100 days
2
NTP
0 days
3
Bypass Setup
25 days
4
Mobilization
8 days
5
SWPPP Setup
2 days
6
Pothole
5 days
7
Sawcut
3 days
8
Fusion Pipe
8 days
9
Trenching
5 days
10
Dig Suction Pit
2 days
11
Dig Discharge Pit
2 days
12
Temp Pavement
3 days
13
Setup Pump Station
3 days
14
Test Pipe
2 days
15
Set Plugs
2 days
16
Start Bypass
0 days
17
Rehabilitation Under Bypass
25 days
18
Installation of Manhole
7 days
19
Dewatering Pipe
2 days
20
Clean & CCTV Pipe
4 days
21
Remove Inversion Cones and Widen Benches
3 days
22
CIPP Line 42-inch
8 days
23
Post Pano Video
4 days
24
Rehabilitate Manhole
9 days
25
Test New Manhole
1 day
26
Remove Plugs
1 day
27
Reinstate Inversion Manholes
4 days
28
Remove Bypass
52 days
29
Complete Discharge Manhole Reinstate
4 days
30
Remove Pumps
4 days
31
Remove Pipes
8 days
32
Demo PCCP / Concrete
4 days
33
Pour Concrete Curb Back
3 days
34
Dowell Rebar for PCCP
3 days
35
Northbound Replace PCCP
3 days
36
Southbound Replace PCCP
3 days
37
Temp Striping
1 day
38
Landscape Restoration
1 day
39
Final Striping
1 day
40
Punchlist 
0 days
41
Final Punchlist
0 days
NTP
Mobilization
SWPPP Setup
Pothole
Sawcut
Fusion Pipe
Trenching
Dig Suction Pit
Dig Discharge Pit
Temp Pavement
Setup Pump Station
Test Pipe
Set Plugs
Start Bypass
Installation of Manhole
Dewatering Pipe
Clean & CCTV Pipe
Remove Inversion Cones and Widen Benches
CIPP Line 42-inch
Post Pano Video
Rehabilitate Manhole
Test New Manhole
Remove Plugs
Reinstate Inversion Manholes
Complete Discharge Manhole Reinstate
Remove Pumps
Remove Pipes
Demo PCCP / Concrete
Pour Concrete Curb Back
Dowell Rebar for PCCP
Northbound Replace PCCP
Southbound Replace PCCP
Temp Striping
Landscape Restoration
Final Striping
Punchlist 
Final Punchlist
8
11
14
17
20
23
26
29
1
4
7
10
13
16
19
22
25
28
1
4
7
10
13
16
19
22
25
28
31
3
6
9
12
15
18
21
24
27
30
3
6
9
12
15
18
21
24
27
30
2
5
8
11
14
17
20
2
5
April 2025
May 2025
June 2025
July 2025
August 2025
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Arrowhead Sewer Line Phase 1.1 CMAR
Page 1
Date: Tue 1/28/25

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
EXHIBIT H 
Dispute Resolution Procedures 
 
1. 
Disputes. 
1.1 
Each Dispute arising out of or related to this Agreement (including Disputes 
regarding any alleged breaches of this Agreement) shall be initiated and decided 
under the provisions of this Exhibit. 
1.2 
CMAR and City shall each designate in writing to the other party, from time to 
time, a member of senior management who shall be authorized to attempt to 
expeditiously resolve any Dispute relating to the subject matter of this Agreement 
in an equitable manner. 
1.3 
A party shall initiate a Dispute by delivery of written notice to the members of 
management designated by the respective parties under Section 1.2 of this Exhibit.   
1.4 
The parties must:   
(A) 
Attempt to resolve all Disputes promptly, equitably and in a good faith 
manner; and  
(B) 
Provide each other with reasonable access during normal business hours to 
any and all non-privileged records, information and data pertaining to any 
such Dispute. 
1.5 
With respect to matters concerning modification of the GMP or any schedule, 
CMAR must first follow the provisions of any Claim procedure established by the 
Design-Build Agreement before seeking relief under these Procedures. 
2. 
Emergency Arbitration. 
2.1 
If the parties are unable to accomplish resolution of a Dispute, the expedited 
resolution of which either party considers necessary to prevent or mitigate a 
material delay to the critical path of the Services (a "Time Sensitive Dispute") 
within two days after the Time Sensitive Dispute has been initiated by a party, either 
party may thereafter seek emergency relief before an emergency arbitrator (the 
"Emergency Arbitrator") appointed as follows:   
(A) 
The parties will exercise best efforts to pre-select an Emergency Arbitrator 
within 20 days after entering into this Agreement;  
(B) 
If the Emergency Arbitrator has not been selected at the time a party delivers 
Notice of a Time Sensitive Dispute, the parties will each select a 
representative within one day after the Notice is delivered and the two 
representatives will then select the Emergency Arbitrator by the third day 
following delivery of the Notice. 
(C) 
The Emergency Arbitrator shall be an attorney with at least ten (10) years’ 
experience with commercial construction legal matters in Maricopa County, 
Arizona, be independent, impartial, and not have engaged in any business 
for or adverse to either party for at least ten (10) years.   
2.2 
The Emergency Arbitrator will conduct a hearing and render a written 
determination on the Dispute to both parties within five business days of the matter 
being referred to him or her, all in accordance with Rules O-1 to O-8 of the

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
American Arbitration Association ("AAA") Commercial Rules-Optional Rules for 
Emergency Protection Commercial Rules ("AAA Emergency Rules"). 
2.3 
Although the hearing will be conducted using AAA rules, unless both parties agree 
otherwise, this dispute process will not be administered by the AAA but will be 
conducted by the parties in accordance with these procedures.  
2.4 
If, however, an Emergency Arbitrator has not selected within three days after 
delivery of the Notice, either party may upon three days additional notice, thereafter 
seek emergency relief before the AAA, in accordance with the AAA Emergency 
Rules, provided that the Emergency Arbitrator meets the qualifications set forth 
above.   
2.5 
All proceedings to arbitrate Time Sensitive Disputes shall be conducted in 
Glendale, Arizona.   
2.6 
Presentation, request for determination (i.e., a party’s prayer), and the Emergency 
Arbitrators decision will adhere to the procedures required in Section 3.6 of this 
Exhibit. 
2.7 
The finding of the Emergency Arbitrator with respect to any Time Sensitive 
Dispute will be binding upon the parties on an interim basis during progress of the 
Services, subject to review de novo by arbitration after the Project Substantial 
Completion Date. 
2.8 
The time and extent of discovery will be as determined by the Emergency 
Arbitrator. 
(A) 
 Discovery orders of the Emergency Arbitrator will consider the time 
sensitivity of the matter and the parties desire to resolve the issue in the 
most time and costs efficient manner; 
(B) 
The parties are obligated to cooperate fully and completely in the provision 
of documents and other information, including joint interviews of 
individuals with knowledge such that the matter moves toward resolution 
in the most time and costs efficient manner and the Emergency Arbitrator 
is empowered to fashion any equitable penalty against a party that fail to 
meet this obligation. 
3. 
Non-Emergency Arbitration. 
3.1 
Except as provided in Section 5 of this Exhibit, any Dispute that is either a non-
emergency Dispute that has not been resolved by negotiation, or a de novo review 
of an AAA emergency arbitration will be decided by binding arbitration by a panel 
of three arbitrators in accordance with, but not necessarily administered by, the 
Construction Industry Rules of the AAA.   
(A) 
The parties shall each select an arbitrator within 15 days after notice that a 
party desires to resolve a dispute by arbitration.   
(B) 
The two arbitrators shall then each select a third arbitrator.  If an arbitrator 
is not selected within any such 15 day period, then the arbitrator shall be 
appointed by the AAA.   
3.2 
The arbitrator(s) shall meet the qualifications of Emergency Arbitrators as provided 
in Section 2 of this Exhibit.

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
3.3 
The arbitrators do not have the authority to consider or award punitive damages as 
part of the arbitrators' award.   
3.4 
In connection with such arbitration, each party shall be entitled to conduct up to 
five depositions, and, no less than 90 days prior to the date of the arbitration hearing, 
each party shall deliver to the other party copies of all documents in the delivering 
party's possession that are relevant to the dispute.   
3.5 
The arbitration hearing shall be held within 150 days of the appointment of the 
arbitrators. 
3.6 
At the arbitration hearing, each party will argue its position to the arbitrators in 
support of one proposed resolution to the dispute (a “Proposed Resolution”).   
(A) 
Each party’s Proposed Resolution must be fully dispositive of the dispute.   
(B) 
The arbitrators must select one Proposed Resolution by majority consent 
and are not free to fashion any alternative resolutions. 
(C) 
The parties must submit their proposed resolution of the matter to the 
arbitrators and the other party 15 days prior to the date set for 
commencement of the arbitration proceeding. 
(D) 
The decision of the arbitrators will be forwarded to the parties within 15 
days after the conclusion of the arbitration hearing. 
(E) 
The decision of the arbitration panel is final and binding on the parties and 
may be entered in any court of competent jurisdiction for the purpose of 
securing an enforceable judgment.   
(F) 
All costs and expenses associated with the arbitration, including the 
reasonable legal fees and costs incurred by the prevailing party, must be 
paid by the party whose position was not selected by the arbitrators. 
4. 
Continuing Work.  Unless otherwise agreed to in writing, CMAR must continue to 
perform and maintain progress of the Work during any Dispute Resolution or arbitration 
proceedings, and City will continue to make payment to CMAR in accordance with the 
Agreement. 
5. 
Exceptions. 
5.1 
Neither City nor CMAR are required to arbitrate any third-party claim, cross-claim, 
counter claim, or other claim or defenses in any action that is commenced by a 
third-party who is not obligated by contract to arbitrate disputes with City and 
CMAR. 
5.2 
City or CMAR may commence and prosecute a civil action to contest a lien or stop 
notice, or enforce any lien or stop notice (but only to the extent the lien or stop 
notice the party seeks to enforce is enforceable under Arizona law), including, 
without limitation, an action under A.R.S. § 33-420, without the necessity of 
initiating or exhausting the procedures of this Exhibit. 
5.3 
This Exhibit does not apply to, and may not be construed to require arbitration of, 
any claims, actions or other process undertaken, filed, or issued by the City of 
Glendale Building Safety Department, Code Compliance Department, Police 
Department, Fire Department, or any other agency of City acting in its

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
governmental permitting, for the benefit of public health, safety, and welfare, or 
other regulatory capacity. 
5.4 
In connection with any arbitration, the arbitrators do not have the authority to, and 
may not enforce, any provision of the Federal or Arizona Rules of Civil Procedure.