Update #31 Downtown Campus Reinvestment Project City Council Workshop March 25, 2025 Presenter: Eddie Garcia 2 Site Activities 3 Site Activities 4 Site Activities 5 Site Activities 6 Caissons 7 Exterior Envelope 8 Interior Framing 9 Interior Framing 10 Interior Framing – Council Chambers 11 Council Chambers - AHUs 12 Council Chambers - Exterior 13 Council Chambers-Roof 14 In Progress Scope Schedule Budget • Masonry, elevator steel, interior stairs, roofing, plumbing rough & mechanical rough, interior framing level 2 • Amphitheater Link and Canopy Foundations • Council Chamber Expansion Foundations • Call to Artists RFP & Amphitheater Technology RFP Next Month • Glazing Anchors and South Elevation Glazing • Council Chambers Roof Sheathing replacement • Curb and Gutter/Drive on Glenn Drive • More Masonry 15 Thank You