PowerPoint Presentation (Added 4/18/2025)*
Extracted text (via pymupdf)
911 characters
Update #32 Downtown Campus Reinvestment Project City Council Workshop April 22, 2025 Presenter: Eddie Garcia 2 Site Activities 3 Site Activities 4 Site Activities 5 Site Activities 6 Site Activities 7 Site Activities 8 Site Activities 9 Site Activities 10 Site Activities 11 Interior Framing – Virtual and Real 12 Interior Framing 13 Engaged Leadership 14 North Stair 15 Electrical Rooms 16 Service Entrance Section (SES) 17 Council Chambers 18 Council Chambers-Roof 19 Council Chambers-Roof 20 Council Chambers 21 In Progress Scope Schedule Budget • Masonry, elevator steel, interior stairs, roofing, plumbing rough & mechanical rough, interior framing • Glazing Anchors on South and North elevations • Steel for Council Chambers Expansion • Service Entrance Section (SES) work Next Month • East Elevation Glazing/South Curtain Wall • Steel arrives for Link and Amphitheater 22 Thank You