Amendment to Agreement with B & F Contracting Inc.

City of Glendale — Regular Meeting (2025-05-27)

View PDF Item 8 Meeting page

Extracted text (via pymupdf) 206647 characters
City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
Project Name: Arrowhead Sewer Line Phase 1.1 - Construction Manager at Risk 
Project No.: 
202104.1 
Amendment No: 2 
Date: 
 
      
 
This Amendment to that certain Standard Form Agreement dated June 11, 2024 by and between the City of Glendale 
and B & F Contracting, Inc. (CM@Risk) for services, deliverables and work related to Project No. 202104.1, Project 
Name: Arrowhead Sewer Line Phase 1.1 - Construction Manager at Risk, (the “Agreement”) is made and entered 
into effective this       day of      , 2025. 
 
1. This Amendment #2 establishes a Guaranteed Maximum Price (“GMP”) and Construction Phase Fee for 
Construction Services and incorporates such terms into the Agreement, making the Agreement effective 
for Construction Phase Services: 
 
a. 
The total fee for Construction Phase Services, which is included in the Guaranteed Maximum Price (GMP) 
as defined under the Agreement, shall be fixed at Forty-Seven Thousand Ninety-Four and 85/100 Dollars 
($47,094.85).       
 
b. The Guaranteed Maximum Price (“GMP”) for Construction Services, as defined under the Agreement, shall 
be Nine Hundred Thirty-Five Thousand Eight Hundred Twenty-Six and 55/100 Dollars ($935,826.55). 
This GMP2 package is for the Arrowhead Waste Activated Sludge (WAS) Line Realingment. 
 
c. 
The total compensation under the Agreement, as amended by this Amendment, shall be: 
 
 
Pre-Construction Phase 
Construction Phase 
Total 
Original Agreement: 
$143,068.20 
$      
$143,068.20 
 
 
 
 
Previous Amendments: 
$      
$2,329,250.74 
$2,329,250.74 
 
 
 
 
This Amendment: 
$      
$935,826.55 
$935,826.55 
 
 
 
 
Total (including this 
Amendment): 
 
$143,068.20 
 
$3,265,077.29 
 
$3,408,145.49 
 
 
2. DELETE the blank template “Exhibit C – Cost of the Work – Schedule of Values” from the Agreement, 
and ADD “Exhibit C – B & F Contracting, Inc. Cost of the Work – Schedule of Values” dated April 11, 
2025 (33 Pages), attached herein. 
 
3. ADD “Exhibit E – Construction Documents necessary to define Scope of Work and deliverables for the 
Construction Phase Services, including plans, designs, drawings, specifications and other required 
Contract Documents” dated December 20, 2024 (82 Pages), attached herein. 
 
4. ADD “Exhibit F - Statement of All Clarifications and Assumptions” dated April 11, 2025 (6 Pages), 
attached herein. 
 
5. ADD “Exhibit G – Schedule of Major Milestones” dated April 11, 2025 (1 Pages), attached herein. 
 
6. All other provisions, terms and conditions of the Agreement shall remain unchanged and in full effect. 
 
(Signature on following page)

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
IN WITNESS WHEREOF, the Parties hereto have duly executed this Amendment, effective as of the date first 
written above. 
OWNER 
CM@RISK 
City of Glendale 
B & F Contracting, Inc. 
5850 W. Glendale Avenue 
11011 N. 23rd Avenue 
Glendale, AZ 85301 
Phoenix, AZ 85029 
By: Its Authorized Representative: 
By Its Authorized Representative: 
Signature 
Signature 
Printed Name 
Printed Name 
Title 
Title 
Date 
Date 
ATTEST: 
___________________________ 
Julie K. Bower   (SEAL) 
City Clerk 
APPROVED AS TO FORM: 
___________________________ 
Michael D. Bailey 
City Attorney 
DESIGN PROFESSIONAL 
Dibble & Associates Consulting Engineers, Inc.
3020 E. Camelback Rd., Ste.201 Ste. 1246 
Phoenix, AZ 85016 
By Its Authorized Representative: 
Signature (Reviewed in accordance with the “Agreement Between Owner and Design Professional” Section 4.8.1.14 
of Exhibit A “Scope of Services for the Design Professional”) 
Printed Name 
Title 
Date 
Joshua Onstott
President
04/29/2025
Ezra M Page
Vice President
05/01/2025

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
EXHIBIT C 
Cost of the Work 
(One (1) page - template) 
(33 pages - final document to be included with GMP Amendment) 
SEE ATTACHED

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
T H I S  P A G E  I S  B L A N K

ROC-089744   |   BFCONTRACTING.COM   |   11011 N. 23rd Avenue|   Phoenix, AZ 85029 
P: 623.582.1170   |   F: 623.582.3761 
 
 
 
EXHIBIT C: COST OF THE WORK 
Arrowhead Phase 1.1 
Waste Activiate Sludge Line Realignment 
 
GMP2 
 
PROJECT NO. 202104 
 
April 11, 2025  
 
 
 
SUBMITTED BY B&F CONTRACTING, INC. 
 
 
 
B&F Contracting, Inc., serving as the Construction Manager at Risk, is providing GMP2 for the 
Waste Activated Sludge Line Realignment Phase of the Arrowhead Phase 1.1 project.

Item No.
Item of Work
Quantity
Unit of Measure
Unit Cost 
Total GMP
1
General Conditions
2.5
 MO 
 $                    36,730.86  $                       91,827.16 
2
Mobilization/Demobilization
1
 LS 
 $                    27,152.00  $                       27,152.00 
3
SWPPP
1
 LS 
 $                      6,626.08  $                         6,626.08 
4
Potholing
13
 EACH 
 $                         403.97  $                         5,251.58 
5
Skunk Creek Clearing/Grubbing/Grading/Restoration
1
 LS 
 $                    18,801.29  $                       18,801.29 
6
Remove & Replace AC Pavement, COG Std Det G-319
515
 SY 
 $                         118.17  $                       60,857.59 
7
Remove & Replace Concrete Vertical Curb & Gutter To Nearest Joint MAG Std Det 
220-1, Type A
45
 LF 
 $                           68.72  $                         3,092.24 
8
Remove & Reinstall Guardrail (ADOT Std Det C-10.30)
6
 LF 
 $                         394.19  $                         2,365.16 
9
Remove & Replace Sidewalk To The Nearest Joint, MAG Std Det 230
100
 SF 
 $                           40.31  $                         4,030.73 
10
Remove And Replace Sidewalk Ramp, MAG Std Det 237-2
1
 EACH 
 $                      6,858.14  $                         6,858.14 
11
Abandon Existing 6" WAS Line, Fill W/ Grout
1108
 LF 
 $                             7.45  $                         8,249.99 
12
Furnish & Install 12" Steel Casing
159
 LF 
 $                         444.51  $                       70,677.61 
13
Furnish & Install 6" HDPE DR11
1137
 LF 
 $                         200.04  $                     227,445.91 
14
Furnish & Install 2" Combination Air Valve & Drain Line
1
 EACH 
 $                    13,413.76  $                       13,413.76 
15
Concrete Encasement, MAG STD DTL 404-1, 2, 3
115
 LF 
 $                         177.43  $                       20,404.30 
16
Connect To Exst 6" WAS Line
2
 EACH 
 $                      9,566.07  $                       19,132.14 
17
Striping (Min Mob)
1
 LS 
 $                      2,500.00  $                         2,500.00 
 $                     588,685.68 
FEE
Fixed Fee, Equal to 8% of DCC
1
 LS 
 $                    47,094.85  $                       47,094.85 
 $                       47,094.85 
BONDS
CMR Performance and Payment Bonds - Actual Cost, not-to-Exceed 1% of DCC
1
 LS 
 $                      6,357.81  $                         6,357.81 
CMR-managed Sub-Contractor Bond Program - Actual Cost not-to- exceed 0% of 
DCC of covered Sub-Contractors (if applicable)
INSURANCE
CMR Insurances (Worker's Comp, General Liability, Auto Liability, Umbrella) - 
Actual Cost, not-to-exceed 1.1% of DCC
1
 LS 
 $                      7,063.52  $                         7,063.52 
Builder's Risk - Actual Cost not-to-exceed 0% of DCC
$                                    -   
CMR-managed Sub-Contractor Inssurance Program - Actual Cost
not-to-exceed 0% of DCC of covered Sub-Contractors (if applicable)
TAXES
Actual Cost, Equal to 5.98% of DCC + Fee + Bond + Insurance
1
 LS 
 $                    38,822.27  $                       38,822.27 
 $                       52,243.60 
ALLOWANCES & CONTINGENCIES
Traffic Control
1
 AL 
 $                    45,000.00  $                       45,000.00 
Construction Survey & Layout
1
 AL 
 $                    12,000.00  $                       12,000.00 
Pump & Transport Waste Sludge From ARWRF
1
 AL 
 $                    35,000.00  $                       35,000.00 
Above Ground Pipe Protection Cage
1
 AL 
 $                    25,000.00  $                       25,000.00 
Quality Control Testing
1
 AL 
 $                    12,500.00  $                       12,500.00 
Landscape Restoration
1
 AL 
 $                      4,500.00  $                         4,500.00 
Flood Control Channel Liner Restoration
1
 AL 
 $                    45,000.00  $                       45,000.00 
Owner's Contingency (10%)
1
 CONT 
 $                    68,802.41  $                       68,802.41 
 $                     935,826.55 
City of Glendale Exhibit C - Construction Manager at Risk Agreement Cost of the Work (May 15, 2023)
SUBTOTAL DIRECT CONSTRUCTION COST  (DCC)
CONSTRUCTION PHASE FEE
SUBTOTAL CONSTRUCTION PHASE FEE
GMP-002 SCHEDULE OF VALUES
B&F Contracting, Inc.
CONSTRUCTION MANAGER AT RISK AGREEMENT - Exhibit C - Cost of the Work
DIRECT CONSTRUCTION COST
Date: 4/11/2025
INDIRECT CONSTRUCTION COSTS  (ICC)
SUBTOTAL INDIRECT CONSTRUCTION COST  (ICC)
TOTAL GMP  =  DCC + FEE + ICC
ADDITIONAL GMP PROPOSAL REQUIREMENTS AND INFORMATION
Attach to this Cost of the Work a detailed breakdown of the complete GMP, including General Conditions, using the CM@Risk's own format.

Man Hours Report - Task
Project Name:
202104 WAS Line Realignment
Customer:
City of Glendale
Job Number:
202104.1
Bid Number: 24-3330-00
Billing Address:
5850 West Glendale Ave, Suite 315
Bid As:
Prime Contractor
Glendale, AZ 85301  USA
Estimator:
Phone:
Travis Monk
Project Address:
67th Ave And Grovers, Glendale, AZ
Contact:
Hugh Alter
Completion Date:
Pay Items
Description
Method
Cost
Quantity
Bid
UM
Hours
Man
Direct
Cost/MH
Unit
Direct Cost
Direct Cost
Total
1 - General Conditions
2.50 MO
632.00
Detail
$145.30
$36,730.86
$91,827.16
Project Management
2.50 MO
112.00
Detail
$129.08
$5,782.78
$14,456.96
Project Engineer
2.50 MO
160.00
Detail
$105.29
$6,738.56
$16,846.40
Project Superintendent
2.50 MO
360.00
Detail
$119.58
$17,219.52
$43,048.80
Porta Johns
3.00 MO
0.00
Detail
$0.00
$850.00
$2,550.00
ST&S
2,300.00 MH
0.00
Plug
$0.00
$3.00
$6,900.00
Job Office Expense
3.00 MO
0.00
Plug
$0.00
$350.00
$1,050.00
Field Connectivity
3.00 MO
0.00
Plug
$0.00
$275.00
$825.00
Yard Location
3.00 MO
0.00
Plug
$0.00
$1,500.00
$4,500.00
Connex
3.00 MO
0.00
Plug
$0.00
$550.00
$1,650.00
Porta Johns
3.00 MO
0.00
Sub.
$0.00
$850.00
$2,550.00
2 - Mobilization/Demobilization
1.00 LS
60.00
Detail
$452.53
$27,152.00
$27,152.00
B&F Equipment, Materials, Etc. 
Mobilization
1.00 LS
60.00
Detail
$161.53
$9,692.00
$9,692.00
Shoring & Plates Delivery/Pickup
8.00 TRIP
0.00
Sub.
$0.00
$350.00
$2,800.00
Project Signs
2.00 EACH
0.00
Detail
$0.00
$665.00
$1,330.00
Construction Water
750,000.00
GAL
0.00
Detail
$0.00
$0.01
$10,000.00
Dust Permit
1.00 EACH
0.00
Sub.
$0.00
$1,080.00
$1,080.00
Temp Fence
3.00 MO
0.00
Detail
$0.00
$750.00
$2,250.00
Furnish Signs
2.00 EACH
0.00
Sub.
$0.00
$250.00
$500.00
Labor For Delivery & Initial Setting Of 
Signs
4.00 HR
0.00
Sub.
$0.00
$95.00
$380.00
Spring Stand Rental 3 Each X 30 Days
60.00 DY
0.00
Sub.
$0.00
$7.50
$450.00
Water Meter
1.00 EACH
0.00
Sub.
$0.00
$1,500.00
$1,500.00
Backflow Preventer
1.00 EACH
0.00
Sub.
$0.00
$1,000.00
$1,000.00
Construction Water
750,000.00
GAL
0.00
Sub.
$0.00
$0.01
$7,500.00
Temp Fance
3.00 MO
0.00
Sub.
$0.00
$750.00
$2,250.00
3 - SWPPP
1.00 LS
32.00
Detail
$207.07
$6,626.08
$6,626.08
SWPPP Permit & Inspection (1 MO)
1.00 MO
0.00
Sub.
$0.00
$1,500.00
$1,500.00
Sweeping
16.00 HR
0.00
Sub.
$0.00
$140.00
$2,240.00
SWPPP Maintenance
1.00 MO
32.00
Detail
$90.19
$2,886.08
$2,886.08
4 - Potholing
13.00 EACH
40.00
Detail
$131.29
$403.97
$5,251.58
Pothole Crew
13.00 EACH
40.00
Detail
$131.29
$403.97
$5,251.58
4/11/2025 2:13:02 PM
Page 1 of 3

Description
Method
Cost
Quantity
Bid
UM
Hours
Man
Direct
Cost/MH
Unit
Direct Cost
Direct Cost
Total
5 - Skunk Creek 
Clearing/Grubbing/Grading/Restorat
ion
1.00 LS
192.00
Detail
$97.92
$18,801.29
$18,801.29
Clearing/Grubbing/Grading/Restoration
1.00 LS
192.00
Detail
$97.92
$18,801.29
$18,801.29
6 - Remove & Replace AC Pavement, 
COG Std Det G-319
515.00 SY
36.00
Detail
$1,690.49
$118.17
$60,857.59
Sawcut Asphalt
1,425.00 LF
36.00
Detail
$103.57
$2.62
$3,728.64
Asphalt Replacement
515.00 SY
0.00
Sub.
$0.00
$110.93
$57,128.95
7 - Remove & Replace Concrete 
Vertical Curb & Gutter To Nearest 
Joint MAG Std Det 220-1, Type A
45.00 LF
25.10
Detail
$123.20
$68.72
$3,092.24
Curb & Gutter Removal
45.00 LF
5.10
Detail
$103.96
$11.78
$530.20
Install New Concrete
45.00 LF
20.00
Detail
$128.10
$56.93
$2,562.04
8 - Remove & Reinstall Guardrail 
(ADOT Std Det C-10.30)
6.00 LF
30.00
Detail
$78.84
$394.19
$2,365.16
Guardrail Removal
6.00 LF
10.00
Detail
$71.67
$119.45
$716.72
Guardrail Replacement
6.00 LF
20.00
Detail
$82.42
$274.74
$1,648.44
9 - Remove & Replace Sidewalk To 
The Nearest Joint, MAG Std Det 230
100.00 SF
36.40
Detail
$110.73
$40.31
$4,030.73
Sidewalk Removal
100.00 SF
12.40
Detail
$95.48
$11.84
$1,183.97
Install New Sidewalk
100.00 SF
24.00
Detail
$118.62
$28.47
$2,846.76
10 - Remove And Replace Sidewalk 
Ramp, MAG Std Det 237-2
1.00 EACH
63.60
Detail
$107.83
$6,858.14
$6,858.14
Sidewalk Ramp Removal
1.00 EACH
15.60
Detail
$94.63
$1,476.22
$1,476.22
Replace Sidewalk Ramp, MAG STD DTL 
237-2
1.00 EACH
48.00
Detail
$112.12
$5,381.92
$5,381.92
11 - Abandon Existing 6" WAS Line, 
Fill W/ Grout
1,108.00 LF
48.00
Detail
$171.87
$7.45
$8,249.99
Grout Fill Existing Line
1,108.00 LF
48.00
Detail
$171.87
$7.45
$8,249.99
12 - Furnish & Install 12" Steel 
Casing
159.00 LF
408.00
Detail
$173.23
$444.51
$70,677.61
Concrete Scanning & Marking Rebar 
Layout
159.00 LF
72.00
Detail
$191.72
$86.82
$13,804.08
Install Pipe Hangers
17.00 EACH
160.00
Detail
$91.71
$863.13
$14,673.28
String & Weld Casing
159.00 LF
48.00
Detail
$162.84
$49.16
$7,816.32
Mount Steel Casing
159.00 LF
128.00
Detail
$112.45
$90.52
$14,392.96
Material Buy
1.00 LS
0.00
Detail
$0.00
$19,990.97
$19,990.97
Concrete Scanning Subcontractors
3.00 DY
0.00
Sub.
$0.00
$1,800.00
$5,400.00
PPS Casing Welds
1.00 DY
0.00
Sub.
$0.00
$2,080.00
$2,080.00
13 - Furnish & Install 6" HDPE DR11
1,137.00 LF
1,136.00
Detail
$200.22
$200.04
$227,445.91
Dig, Lay, & Backfill 6" HDPE
937.00 LF
816.00
Detail
$121.13
$105.49
$98,840.44
Realignments (Horizontal/Vertical)
5.00 EACH
176.00
Detail
$100.05
$3,521.76
$17,608.80
Fuse HDPE & Install In Casing / 
Assemble & Fuse Fittings And Above 
Ground Piping
200.00 LF
64.00
Detail
$95.29
$30.49
$6,098.56
Hydro Excavate Near Bridge/Concrete 
Walls
2.00 DY
40.00
Detail
$131.29
$2,625.79
$5,251.58
Hydrostatic Pressure Test
1.00 LS
40.00
Detail
$89.74
$3,589.52
$3,589.52
Material Buy
1.00 LS
0.00
Detail
$0.00
$96,057.01
$96,057.01
14 - Furnish & Install 2" Combination 
Air Valve & Drain Line
1.00 EACH
60.00
Detail
$223.56
$13,413.76
$13,413.76
Install ARV & Drain Line
1.00 EACH
60.00
Detail
$223.56
$13,413.76
$13,413.76
202104 WAS Line Realignment
4/11/2025 2:13:02 PM
Page 2 of 3

Description
Method
Cost
Quantity
Bid
UM
Hours
Man
Direct
Cost/MH
Unit
Direct Cost
Direct Cost
Total
15 - Concrete Encasement, MAG STD 
DTL 404-1, 2, 3
115.00 LF
172.00
Detail
$118.63
$177.43
$20,404.30
Concrete Encasement
115.00 LF
160.00
Detail
$117.84
$163.95
$18,853.74
Utility Adjustment/Valve Collar
1.00 EACH
12.00
Detail
$129.21
$1,550.56
$1,550.56
16 - Connect To Exst 6" WAS Line
2.00 EACH
164.00
Detail
$116.66
$9,566.07
$19,132.14
MOPO/Existing WAS Line Tie-ins
2.00 EACH
144.00
Detail
$114.63
$8,253.18
$16,506.35
Soft Dig/Expose Existing WAS Line @ 
Tie-ins
1.00 DY
20.00
Detail
$131.29
$2,625.79
$2,625.79
17 - Striping (Min Mob)
1.00 LS
0.00
Detail
$0.00
$2,500.00
$2,500.00
Cross Walk Replacement (Replace 
Impacted Striping Only/No Addtional 
Oblit Included)
1.00 LS
0.00
Sub.
$0.00
$2,500.00
$2,500.00
3,135.10
Pay Item Totals:
$588,685.68
$187.77
Summary Totals:
3,135.10
$588,685.68
$187.77
202104 WAS Line Realignment
4/11/2025 2:13:02 PM
Page 3 of 3

SUBCONTRACTOR / SUPPLIER 
SELECTED
BID RESPONSE
PRICE
SOLICITATION/SELECTION NOTES
Pipe Material Buy
Ferguson
X
Yes
26,762.25
$               
Selected as lowest bidder.
Fullerform
Yes
29,805.36
$               
ISCO
Yes
Incomplete quote
Asphalt Replacement
YSC
X
Yes
$110.93/SY
Selected as lowest bidder.
Vortex
Yes
$144.68/SY
P1 Paving
No
Ready Mix Materials
Arizona Materials
X
Yes
81,384.91
$               
Averaged lowest bidders due to scheduling
Desert Ready Mix
X
Yes
81,973.75
$               
Averaged lowest bidders due to scheduling
Martin Marietta
Yes
82,000.00
$               
MAG Spec ABC
Arizona Materials
X
Yes
$19.55/Ton
Average top Two 
Vulcan Materials Company
Yes
$22.85/Ton
Insearch Corp
No
Steel Casing Welding
Professional Piping Systems
X
Yes
2,080.00
$                 
SUBCONTRACTOR & SUPPLIER SOLICITATIONS & SELECTIONS

April 9, 2025 
 
To our valued customers, 
 
The tariff landscape is constantly evolving, and the implementation schedule is fast-paced. Ferguson relies on our 
manufacturer partners to notify us of price increases, which we immediately implement on the announcement effective 
date. These increases vary significantly based on each manufacturers’ unique business. 
 
While we cannot predict the exact impacts of every tariff, our general guidance on how to best navigate tariffs remains 
consistent: It is critical that customers work closely with their Ferguson Sales associate to discuss product needs, 
understand pricing impact, and make informed decisions regarding each of your individual projects. Together, we 
can determine the best course of action to mitigate job disruption. 
Important things to know: 
• 
Pricing is extremely volatile and changes day by day, hour by hour. All prices are subject to change at any time 
based on evolving market conditions. 
• 
We will continue to communicate price adjustments and provide competitive quotes based on current market 
conditions, though these quotes may change due to manufacturer price increases. 
• 
Regularly review open bids and quotes with your Sales associate so you know how these pricing changes might 
impact your project.  
 
We appreciate your loyalty and understanding as we manage this changing business environment. If you have questions 
concerning upcoming jobs or existing quotes, please speak with your Ferguson Sales associate to help plan for your 
business needs. 
 
Thank you for your continued support and partnership.  
 
Ferguson  
 
 
Tariff Timeline 
• 
Apr. 9, 2025: Effective date for additional reciprocal varied tariffs from other countries; tariffs on goods from China 
to increase to 104%.  
• 
Apr. 5, 2025: Effective date for baseline universal tariffs of 10%. 
• 
Mar. 12, 2025: Effective date of 25% tariffs on all steel and aluminum imports. 
• 
Mar. 4, 2025: Effective date of 25% tariffs on Mexico and Canada imports plus an added 10% on Chinese 
imports, bringing the total tariff to 20%. 
• 
Amendment: Goods that fall under the U.S.-Mexico-Canada Agreement (USMCA) will be exempt from 
Mexico until April. 
• 
Feb. 4, 2025: Effective date of 10% tariffs on Chinese imports. 
• 
Feb. 1, 2025: Both Mexico and Canada tariffs are delayed.

FERGUSON WATERWORKS (3083)
1324 S 3RD ST SUITE 140
PHOENIX, AZ 85004-2725
Phone: 602-495-8420
Fax: 602-262-4276
Deliver To: EXP 12/2020 EM ECMS
From:
Dustin Marcus 
dustin.marcus@ferguson.com
Comments:
HOW ARE WE DOING?  WE WANT YOUR FEEDBACK!
Scan the QR code or use the link below to 
complete a survey about your bids:
https://survey.medallia.com/?bidsorder&fc=3083&on=1079
11:12:59 APR 04 2025
FERGUSON WATERWORKS #3083
Price Quotation
Phone: 602-495-8420
Fax: 602-262-4276
Bid No:
B442701
Bid Date:
01/10/25
Quoted By:
KL
Cust Phone:
623-582-1170
Terms:
NET 10TH PROX
Customer:
B & F CONTRACTING INC
11011 N 23RD AVE
PHOENIX, AZ 85029-4807
Ship To:
SKUNK CREEK TRAIL & NORTH 6
GLENDALE, AZ 85308
Cust PO#:
Job Name:
ARROWHEAD WAS
Page 1 of 4
 Item
 Description
 Quantity
 Net Price
 UM
 Total 
----
REVISED BY DUSTIN ON 4.3
----
----
WASTE ACTIVATED SLUDGE
LINE
GLENDALE, AZ
----
----
QUOTED PER CUSTOMER LIST
QUOTED PER GLENDALE SPECS
----
----
PT-QUOTE-NOTES
BID NOTES FOR CUSTOMER
1
EA
***********************************
QUOTE VALID FOR 30-DAYS FROM TIME
QUOTE WAS RECEIVED - MAY VARY ON
SPECIAL MATERIAL.
***********************************
SERVICE BRASS & DI PIPE HAS LONGER
LEAD TIMES THAN NORMAL. GET WITH
YOUR SALESMAN FOR CURRENT LEAD
TIMES AT TIME OF ORDER.
***********************************
"Any reference to or incorporation
of Executive Order 14042 and/or the
EO-implementing Federal clauses
(FAR 52.223 -99 and/or DFARS
252.223-7999) is expressly rejected
by Seller and shall not apply as
Seller is a materials supplier and
therefore exempt under the
Executive Order."
***********************************
----
PT-QUOTE-NOTES
0.00

Page 2 of 4
11:12:59 APR 04 2025
FERGUSON WATERWORKS #3083
Price Quotation
Fax: 602-262-4276
Reference No: B442701
HOW ARE WE DOING?  WE WANT YOUR FEEDBACK!
Scan the QR code or use the link below to 
complete a survey about your bids:
https://survey.medallia.com/?bidsorder&fc=3083&on=1079
 Item
 Description
 Quantity
 Net Price
 UM
 Total 
----
----
PT-COPPERTERMS
***********************************
1
EA
DUE TO COPPER BEING A COMMODITY,
QUOTE IS SUBJECT TO REPRICE AT
TIME OF SHIPMENT.
***********************************
----
PT-COPPERTERMS
0.00
----
----
==========================
STORM MATERIAL
==========================
----
--------------------------
6" DR11 HDPE
--------------------------
----
PEI11AU40
6X40 IPS DR11 HDPE PIPE
1160
737.500
C
8555.00
TW12SLDUFG500
12GA SLD COP UF WIRE GREE 500
1500
309.552
M
464.33
PSD3105G1054
*TNA 3X1000 UG DET STORM DRN GREE
1
76.500
EA
76.50
----
6" DR11 SUBTOTAL
9095.83
----
--------------------------
6" DR11 FITTINGS
--------------------------
----
PEI11F22U
6 IPS PC160 DR11 FAB 2PC 22-1/2
1
81.120
EA
81.12
PEI11B4U
6 IPS PC200 DR11 45
10
36.080
EA
360.80
PEI11B9U
6 IPS PC200 DR11 90
5
40.334
EA
201.67
----
6" DR11 FITTINGS
643.59
----
--------------------------
6" HDPE (DR11)
VERTICAL REALIGNMENT
--------------------------
----
PEI11B4U
6 IPS PC200 DR11 45
4
36.080
EA
144.32
----
6" VERTICAL SUBTOTAL
144.32
----
--------------------------
12" STEEL CASING W/ CASING
SPACERS AND END SEALS
--------------------------
----
DSCP37512
12 X .375 STL CASING PIPE
168
3694.446
C
6206.67
PEI11AU40
6X40 IPS DR11 HDPE PIPE
160
10.556
C
16.89
 
ALLOW 5-7 ARO 
----
SP-CCCS080663
SPACER SS 8IN WIDE 6IN
28
103.053
EA
2885.48
SP-CCES0106631275
END SEAL 6 X 12
2
79.455
EA
158.91
----
STEEL CASING SUBTOTAL
9267.95
----

Page 3 of 4
11:12:59 APR 04 2025
FERGUSON WATERWORKS #3083
Price Quotation
Fax: 602-262-4276
Reference No: B442701
HOW ARE WE DOING?  WE WANT YOUR FEEDBACK!
Scan the QR code or use the link below to 
complete a survey about your bids:
https://survey.medallia.com/?bidsorder&fc=3083&on=1079
 Item
 Description
 Quantity
 Net Price
 UM
 Total 
STORM MATERIAL TOTAL
19151.69
----
==========================
DOM. WATER MATERIAL
==========================
----
--------------------------
2" ARV
PER DET 3 DWG D1
--------------------------
----
**************************
----
F202BS690IP7
6X2 IP DBL SS STRP BRS SDL DI/PVC
1
186.097
EA
186.10
IS46LNKUE
2X6 SS S40 316L NIP
1
30.230
EA
30.23
FNW100AK
2 SS 1000# THRD 1PC RP BV LL
1
163.286
EA
163.29
IS46LNKCLE
2XCLOSE SS S40 316L NIP
1
10.820
EA
10.82
SP-D9545351
2" SGL BDY SEWAGE COMBO AIR VLV 
1
4910.830
EA
4910.83
SYLE: ASU- SINGLE BODY SEWAGE COMBO
AIR VALVE 
SIZE: 2" (50MM)
BODY STYLE: SCAV- CLEAN OR WASTEWAT
ER SERVICE 150PSI
END CONNECTION: T1- THRD INLET ;NPT
UP TO 300PSI
BODY MATERILA: S2- 316SS 
 
LEAD TIME: 12WEEKS 
SP-M1LATCHCAGE
 M1 ENCLOSURE 6" PIPE W/ ADPT+CLAMP
1
2200.320
EA
2200.32
----
----
ARV SUBTOTAL
7501.59
----
--------------------------
----
CONNECT TO EXISTING 6" WAS
WAS LINE DET 1, DWG D1, D2
==========================
----
E3806ST
6 RESTRAINED SLV C900/DI X IPS
2
378.930
EA
757.86
 
----
CONNECT TO 6" SUBTOTAL
757.86
----
--------------------------
2" ARV DRAIN LINE
--------------------------
----
P80BK
2 X 20 FT PVC S80 BE PIPE
40
188.000
C
75.20
O30757
16 OZ PURP PRMR - NSF LISTED
1
17.010
EA
17.01
O31095
16 OZ PVC HD GRAY CMNT
1
19.615
EA
19.62
----
2" S80 SUBTOTAL
111.83
----
DOM. WATER MATERIAL TOTAL
8371.28
==========================
ADDED PER TRAVIS ON 4/1/25
----

Page 4 of 4
11:12:59 APR 04 2025
FERGUSON WATERWORKS #3083
Price Quotation
Fax: 602-262-4276
Reference No: B442701
HOW ARE WE DOING?  WE WANT YOUR FEEDBACK!
Scan the QR code or use the link below to 
complete a survey about your bids:
https://survey.medallia.com/?bidsorder&fc=3083&on=1079
 Item
 Description
 Quantity
 Net Price
 UM
 Total 
PEI11FLAU
6 IPS PC200 DR11 FLG ADPT
4
39.493
EA
157.97
SP-BUP-SDR7-06C
6 DI BACKING RING
4
14.720
EA
58.88
BUP-SDR11-06B, NOT SDR7
SP-P6SUS3PRO6
6" STUD SET/2 NUTS 304SS
4
59.460
EA
237.84
CONTRACTOR TO VERIFY BOLT
SIZE PRIOR TO ORDER
----
Net Total:
$27977.66
Tax:
$0.00
Freight:
$0.00
Total:
$27977.66 
Quoted prices are based upon receipt of the total quantity for immediate shipment (48 hours).  SHIPMENTS BEYOND 48 HOURS SHALL BE
AT THE PRICE IN EFFECT AT TIME OF SHIPMENT UNLESS NOTED OTHERWISE. QUOTES FOR PRODUCTS SHIPPED FOR RESALE
Due to the uncertain impact of potential tariffs, Ferguson's quotation/proposal has not included any provision or contingency for future tariffs or increase of 
existing tariffs. Ferguson reserves the right to adjust prices to reflect the impact of any new or increased tariffs that affect our costs at the time of shipment. 
Ferguson will provide notice of any such adjustments along with documentation supporting the changes. 
 
CONTRACTOR CUSTOMERS: IF YOU HAVE DBE/MBE/WBE//VBE/SDVBE/SBE GOOD FAITH EFFORTS DIVERSITY GOALS/ REQUIREMENTS ON A 
FEDERAL, STATE, LOCAL GOVERNMENT, PRIVATE SECTOR PROJECT, PLEASE CONTACT YOUR BRANCH SALES REPRESENATIVE 
IMMEDIATELY PRIOR TO RECEIVING A QUOTE/ORDER.
ARE NOT FIRM UNLESS NOTED OTHERWISE.
https://www.ferguson.com/content/website-info/terms-of-sale
LEAD LAW WARNING: It is illegal to install products that are not "lead free" in accordance with US Federal or other applicable law in potable water 
systems anticipated for human consumption. Products with *NP in the description are NOT lead free and can only be installed in non-potable 
applications. Buyer is solely responsible for product selection. 
Buyer shall accept delivery of products within 60 days of Seller receiving the products at Seller's warehouse. If Buyer causes or requests a delay in 
delivery of the products, Buyer may be subject to storage fees and additional costs caused by such delay. Seller reserves the right to requote the 
products and reschedule the delivery date, subject to manufacturer's lead times and price increases, if Buyer is unable to accept delivery within 60 
days.
Seller not responsible for delays, lack of product or increase of pricing due to causes beyond our control, and/or based upon
Local, State and Federal laws governing type of products that can be sold or put into commerce.  This Quote is offered contingent upon the
Buyer's acceptance of Seller's terms and conditions, which are incorporated by reference and found either following this document, or
on the web at 
Govt Buyers:  All items are open market unless noted otherwise.

B&F CONTRACTING, INC
11011 N. 23RD AVENUE
PHOENIX, AZ 85029
Fullerform Systems Inc.
24 East Pioneer St.
PHOENIX, AZ 85040
Phone (602) 268-5701
EXPIRATION DATE
PAGE NO.
Quotation
QUOTE NUMBER
S100048437
01/11/2025
1 of 4
Fullerform Systems Inc.
24 East Pioneer St.
PHOENIX, AZ 85040
Phone (602) 268-5701
CUSTOMER NUMBER
CUSTOMER PO NUMBER
JOB NAME / RELEASE NUMBER
SALESPERSON
WRITER
SHIP VIA
TERMS
SHIP DATE
FREIGHT ALLOWED
JJ PARKINSON
12/12/2024
LINDSAY VIKER
1% disc 20 days, Net 30
129
Waste Activated Sludge Line
ORDER QTY
DESCRIPTION
UNIT PRICE
EXT PRICE
QUOTE TO:
B&F CONTRACTING, INC
11011 N. 23RD AVENUE
PHOENIX, AZ 85029
SHIP TO:
No
Project: Waste Activated Sludge
Line
Location: Skunk Creek & 67th Ave
Spec: Glendale
Bid Date: 1/14/2025
Pricing Valid: 15 Days*
6" HDPE
-----------------------------------
^6" DR-11 IPS HDPE
Non Return / Non Cancellable
1160ft
6.850/ft
7946.00
Subtotal -------
7946.00
______________
6" Fittings
-----------------------------------
6 IPS HDPE DR11 22.5-DEG ELBOW
Non Return / Non Cancellable
1ea
52.615/ea
52.62
6 IPS HDPE DR11 45-DEG ELBOW
Non Return / Non Cancellable
10ea
123.692/ea
1236.92
6 IPS HDPE DR11 90-DEG ELBOW
Non Return / Non Cancellable
5ea
55.385/ea
276.92
14UF GREEN WIRE X 500 ||
3ea
76.667/ea
230.00
3DT-GREEN / 3DT-SEWER
3" X 1000' ROLL OF DETECTABLE SEWER
TAPE GREEN
2ea
37.833/ea
75.67
^FREIGHT CHARGE HDPE FITTINGS
1ea
365.000/ea
365.00
Subtotal -------
2237.13
______________
Printed By: JPARKINS on 1/14/2025 12:51:08 PM PST
** Continued on Next Page **

Quotation
EXPIRATION DATE
PAGE NO.
QUOTE NUMBER
S100048437
01/11/2025
2 of 4
ORDER QTY
DESCRIPTION
UNIT PRICE
EXT PRICE
6" HDPE (DR 11) VERTICAL
REALIGNMENT
-----------------------------------
6 IPS HDPE DR11 45-DEG ELBOW
Non Return / Non Cancellable
4ea
55.385/ea
221.54
Subtotal -------
221.54
______________
Casing
-----------------------------------
^12" STEEL CASING .375 Wall
(40' -42' Lenght Sticks - 159'
Needed)
168ft
45.000/ft
7560.00
Non Return / Non Cancellable
^CCS08-0663 CASING SPACER
SPACER SS 8IN WIDE 6IN
6X12 SS CENTERED RESTRAINED
CCS08-663-CTD12.00ID
20ea
101.057/ea
2021.14
Non Return / Non Cancellable
^CES01-0663-1275
END SEAL 6 X 12
Non Return / Non Cancellable
2ea
77.914/ea
155.83
16"W X 37"H X 18"W M STYLE HINGED
GUARD SHACK (EPCOR ARV) || QE-M-1
1ea
738.667/ea
738.67
Subtotal -------
10475.64
______________
Air Release
-----------------------------------
*Quoting Nylon Coated Ductile Iron
Body Saddle with Stainless Steel
Straps.*
**All Stainless Steel Saddle with
single (Wide) Strap also available
$425.00/ea**
202N-H-6x2
6"x2" ROMAC SERIES 202N-H NYLON w/
SSTL DOUBLE STRAP SADDLE FOR IPS
HDPE (6.63 O.D.)
1ea
384.169/ea
384.17
Non Return / Non Cancellable
S20-060 || 2" X 6" 316 STAINLESS
NIPPLE
*Verify Length*
1ea
46.262/ea
46.26
Printed By: JPARKINS on 1/14/2025 12:51:08 PM PST
** Continued on Next Page **

Quotation
EXPIRATION DATE
PAGE NO.
QUOTE NUMBER
S100048437
01/11/2025
3 of 4
ORDER QTY
DESCRIPTION
UNIT PRICE
EXT PRICE
Non Return / Non Cancellable
20SSTH08M
2" STAINLESS STEEL BALL VALVE
1ea
104.726/ea
104.73
D26TSS02 2" MIP Inlet 316SS Body
Combination Air Valve for
Wastewater
Non Return / Non Cancellable
1ea
5495.000/ea
5495.00
2" SCH80 90 BEND SOC X FIPT ||
807-020
Outlet on ARV is 2" MIP
1ea
17.945/ea
17.94
16"W X 37"H X 18"W M STYLE HINGED
GUARD SHACK (EPCOR ARV) || QE-M-1
Modified to mount on 6" IPS HDPE
Pipe.
1ea
1000.000/ea
1000.00
Metal Cage is Powder Coated Desert
Tan (Will not be galvanized)
Subtotal -------
7048.10
______________
Connect to Existing 6" WAS Line
-----------------------------------
ALPHA-A-7.00
6" ALPHA ROMAC COUPLING 6.60-7.00
2ea
634.032/ea
1268.06
Subtotal -------
1268.06
______________
2" ARV Drain Line
-----------------------------------
2" SCH80 PVC PIPE BELLED END ||
2S80BE
40ft
1.973/ft
78.94
2" SCH80 45 BEND || 817-020
3ea
16.948/ea
50.84
2" SCH80 90 BEND || 806-020
2ea
7.179/ea
14.36
LS300
LINK SEAL W/ 316SS HARDWARE
1/ea 2" penetration into 4" cored
Hole (6 Links required)
6ea
30.000/ea
180.00
Subtotal -------
324.14
______________
6TJ350
6" TJ DIP CL350 || 6DIP350
1ft
26.598/ft
26.60
6HDSS350 / 6TR350
6" HDSS/TR FLEX DIP CL350
1ft
36.424/ft
36.42
Printed By: JPARKINS on 1/14/2025 12:51:08 PM PST
** Continued on Next Page **

Quotation
EXPIRATION DATE
PAGE NO.
QUOTE NUMBER
S100048437
01/11/2025
4 of 4
ORDER QTY
DESCRIPTION
UNIT PRICE
EXT PRICE
EB1706
EBAA 6" 1700 SERIES JOINT RESTRAINT
FOR DIP
1ea
123.775/ea
123.78
6" FIELD LOK GASKET || 60102
1ea
97.955/ea
97.95
Subtotal
S&H Charges
Amount Due
29805.36
0.00
29805.36
Printed By: JPARKINS on 1/14/2025 12:51:08 PM PST
*ALL PRODUCTS WILL BE PRICED IN EFFECT AT TIME OF SHIPMENT.
*DUE TO SUPPLY CHAIN PRICE INCREASES.
Estimated Tax
0.00

Young, Swenson Cross Paving, Inc.
1329 E. Gibson Lane, Phoenix, AZ 85034
Phone: 602-254-7474, Fax 602-254-7476
License #: ROC299308
Bid To:
B&F Contracting, Inc.
Date:
Wesley Johnston
Estimate #:
11011 N. 23rd Ave.
Phoenix, AZ. 85029
Project Name:
Arrowhead WAS Line - asphalt patching - REV2
Phone:
Project Address:
67th Ave. & Grovers Ave.
e-mail: wesley.johnston
Glendale, AZ.
Bid Detail
A.
Install 6" of Asphalt per COG STD DTL G319 to an area that totals approximately 614 SY.
$65,109
1. Apply tack to existing saw cut edges.
2. Install new 3/4" MAG Gyratory hot mix asphalt to a depth of 3", and compact to proper density.
3. Saw cut asphalt in prepartation for removal.
4. Demo, remove, and haul away exisiting asphalt for T-top.
5. Apply tack to existing asphalt surface .
6. Install new 1/2" MAG Gyratory hot mix asphalt to a depth of 3", and compact to proper density.
7. Use hot rubber sealant to seal all joints of the newly installed asphalt.
NOTE:
Includes (2) weekday mobilizations.
NOTE:
Asphalt to be installed in (2) lifts.
NOTE:
Area is to be at proper grade (+/- 0.25") and base compacted to proper density by others.
NOTE:
Additional paving mobilization charges will be at $3,000 each.
NOTE:
YSC Paving, Inc. will not be held responsible for any settling of asphalt due to
subgrade/ABC preparation by OTHERS.
NOTE:
Includes demo and removal of existing materials for T-top.
NOTE:
Any additional square yards patched back will be billed via change order.
NOTE:
Excludes traffic control / barricades, Slurry Seal, Fog Seal, Engineering, Survey, Testing, Permits, or any
other items not specified above.
NOTE:
Changes in the asphalt thickness will require a signed change order prior to paving.
Total:
$65,109
ESTIMATE
4/11/2025
CC25004REV
623-582-1170
WHERE SUCCESSFUL PROJECTS BEGIN.
Pricing is valid until 7/30/2025, if we receive a subcontract by 5/30/2025.
Page 1 of 2

Young, Swenson Cross Paving, Inc.
1329 E. Gibson Lane, Phoenix, AZ 85034
Phone: 602-254-7474, Fax 602-254-7476
License #: ROC299308
TERMS AND CONDITIONS:
Price includes (unless otherwise stated) 1 weekday mobilization, equipment, labor, license, and materials. Weekend work is extra.
Sprinkler and irrigation water to be turned off for the duration of projects by owner.
A two(2) year warranty on all workmanship, labor, and materials (except ordinary wear/abuse, failure due to work placed by Others)
is standard.
Price EXCLUDES engineering, testing, inspection, permits, bonds, utility adjustments, utility asphalt repairs, stripes, sawcut, 
prime coat, soil sterilant, colored concrete, Rip Rap, spillways, extruded curb, parking blocks, encasements, drywells, trenches, 
demolition, environmental controls, ABC, private utility locators, traffic control plans, or any other items unless specifically noted.
Seal Coat and Slurry Seal adhesion cannot be guaranteed on heavily oil contaminated areas.
Tire marks due to hard steering, hot weather, abuse are normal and unavoidable and should not be concern.
YSC is not responsible for drainage on projects with less than 1% fall, subgrade deficiencies, damage to underground utilities
or survey monuments not located by Blue Stake "811" or for private lines by owner prior to start of work.
Material prices are good for 30 days from the date on the estimate unless otherwise stated. ****See Market Volatility note above.
Unless stated specifically in the above scope YSC Paving, Inc. is not responsible for making any site conditions or improvements
ADA compliant. It is recommended that the client use a certified ADA consultant for site evaluations and recommendations as
required by applicable Federal and State laws. YSC Paving will then make the recommended changes and additional charges will
apply. 
PRELIMINARY / LIEN PROCEDURES:  A preliminary notice will be mailed within 20 days, from the start of the project.  This is
NOT A LIEN and is NOT RECORDED AGAINST YOUR PROPERTY.
This notice will be mailed to the owner, construction lender, general contractor, and/or owner/owner's agent in order to preserve the 
claimant's right to later file a mechanic's lien or make claim against a payment bond if he or she is not paid.  This Pre-lien is also
for your protection.  It informs you, at the outset of the claimant's work, of the type and dollar range of the materials or services 
to be provided to your project.  This allows you to track payments downstream to the claimant, and in return, collect partial and  
final lien waivers throughout the project.  The Pre-lien enables you to make sure the appropriate parties are paid, and to minimize 
the chance of a mechanic's lien or a bond claim at the conclusion of the project.  NOTE: You may also receive other Pre-liens 
from other subcontractors, suppliers, or similar entities involved in you project.
Any deviations from the specifications involving extra costs will become an extra charge above the estimate.
The above proposal is not intended to be used as specifications for other vendors or contractors.
All sales tax included in total.
Payment terms to be - 50% Down and Balance due upon completion of project.
Payment can be made by Check, ACH transfer, or Credit Card (Visa, Mastercard). A processing fee of 3% will be applied to 
all credit card payments.
Total:
$65,109
The above prices, specifications, and conditions
are satisfactory and are hereby accepted. You
Date:
Print Name & Title:
are authorized to do the work as specified.
Signature:
CC25004REV
Acceptance of Estimate #
Submitted By:
Chris Cathcart
602-254-7474
chris@yscpaving.com
Page 2 of 2

Date: 
Bid #:
AZ ROC # 346003
Description
Unit of 
Measure
QTY
Unit Price 
AMOUNT
Mobilization
EA
2
$3,000.00
$6,000.00 
COG STD DET G-319 (Prep 
and Pave >6")
SY
613
$130.00
$79,690.00 
TOTAL
Date: __________________________
Date: __________________________
Project Scope:  *Pricing Valid for 30 Days* 
BID PROPOSAL
$85,690.00
1/21/2025
B & F Construction
BFArrowhead.001
Arrowhead WAS Line Realignment
Job:
Client:
Customer: 
_____________________________________________________
Vortex Construction Services: 
_____________________________________________________
Exclusions:  Sales Tax, Bonds, Permits, Traffic Control, Inspection Fees, Removals from other trades, 
Temp. Fencing, Pedestrian Access, Signage, Landscape Restoration, Weekend, Night or Holiday Work, 
Crack Sealing, Striping, Off Duty Officers.
2. COG STD DET G-319-Prep trench and pave in accordance with STD DET G-319.  Utilization of MAG EVAC PG 70-
10 Conventional Mix's.  Total Pavement thickness not to exceed 6".
1. Mobilization -Two mobilizations to include saw cut and removal to obtain 4' trench patch, the re-grade and 
paving prep prior to asphalt placement.

DESERT READY MIX 
                                                                                                           READY MIX CONCRETE SALES AND SERVICE 
 
                                                                                                       4011 PRESIDO STREET 
 
                                                                                                    MESA, AZ  85215 
                                                                                                            OFFICE: 480-428-2280  FAX: 480-985-4248 
* E – Environmental | S – Saturday Fee | F – Fuel Surcharge  
 
Begin Date: 
April 1, 20255 
Quote # : 
25284 
Expiration Date: 
December 31, 2025 
MAP/GRID 
 
 
 
 
 
Item Code 
Item Description 
Est. Qty 
Price 
S500501      
PHCLSM.5 (1/2 SACK SLURRY COP)             
484 Yards 
$110.00 
SRP104       
1/2 SACK MAG CLSM (SRP MIX IF NEEDED)                           
Per Yard 
$110.00 
A202001      
MAG C 2000 PSI W/ASH                     
18 Yards 
$142.00 
A202501      
MAG B 2500 PSI W/ASH                     
9 Yards 
$146.00 
A203001      
MAG A 3000 PSI W/ASH                     
3 Yards 
$150.00 
G402069      
2000 PSI RIP RAP GROUT                   
8 Yards 
$159.00 
TC           
TEMPERATURE CONTROL                      
Per Yard 
$1.00 
AG010003 DELIVERED    MAG SPEC ABC (NON-LIME) (GOOD THRU 9/30/2025)           231 Tons 
$19.55 
              Additional Fees                                                                                 Minimum Load Fee 
Quoted By:
BRUCE A. TABET                             
 
Customer: 
B & F CONTRACTING INC                    
Customer Code: 
BFCO001    
Address: 
11011 N 23RD AVE                         
 
PHOENIX, AZ  85029 
Contact: 
WESLEY JOHNSTON (ESTIMATOR) 
Phone: 
623-582-1170  
Fax: 
 
Project: 
ARROWHEAD WAS LINE                       
Job Address: 
67TH AVENUE & GROVERS                    
Terms Description: 
2% 10TH NET 30                            
Fee ID * 
UOM 
Price 
E01 
Per Yard 
$3.25 
FSC 
Per Load 
$TBD 
Less than or equal to 
UOM 
Price 
2 Yards 
Load 
$0.00 
3.5 Yards 
Load 
$0.00 
5.5 Yards 
Load 
$0.00 
 
Normal operating hours are Mon-Fri, Sat, Sun or Holidays are subject to surcharges. 
 
Color added at no expressed guarantee. 
 
Drivers do not accept cash or make change. 
 
Desert Ready Mix reserves the right to increase prices due to RAW Material cost increases 
such as Cement, Fly Ash, Aggregates or unexpected Fuel increases. 
 
All specialized aggregate sales are based on availability. 
 
Deliveries less than 6 Cubic yards are subject to our minimum load charges. 
 
This quote does not guarantee product or service availability 
 
All Aggregates and Concrete deliveries include a per load fuel surcharge. 
READY-MIX

Quote Number: 
Q10014561-0
Created On: 
1/6/2025
Expiration Date:
4/6/2025
Project:
Arrowhead WAS Line
Account:
B & F Contracting Inc
Project Address:  
Account Number:
40032
67th Ave & W Grovers Ave
Glendale, AZ 85308
Contact:                              Wesley Johnston              
Estimated Start Date:
1/27/2025
E-mail:
wesley.johnston@bfcontracting
.com
Pricing Valid Until:
4/30/2025
Phone:
480-489-9893
Customer Service: 
Sales Office Address: PO Box 741805 Kilgore Companies
Los Angeles, CA  90074-1805
MATERIAL PRICING
Item Code
Description
Quantity
Unit Price
PHCLSM
1/2 SACK ABC SLURRY (COP)
500 CY
$106.00
-Escalator of $3.00 effective 4/1/2025 recurring every 12 months
--
50020
2000 PSI GROUT W/ASH, ASTM 476
10 CY
$152.00
-Escalator of $6.00 effective 4/1/2025 recurring every 12 months
--
13004
3000 PSI MAG-A
5 CY
$139.00
-Escalator of $6.00 effective 4/1/2025 recurring every 12 months
--
12504
MAG-B 2500 PSI 1" ROCK
10 CY
$137.00
-Escalator of $6.00 effective 4/1/2025 recurring every 12 months
--
12004
2000 PSI MAG C
20 CY
$135.00
-Escalator of $6.00 effective 4/1/2025 recurring every 12 months
--
SUNDRIES AND SURCHARGES
Item
Comments
Price
Unit
Fuel Surcharge RMX
$35.00
EA
WEEKEND TRUCK TIME
$50.00
HRS
ENVIRONMENTAL CHARGE
$25.00
EA
Load Size: 0.00 > 6.00
$200.00
CY
Additional Products & Services
Chilled Water
$2.50
PCY
Color Seal
$0.00
PCY
Color Wash Out
$25.00
EA
Micro Fiber
$7.50
PCY
Nitrogen Cooling
$9.50
GAL
Recover per 1/2 hour
$4.00
OZ
Non-Chloride Accerator (per 1%)
$0.00
GAL
Hot Water
$2.50
PCY
Macro Fiber (Structural)
$7.00
PCY
Respectfully,
Arizona Materials
Sales Rep: Randy Schmolke
Phone: 602-342-6595
Email: Randy.Schmolke@azmatl.com
Customer Acceptance
Signed by:
Date:
__Taxable     __Tax Exempt (Attach Certificate)

PROJECT NAME
JOB / P. O. NUMBER
QUOTE DATE
ARROWHEAD WAS LINE
83389 /
1/28/2025 3:28:47 PM
PROJECT LOCATION
BID DATE
67TH AVE & GROVERS  GLENDALE,  AZ  85308
January 28, 2025
PROJECT START DATE
CUSTOMER
B & F CONTRACTING INC
March 10, 2025
CONTACT
WES JOHNSTON   480-489-9893
QUOTE EXPIRATION DATE
WESLEY.JOHNSTON@BFCONTRACTING.COM
December 31, 2025
**See Price Escalators**
STREET ADDRESS
11011 N 23RD AVE
CITY, STATE, ZIP
PHOENIX, AZ  85029-4828
CUSTOMER NO.
992678
4129 E Van Buren St, Suite 200
Phoenix, AZ 85008
(602) 685-3400
QUOTE NUMBER: 154811
SALES REP: Villegas, Raul
(480) 298-0157
Raul.Villegas@MartinMarietta.com
PRODUCT CODE
MATERIAL DESCRIPTION
UOM
USAGE
SLUMP
QTY
PRICE
PHCLSM
1/2 SACK ABC SLURRY (PHCLSM1/2)
CY
SLURRY
8
231
$108.00
2203141
MAG C, 1"
CY
CURBS
3-5
20
$145.00
2253141
MAG B, 1"
CY
CURBS
3-5
10
$148.00
2303141
MAG A, 1"
CY
CURBS
3-5
5
$151.00
422033A
2000 PSI-F, 30% 3/8" GROUT W/AEA (476)
CY
GROUT
9
10
$169.00
ADDITIONAL COMMENTS
PRICES DO NOT INCLUDE TAX
ESCALATION NOTES:
CUBIC YARD PRICE INCREASE: 1/1/2026 $10.00
Add:
Add Miscellaneous Extra Charges:
$25.00 Per Load Transportation Surcharge - Add to Above Pricing
$8.00
Per Cubic Yard per each 1% Non Chloride Accelerator (available in 0.25% increments)
$2.00 Per Cubic Yard Environmental Fee - Add to Above Pricing
$3.00
Per Cubic Yard per Each 30 Minute Increment of Hydration Stabilizer (Retarder)
N/C Per Cubic Yard Tempered Water Service Fee
$7.00
Per Cubic Yard Mono/Micro Fiber (1LB per Cubic Yard)
$10.00 Per Cubic Yard Saturday Premium Charge
$4.00
Per Pound of Color per Sack of Cement per Cubic Yard
$50.00
Color Washout Fee per Load
$250.00
Per Load Short Load Delivery Fee (Orders of 6 CYs or Less)
$2.00
Per Minute of Wait Time per Load After 45 Minutes (on job standby)
$5.00
Per Gallon Nitro (3 gallons is equivalent to 20 LBs. of ice) Call for Availability
$0.75
Per Pound Ice
$8.00
Per Cubic Yard Cancellation Fee within 24 Hours of Scheduled Start Time ($200 minimum fee)
$100.00
Per Load Multi-Stop Delivery Fee (per stop)
Above pricing is valid for 30 days from quote date, written quote acceptance is required to hold pricing beyond 30 days.
Prices are FOB job site unless noted otherwise and do not include taxes. Sales Tax owed unless exempt documentation is received before the first pour.
See item 7. TERMS: NET 30 DAYS. If not paid when due, Applicant agrees to pay interest charges at the rate of 1.5% per month or the maximum lawful rate, whichever is lower,
and Seller's reasonable costs of collection, including reasonable attorneys’ fees.
Signature:_______________________________________________________
Quote Date: 1/28/2025
Accepted by: __________________________________________
Please Note
All concrete as bid is per 90 minute max delivery and 95 degree max concrete temperature unless noted otherwise. All Concrete as Bid contains Type F Ash and normal weight aggregate unless specifically
 
noted. All concrete pricing above is valid from Monday thru Friday during normal business hours unless noted otherwise. Aggregates are a naturally occurring material which can contain particles that
 
degrade or stain concrete. It is not possible to completely remove all such particles; however, the occurrence is infrequent, and the bulk aggregate meets the Limits for Deleterious Substances and Physical
 
Property Requirements of Coarse Aggregate for Concrete as outlined in ASTM C 33. Martin Marietta does not warranty against these infrequent occurrences.
Minimum amount of standard concrete for deliveries is 2 cubic yards, specialty concrete is 4 cubic yards. Buyer is responsible for safe access to work area and wash out containment area for all deliveries.

DESERT READY MIX 
                                                                                                           READY MIX CONCRETE SALES AND SERVICE 
 
                                                                                                       4011 PRESIDO STREET 
 
                                                                                                    MESA, AZ  85215 
                                                                                                            OFFICE: 480-428-2280  FAX: 480-985-4248 
* E – Environmental | S – Saturday Fee | F – Fuel Surcharge  
 
Begin Date: 
April 1, 20255 
Quote # : 
25284 
Expiration Date: 
December 31, 2025 
MAP/GRID 
 
 
 
 
 
Item Code 
Item Description 
Est. Qty 
Price 
S500501      
PHCLSM.5 (1/2 SACK SLURRY COP)             
484 Yards 
$110.00 
SRP104       
1/2 SACK MAG CLSM (SRP MIX IF NEEDED)                           
Per Yard 
$110.00 
A202001      
MAG C 2000 PSI W/ASH                     
18 Yards 
$142.00 
A202501      
MAG B 2500 PSI W/ASH                     
9 Yards 
$146.00 
A203001      
MAG A 3000 PSI W/ASH                     
3 Yards 
$150.00 
G402069      
2000 PSI RIP RAP GROUT                   
8 Yards 
$159.00 
TC           
TEMPERATURE CONTROL                      
Per Yard 
$1.00 
AG010003 DELIVERED    MAG SPEC ABC (NON-LIME) (GOOD THRU 9/30/2025)           231 Tons 
$19.55 
              Additional Fees                                                                                 Minimum Load Fee 
Quoted By:
BRUCE A. TABET                             
 
Customer: 
B & F CONTRACTING INC                    
Customer Code: 
BFCO001    
Address: 
11011 N 23RD AVE                         
 
PHOENIX, AZ  85029 
Contact: 
WESLEY JOHNSTON (ESTIMATOR) 
Phone: 
623-582-1170  
Fax: 
 
Project: 
ARROWHEAD WAS LINE                       
Job Address: 
67TH AVENUE & GROVERS                    
Terms Description: 
2% 10TH NET 30                            
Fee ID * 
UOM 
Price 
E01 
Per Yard 
$3.25 
FSC 
Per Load 
$TBD 
Less than or equal to 
UOM 
Price 
2 Yards 
Load 
$0.00 
3.5 Yards 
Load 
$0.00 
5.5 Yards 
Load 
$0.00 
 
Normal operating hours are Mon-Fri, Sat, Sun or Holidays are subject to surcharges. 
 
Color added at no expressed guarantee. 
 
Drivers do not accept cash or make change. 
 
Desert Ready Mix reserves the right to increase prices due to RAW Material cost increases 
such as Cement, Fly Ash, Aggregates or unexpected Fuel increases. 
 
All specialized aggregate sales are based on availability. 
 
Deliveries less than 6 Cubic yards are subject to our minimum load charges. 
 
This quote does not guarantee product or service availability 
 
All Aggregates and Concrete deliveries include a per load fuel surcharge. 
MAG SPEC ABC

QUOTATION  
 
 
Date: 01/07/2025 
Quote #: 1462062110 
Account: 213518 
 
 
 
 ACCOUNT :  B & F GENERAL CONTRACTING 
 
QUOTE NAME : ARROWHEAD WAS LINE / N 67TH
AVE & W GROVERS AVE / GLENDALE 
 
Bill-To Address: 11011 N 23RD AVE  
PHOENIX AZ 85029
 
Attn: Wesley Johnston 
 
Ship-To Address: N 67TH AVE & W GROVERS
AVE AZ062243 
GLENDALE AZ 85308
 
 
Effective Date: 01/07/2025 
Expiration Date: 02/06/2025 
Upon Acceptance Price Valid Until: 03/31/2025 
 
Sales Representative: Jesse Paul Castro 
Phone: +1 (480) 708-9498
Email: castroje@vmcmail.com
 
100 - Aggregates
Plant
 
Product ID
 
Product Name
 
Qty
 
U/M
 
Unit Price
 
Haul Rate
 
Delivered
 
SUN CITY SAND
& GRAVEL 
 
16272 
 
MAG SPEC ABC 
 
 
231
 
TON 
 
$17.00 
 
$5.85 
 
$22.85 
 
Additional Charges
 
Product ID
 
Product Name
 
Price/%
 
Per UOM
 
ENVFEE 
 
Environmental Fee -Agg & Asphalt 
 
 $4.00 
 
LOAD 
 
 SPECIAL INSTRUCTIONS
 
All daily orders under 100 tons of asphalt are subject to Gomez Price plus the haul.
Material pricing is good to the end of the quote/sales order date only, regardless of the quote acknowledgment
or PO status. Any material provided after that date is subject to price increases.
Vulcan Material plants are commercial asphalt sources that provide a wide range of mixes to multiple
customers on a production day. Every effort is made to ensure production quantities and times for each
customer are met. Vulcan will not be responsible for project or trucking impacts due to the availability to all of
our customers. Due to current aggregate demand, the quote is also subject to product or material availability.
Production is scheduled based on a first-come, first-served basis as available.
 
 
 
1

ATTEN: Travis Monk 
B&F Contracting Inc 
11011 N 23rd Ave 
Phoenix AZ 85029 
 
 
 
PROFESSIONAL PIPING SYSTEMS 
738 S 52ND STREET 
Tempe, AZ 85281 
CASING FIELD WELD AND COATINGS 
QUOTE: 25-143
ERIC JOHNSON 
Estimator  
Professional Piping Systems LLC  
319 E. Pioneer Street 
Phoenix, AZ 85040 
C: 602-510-2638 
www.ppsphx.com

Professional Piping Systems, LLC 
 
 
738 S 52nd Street 
 
 
Tempe, AZ 85281 
 
 
www.ppsphx.com 
 
 
2/20/2025 
Proposal 25-143 | Professional Piping Systems, 738 S 52nd Street, Tempe, AZ 85281 
 
Attachment 1 
Scope of work 
 
Drawings Provided for Estimating  
• NA 
 
Material Grades 
• CS pipe provided by B&F 
 
Procedures 
• 
Inspection criteria 
o None 
 
Coatings 
• 
Surface Prep: SSPC-SP6 
• 
First Prime coat: Macropoxy 646 
• 
Second finish coat: High Solids Poly Semi-Gloss (Finish Color TBD) 
• 
3 Gal for coating the weld affected zones and field touch up. (B&F to do touch up) 
 
 
 
 
Clarifications and Assumptions 
 
 
• 
THIS PRICING IS GOOD FOR 30 DAYS FROM THE DATE ON THIS PROPOSAL. IF PO OR 
NOTICE TO PROCEED IS GIVEN 30 DAYS AFTER THE DATE OF THIS PROPOSAL, PPS 
MUST VERIFY MATERIAL AND EQUIPMENT COSTS AND ADD ANY INCREASE TO THE 
FINAL COSTS.  
• 
PPS WILL NOT BE BOUND TO ANY SCHEDULE IN WHICH WE HAVE NOT FULLY 
PARTICIPATED.  FURTHER, WE WILL NOT ALLOW OUR WORK ACTIVITIES TO BE 
COMPRESSED DUE TO THE SCHEDULE SLIPPAGE OF OTHER TRADES OF SUPPLIERS 
FOR WHICH WE ARE NOT RESPONSIBLE. 
• 
PPS SHALL NOT BE LIABLE FOR DELAYS RESULTING FROM INDUSTRY CONDITIONS 
CONSTRICTING THE SUPPLY OF ESSENTIAL COMPONENTS OF MATERIALS, INCLUDING 
THE INTERRUPTION IN THE SUPPLY OF STEEL PRODUCTS. 
• 
ALL PRICING IS CALCULATED WITH STRAIGHT AND OVERTIME BEING WORKED. 
• 
IN THE EVENT THAT TARIFFS, DUTIES, OR OTHER GOVERNMENT-IMPOSED FEES ARE 
ENACTED, MODIFIED, OR INCREASSED AFTER THE DATE OF THIS PROPOSAL AND 
SUCH TARIFFS DIRECTLY IMPACT THE COST OF RAW MATERIALS REQUIRED FOR THE 
PERFORMANCE OF THE WORK, THE QUOTED PRICE SHALL BE SUBJECT TO 
ADJUSTMENT.  THE ADJUSTMENT SHALL REFLECT THE ACTUAL INCREASE IN MATERIAL 
COSTS INCURRED BY PPS DUE TO THE TARIFF CHANGES. PPS SHALL PROVIDE 
REASONABLE DOCUMENTATION TO SUBSTANTIATE THE ADDITIONAL COSTS.  THE

Professional Piping Systems, LLC 
 
 
738 S 52nd Street 
 
 
Tempe, AZ 85281 
 
 
www.ppsphx.com 
 
 
2/20/2025 
Proposal 25-143 | Professional Piping Systems, 738 S 52nd Street, Tempe, AZ 85281 
 
CUSTOMER AND PPS AGREE TO NEGOTIATE IN GOOD FAITH TO EQUITABLY ADJUST THE 
CONTRACT PRICE TO ACCOUNT FOR SUCH INCREASED COSTS. 
• 
NDT OTHER THAN VISUAL INSPECTION IS ONLY INCLUDED IF IT IS SPECIFICALLY 
NOTED IN THIS PROPOSAL. 
• 
ALL LABOR HAS A ONE YEAR WARRANTY. 
 
 
 
 
 
            DESCRIPTION OF WORK 
 
• 
FIELD WELD 12” DIA CASING PIPE. 
• 
OPTION INCLUDED FOR COATING. 
 
 
 
 
 
Attachment 2 
Proposed Schedule and Pricing 
 
Leadtime 
• Pricing is for 2ea welders for 1 day to weld 3ea 12” BW Joints 
• Includes option for painting the Casing in the shop. 
 
 
Shipping 
• Not included 
 
Total Proposal 
 
Total = $2,080.00 
PAINTING OPTION = $7,250.00 
 
 
Terms 
• 
PAID WHEN COMPLETE 
• NET-30 
 
 
 
 
COATING NOT IDENTIFIED
AS BEING REQUIRED IN
PLANS. IF COATING IS
REQUIRED, CONTINGENCY
BUDGET SHALL BE
UTILIZED FOR
REIMBURSEMENT

Professional Piping Systems, LLC 
 
 
738 S 52nd Street 
 
 
Tempe, AZ 85281 
 
 
www.ppsphx.com 
 
 
2/20/2025 
Proposal 25-143 | Professional Piping Systems, 738 S 52nd Street, Tempe, AZ 85281 
 
 
 
Attachment 3 
INCLUSIONS 
PPS HAS INCLUDED THE FOLLOWING: 
• 2EA WELDERS FOR ONE DAY TO WELD 3EA BW JOINTS ON THE CASING 
PIPE. 
• IF SELECTED: PAINTING THE CASING PIPE IN THE SHOP AND SUPPLYING 
EXTRA PAINT FOR WELD AREAS AND TOUCH UP. 
 
 
 
 
 
 
Attachment 4 
Exclusions 
 
PPS has specifically EXCLUDED from this proposal the following: 
• All field installation. 
• Delivery and unloading pipe on the job site. 
• Coatings (if option is not taken.) 
• Taxes and bonds. 
• Anything not specifically addressed in this Proposal. 
 
 
 
 
 
 
Attachment 5 
Terms & Conditions 
The following terms and conditions (these "Terms & Conditions") apply to the sale of 
goods, materials or products (collectively, "Products") or provision of services (collectively, 
"Services") by Professional Piping Systems, LLC, an Arizona limited liability company 
("PPS"), to the customer identified on the Purchase Order to which these Terms & 
Conditions are attached (the "Customer") and all purchase orders and the provision of all 
Products or Services by PPS are subject to the Terms & Conditions. 
 
1. 
Prices. Except as provided herein, prices offered by PPS for Services or Products in 
any written quote or estimate (“Quote”) will remain in effect for a period of fifteen (15) 
days after the date of the Quote (the "Quote Date"). After said fifteen (15) day period, 
prices are subject to change. Prices for Products to be used in any Work (hereafter 
defined) which are obtained by PPS from a third party, are subject to change at any time 
to account for any fluctuations in the market price after the Quote Date.

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
EXHIBIT E 
Construction Documents necessary to define Scope of Work and Deliverables for the 
Construction Phase Services, including plans, designs, drawings, specifications and other 
required Contract Documents 
(88 pages - To be Incorporated by Amendment) 
SEE ATTACHED

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
T H I S  P A G E  I S  B L A N K

EXHIBIT E: CONSTRUCTION DOCUMENTS 
ARROWHEAD SEWER LINES PHASE 1.1 
WAS LINE REALIGNMENT 
COG PROJECT NUMBER: 202104 
GMP2 
 
 
 
DOCUMENTS: 
 
• 
Drawings: City of Glendale Project #202104.1 Arrowhead Sewer Lines Phase 1.1 Waste Activated 
Sludge (WAS) line Realignment December 2024 Sealed 12/20/24 
• 
Technical Specifications: Arrowhead Sewer Lines Phase 1.1 Waste Activated Sludge (WAS) Line 
Realignment Contract No. 202104.01 Technical Specifications Draft Submitted to City of Glendale 
December 20, 2024

WAS LINE REALIGNMENT
COVER
01
MAYOR
CITY COUNCIL
JERRY P. WEIERS
RAY MALNAR
JOYCE V. CLARK
LAUREN TOLMACHOFF
BART TURNER
IAN HUGH
LEONARDO BALDENEGRO
PINNACLE PEAK RD.
DEER VALLEY RD.
BEARDSLEY RD.
UNION HILLS DR.
BELL RD.
GREENWAY RD.
THUNDERBIRD RD.
CACTUS RD
PEORIA AVE.
OLIVE AVE.
NORTHERN AVE.
GLENDALE AVE.
BETHANY HOME RD.
CAMELBACK RD.
GRAND AVE./ U.S.60
115TH AVE
107TH AVE.
99TH AVE.
EL MIRAGE RD.
SARIVAL AVE.
REEMS RD.
BULLARD AVE.
LITCHFIELD RD.
DYSART RD.
LOOP 303
COTTON LN.
CITRUS RD.
PERRYVILLE RD.
LOOP 101
CITY CLERK
CITY ATTORNEY
JULIE K. BOWER
MICHAEL D. BAILEY
CITY MANAGER
KEVIN R. PHELPS
CITY OF GLENDALE
GLENDALE, ARIZONA
PROJECT # 202104.1
ARROWHEAD SEWER LINES PHASE I.I
WASTE ACTIVATED SLUDGE (WAS) LINE REALIGNMENT
DECEMBER 2024
VICINITY MAP
NTS
SHEET INDEX                       
G1
G2
COVER
GENERAL NOTES
G3
STANDARD ABBREVIATIONS & LEGEND
G4
KEY MAP
G5
SURVEY CONTROL 
101
101
01
02
03
04
05
G1
RECORD  DRAWING
PLANS  ACCEPTANCE
ARROWHEAD SEWER LINES PHASE I.I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104.1
CITY OF GLENDALE
11
JAR
SKF
MCN
LOCATION  MAP
1,141 LF OF
159 LF OF
1 EA OF
6 INCH DIA HDPE
12 INCH DIA STEEL CASING
1 INCH AIR RELEASE VALVE
C1-C3
PLAN AND PROFILE
D1-D2
CIVIL DETAILS
06-08
09-10
91ST AVE.
83RD AVE.
75TH AVE.
67TH AVE.
59TH AVE.
51ST AVE.
43RD AVE.
NTS
S1
STRUCTURAL DETAILS
11
WASTE ACTIVATED SLUDGE (WAS) LINE
PROJECT BENCHAMRK:
POINT NUMBER 20
FOUND CITY OF PHOENIX PUBLISHED BENCHMARK
DESCRIBED AS:
BRASS CAP IN HAND HOLE AT THE INTERSECTION OF
51ST/ AVE AND GROVERS.
OBSERVED GROUND NORTHING = 963258.56
OBSERVED GROUND EASTING = 623311.21
PUBLISHED ELEVATION = 1278.42
OWNER   
CITY OF GLENDALE
ENGINEERING DEPARTMENT
5850 W GLENDALE AVE
GLENDALE, AZ 85301
CONTACT: HUGH ALTER
PHONE: (623) 930-3689
CIVIL ENGINEER
DIBBLE
3020 E CAMELBACK RD, STE 201
PHOENIX, AZ 85016
CONTACT: MARC NELSON, PE
PHONE: (602) 957-1155

WAS LINE REALIGNMENT
GENERAL NOTES
CITY OF GLENDALE GENERAL NOTES
CITY OF GLENDALE STREET NOTES
CITY OF GLENDALE SEWER NOTES
ENGINEER'S NOTES
G2
ARROWHEAD SEWER LINES PHASE I.I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104.1
CITY OF GLENDALE
11
JAR
SKF
MCN
02
HDPE PIPE SPECIFICATION

STANDARD ABBREVIATIONS & LEGEND
EXISTING
NEW
EXISTING
NEW
WAS LINE REALIGNMENT
STANDARD ABBREVIATIONS & LEGEND
G3
ARROWHEAD SEWER LINES PHASE I.I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104.1
CITY OF GLENDALE
11
JAR
SKF
MCN
03

67TH AVE
WAS LINE REALIGNMENT
KEY MAP
G4
ARROWHEAD SEWER LINES PHASE I.I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104.1
CITY OF GLENDALE
11
JAR
SKF
MCN
04

WAS LINE REALIGNMENT
SURVEY CONTROL

WAS LINE REALIGNMENT
 PLAN AND PROFILE
C1
67TH AVE
REMOVAL NOTES
CONSTRUCTION NOTES
REFERENCE NOTES
ARROWHEAD SEWER LINES PHASE I.I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104.1
CITY OF GLENDALE
11
JAR
SKF
MCN
06

WAS LINE REALIGNMENT
 PLAN AND PROFILE
C2
67TH AVE
REMOVAL NOTES
CONSTRUCTION NOTES
REFERENCE NOTES
ARROWHEAD SEWER LINES PHASE I.I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104.1
CITY OF GLENDALE
11
JAR
SKF
MCN
07

WAS LINE REALIGNMENT
 PLAN AND PROFILE
REMOVAL NOTES
CONSTRUCTION NOTES
REFERENCE NOTES
C3
67TH AVE
ARROWHEAD SEWER LINES PHASE I.I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104.1
CITY OF GLENDALE
11
JAR
SKF
MCN
08

WAS LINE REALIGNMENT
CIVIL DETAILS
09
D1
ARROWHEAD SEWER LINES PHASE I.I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104.1
CITY OF GLENDALE
11
JAR
SKF
MCN

A
A
WAS LINE REALIGNMENT
CIVIL DETAILS
10
ARROWHEAD SEWER LINES PHASE I.I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104.1
CITY OF GLENDALE
11
JAR
SKF
MCN
D2
67TH AVE

WAS LINE REALIGNMENT
STRUCTURAL DETAILS
11
S1
A
-
ARROWHEAD SEWER LINES PHASE I.I
Checked
Drawn
Designed
OF
SHT.
REVISIONS
Description
Date
No.
GLENDALE, ARIZONA 85301 (623) 930-3630
5850 W. GLENDALE AVE.
ENGINEERING DEPARTMENT
CITY OF GLENDALE
PROJECT # 202104.1
CITY OF GLENDALE
11
JMW

Arrowhead Sewer Lines Phase 1.1 
Waste Activated Sludge (WAS) Line Realignment 
 
Contract No.: 202104.01 
 
TECHNICAL SPECIFICATIONS 
 
 
 
 
 
 
 
 
 
Submitted To: 
CITY OF GLENDALE 
 
December 20, 2024 
 
Mayor 
Jerry P. Weiers 
 
 
City Council 
 
Ray Malnar 
Bart Turner  
 
 
 
 
 
 
 
Prepared by: 
Ian Hugh   
 
 
 
 
 
 
Lauren Tolmachoff 
 
 
 
 
 
   
     
Leandro Baldenegro 
Joyce Clark   
 
 
 
 
 
 
 
www.dibblecorp.com

[This page intentionally left blank for double sided printing]

_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
TOC - 1 
 
 
 
Arrowhead Sewer Lines Phase 1.1 
Waste Activated Sludge (WAS) Line Realignment 
 
TECHNICAL SPECIFICATIONS 
 
  
TABLE OF CONTENTS 
Section 
Subject 
 
 
 
 
 
 
             Pages 
 
DIVISION 1 – GENERAL REQUIREMENTS 
 
01010 
Summary of Work 
01010-2 
01014 
Work Sequence 
01014-4 
01015 
Contractor’s Use of Premises 
01015-2 
01060 
Health and Safety 
01060-4 
01062 
Permits and Easements 
01062-2 
01064 
Inspection and Testing 
01064-2 
01071 
Standard References 
01071-6 
01102 
Contractor’s Hazardous Materials Management Program 
01102-4 
01300 
Submittals 
01300-6 
01310 
Progress Schedule 
01310-2 
01380 
Photographs and Video Recordings 
01380-2 
01400 
Public Awareness 
01400-4 
01550 
Contractor’s Utilities 
01550-2 
01560 
Environmental Controls 
01560-8 
01700 
Restoration of Improvements 
01700-2 
01999 
Reference Forms 
01999-12 
 
 
DIVISION 2 – SITE WORK 
 
02100 
Traffic Control 
02100-2

_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
TOC - 2 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[This page intentionally left blank for double sided printing]

SECTION 01010 
SUMMARY OF WORK 
______________________________________________________ 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
01010 - 1 
 
PART 1 - GENERAL  
  
1.01 
SCOPE  
  
A. All construction shall be provided in accordance with the requirements of the 2015 City 
of Glendale Engineering Design Standards & Details and the 2024 revision to the 2024 
Maricopa Association of Government (MAG) Standard Specifications and Details for 
Public Works Construction. 
  
B. The Contractor shall provide all materials, equipment, and labor necessary to realign 
the waste activated sludge line as described in the project Drawings and Technical 
Specifications. 
 
C. Major work to be performed under this contract includes, but is not limited to the 
following:   
1. Provide traffic control as necessary for waste activated sludge line realignment. 
Traffic control plans shall be submitted to the City for approval and receive a traffic 
control permit prior to construction activities. 
2. Restore area disturbed by construction activities back to pre-construction 
conditions. 
3. Provide coordination with Public Outreach Consultant provided by the City for 
notification of construction activities to the general public, if applicable. 
4. Coordinate work activities with adjacent businesses, public events and special 
needs (e.g. medical and emergency response). 
5. Maintain access to private properties including sidewalks and driveways during the 
course of the work.  
 
1.02 
UTILITIES  
  
A. The Contractor shall field locate and verify the horizontal and vertical location of all 
pipe along with wet and dry utilities prior to conducting any excavation work.  
  
B. The Contractor is required to contact Arizona 811, formerly Blue Stake, at 811 at least 
two (2) working days prior to start of any excavation.  
  
C. Quarter Section maps of the City’s sanitary sewer collection system are available upon 
request from the City. It shall be the responsibility of the Contractor to coordinate and 
obtain copies of these maps. The Contractor shall not solely rely upon the information 
contained in the mapping and shall field verify for accuracy.

SECTION 01010 
SUMMARY OF WORK 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
01010 - 2 
 
1.03 
FLOW CHARACTERISTICS  
  
A. The waste activated sludge pipeline receives flows from the Arrowhead Ranch Waste 
Reclamation Facility. The Contractor shall coordinate with the treatment facility to 
allow all treatment processes to be maintained by the City and to transport the sludge 
from Arrowhead Ranch Waste Reclamation Facility to its discharge point for the 
duration of the project.    
 
 
 
PART 2 - PRODUCTS  
(NOT USED)  
  
PART 3 - EXECUTION 
 (NOT USED) 
 
** END OF SECTION *

SECTION 01014 
WORK SEQUENCE 
_____________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01014 - 1 
 
PART 1 - GENERAL  
  
1.01 
CONTINUITY OF PUBLIC AND PRIVATE FACILITY OPERATIONS  
  
Work under this Contract shall be planned, scheduled and performed to minimize 
disruption to the operation of existing business, facilities, surrounding residents and the 
traveling public. The Contractor shall provide all equipment and facilities necessary to 
maintain flow through and/or around existing facilities. Contractor shall be responsible for 
traffic control to redirect the flow of traffic through and/or around the work area, including 
pedestrian traffic. 
  
1.02 
PROJECT COMPLETION  
  
The project shall be completed within the contract time as outlined in the Construction 
Contract.  
 
1.03 
PROJECT CONSTRUCTION COORDINATION 
  
A. At the Pre-construction Meeting, the Contractor shall designate a Representative who 
will be on the job and available for communication at all times for the duration of the 
construction contract. The Contractor’s Representative shall be available 24 hours a 
day by mobile telephone, home telephone, or other means acceptable to the City or 
City’s Representative. The Contractor’s Representative shall be the contact person 
representing the Contractor and shall be capable of giving direct field orders as the need 
arises. Official job communication shall be conducted between Contractor’s 
Representative and the City.  
  
B. The Contractor shall obtain written approval from the City’s Representative 72 hours 
in advance of any change in the Contractor’s daily work schedule. Work performed at 
times other than the approved schedule must first be approved by the City’s 
Representative, except in case of emergency.  
  
C. The Contractor’s Representative shall attend construction progress meetings on a 
weekly basis or as scheduled by the City’s Representative.  Location of the meetings 
shall be determined by the City’s Representative. The Contractor shall present and 
distribute copies of a three-week look-ahead schedule, report on status of any resident 
concerns reported, any Traffic Control Plan updates, and upcoming construction 
activity coordination.  
 
D. The Contractor’s Representative shall be responsible for coordination of the work 
schedule. It shall be the responsibility of the Contractor to sequence work to resolve 
conflicts with ongoing adjacent construction (if any), and schedule work accordingly 
to minimize disruption. The City will not entertain Contractor claims for additional

SECTION 01014 
WORK SEQUENCE 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01014 - 2 
 
compensation arising out of construction delays caused by adjacent construction work. 
City may at its sole discretion grant an extension of contract time due to unforeseen 
delays caused by adjacent construction activity conflicts. 
 
1.04 
SCHEDULING AND SEQUENCING CONSTRAINTS  
  
 
A. The Contractor shall realign the waste activated sludge (WAS) line identified in the 
Construction Documents. Once construction activities commence, the Contractor shall 
continue uninterrupted until all work identified is completed.  
B. No construction activities shall begin on-site until a plan to coordinate with the City to 
transport waste sludge from the Arrowhead Ranch Water Reclamation Facility is 
submitted to the City and approved.   
C. No construction activities shall begin on-site until all required submittals are 
transmitted to the City or City’s Representative and returned stamped with “No 
Exceptions Taken” or “Make Corrections Noted”.  
D. The Contractor shall receive written approval from the property owner of equipment 
storage sites and/or corridors used for facility access (if any). Maps depicting 
locations of the equipment storage sites and copies of signed agreements shall be 
submitted to the City’s Representative prior to occupancy. 
E. Traffic control shall remain in effect as dictated by the approved Traffic Control Plan 
and Permit until all work is completed and inspected. Contractor shall maintain access 
to all private properties within the project area on a 24-hour basis unless written 
approval is otherwise obtained from property(s) owners for reduced access. Copies of 
all written approvals shall be provided to the City or City’s Representative prior to 
work commencing. Refer to Technical Specification Section 02100 – TRAFFIC 
CONTROL.  
F. Odor control shall be provided at all times during the construction work. The odor 
control plan shall be submitted to the City’s Representative at the project progress 
meeting prior to commencement of work within the individual work area.  
G. The Contractor shall perform a detailed inspection of the work to confirm completion 
of all work items and conformance to the project Technical Specifications. Final 
inspection of the work will be carried out by the City or City’s Representative after 
receipt of the Contractor’s written request for final inspection.  
H. After receipt of the Contractor’s written notice of work completion, the City or City’s 
Representative will perform a detailed inspection and will create a punch list of 
omissions and defects observed. Punch list items shall be promptly corrected by the 
Contractor. The Contractor shall then schedule a time for the final inspection by the 
City or City’s Representative upon satisfactory completion of the punch list items. All 
costs associated with additional inspections after the final inspection, including the 
City’s Representative’s time and inspection costs, shall be the responsibility of the 
Contractor.

SECTION 01014 
 
 
WORK SEQUENCE 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01014 - 3 
 
 
 
 
1.05 
CONTRACTOR WORK HOURS  
  
A. The Contractor shall ensure adequate resources are available to complete all work 
within regular business hours per City of Glendale-Code of Ordinances Chapter 25, 
Part V.25-68 Construction of Buildings and Other Projects, unless an appropriate 
permit has been obtained beforehand from the City.  
 
B. Work at night to minimize disruption to area residents or businesses may be required. 
It shall be the responsibility of the Contractor to apply for the necessary permits for the 
extended work hours. 
  
PART 2 - PRODUCTS  
(NOT USED) 
  
PART 3 - EXECUTION  
(NOT USED) 
 
 
 
 
 ** END OF SECTION **

SECTION 01014 
WORK SEQUENCE 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01014 - 4 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[This page intentionally left blank for double sided printing]

SECTION 01015  
CONTRACTORS USE OF PREMISES 
  
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
              01015 - 1 
 
 
PART 1- GENERAL  
  
1.01 
OWNER’S RESPONSIBILITIES  
  
A. The City of Glendale operations personnel is responsible for operating the existing 
sewers, WAS line and facilities throughout the execution of this Project.   
 
1.02 
CONTRACTOR’S RESPONSIBILITIES  
  
A. Sewage treatment and WAS disposal shall remain in operation throughout the 
performance of this Project. All coordination between the City’s operations personnel 
and the Contractor on all matters shall be through the City’s Representative unless 
otherwise approved in writing by the City.  
 
1.03 
USE AND OPERATION OF EXISTING FACILITIES 
 
A. All costs, coordination, permits, and fees associated with the location of staging areas, 
material storage, equipment storage, and site trailer location (if applicable) shall be the 
responsibility of the Contractor. The Contractor shall submit copies of individual 
landowner agreements (if present) to the City. All disturbed areas shall comply with 
the dust control permit required by Maricopa County Air Quality Department as 
specified in Technical Specification Section 01062 – PERMITS AND EASEMENTS.  
 
1.04 
TRAFFIC:  
  
A. The Contractor shall comply with Technical Specification Section 02100 – TRAFFIC 
CONTROL. 
  
1.05 
DAMAGE TO EXISTING PROPERTY  
  
A. Contractor shall be responsible for any damage to existing structures, piping, work, 
materials, or equipment caused by its operations, and shall repair or replace any 
damaged structures, piping, work, materials or equipment, etc., to the satisfaction of 
the City, and at no additional cost to the City.  
 
B. Contractor shall protect all existing structures and property from damage.  
  
C. Contractor shall be responsible for all damage to streets, roads, curbs, sidewalks, 
walking trails, driveways, ditches, embankments, drainages, floodways, landscaping, 
or other public or private property, which may be caused by the work including 
transporting equipment, materials, or workers to or from the work. Contractor shall 
make satisfactory and acceptable arrangements with the agency having jurisdiction 
over the damaged property concerning its repair or replacement and/or as specified in

SECTION 01015  
CONTRACTORS USE OF PREMISES  
 
                                                            
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
              01015 - 2 
 
these Technical Specifications.  
  
D. Contractor shall be responsible for any and all damage to private property as caused by 
the Contractor’s operations including but not limited to waste sludge and sewage 
spills/backups.  
 
1.06  RESIDENT SERVICES 
 
 
PART 2 - PRODUCTS  
NOT USED   
 
PART 3 - EXECUTION  
NOT USED  
 
 
 
 
** END OF SECTION **

SECTION 01060 
HEALTH AND SAFETY 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
              01060 - 1 
 
 
PART 1 - GENERAL  
  
1.01 
HEALTH AND SAFETY REGULATIONS  
  
A. The Contractor shall exercise precaution at all times for the protection of persons 
(including employees) and property. The Contractor shall comply with the provisions 
of all applicable laws, pertaining to such protection including all federal, state and local 
occupational safety and health acts, codes, standards and regulations promulgated 
thereunder. Contractor shall have copies of, but not limited to, confined space entry 
permit on-site and available for review any time work activities are commencing.  
  
B. Contractor shall comply with the provisions of the Federal Occupational Safety and 
Health Act, as amended.  
 
C. Contractor shall comply with the provisions of the Maricopa County Air Quality 
Department.  
 
D. The Contractor shall provide and maintain in a neat, sanitary condition such 
accommodations for the use of the employees as may be necessary to comply with the 
requirements and regulations of the Arizona Department of Health Services and/or as 
specified by the Maricopa County Public Health Department, Sanitary Code.  
  
E. The Contractor shall provide all safeguards, safety devices and protective equipment 
and take any other needed actions reasonably necessary to protect the life and the health 
of employees on the job, the safety of the public, and to protect property in connection 
with the performance of the work covered by this contract.  
  
1.02 
SPECIAL CONSIDERATIONS  
  
A. GENERAL 
 
This Technical Specification Section describes certain minimum precautions the 
Contractor shall consider in developing its health and safety program. It supplements 
the regulatory requirements of Paragraph 1.01 and the requirements of the General 
Conditions. WAS line appurtenant vault structures are considered confined spaces and 
are subject to federal, state, and local regulations governing confined space entry and 
safety procedures.   
  
B. INFECTIOUS DISEASES:  
  
Contractor should anticipate that a wide spectrum of disease-producing organisms will 
be present in the sewer. In addition to the requirements set forth in the regulations 
described in Paragraph 1.01 above, the Contractor shall provide the following as a

SECTION 01060 
HEALTH AND SAFETY 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
              01060 - 2 
 
minimum:  
 
1. Instruction in appropriate disease-prevention mechanisms and personal sanitation 
practices for all workers and supervisors.  
  
2. A preventative inoculation program (tetanus/diphtheria, hepatitis, etc.) to all 
workers and supervisors.  
  
3. Clothing to protect against infection, including rubber boots with full sole and heel 
steel insert-liners, safety glasses or goggles, and gloves to all workers and 
supervisors.  
 
C. DANGEROUS GASES AND OXYGEN DEFICIENCY:  
  
WAS line vault structures are confined spaces, which mean they have a limited means 
of egress and may be subject to the accumulation of dangerous gases or oxygen 
deficiency. Volatile petroleum products and common household hazardous materials 
may be present within the WAS line. Explosive gases, such as methane generated from 
decomposing organic material, may be accumulated. Toxic gases, such as hydrogen 
sulfide, may be present in life-threatening concentrations.  Significant oxygen depletion 
may occur. In addition, construction procedures may require combustion engine 
machinery to be located in or near the work site. Therefore, gaseous combustion by-
products, such as carbon monoxide, may be present.    
  
In addition to the requirements set forth in the regulations described in Paragraph 1.01 
above, the Contractor shall provide the following:  
  
1. Portable atmospheric monitors that measure levels of oxygen, explosive gas 
(methane), carbon monoxide, and toxic gas (hydrogen sulfide). Monitors shall be 
properly calibrated and carefully maintained throughout the construction period.  
Monitors shall be used continuously while personnel are in confined spaces.  
  
D. TOXIC CHEMICALS:  
  
Toxic chemicals may be part of the construction process. The Contractor shall abide by 
all handling procedures recommended by the manufacturer when dealing with toxic 
chemicals.  
  
1.03 
SUBMITTALS  
  
Contractor shall submit a Health and Safety Plan according to Technical Specification 
Section 01300 – SUBMITTALS. The City does not approve Contractor safety plans but 
can issue stop work orders to the contractor if an unsafe condition has been observed.

SECTION 01060 
 
 
HEALTH AND SAFETY 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
              01060 - 3 
 
PART 2 - PRODUCTS  
  
2.01 
HEALTH AND SAFETY PLAN  
  
A. GENERAL  
  
The Contractor shall develop and maintain for the duration of the Contract three copies 
of a Health and Safety Plan that will effectively incorporate and implement all required 
health and safety precautions. At least one copy shall be located on the Contractor's 
work site.  
  
B. COMPLIANCE 
  
The Contractor shall appoint an on-site employee who is qualified, trained and 
authorized to supervise and enforce compliance with the Health and Safety Plan. The 
Contractor is responsible for ensuring that necessary gas monitoring, protective 
clothing, and other supplies and equipment as specified are available to implement this 
Plan.  
  
C. REVISIONS 
  
In the event that regulatory agencies or jurisdictions determine the Health and Safety 
Plan to be inadequate to protect employees and the public:  
  
1. The Contractor shall stop the work in progress until adequate safety measures are 
implemented.  
  
2. The Contractor shall modify the Plan to meet the requirements of said regulatory 
agencies, jurisdictions, and the City.  
  
3. The Contractor shall notify the City and the City’s Representative immediately 
when a notification of deficiency is issued by another agency and/or jurisdiction. 
 
4. The Contractor shall provide the City and City’s Representative with the revisions 
to the Plan within two (2) days of the notice of deficiency.  
 
D. MINIMUM CONSIDERATIONS  
  
The Health and Safety Plan shall, as a minimum, include the following considerations:  
  
1. Objective.  
  
2. Key personnel and responsibilities.  
  
3. Hazard analysis of the work activities and environment.

SECTION 01060 
HEALTH AND SAFETY 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
              01060 - 4 
 
  
4. Training requirements, including contractor’s and sub-contractor’s authorized 
personnel and qualifications for work in confined spaces.  
  
5. Personal protective equipment.  
  
6. Confined Space Entry Plan. 
 
7. Fall protection plan and tie-off points. 
  
8. Site control measures.  
  
9. Work practices, decontamination procedures, and work limitations.  
  
10. Emergency procedures, including sewer evacuation plan, location of first aid, fire 
extinguishers, eyewash, drinking water, map showing route to nearest medical 
facility, list of key personnel who are currently certified in first aid/CPR.  
  
11. Job site cleanup, and spill containment and cleanup procedures.  
  
12. Telephone numbers:  
a. 24-hour number to contact Contractor's Representative.  
b. Emergency services. 
c. City’s Project Manager. 
d. City’s Representative.  
  
13. Documentation (training, injury or illness, respirator-fit tests, hazards notification 
log, etc.).  
 
PART 3 - EXECUTION  
(NOT USED) 
  
 
** END OF SECTION **

SECTION 01062 
PERMITS AND EASEMENTS 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
              01062 - 1 
 
 
PART 1 - GENERAL  
  
1.01 
EASEMENTS  
  
WAS line and vault structures may be located in the City of Glendale right-of-way or utility 
easements. Contractor shall be responsible to obtain permits or permissions to access all 
applicable areas and to limit construction activities to within these areas. 
 
1.02 
PERMITS TO BE OBTAINED BY THE CONTRACTOR  
  
Contractor shall obtain any additional permits and access agreements required by the work 
and shall pay all costs thereof, including agency inspections. The Contractor shall comply 
with all applicable terms and conditions therein and provide copies to the City’s 
Representative before working in areas covered by those permits. The following permits, 
but not necessarily limited to the following, shall be obtained by the Contractor if 
applicable to the work:  
  
1) 
Occupational Safety and Health Association (OSHA): 
 
a) Confined Space Entry Permit. 
 
 
2) 
Arizona Department of Environmental Quality (ADEQ): 
 
a) Stormwater Pollution Prevention Plan (SWPPP). 
 
 
3) 
Maricopa County Air Quality Department: 
 
a) Dust Control Permit. 
 
 
4) 
City of Glendale:  
 
a) Right-of-Way Permit. 
 
b) Traffic Control Permit. 
 
 
5) 
Others: 
 
a) Debris Disposal Permit(s). 
 
b) as applicable. 
 
1.03 
POSTING  
  
Permits shall be posted (or available for review) at the site of the work at all times work 
is commencing. All permits shall be submitted to the City in accordance with Technical 
Specification Section 01300 – SUBMITTALS.

SECTION 01062 
PERMITS AND EASEMENTS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
              01062 - 2 
 
PART 2 – PRODUCTS 
(NOT USED) 
  
PART 3 - EXECUTION 
(NOT USED) 
 
 
 
 
** END OF SECTION **

SECTION 01064 
INSPECTION AND TESTING 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
              01064 - 1 
 
PART 1 - GENERAL  
  
1.01  INSPECTION AND TESTING OF MATERIALS  
  
All workmanship and materials shall be subject to inspection by the City or City’s 
Representative, who may select samples of materials in such a quantity as the City’s 
Representative may deem necessary to determine their qualities, as herein specified. Any 
samples taken shall be at the discretion of the City and shall be in addition to those required 
to be taken by the Contractor as specified in these Technical Specifications, manufacturer’s 
recommendations, and permits requiring test results. The City or City’s Representative will 
accept or reject the materials in accordance with the results of such trials or from test results 
submitted from an independent testing laboratory. All rejected materials shall be promptly 
replaced to the satisfaction of the City or City’s Representative. The Contractor shall assist 
the City or City’s Representative by providing access to the location where the work is in 
progress. The Contractor shall replace rejected work and materials and bear all costs for 
doing so.  
 
 
Non-rejection or non-inspection of materials does not constitute acceptance by the City or 
the City’s Representative. 
  
 
The City or City’s Representative inspection will be provided on an 8-hour per day, 5-day 
per week basis, excluding weekends and holidays. The Contractor shall not schedule any 
overtime work which requires inspection or material testing without written permission 
from the City or City’s Representative two (2) working days before the proposed overtime 
work. The City reserves the right to deny the requested overtime. If an overtime request is 
denied, the City may extend the contract time at no additional cost to the City.  
  
1.02  SPECIAL INSPECTIONS 
  
Special inspections will be required for attaching the WAS line and casing pipe to the 
bridge.  The Contractor shall notify the engineer at least 48 hours in advance of structural 
work. 
 
PART 2 - PRODUCTS  
(NOT USED) 
  
PART 3 - EXECUTION  
(NOT USED) 
 
 
** END OF SECTION **

SECTION 01064 
INSPECTION AND TESTING 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
              01064 - 2 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[This page intentionally left blank for double sided printing]

SECTION 01071  
STANDARD REFERENCES 
_ 
 
 
 
 
 
 
 
 
 
 
 
_ 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01071 - 1 
 
PART 1 - GENERAL  
  
1.01  ABBREVIATIONS  
  
Wherever used in the Contract Documents, the following abbreviations will have the 
meanings listed:  
  
AAC  
Arizona Administrative Code  
 
1700 West Washington, 7th Floor  
 
Phoenix, AZ  85007-2808  
  
AASHTO  
American Association of State Highway and Transportation 
Officials  
 
444 North Capitol Street, N.W., Suite 249  
 
Washington, D.C. 20001  
  
ACI    
American Concrete Institute  
 
38800 Country Club Drive  
 
Farmington Hills, MI 48331-3439 
  
ADEQ  
Arizona Department of Environmental Quality  
 
1110 West Washington Street  
 
Phoenix, AZ 85007 
  
ADOT  
Arizona Department of Transportation  
 
206 South 17th Avenue  
 
Phoenix, AZ 85004  
  
ADWR  
Arizona Department of Water Resources  
 
3550 North Central Avenue, Suite 200  
 
Phoenix, AZ 85012 
 
  
AEIC  
Association of Edison Illuminating Companies  
 
600 North 18th Street  
 
Birmingham, AL 35203  
  
AISC 
American Institute of Steel Construction, Inc.  
 
130 East Randolph, Suite 2000 
 
Chicago, IL 60601 
 
AISI    
American Iron and Steel Institute  
 
25 Massachusetts Avenue, N.W., Suite 800  
 
Washington, D.C. 20001

SECTION 01071 
STANDARD REFERENCES 
 
 
 
 
 
 
 
 
 
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01071 - 2 
 
 
Ameron  
Ameron International Protective Lining Products 
 
8000 Research Forest Drive 
 
Suite 115-118 
 
The Woodlands TX 77382 
  
ANSI  
American National Standards Institute, Inc.  
 
1899 L Street, N.W., 11th Floor  
 
Washington, D.C. 20036  
  
API    
American Petroleum Institute  
 
1220 L Street, N.W.  
 
Washington, D.C. 20005  
  
ASCE  
American Society of Civil Engineers  
 
1801 Alexander Bell Drive  
 
Reston, Virginia 20191  
  
ASCII  
American Standard Code for Information Interchange  
 
United States of America Standards Institute   
 
10 East 40th Street  
 
New York, NY 10016  
  
ASTM  
American Society for Testing and Materials  
 
100 Barr Harbor Drive 
 
P.O. Box C700 
 
West Conshohocken, PA 19428-2959 
 
AT & SFRR 
Atchison, Topeka and Santa Fe Railroad 
  
AWS  
American Welding Society  
 
8669 N.W. 36th Street, Suite 130  
 
Miami, FL 33166-6672 
  
AWWA  
American Water Works Association  
 
6666 West Quincy Avenue  
 
Denver, CO 80235  
  
BOCA    
Building Officials and Code Administrators  
 
7926 Halstead  
 
Homewood, IL 60430

SECTION 01071  
 
 
STANDARD REFERENCES 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01071 - 3 
 
CFR  
Code of Federal Regulations  
 
Superintendent of Documents  
 
Government Printing Office  
 
Washington, D.C. 20402  
  
CMAA 
Crane Manufacturers Association of America, Inc.  
 
(Formerly called: Overhead Electrical Crane Institute) (OECI)  
 
8720 Red Oak Boulevard, Suite 201 
 
Charlotte, NC 28217-3992 
  
CRSI  
Concrete Reinforcing Steel Institute  
 
933 North Plum Grove Road  
 
Schaumburg, IL  60173-4758 
 
COG 
City of Glendale 
 
5850 W. Glendale Avenue 
 
Glendale, Arizona 85301 
  
EEI   
Edison Electric Institute  
 
701 Pennsylvania Avenue, N.W.  
 
Washington, D.C. 10016  
  
FEDSPEC  
Federal Specifications  
 
General Services Administration  
 
Specification and Consumer Information   
 
Distribution Branch  
 
Washington Navy Yard, Building 197   
 
Washington, DC 20407  
  
FEDSTDS  
Federal Standards  
 
(see FEDSPECS)  
 
FCDMC 
Flood Control District Maricopa County 
 
2801 West Durango Street 
 
Phoenix, AZ 85009 
  
IES    
Illuminating Engineering Society  
 
120 Wall Street, Floor 17  
 
New York, NY 10005-4001  
  
MAG  
Maricopa Association of Governments  
 
302 North 1st Avenue, Suite 300  
 
Phoenix, AZ 85003

SECTION 01071 
STANDARD REFERENCES 
 
 
 
 
 
 
 
 
 
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01071 - 4 
 
MCESD 
Maricopa County of Environmental Services Department 
 
1001 North Central Avenue, Suite 200 
Phoenix, AZ 85004 
 
NACE  
National Association of Corrosion Engineers  
 
15835 Park Ten Place  
 
Houston, TX 77084  
  
NASSCO  
National Association of Sanitary Service Companies  
 
2470 Longstone Lane, Suite M 
 
Marriottsville, MD 21104  
  
NFPA  
National Fire Protection Association  
 
1 Batterymarch Park 
 
Quincy, MA 02169-7471 
 
NPDES  
National Pollutant Discharge Elimination System  
 
U.S. Environmental Protection Agency 
 
National Pollutant Discharge Elimination System Program  
 
Office of Water, Office of Wastewater Management 
 
1200 Pennsylvania Avenue, N.W. (Mail code 4203M)  
 
Washington, D.C. 20460  
  
OSHA   
Occupational Safety and Health Act 
 
U.S. Department of Labor 
 
Occupational Safety and Health Administration  
 
200 Constitution Avenue, N.W.  
 
Washington, D.C. 20210  
 
RID 
Roosevelt Irrigation District 
 
103 West Baseline Road 
 
Buckeye, AZ   85326 
   
SWPPP  
Storm water Pollution Prevention Plan 
 
Environmental Protection Agency, Region 9  
 
75 Hawthorne Street,  
 
San Francisco, CA  
  
UBC  
Uniform Building Code 
 
Published by ICBO  
  
UL  
Underwriters Laboratories Inc. 
 
207 East Ohio Street  
 
Chicago, IL 60611

SECTION 01071  
 
 
STANDARD REFERENCES 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01071 - 5 
 
  
WABO  
Washington Association of Building Officers  
 
Post Office Box 7310  
 
Olympia, WA 98507  
 
 
PART 2 - PRODUCTS  
(NOT USED) 
 
  
PART 3 - EXECUTION  
(NOT USED) 
 
 
 
  
** END OF SECTION **

SECTION 01071 
STANDARD REFERENCES 
 
 
 
 
 
 
 
 
 
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01071 - 6 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page left intentionally blank for double sided printing ]

SECTION 01102 
CONTRACTORS HAZARDOUS MATERIALS  
MANAGEMENT PROGRAM 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01102 - 1 
 
PART 1 - GENERAL  
 
1.01 
DESCRIPTION 
 
A. The Contractor shall Comply with all Federal, State, and local rules and regulations 
related to environmental protection and environmental safety including, but not limited 
to, the following: 
 
1. Title 29 Code of Federal Regulations Parts 1910, Occupational Safety and Health. 
 
2. Title 40 Code of Federal Regulations, Protection of Environment. 
 
3. Title 49 Code of Federal Regulations, Transportation. 
 
4. State Occupational Safety and Health Administration (OSHA). 
 
5. Arizona Department of Environmental Quality (ADEQ). 
 
6. Arizona Department of Water Resources (ADWR). 
 
7. Maricopa County Air Pollution Control Regulations. 
 
8. Maricopa County Air Quality Department Regulations. 
 
B. In order to ensure the City that the Contractor is complying with the intent of the 
regulations stated in Paragraph 1.01.A above, as they relate to the on-site use of 
hazardous materials, hazardous wastes and other substances similarly defined in those 
regulations, develop and maintain a Contractor’s Hazardous Materials Management 
Program that includes as a minimum, but is not limited to the requirements specified 
herein. The interests of the City are that accidental spills, site contamination, and injury 
of personnel on the site are avoided. The City will not enforce suspected violations of 
the rules and regulations referenced in Paragraph 1.01.A above, however the City will 
notify the Contractor of suspected violations. If in the opinion of the City, the 
Contractor fails to address the suspected violations in a timely and appropriate manner, 
the City will notify federal, state, or local regulatory agencies, report the suspected 
violations to them, and request that they inspect the Contractor’s operations. Any fines 
that may be levied against the City for violations committed on the site by the 
Contractor, as well as any costs associated with cleanup of materials, shall be paid by 
the Contractor or compensation to the Contractor shall be reduced by equal amount to 
reimburse the City. All documents required by the program shall be made available to 
the City’s Environmental Representative immediately, upon request.

SECTION 01102 
CONTRACTORS HAZARDOUS MATERIALS  
MANAGEMENT PROGRAM 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01102 - 2 
 
 
C. Responsibility for any hazardous waste, as defined in any of the above listed 
regulations, and those generated by the Contractor, belongs to the Contractor. If the 
Contractor is going to generate, or has generated, a substance that qualifies as a 
hazardous waste, Contractor must obtain an Environmental Protection Agency (EPA) 
identification number, listing the Contractor’s name and construction site address as 
the generator of the hazardous waste. Responsibility for the identification, analysis, 
profiling, transport and disposal of hazardous wastes generated, belongs to the 
Contractor. The identification number can be obtained from ADEQ. This number shall 
be provided to the City’s Representative within five (5) days after the Notice to 
Proceed, or before any hazardous materials are brought onto the site. 
 
1.02 
HAZARDOUS MATERIALS PROGRAM REQUIREMENTS 
 
A. Within the regulations listed in Paragraph 1.01.A, above, terms such as hazardous 
material, hazardous wastes, and similar terms have varying definitions. To dispel 
confusion regarding what materials fall under the Program Requirements and for the 
purposes of this section, Hazardous Material is defined as “any material, whether solid, 
semi-solid, liquid, or gas, which, if not stored or used properly, may cause harm or 
injury to persons through inhalation, ingestion, absorption or injection, or which may 
negatively impact the environment through the use or discharge of the material on the 
ground, in the water (including groundwater), or to the air.” 
 
B. All chemicals brought onto the site must be approved by the City. Prior to bringing any 
chemical on site, request approval from the City’s Environmental Representative for 
each chemical the Contractor proposes to bring on site. At the time of request, the City’s 
Environmental Representative may request and receive from the Contractor, specific 
information associated with each chemical. The specific information may include, but 
is not limited to, SDS, manufacture, vendor, container size(s), number of containers, 
minimum and maximum volume of material intended to be stored on site, as well a 
description to the process or procedures in which any requested chemical is to be used. 
The City, within five (5) working day from receipt of the specific chemical information, 
will inform the Contractor as to whether the chemical has been approved for use on 
site. 
 
C. Maintain on site two notebooks containing (1) a chemical inventory, and (2) current 
(dated within the past two years) Safety Data Sheets (SDS) for all materials being used 
on site, whether or not they are defined as a Hazardous Material in Paragraph 1.02.A, 
above. One notebook shall be kept in the Contractor’s on-site office and the other shall 
be kept in a location specified by the City’s Environmental Representative. These 
notebooks must be kept up to date as materials are brought onto and removed from the 
site. Copies of SDS sheets for chemicals removed from the site shall be provided to the 
City’s Environmental Representative.

SECTION 01102 
CONTRACTORS HAZARDOUS MATERIALS  
 
 
MANAGEMENT PROGRAM 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01102 - 3 
 
 
D. Develop an emergency/spill response plan, for each hazardous material or class/group 
of materials. As a minimum, the response plan must address the following: 
 
1. Provide a description of equipment on site available to contain or respond to an 
emergency/spill of the material. 
 
2. Notification procedures. 
 
3. Response coordination procedures between the Contractor, the City, and the City’s 
Representative. 
 
4. Provide a Site Plan showing the location of stored hazardous materials and location 
of spill containment/response equipment.  
 
5. Provide a description of the hazardous material handling and spill response training 
provided to the Contractor’s employees. 
 
E. In accordance with applicable Laws and Regulations, properly and safely store all 
hazardous materials, which shall include as a minimum, the following: 
 
1. A designated storage site for hazardous materials that includes secondary 
containment. The site must include barriers to prevent vehicles from colliding with 
the storage containers and offer protection from environmental factors such as 
weather. 
2. Signage in accordance with applicable Laws and Regulations, clearly identifying 
the hazardous materials storage site. 
3. All hazardous materials containers must bear the applicable Hazard Diamonds. 
 
F. Properly label all containers of consumable materials, whether or not they are classified 
as Hazardous Materials under this Section. The name of the Contractor or subcontractor 
shall be stenciled on any container containing a hazardous material and on any 
container over five-gallon capacity containing a non-hazardous material. Any container 
must have a label clearly identifying the contents. If any such unlabeled containers are 
discovered on the site, the City’s Environmental Representative will notify the 
Contractor. Responsibility to remove such containers belongs to the Contractor. 
Containers will be properly labeled or removed from the site within one (1) hour. Any 
containers that are filled from larger containers must also be properly labeled. 
 
G. The City encourages storage of hazardous materials off site until the materials are 
needed on site. 
 
H. Provide all documentation required herein available immediately upon request of the 
City’s Environmental Representative. The Contractor’s Safety Representative will

SECTION 01102 
CONTRACTORS HAZARDOUS MATERIALS  
MANAGEMENT PROGRAM 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01102 - 4 
 
meet at least monthly with the City’s Environmental Representative to review the 
Contractor’s Hazardous Materials Management Program documents, procedures, and 
inspect the storage site and job site to ensure the requirements specified herein are being 
complied with. Also, provide the City’s Environmental Representative and the City’s 
Representative with copies of all permits obtained from environmental regulatory 
agencies. 
 
I. Provide documentation to the City’s Representative and the City’s Environmental 
Representative that the Contractor, subcontractors, or others hired by the Contractor 
making deliveries of hazardous Materials (as defined in Title 49 CFR) to the site are in 
compliance with Title 49 CFR 172.800 – 172.804, which requires each person who 
offers for transportation in commerce or transports in commerce one or more of the 
following hazardous materials, as defined by Title 49 CFR, must develop and adhere 
to a security plan for hazardous materials that conforms to the requirements of this 
subpart. 
 
PART 2 – PRODUCTS 
(NOT USED) 
 
PART 3 – EXECUTION  
(NOT USED) 
 
 
**END OF SECTION**

SECTION 01300 
SUBMITTALS 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01300 - 1 
 
PART 1 - GENERAL  
 
1.01 
GENERAL  
  
Submittals covered by these requirements include manufacturers' information, shop 
drawings, test procedures, test results, samples, requests for substitutions, and 
miscellaneous work-related submittals. The Contractor shall furnish all specifications, 
descriptive data, certificates, samples, tests, methods, schedules, and manufacturer's 
installation and other instructions as specifically required in the contract documents to 
demonstrate fully that the materials to be furnished and the methods of work comply with 
the provisions and intent of the contract documents.  
  
1.02 
CONTRACTOR'S RESPONSIBILITIES  
  
The Contractor shall be responsible for the accuracy and completeness of the information 
contained in each submittal and shall assure that the material, equipment or method of work 
shall be as described in the submittal. The Contractor shall verify that all features of all 
products conform to the specified requirements. Submittal documents shall be clearly 
edited to indicate only those items which are being submitted for review. All extraneous 
materials shall be crossed out or otherwise obliterated. The Contractor shall ensure that 
there is no conflict with other submittals and notify the City’s Representative in each case 
where his submittal may affect the work of another Contractor or the City. The Contractor 
shall coordinate submittals among his subcontractors and suppliers.  
  
The Contractor shall coordinate submittals so that work will not be delayed. The Contractor 
shall coordinate and schedule different categories of submittals, so that one will not be 
delayed for lack of coordination with another. No extension of time will be allowed because 
of failure to properly schedule submittals. The Contractor shall not proceed with work 
relating to a submittal until the submittal process is complete. This requires that submittals 
for review and comment shall be returned to the Contractor stamped "No Exceptions 
Taken" or "Make Corrections Noted."  
  
The Contractor shall certify each submittal document by signing Form 01999-A Submittal 
Transmittal specified in Technical Specification Section 01999 – REFERENCE FORMS 
that the Contractor has reviewed the submittal, verified field conditions, and complied with 
the contract documents.  
  
The Contractor may authorize in writing a material or equipment supplier to deal directly 
with the City’s Representative or with the City with regard to a submittal. These dealings 
shall be limited to contract interpretations to clarify and expedite the work.

SECTION 01300 
SUBMITTALS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01300 - 2 
 
 
1.03 
CATEGORIES OF SUBMITTALS  
  
A. GENERAL  
  
Submittals fall into two general categories; submittals for review and comment, and 
submittals, which are primarily for information only. Submittals, which are for 
information only, are typically specified in the Part 2 - PRODUCTS of the individual 
Technical Specification section.  
  
a. SUBMITTALS FOR REVIEW AND COMMENT: 
  
All submittals except where specified to be submitted as product data for 
information only shall be submitted by the Contractor to the City and/or City’s 
Representative for review and comment.  
  
b. SUBMITTALS (PRODUCT DATA) FOR INFORMATION ONLY  
  
Where specified, the Contractor shall furnish submittals (product data) to the City 
and/or City’s Representative for Information only.  
 
1.04 
TRANSMITTAL PROCEDURE  
  
A. GENERAL 
  
The City or City’s Representative will furnish the Contractor a list of numbers for 
anticipated submittals as specified in the Construction Documents. The list of 
submittals will be marked for review and comment and product data (submittals) for 
information only. The list is not intended to be an all-inclusive list of submittals 
required. Contractor shall coordinate additional submittals and corresponding submittal 
numbers with the City or City’s Representative. 
Unless otherwise specified, all submittals shall be accompanied by Submittal 
Transmittal Form 01999-A specified in Technical Specification Section 01999 – 
REFERENCE FORMS. A separate Transmittal Form shall be used for each specific 
item, class of material, and items specified in separate, discrete sections, for which the 
submittal is required.  Submittals for various items shall be made with a single form 
when the items taken together constitute a manufacturer's package or are so 
functionally related that expediency indicates checking or review of the group or 
package as a whole.  
A unique number, sequentially assigned, shall be noted on the transmittal form 
accompanying each item submitted. Original submittal numbers shall have the 
following format:  "XXX"; where "XXX" is the sequential number assigned by the City 
or City’s Representative. Re-submittals shall have the following format: "XXX-Y"; 
where "XXX" is the originally assigned submittal number and "Y" is a sequential letter

SECTION 01300 
 
 
SUBMITTALS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01300 - 3 
 
assigned for re-submittals, e.g., A, B, or C being the 1st, 2nd, and 3rd re-submittals, 
respectively. Submittal 25B, for example, is the second re-submittal of submittal 25. 
Re-submittals shall include original information with all revisions. 
 
B. DEVIATION FROM CONTRACT  
  
1. The Contractor shall submit a copy of the specification section, with addendum 
updates included, and all referenced and applicable sections with addendum 
updates included, with each paragraph check-marked as follows: 
 
a. Marked to indicate specification compliance. Check marks (√) shall denote full 
compliance with a paragraph as a whole.   
 
b. Marked to indicate requested deviations from specification requirements.  If 
deviations from the specifications are indicated, and therefore requested by the 
Contractor, each deviation shall be underlined and denoted by a number in the 
margin to the right of the identified paragraph, referenced to a detailed written 
explanation of the reasons for requesting the deviation. The City shall be the 
final authority for determining acceptability of requested deviations. The 
remaining portions of the paragraph not underlined will signify compliance on 
the part of the Contractor with the specifications. Failure to include a copy of 
the marked-up specification sections, along with justification(s) for any 
requested deviations to the specification requirements, with the submittal shall 
be sufficient cause for rejection of the entire submittal with no further 
consideration. 
 
2. If the Contractor proposes to provide material, equipment, or method of work, 
which deviates from the Construction Documents, he shall indicate so under 
"Deviation" on Form 01999-A Submittal Transmittal accompanying the submittal 
copies. 
  
C. SUBMITTAL COMPLETENESS  
  
Submittals which do not have all the information required to be submitted, including 
deviations and Contractor’s signature, are not acceptable and will be returned without 
review. The Contractor will be charged an additional cost if a submittal requires three 
or more reviews. (See Sub-section: 1.07 THIRD AND SUBSEQUENT 
SUBMITTALS) 
 
1.05 
REVIEW PROCEDURE  
  
A. GENERAL 
  
Submittals are specified for those features and characteristics of materials, and methods 
of operation, which can be selected, based on the Contractor's judgment of their

SECTION 01300 
SUBMITTALS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01300 - 4 
 
conformance to the specified requirements. Other features and characteristics are 
specified in a manner, which enables the Contractor to determine acceptable options 
without submittals. The review procedure is based on the Contractor's guarantee that 
all features and characteristics not requiring submittals conform as specified. Review 
shall not extend to means, methods, techniques, sequences or procedures of 
construction, or to verifying quantities, dimensions, weights or gages, or fabrication 
processes (except where specifically indicated or required by the contract documents) 
or to safety precautions or programs incident thereto. Review of a separate item, as 
such, will not indicate approval of the assembly in which the item functions.  
  
When the contract documents require a submittal, the Contractor shall submit the 
specified information as follows:  
  
1. Unless otherwise specified, one (1) electronic Copy (.pdf format) of all submitted 
information shall be transmitted with submittals for review and comment.  
 
2. Unless otherwise specified, one (1) electronic Copy (.pdf format) of all submitted 
information shall be transmitted with submittals (Product Data) for information 
only.  
 
B. SUBMITTALS FOR REVIEW AND COMMENT 
  
Unless otherwise specified, within ten (10) calendar days after receipt of a submittal 
for review and comment, the City and/or City’s Representative shall review the 
submittal and return one copy of the electronically marked-up original in PDF format.  
Shop drawing submittals that require markups shall be marked up in red by the City 
and/or City’s Representative. The City and/or City’s Representative will retain the 
original.   
 
The returned submittal shall indicate one of the following actions:  
  
1. If the review indicates that the material, equipment or work method complies with 
the contract documents, submittal copies will be marked "NO EXCEPTIONS 
TAKEN." In this event, the Contractor may begin to implement the work method 
or incorporate the material or equipment covered by the submittal.  
 
2. If the review indicates limited corrections are required, copies will be marked 
"MAKE CORRECTIONS NOTED." The Contractor may begin implementing the 
work method or incorporating the material and equipment covered by the submittal 
in accordance with the noted corrections. A corrected copy shall be resubmitted.  
 
3. If the review reveals that the submittal is insufficient or contains incorrect data, 
copies will be marked "AMEND AND RESUBMIT." Except at his own risk, the 
Contractor shall not undertake work covered by this submittal until it has been 
revised, resubmitted and returned marked either "NO EXCEPTIONS TAKEN" or

SECTION 01300 
 
 
SUBMITTALS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01300 - 5 
 
"MAKE CORRECTIONS NOTED."  
 
4. If the review indicates that the material or work method does not comply with the 
contract documents, copies of the submittal will be marked "REJECTED - SEE 
REMARKS." Submittals with deviations, which have not been identified, clearly 
may be rejected. Except at his own risk, the Contractor shall not undertake the work 
covered by such submittals until a new submittal is made and returned marked 
either "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED."  
  
C. SUBMITTALS (PRODUCT DATA) FOR INFORMATION ONLY:  
  
Such information is not subject to submittal review procedures and shall be provided 
as part of the work under this contract and its acceptability determined under normal 
inspection procedures.  
  
1.06 
EFFECT OF REVIEW OF CONTRACTOR'S SUBMITTALS  
  
Review methods of work or information regarding materials the Contractor proposes to 
provide, shall not relieve the Contractor of his responsibility for errors therein and shall not 
be regarded as an assumption of risks or liability by the City’s Representative and/or the 
City, or by any officer or employee thereof, and the Contractor shall have no claim under 
the contract on account of the failure, or partial failure, of the method of work, material, or 
equipment so reviewed. A mark of "NO EXCEPTIONS TAKEN" or "MAKE 
CORRECTIONS NOTED" shall mean that the City has no objection to the Contractor, 
upon his own responsibility, using the plan or method of work proposed, or providing the 
materials proposed.  
 
1.07 
THIRD AND SUBSEQUENT SUBMITTALS  
  
The cost for third and subsequent submittals shall be borne by the Contractor. The cost of 
reviews for third and subsequent reviews shall be at a rate of $300 per hour and shall be 
charged to the Contractor as a reduction in Contractor’s pay request.  
  
PART 2 - PRODUCTS  
(NOT USED) 
  
PART 3 - EXECUTION  
(NOT USED) 
 
 
**END OF SECTION**

SECTION 01300 
SUBMITTALS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01300 - 6 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[This page intentionally left blank for double sided printing]

SECTION 01310 
PROGRESS SCHEDULE 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01310 - 1 
 
PART 1 - GENERAL  
  
1.01 
DESCRIPTION  
  
This Technical Specification section specifies requirements and procedures for the 
Contractor in preparing schedules. The purpose of the schedule shall be to ensure adequate 
planning and execution of the work by the Contractor, notification and coordination of 
construction activities with the general public, to establish the standard against which 
satisfactory completion of the project shall be judged, to assist the City or City’s 
Representative in monitoring progress and for the assessment of the impact of change 
orders on the Schedule.  
  
1.02 
SUBMITTAL PROCEDURES  
  
The Contractor shall submit a schedule to the City or City’s Representative within ten (10) 
calendar days of receiving Notice to Proceed and prior to Pre-construction meeting (if 
scheduled) with work identifying the duration of mobilization, anticipated time when work 
is to be performed, construction activity sequence and duration, and date of project 
completion. Schedule shall be transmitted to the City or City’s Representative per 
Technical Specification Section 01300 – SUBMITTALS.   
  
PART 2 - PRODUCTS  
  
2.01 
PROGRESS SCHEDULES  
  
A. Contractor shall provide a Schedule to the City and/or City’s Representative.  Schedule 
shall be updated weekly with anticipated activities and durations. Schedule shall also 
list work completed to date.  
 
B. Schedule shall be prepared on computer software (such as Microsoft Project) that 
facilitates schedule updates and electronic distribution such as e-mailing.  
 
C. Special considerations, coordination requirements, etc., as encountered for certain 
areas of the work shall be noted on schedule.  
 
D. Time for completion for each operation shall be shown on the schedule.  
 
E. The schedule duration of each activity shall be based on the work being performed 
during the normal work week with allowances made for legal holidays. The schedule 
shall include a critical path. 
 
F. Dates imposed on the schedule by the Contractor shall not be binding on the City or 
City’s Representative.

SECTION 01310 
PROGRESS SCHEDULE 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01310 - 2 
 
 
G. Failure to include elements of work required for the performance of this Project shall 
not excuse the Contractor from completing the work as described in the Construction 
Documents.  
 
H. Provide a list of the holidays and non-work days applicable to the schedule. 
  
I. Traffic Control concerns may necessitate work during nights, weekends, or holidays. 
 
J. Provide a schedule and narrative summary stating project status so the City and/or 
City’s Representative may use them as a basis for determining the Contractor’s 
compliance with the Technical Specification requirements regarding progress 
payments, contract time extensions, change order prices and impacts, and the overall 
progress of the work. Failure of the Contractor to comply with the requirements of this 
Technical Specification Section may delay the review and acceptance of the progress 
payment requests.  
 
PART 3 - EXECUTION  
  
3.01 
GENERAL  
 
The Contractor and the Contractor’s Field Superintendent shall attend regularly scheduled 
construction progress meetings with the City or City’s Representative and others invited 
by the City or City’s Representative.  
  
3.02 
UPDATES  
  
A. Requests for extensions in time resulting from changes issued by the City shall be 
accompanied by a Time Extension Request - Narrative Report explaining the impacts 
and costs associated with the extension if it were to be granted.  
 
B. If actual progress on the critical path items is observed to deviate from the schedule 
by ten (10) or more days behind, the Contractor shall update and submit a revised 
(updated) schedule. In the case of the work being behind schedule, the Contractor shall 
submit, along with the revised schedule, a written plan for completing the work within 
the milestone and contract times.  
 
 
** END OF SECTION **

SECTION 01380  
PHOTOGRAPHS AND VIDEO RECORDINGS  
 
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01380 - 1 
 
PART 1 - GENERAL  
  
1.01  DESCRIPTION  
  
A. This section specifies digital color photographs and digital video recordings to be taken 
at the ground surface level by the Contractor before and after construction commences. 
These recordings shall clearly document site conditions prior to construction activities 
commencing and again following the completion of construction activities.  
  
1.02  PAYMENT  
  
A. Contractor shall pay costs for photography, video recordings and prints. Parties 
requiring additional photography, video recordings or prints shall invoice and pay 
photographer directly. 
  
1.03 
SUBMITTALS  
  
A. Contractor shall submit the following information for review per Technical 
Specification Section 01300 – SUBMITTALS at the pre-construction conference. 
  
1. Site condition color photographs and video with audio commentary taken prior to 
construction. 
 
PART 2 - PRODUCTS  
  
2.01  GENERAL  
  
A. The color photographs and audio-video recordings are intended for use as indisputable 
evidence in ascertaining the extent of any damage which may have occurred as a result 
of the Contractor's operations and are for the protection of the Contractor and the City, 
and may, at the City’s discretion, be a means of determining whether and to what extent 
damage, resulting from the Contractor's operations, occurred during the Contract work.  
 
B. PHOTOGRAPHS:  
  
Photographs shall be color digital (high resolution) .jpeg format stored on a file sharing 
website or USB media. Submitted media shall indicate the date, name of Project, and 
City where the photographs were taken. Submitted USB media shall contain an 
identification tag along with a Readme Notepad file that contains the date, name of 
Project, and City where the photographs were taken. One (1) copy of each USB shall 
be delivered to the City.

SECTION 01380  
PHOTOGRAPHS AND VIDEO RECORDINGS  
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01380 - 2 
 
C. VIDEO RECORDINGS: 
Video recordings shall be .mpeg format stored on a file sharing website or USB media. 
Submitted media shall indicate the date, name of Project, and City where the videos 
were taken. Submitted USB media shall contain an identification tag along with a 
Readme Notepad file that contains the date, name of Project, and City where the videos 
were taken. The video recordings should contain an audio track, which narrates the 
progression of the video recording through the site. One (1) copy of each USB shall be 
delivered to the City. 
  
PART 3 - EXECUTION  
  
3.01  VIDEO   
  
A. Contractor shall perform video recordings of all areas where the Contractor anticipates 
construction activities to occur, including all staging, storing, working, parking and 
excavation areas. Easements and areas outside of paved roadways are of particular 
interest.  
  
B. After completion of construction and restoration, video recordings shall be taken from 
the same points, in the same direction as the pre-construction examination recording.  
  
3.02  CONSTRUCTION PHOTOGRAPHY  
  
A. Photographs shall be provided of items of special interest and/or special conditions 
during construction.  
  
 
 
**END OF SECTION**

SECTION 01400 
PUBLIC AWARENESS 
______________________________________________________ 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01400 - 1 
 
PART 1 - GENERAL  
  
1.01 
DESCRIPTION  
  
The work under this item consists of informing adjacent property owners regarding the 
impact and schedule of construction work, attendance at public information meeting(s), 
responding to on-site public inquiries along with distribution of public information door 
hanger materials to adjacent property owners as needed, and coordination with the City’s 
Public Information Officer (PIO), Communications and Public Affairs (CAPA) department 
personnel, and City’s Public Outreach Consultant. 
 
The CAPA department shall review all materials for distribution to the public. The 
Contractor shall be responsible for developing and providing to the City the schedule 
outlining the work descriptions, start date, milestones, and duration of work that will be 
distributed to the public per Technical Specification 01310 – PROGRESS SCHEDULE.    
 
Construction information will be distributed to area residents and businesses by the City. 
The Contractor shall be responsible for coordination with the City’s Public Outreach 
Consultant. 
  
1.02 
SUBMITTALS  
  
The Contractor shall submit to the City and/or City’s Representative per Technical 
Specification Section 01300 - SUBMITTALS the following for approval: 
  
1. Schedule outlining construction start date and duration of construction within ten (10) 
days of the Notice to Proceed. 
 
2. Letter containing the name and contact phone number of the Contractor’s on-site 
Representative and stating that this person is duly authorized to act on behalf of the 
Contractor during public relation activities and/or construction problem resolution.  
 
3. The Company logo of the Contractor and any sub-contractors working on the project.  
Contractor shall give the City and/or subconsultant permission and sole discretion to 
reproduce logo on project related documents such as, but not limited to construction 
notices that are distributed to the general public. Company logo shall be provided in 
high resolution digital (.jpeg) format. 
 
1.03 
CONSTRUCTION NOTICES AND DOOR HANGERS  
  
A. The City shall notify properties potentially affected by construction activities by 
distributing a project notification flyer or other electronic, social media, or printed 
means prior to construction occurring.

SECTION 01400 
PUBLIC AWARENESS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01400 - 2 
 
 
 
1.04 
NOTICE OF SERVICE INTERRUPTION  
  
The Contractor shall provide a list to the City and City’s Representative of sewer services 
that may be disrupted due to the construction operations or potential impact from 
construction activities no less than 72 hours prior to service interruption.   
 
1.05 
24-HOUR TELEPHONE HOTLINE  
  
A. The Contractor shall provide the name(s) and contact phone number of the Contractor’s 
on-site Representative who shall be responsible for replying to resident construction 
concerns, damage claims, resident complaints, etc. during construction activities.  
 
The Contractor shall be responsible for coordination with the City’s Public Relations 
department or their Public Outreach Consultant to obtain messages and respond 
accordingly. The Contractor shall provide written response back to the City as to the 
action undertaken for the resolution of the hotline complaint or concern within 24 
hours. 
  
B. A log of telephone and/or on-site contacts of residential complaints shall be maintained 
by the Contractor. The Contractor shall immediately communicate to the City and 
City’s Representative any public issues concerning damage to private property, health 
concerns, nuisances and general complaints. The Hotline Log shall contain at the 
minimum the following information:  
  
Date of Communication. 
Time of Communication. 
Name of Person Receiving the Complaint. 
Contact Name. 
Contact Address. 
Contact Return Telephone Number. 
Description of Complaint or Concern. 
Description of Discussions. 
Description of Proposed Resolution. 
  
C. Hotline Log shall be submitted to City’s Representative within 24 hours of each new 
entry. Summary of all telephone contact shall be submitted to the City and City’s 
Representative at the next construction progress meeting.  
 
1.06 
WORK IN EASEMENTS  
  
A. Work may take place in right-of-way of streets or in easements through private 
property. Access and working space may be limited in easements. Careful attention to 
access and private property protection is required in easements.

SECTION 01400 
 
 
PUBLIC AWARENESS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01400 - 3 
 
 
B. Contractor shall NOT attempt to contact the property owner prior to entering an 
easement. City of Glendale personnel shall be responsible to inform the property owner 
of the details of the work. 
  
C. Contractor shall take surface feature pre-construction videos of easement areas or areas 
potentially impacted by construction activities according to Technical Specification 
Section 01380 – PHOTOGRAPHS AND VIDEO RECORDINGS before beginning 
work. The purpose of these videos is to document existing surface features and 
conditions prior to bringing any equipment into the area or performing any work. 
 
1.07  ON-SITE SUPERINTENDENT  
   
The Contractor shall have a Representative familiar with the work on-site during project 
work hours and shall be available to answer questions received from the public on a 24-
hour basis and assist the public with access needs.   
 
 
PART 2 - PRODUCTS  
 
2.01 
PUBLIC NOTIFICATION 
 
Information provided to the general public shall be determined and produced by the City 
or the City’s Public Outreach Consultant.  Project notification will be distributed by the 
City through printed flyer, door hanger, or other electronic and social media platforms.  
 
 
PART 3 - EXECUTION  
(NOT USED) 
 
** END OF SECTION **

SECTION 01400 
PUBLIC AWARENESS 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01400 - 4 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[This page intentionally left blank for double sided printing]

SECTION 01550  
CONTRACTORS UTILITIES 
  
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01550 - 1 
 
PART 1 - GENERAL  
  
1.01 
DESCRIPTION  
  
A. This section specifies the facilities, utilities, and security the Contractor is required to 
furnish and maintain during construction.  
 
B. Copies of any Contract Documents shall be kept at the work site and available for use 
at all times.  
  
PART 2 - PRODUCTS  
  
2.01  POWER  
  
A. Contractor shall use battery, pneumatic, or hydraulic power for all interior sewer pipe 
work. This limitation is not necessary for work on the surface or for sewer pipe 
illumination.  
  
2.02 
LIGHTING AND ILLUMINATION  
  
A. As necessary, the Contractor shall provide low voltage lighting and illumination in the 
sewer pipe interior, in accordance with the guidelines published in Practice for 
Industrial Lighting, ANSI/IES RP-7-2017. Lighting used by the Contractor on the 
surface shall be placed and directed to avoid nuisance to traffic or local residences. 
Light shields may be required to limit light pollution into adjacent residences or 
businesses. 
  
2.03  TELEPHONE  
  
A. Contractor shall provide and maintain telephone service at the construction site and the 
telephone shall be manned by the Contractor or Contractor’s Representative 24 hours 
per day. Contractor or Contractor’s Representative manning the telephone service shall 
be fluent in written and verbal English as well as Spanish languages. Cellular telephone 
service is acceptable as a substitute for telephone service. These telephone and labor 
costs shall be paid by the Contractor.  
  
2.04  WATER  
  
A. All water for testing, flushing, cleaning and construction activities shall be furnished 
and paid for by the Contractor. Water may be available upon request to the City for 
connecting to the City’s water distribution system. Connection may be approved by the 
City with appropriate backflow prevention and metering devices installed by the 
Contractor according to City requirements. Authorization to receive water may be 
rescinded by the City upon written notice to the Contractor at any time and for any 
reason.

SECTION 01550  
CONTRACTORS UTILITIES  
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01550 - 2 
 
 
The City shall charge the Contractor for water used in performing the above functions 
in accordance with the City’s established rate schedule. At Contractor’s expense, an 
approved water meter and backflow prevention device, meeting the requirements of 
ANSI A40.6, latest revision, shall be installed in each and every connection to the 
City’s water supply. The Contractor shall be required to meter all water used.  
  
2.05  DEBRIS DISPOSAL  
  
A. Contractor shall make provisions for legal, off-site debris disposal. Contractor shall be 
responsible to obtain and submit to the City a written letter of acceptance, signed by an 
authorized representative of the agency and/or authorized party accepting debris.  
Disposal of debris shall not occur until City has reviewed and accepted the disposal 
site. Contractor shall pay all fees and charges for debris disposal. Contractor shall be 
responsible for all permits and fees according to Technical Specification Section 01062 
– PERMITS AND EASEMENTS, subsection 1.02 Permits to be Obtained by the 
Contractor for transport to the disposal site. 
 
B. Contractor shall make provisions for proper disposal of hazardous materials, such as 
asbestos, hazardous chemicals, etc. with appropriate documentation and chain of 
authority for such disposal. 
  
PART 3 - EXECUTION  
  
NOT USED  
   
  
  
**END OF SECTION**

SECTION 01560  
ENVIRONMENTAL CONTROLS  
  
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01560 - 1 
 
PART 1 - GENERAL  
  
1.01 
DESCRIPTION  
  
A. Provide and maintain methods, equipment, and temporary construction, as necessary 
to provide controls over environmental conditions at the construction site and adjacent 
areas.  Remove physical evidence of temporary facilities at completion of work.  
  
1.02 
TRANSPORTATION ROUTES  
  
A. The Contractor shall select its transportation routes for hauling materials, equipment, 
or imported products based on the existing condition of the pipelines and impacts on 
local traffic. Transportation routes shall be documented in a traffic control plan on a 
case by case basis.  
  
1.03 
TRAFFIC CONTROL  
  
A. All streets, traffic ways, and sidewalks shall be kept open in a safe manner for the 
passage of traffic and pedestrians during the construction period unless otherwise 
approved by the City.  
 
B. When required to cross, obstruct or close a street, traffic way, or sidewalk for a short 
duration that is approved by the City, the Contractor shall provide and maintain suitable 
bridges, detours or other approved temporary means for the accommodation of 
vehicular and pedestrian traffic. Closings shall be for the shortest time practical, and 
passage shall be restored immediately after completion of construction.  
 
C. Contractor shall give the City 24 hours advance notice of his proposed operations 
within any public rights-of-way and temporary roadway closings. All proposed 
roadway closings shall be submitted in the Traffic Control Plan and approved prior to 
commencement of operations.   
 
D. Contractor shall provide signs, signals, barricades, lights and all other equipment, 
service and personnel required to regulate and protect all traffic and warn of hazards in 
accordance with MAG specifications. All such work shall conform to requirements of 
the City or authority having jurisdiction. Remove temporary equipment and facilities 
when no longer required and restore grounds to original condition.  
 
E. As specified in Technical Specification Section 02100 – TRAFFIC CONTROL, the 
Contractor shall provide a Traffic Control Plan and implement traffic control around 
all work as part of the contract.  
 
F. Qualified and suitably equipped flaggers shall be used to assist all construction 
equipment and vehicle access to and from the construction site.

SECTION 01560 
ENVIRONMENTAL CONTROLS 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01560 - 2 
 
1.04 
SEWAGE SPILL CONTROL  
  
A. A spill is defined as any uncontrolled release of raw sewage outside of the intended 
sanitary sewer collection system. Raw sewage releases shall not be allowed to occur 
and are not permitted. The Contractor shall be responsible for all consequences and 
damages caused by the overflow, backup, or spill due to the Contractor's work 
activities.  
 
B. Contractor shall give both verbal and written notification to the City immediately in 
the event of any sewage release, overflow, backup, or spill.  
 
C. Contractor shall complete and submit to the City the Confidential Spill Report form 
found in Technical Specification Section 01999 – REFERENCE FORMS within 2 
hours of any spill. 
 
1.05 
EMERGENCY SPILL RESPONSE PLAN  
 
A. The Contractor shall be responsible to develop, submit for approval and follow an 
emergency spill response plan. Plan shall be well communicated to all personnel in the 
event an emergency should occur, it can be handled in the safest and most efficient 
manner possible.  
 
B. The primary responsibility for all Contractor personnel is to respond to sewer spills as 
quickly as possible.  
 
C. Emergency telephone list is part of this procedure and will be kept up-to-date at all 
times.  
 
D. Follow Standard Procedure List.  
 
E. Fill out attached Confidential Spill Reporting Form.  See Technical Specification 
Section 01999 - REFERENCE FORMS.  
 
F. Contractor shall develop an Emergency Spill Response Phone List containing, but not 
limited to the following: 
 
(name) ____  (Contractors Field Superintendent)  
(___) __ - ____ 
(name) ____  (Engineer’s Field  Representative)   
(___) __ - ____ 
(name) ____  (City’s Construction Project Manager)(___) __ - ____ 
(name) ____  (Engineer's Project Manager)  
(___) __ - ____ 
 
Submit list to City according to Technical Specification Section 01300 – SUBMITTALS.   
 
List shall remain current at all times. Any proposed changes shall be provided to the City 
a minimum of 24 hours in advance of the change or within 1 hour if the change is due to 
an emergency.

SECTION 01560 
 
 
ENVIRONMENTAL CONTROLS 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01560 - 3 
 
1.06 
STANDARD REPORTING PROCEDURES  
  
A. HANDLING EMERGENCIES  
 
1. Medical emergency, fire, or explosion, call 911 immediately.  Do not call 911 to 
report a wastewater spill. 
 
B. OBSERVATION 
 
1. Contractor shall obtain enough information to make an initial assessment of the 
situation without endangering themselves.  
 
C. PROTOCOL FOR NOTIFICATION OF SPILL  
 
1. Contractor’s Field Superintendent:  
Contractor’s field personnel shall verbally notify the Contractor’s Field 
Superintendent. 
Field 
Superintendent 
shall 
promptly 
notify 
City 
Representatives immediately, always less than one (1) hour from the time of 
being made aware of the spill. Document all calls and conversations.  
 
D. REPORT 
 
As soon as possible, but no later than 24 hours following discovery of the spill, the 
Contractor shall complete the Form 01999-C Confidential Spill Reporting, reference 
Technical Specification Section 01999 – REFERENCE FORMS. The Contractor shall 
take photographs at all stages of the incident to include in the report. Submit copies of 
all documentation to City per Technical Specification Section 01300 – SUBMITTALS 
except as herein modified. Spill reports shall be hand carried to the City’s 
Representative as soon as complete.  
  
E. SUBMITTAL 
 
The Contractor shall verify that City has received a copy of completed Form 01999-C 
Confidential Spill Reporting and supporting documentation and submitted copy of said 
report to the City’s Representative in a timely manner. Provide all reports and report 
discrepancies to the City’s Representative and retain one (1) copy in the Project File 
located at Contractor’s office.  
 
1.07 
SANITARY SEWAGE SPILL 
  
A. If a sanitary sewage spill occurs and a citizen or business sustains property damage, the 
following procedure is to be adhered to:  
  
1. The initial responsibility of the Contractor is to locate and eliminate the cause of 
the spill as soon as possible. Contractor will obtain an emergency clean-up service 
and relocate the residents, if necessary, to minimize health risks. Contractor shall

SECTION 01560 
ENVIRONMENTAL CONTROLS 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01560 - 4 
 
be responsible for all costs and coordination efforts associated with the sewer spill 
and cleanup including but not limited to:  
 
a. Relocation of residents, businesses, and schools 
b. Temporary housing of displaced residents 
c. Clean-up and sanitizing costs 
d. Replacement of damaged personal items 
e. Relocation of residents back into the residence 
 
 
2. Determine the extent of the property damage (photographs are recommended).  A 
report (Incident Report), with the photos must be provided to the Contractor’s 
designated Safety Officer. The Safety Officer will forward the information to the 
Contractor’s corporate liability insurance carrier. Information compiled should 
include:  
 
a. Time call was received  
b. Time the crew arrived at the site  
c. Time work was completed 
d. Cause of stoppage/source of backup sewage (if possible) and location of 
stoppage causing the backup 
e. Name of property owner/tenant and address of affected property  
f. Extent of damage  
g. Action taken  
  
3. Contractor-authorized personnel will also assist and pay all costs for obtaining and 
coordinating a sub-contractor to perform restoration work and will work with the 
selected sub-contractor to equitably restore the premises to its pre-loss condition.    
  
4. The Contractor’s Superintendent shall notify the City of the stoppage in the sanitary 
sewer pipe.  
  
5. Notify City in the event of any spills. 
 
6. The City of Glendale shall notify Arizona Department of Environmental Quality 
(ADEQ) only as it pertains to Arizona State Law Requirements.  
 
PART 2 - PRODUCTS  
(NOT USED)  
 
PART 3 - EXECUTION  
  
3.01  SITE MAINTENANCE  
  
A. Contractor shall keep the work site, staging areas, storage and parking area, 
Contractor's facilities clean and free from rubbish and debris. Materials and equipment 
shall be promptly removed from the site when they are no longer necessary. Upon

SECTION 01560 
 
 
ENVIRONMENTAL CONTROLS 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01560 - 5 
 
completion of the work and before final acceptance, the work site shall be cleared of 
equipment, unused materials, and rubbish to present a clean and neat appearance in 
conformance with the preconstruction condition of the site.    
 
B. Contractor shall not store equipment or materials anywhere other than locations 
approved by the City. Property surrounding the work site shall be completely free of 
all debris and rubbish at all times.  
 
3.02  CLEAN-UP 
  
A. Waste material of any kind will not be permitted to remain on the site of the work or 
on adjacent streets. Immediately, upon such materials becoming unfit for use in the 
work, they shall be collected, carried off the site and legally disposed of by the 
Contractor. The Contractor shall be responsible for obtaining necessary permits or 
approval for the Contractor's disposal site. 
 
B. The Contractor shall keep all buildings and areas occupied by the Contractor clear of 
all refuse, rubbish and debris that may accumulate from any source and shall keep them 
in a neat condition to the satisfaction of the City.  
 
C. In the event that waste material, refuse, debris and/or rubbish are not so removed from 
the work area by the Contractor, the City reserves the right to have the waste material, 
refuse, debris and/or rubbish removed and the expense of the removal and disposal 
charged to the Contractor. 
 
D. Paints, solvents, and other construction materials shall be handled with care to prevent 
entry of contaminants into storm drains, surface waters, or soils.  
  
3.03.  BARRIERS 
  
A. A barrier shall be provided around all unattended excavations and open structures.  The 
barrier shall enclose the area and prevent unauthorized access.  
  
3.04  STREET CLEANING 
  
A. Contractor shall be responsible for preventing dirt, dust, and sediments from escaping 
from trucks departing the project site, by covering dusty loads, washing truck tires 
before leaving the site, or other reasonable methods. 
 
B. When working trucks and/or other equipment on paved streets and roadways, the 
Contractor will be required to clean said streets as soon as possible, but no later than at 
the conclusion of each day's operations or 24-hour period and at such interim periods 
as required by the City. 
 
C. All streets in the construction area used by Contractor's trucks or any other equipment 
hauling material to and from the area, whether within the Contract limits or adjacent

SECTION 01560 
ENVIRONMENTAL CONTROLS 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01560 - 6 
 
thereto, shall be kept clean by the Contractor and shall be continuously serviced by the 
Contractor's use of water trucks to control dust. 
 
D. Cleaning and dust control shall be as specified in MAG Section 104.1.4 “Cleanup and 
Dust Control” and shall be at the Contractor's expense.  
 
E. Any violation of the requirements shall be sufficient grounds for the City to order the 
streets in question cleaned by others and the cost to be paid by the Contractor.  
 
F. No solid materials or soils may be flushed into storm drains or in the sanitary sewers 
or wastewater facilities.  
 
G. Contractor shall use a power pick-up broom as part of the dust control effort.  
  
3.05  AIR POLLUTION CONTROL  
  
A. GENERAL  
  
The Contractor shall not discharge smoke, dust, and other contaminants into the 
atmosphere that violate the regulations of any legally constituted authority. The 
Contractor shall maintain construction vehicles and equipment in good repair. 
Equipment exhaust emissions that are determined to be excessive by the City shall 
cause the equipment to be repaired or replaced.  
  
B. Contractor shall also minimize dust nuisance by cleaning, sweeping, and sprinkling 
with water, or other means. The use of water, in amounts, which result in mud on public 
streets, is not acceptable as a substitute for sweeping or other methods. Equipment for 
this operation shall be on the job site or available at all times.    
 
3.06  ODOR 
  
A. The Contractor shall employ methods and procedures that mitigate the generation and 
discharge of objectionable odors to the surface environment at all times.  
  
3.08  NOISE CONTROL  
  
A. Contractor shall perform all work in compliance with OSHA standards and in no case 
will noise levels be permitted which would interfere with the work of the City or others. 
Noise levels shall be in accordance with City noise ordinance.  
 
B. Each internal combustion engine, used for any purpose on the job or related to the job, 
shall be equipped with a muffler of a type recommended by the manufacturer for 
residential use. No internal combustion engine shall be operated on the project without 
said muffler.

SECTION 01560 
 
 
ENVIRONMENTAL CONTROLS 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01560 - 7 
 
C. Noisy portable equipment, such as generators, pumps, or compressors, shall be located 
as far away from sensitive noise receptor areas as practical. Sensitive noise receptors 
are defined as occupied buildings with windows or doors facing the site. Noise barriers 
shall be constructed around noisy, stationary, construction equipment such as 
compressors, pumps, or generators that have to be utilized at locations near (within 100 
feet of) sensitive noise receptors as defined above.  
 
D. Idling equipment not actively utilized for extended periods of time shall be shut off.  
  
3.09  TREE AND PLANT PROTECTION  
  
A. If a tree or any landscaped vegetation is damaged or destroyed by construction, or any 
action of the Contractor, the Contractor shall replace the damaged tree or plant with a 
healthy one of the same species. The replacement tree or plant shall be of the same size 
as the damaged tree or plant and will be placed at the existing grade. The Contractor 
shall bear all expenses required to clear and grub the damaged tree or plant and to 
establish the replacement tree or plant. The replacement tree or plant shall be installed 
per City Standard Landscaping Specifications and Details and guaranteed healthy for 
1 year after final completion. The Contractor shall be responsible for any tree or plant 
that the Contractor had replaced that is deemed unhealthy during that year.  
 
B. All landscaped areas and other surface improvements which are damaged by actions of 
the Contractor shall be restored to their original condition at the Contractor's expense.  
When the impact is to private property, the property owner shall confirm acceptance to 
original condition 
 3.10  SURFACE WATER CONTROL  
  
A. Contractor shall conform to the regulations and requirements of legally authorized 
surface water management agencies. The Contractor is responsible to provide and 
maintain any temporary pumping, drainage structures, or other means to manage or 
control nuisance surface water.  
 
B. The Contractor shall be responsible for keeping any open excavations and other areas 
free from water as required to permit continuous progress of, or to prevent damage to, 
its own work or work of others. The Contractor shall cover exposed excavated areas 
and spoil piles when runoff from rain is or would be likely to cause turbid waters to 
enter local waterways. The Contractor shall suspend work in the rain, if such work 
cannot be performed without causing turbid runoff.  
  
3.11  STORM SEWER  
  
A. Contractor shall not discharge any wastewater, potable water used for testing, or 
cleaning, or any chemical or waste materials from the construction operation into the 
storm sewer system.

SECTION 01560 
ENVIRONMENTAL CONTROLS 
 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01560 - 8 
 
3.12 
SANITARY SEWER  
  
A. Contractor shall not dispose of chemical or any waste materials from the construction 
operations into the sanitary sewer system.  
 
 
  
** END OF SECTION **

SECTION 01700  
RESTORATION OF IMPROVEMENTS  
  
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01700 - 1 
 
PART 1 - GENERAL  
  
1.01  GENERAL  
  
This section specifies restoration of improvements of the Contractor's work area, staging 
area, storage area, and parking area.  
  
1.02  STRUCTURES  
  
Contractor shall remove such existing structures as may be necessary for the performance 
of the work and shall rebuild the structures thus removed, with the specified requirements, 
in as good a condition as found. The Contractor shall also repair existing structures that 
workers damage as a result of the work under this Project at no additional cost to the City. 
  
1.03 
ROADS AND STREETS  
  
Unless otherwise specified, roads and streets in which the surface is removed, broken, or 
damaged, or in which the ground has caved or settled during or as a result of the work 
under this Project, shall be resurfaced and/or repaved and brought back to the original grade 
and section or City Standard section, whichever is greater, at the Contractor’s expense. The 
Contractor shall document in video the entire road or street area to be used for the work 
and parking area as specified in Technical Specification Section 01380 – PHOTOGRAPHS 
AND VIDEO RECORDINGS. Copies of the USB storage device shall be submitted to the 
City prior to starting the work. Once construction starts, Contractor assumes responsibility 
for road condition and repair.   
 
Roadways used by the Contractor shall be cleaned and repaired if damaged. Before 
resurfacing and/or repaving material is placed, edges of pavements shall be trimmed back 
far enough to provide clean, solid, vertical faces, and shall be free of loose material. Streets, 
sidewalks, and other City, County, or State-owned facilities impacted by construction 
activities shall be replaced or repaired in accordance with current City and MAG 
requirements.  
  
1.04  CULTIVATED AREAS AND OTHER SURFACE IMPROVEMENTS  
  
A. Cultivated or planted areas, other unpaved areas, and other surface improvements 
which are damaged by actions of the Contractor shall be restored to their original 
condition. In addition to City inspection, the Contractor shall document in video the 
entire area to be used as the work area, staging area, storage area, and parking area as 
specified in Technical Specification Section 01380 – PHOTOGRAPHS AND VIDEO 
RECORDINGS.  
 
B. Contractor shall be responsible for coordination of all irrigation piping and facilities 
located within cultivated areas with appropriate jurisdictional agency. Contractor shall 
protect the work area(s) from uncontrolled irrigation waters that impact the work or

SECTION 01700 
RESTORATION OF IMPROVEMENTS 
 
 
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01700 - 2 
 
work area(s).   City will not entertain damage claims as a result of irrigation water. 
 
C. Repair of irrigation facilities damaged by construction activities shall be the 
responsibility of the Contractor.  Irrigation schedules shall be maintained to sustain 
vegetation health.  Any sod, vegetation, or foliage damaged due through insufficient 
water as a result of construction activities shall be replaced in kind and size to the 
satisfaction of the City by the Contractor at no additional cost to the City.   
 
D. Existing guard posts, barricades, and fences shall be protected and replaced if damaged. 
 
1.05  PROTECTION OF EXISTING INSTALLATIONS  
  
A. Contractor shall protect all existing operating facilities and structures from damage. 
However, if damage occurs, the Contractor shall immediately correct or replace 
existing equipment, materials, or systems that are damaged as a result of its operations 
to the satisfaction of the City.  
   
PART 2 - PRODUCTS  
(NOT USED)  
  
 PART 3 - EXECUTION  
  
3.01  RESTORATION ACCEPTANCE  
  
A. The Contractor shall restore the area to existing condition of the Contractor’s work 
area, staging area, storage area, and parking area as documented in the photographs and 
video recordings.  
 
B. The City shall determine if and when restoration of the site is acceptable following on-
site inspection and review of the pre-construction and post-construction recordings as 
specified in Technical Specification Section 01380 – PHOTOGRAPHS AND VIDEO 
RECORDINGS.   
  
   
** END OF SECTION **

SECTION 01999 
REFERENCE FORMS 
______________________________________________________ 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01999 - 1 
 
PART 1 - GENERAL  
 
1.01 
REQUIRED FORMS  
  
The forms listed below and included in this section are referenced from other Technical 
Specification sections of the contract documents:  
  
Form No.  
Title 
 
 
 
  
01999- A  
Submittal Transmittal  
  
01999- B  
Request for Information  
  
01999- C  
Confidential Spill Reporting  
 
01999- D 
Chain of Custody 
 
1.02 
SCOPE  
  
The Contractor shall be responsible for the documentation forms for tests and evaluations 
required of the contract that do not have specific forms identified.  Contractor generated 
forms shall follow the format established on Form 01999-A Submittal Transmittal 
contained herein.  
  
  
PART 2 - PRODUCTS  
(NOT USED) 
  
  
PART 3 - EXECUTION  
(NOT USED)

SECTION 01999 
REFERENCE FORMS 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01999 - 2 
 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double sided printing ]

SECTION 01999 
 
 
REFERENCE FORMS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01999 - 3 
 
 
FORM 01999-A         SUBMITTAL TRANSMITTAL  
 
 
Submittal Description:    
 
 
 
 
               Submittal No:    
       
  
 
 
 
 
 
 
 
 Spec Section:    
 
  
Routing  
Sent  
Received  
OWNER:               
Contractor  
  
  
PROJECT NUMBER AND NAME:  
Engineer  
  
  
  
Contractor  
  
  
CONTRACTOR:  
  
  
  
  
 
  
We are sending you    
Attached    
 
Under separate cover via         
 ˜ Submittals for review and comment  
 ˜ Product data for information only  
 
Remarks:     
 
  
Item  
Copies  
Date  
Section 
No.  
Description  
Review 
action
a 
Reviewer 
initials  
Review comments 
attached  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
 
aNote:  NET = No exceptions taken; MCN = Make corrections noted; A&R = Amend and resubmit; R = Rejected  
Attach additional sheets if necessary.  
  
Contractor:  Certify either A or B:  
  
 A. We have verified that the material or equipment contained in this submittal meets all the requirements, including 
coordination with all related work specified (no exceptions).  
  
 B. We have verified that the material or equipment contained in this submittal meets all the requirements specified 
except for the attached deviations.  
No. 
  
Deviation 
  
  
                
  
  
                
  
  
               
  
  
  
  
 
Certified by:  ______________________________________________________________  
 Contractor's Signature

SECTION 01999 
REFERENCE FORMS 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01999 - 4 
 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double sided printing ]

SECTION 01999 
 
 
REFERENCE FORMS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01999 - 5 
 
 
FORM 01999-B       REQUEST FOR INFORMATION  
  
RFI NO.     
 
 
OWNER:  
___________________   
ROUTING  
  
SENT  
  
RECEIVED  
PROJECT 
NAME:  
 
  
_________________ 
  
Contractor  
 
 
________              _______________ 
PROJECT 
NUMBER: 
 
 
City 
Representative 
 
 
 
 
 
CONTRACTOR 
  
 
 
 
 
  
  
  
  
 
 
 
 
RFI TITLE:  
  
  
  
    
  
  
  
  
  
  
  
  
REFERENCES:  
DRAWING NO:  
  
LOCATION:  
  
  
SPEC. SECTION:  
  
    PAGE:    
  
OTHERS:  
  
  
  
  
  
  
  
    
  
  
The following information is requested as described below or in the attachments:  
  
  
  
  
  
  
  
  
By:  
  
  
  
  
  
Date:    
  
 
The following information is provided as described below or in the attachments:  
  
  
  
  
  
  
  
  
 
By:  
  
 
Date:

SECTION 01999 
REFERENCE FORMS 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01999 - 6 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double sided printing ]

SECTION 01999 
 
 
REFERENCE FORMS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01999 - 7 
 
FORM 01999-C   CONFIDENTIAL SPILL REPORTING  
  
  
INSTRUCTIONS:  The Contractor shall ensure that appropriate on-site personnel complete 
this form.  The form shall be completed immediately upon discovery of a sanitary sewer spill 
or release by the individual who first made the discovery.  
 
  
First at the Scene (name):  
  
1. Facility name and address/location/intersection (or major cross streets): 
 
 _____________________________________________________________________________ 
   
2. Is/was there a fire or explosion or other release (except for sewage release) outside the facility?    
 
      Yes           No   
 
If yes, immediately contact the Fire Department (911) for assistance, initiate appropriate 
facility response procedures, and then continue with this form.  
  
3. Personal injuries and extent, if any: _______________________________________________ 
 
  
4. Date and time of initial call or complaint:___________________________________________ 
 
  
5. Date and time of spill found or confirmed:__________________________________________ 
 
  
6. Date spill reporting completed:___________________________________________________ 
 
  
7. Date and time spill occurred or started, if known:_____________________________________  
 
  
8. What was spilled?  Describe completely.  List chemical names/wastewater if known.  
 
______________________________________________________________________________ 
  
 9. How much was spilled?  Use units such as gallons or pounds, etc._______________________ 
  
10. Where and how did the spill occur?  Include a description of the container or vessel from which 
the spill occurred.  Attach diagram or map, if available.

SECTION 01999 
REFERENCE FORMS 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01999 - 8 
 
______________________________________________________________________________ 
  
11. Where did the spilled material go?  Check all that apply.  
  
 drywell  
 dry wash  
 canal  
 riverbed  
 private property  
retention basin  
 sanitary sewer  
secondary 
containment  
 storm  drain  
city street  
Air (vapors or 
odors)  
other (specify 
below)  
______________________________________________________________________ 
______________________________________________________________________ 
______________________________________________________________________ 
______________________________________________________________________ 
______________________________________________________________________ 
 
12. How far did the spill travel?  Describe the path the spill took to its final destination.   
 
______________________________________________________________________________  
 
13. Was the spill stopped or contained?  Describe how and by whom.  
 
______________________________________________________________________________ 
  
14. How long did the spill last? _____________________________________________________ 
  
 
15. Who found the spill?  Use the back of this form if necessary.  
  
Name_________________ Title_____________________ Phone________________  
  
a. ____________________        _____________________           ________________ 
 
b.____________________         _____________________           ________________  
 
 
16. Who was notified of the spill?  List names and identify how notification was made (phone call, 
fax, etc.  Use the back of this form if necessary).  
 
Name Department/Division/Agency       Date/Time Notified   Method of Notification  
 
a.___________________________        _______________     ___________________

SECTION 01999 
 
 
REFERENCE FORMS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01999 - 9 
 
b.___________________________        _______________     ___________________  
  
Printed name and signature of person who completed this form:  
  
 
 
Printed Name_______________________Title___________________Phone__________ 
 
 
 
Signature_____________________________                      Date____________________

SECTION 01999 
REFERENCE FORMS 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01999 - 10 
 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double sided printing ]

SECTION 01999 
 
 
REFERENCE FORMS 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01999 - 11 
 
FORM 01999-D      CHAIN OF CUSTODY 
 
PROJECT NUMBER AND NAME: 
CITY: 
 
 
 
 
 
 
OWNERS REPRESENTATIVE: 
 
COMPANY NAME: 
ADDRESS 
 
 
CONTACT PHONE NUMBER: 
CONTACT NAME: 
 
 
CONTRACTOR: 
 
COMPANY NAME: 
 
ADDRESS 
 
 
 
CONTACT PHONE NUMBER: 
 
CONTACT NAME: 
 
 
TESTING LABORATORY: 
 
LAB  NAME: 
 
ADDRESS 
 
 
 
CONTACT PHONE NUMBER: 
 
FAX NUMBER 
 
CONTACT NAME: 
 
 
 
 
Pipe Segment No. 
 
Date Sample Taken: 
 
 
Pipe Diameter 
 
Sample Number: 
 
 
Liner Design Thickness: 
 
Quarter Section No. 
 
 
Resign Type: 
 
Upstream Manhole No. 
 
 
Downstream Manhole No. 
 
 
SAMPLE TAKEN BY: 
SIGNATURE: 
 
 
DATE 
 
PRINT NAME: 
 
ENGINEER, RECEIVED BY: 
SIGNATURE: 
 
 
DATE 
 
PRINT NAME: 
 
LABORATORY RECIEVED BY: 
SIGNATURE: 
 
 
DATE 
 
PRINT NAME: 
 
TEST RESULTS, RECEIVED BY: 
SIGNATURE: 
 
 
DATE 
 
PRINT NAME: 
 
** END OF SECTION **

SECTION 01999 
REFERENCE FORMS 
 
 
 
_____________________________________________________________________________________________ 
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 01999 - 12 
 
  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
[ This page intentionally left blank for double sided printing ]

SECTION 02100  
TRAFFIC CONTROL  
 
  
_____________________________________________________________________________________________
City of Glendale 
 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
 
Project No. 1024109 
WAS Line Realignment  
 
December 20, 2024 
Contract No.: 202104.01 
 02100 - 1 
 
PART 1 - GENERAL  
  
1.01  DESCRIPTION  
  
Traffic control during construction shall be provided in accordance with the requirements 
of the 2015 City of Glendale Engineering Design and Construction Standards, MAG 
Uniform Standard Specifications for Public Works Construction Section 401 - Traffic 
Control, and the Manual on Uniform Traffic Control Devices (MUTCD) (latest edition).  
  
1.02  TRAFFIC REGULATIONS  
  
A. A traffic control plan (TCP) must be submitted for review and approval by the City 
for arterial, collector, and local streets impacted by construction operations.   
 
B. All traffic and/or traffic control devices on this project shall be provided, maintained 
and/or controlled as specified section 1.01. 
  
C. Traffic/Pedestrian control shall comply with the requirements of Section 1.01, or any 
special conditions required by the City. 
 
D. The submitter/designer of the TCP shall be IMSA or ATSSA certified.   
 
E. Permission to restrict City streets, sidewalks and alleys (street closure permits) shall 
be requested as specified in Chapter 24, Article III of the City of Glendale Code of 
Ordinances. 
  
F. All traffic on this project shall be regulated as specified in Chapter 24, Article III of 
the City of Glendale Code of Ordinances. 
  
G. No deviation to the “Special Traffic Regulations” will be allowed or implemented 
unless submitted to the City for review and approval two (2) weeks prior to proposed 
work. 
 
H. Variable Message Boards (VMB) are required per City requirements. 
 
I. 
Law enforcement officers may be required within 300 feet of a signalized intersection.  
Officers may be required for non-signalized construction areas at the discretion of the 
City. 
 
J. 
A minimum of three (3) working days, (72 hours), advance notice is required for TCP 
review prior to construction starting. Additional time may be required for review and 
approval and shall be determined during the pre-construction meeting.

SECTION 02100 
TRAFFIC CONTROL 
_____________________________________________________________________________________________
City of Glendale 
Dibble 
Arrowhead Sewer Lines Phase 1.1 
Project No. 1024109 
WAS Line Realignment  
December 20, 2024 
Contract No.: 202104.01 
 02100 - 2 
1.03  TRAFFIC CONTROL / ACCESS  
A.
Contractor shall be responsible to present traffic control plans at the regularly
scheduled construction progress meeting for review as outlined in Technical
Specification Section 01014 – WORK SEQUENCE, subsection 1.04.C. Uninterrupted
access to commercial businesses and residences shall be maintained at all times.
Contractor shall be responsible to adjust work schedule to minimize disruption to
normal operation of businesses.
B.
Contractor shall be responsible to coordinate traffic control plans and inform the
project’s public relations representative of any potential impacts to commercial
businesses or residents. Contractor shall adjust work activities and schedules to
minimize disruptions to the City, residents, and traveling public. City reserves the right
to request the Contractor move his operations or modify work plans and schedules to
minimize disruptions to commercial business or residents at no cost to the City.
1.04  TRAFFIC CONTROL PLAN DISTRIBUTION 
A.
Copy of approved TCP’s shall be submitted to the City and City’s Representative prior
to start of work.
B.
Copy of approved TCP shall be on-site and available for review at all times work
activities are commencing. Failure to have approved TPC on-site while work is
commencing will be grounds for rejection and non-payment of work being performed.
PART 2 - PRODUCTS 
(NOT USED)  
PART 3 - EXECUTION 
(NOT USED) 
** END OF SECTION **

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
EXHIBIT F 
Statement of All Clarifications and Assumptions (if any) 
 
(6 pages - To be Incorporated by Amendment) 
 
SEE ATTACHED

ROC089744   |   BFCONTRACTING.COM   |   11011 North 23rd Avenue   |   Phoenix, AZ 85029 
P: 623.582.1170   |   F: 623.582.3761 
 
EXHIBIT F: CLARIFICATIONS & ASSUMPTIONS 
ARROWHEAD SEWER LINES PHASE 1.1 
WAS LINE REALIGNMENT 
COG PROJECT NO.: 202104 
GMP2 
 
 
General Clarifications & Assumptions: 
1. Fee Exclusions: GMP excludes all costs associated with City and/or Other Entity permit fees and 
plan review fees not specifically identified in this GMP, Right-of-Way Permit fees, City inspection 
and testing costs, impact fees, pavement restoration fees, utility company fees, water meters/meter 
installations except for construction water, and/or any other fees not specifically identified herein.  
2. Unit Price Contract Administration: This GMP will be administered as a Measured Quantity/Unit 
Price, Guaranteed Not‐to‐Exceed Contract. The Schedules of Values are defined by the individual 
work/pay items plus fee structure, and markups. Final contract price/payout will be based on field 
measured, final completed quantities at the approved unit prices, approved allowance, and/or and 
approved change orders. It is understood that these City approved prices including mark‐ups are 
the “Cost of the Work”. Quantity overruns shall be paid at the unit price established in the Schedule 
of Values for the pay item and shall be paid for through Project Contingency or Allowance budgets. 
3. GMP does not include costs associated with blasting or hydraulic breakers of any kind. 
4. Excludes costs for repairing pre-existing damage to any private and public roadways used to 
access this project. If additional pre-existing condition repairs are required, costs shall be 
reimbursed through Project Contingency. 
5. GMP assumes access can be granted to CMAR for suitable staging and construction efforts at the 
various sections of right-of-way (ROW) within approved traffic control plans. 
6. Existing Utilities: GMP excludes cost for the removal or relocation of existing utilities not 
specifically identified as being removed or relocated in Project Documents or in this GMP. If lines 
are encountered that conflict with this GMP’s scope of work, it will be considered a change in 
scope of work to be reimbursed through Project Continency. Costs for Private irrigation or any 
other unmarked utility damaged as part of this project shall compensated out of Project 
Contingency. 
7. GMP does not include any specialty asphalt, concrete, and/or pavers, unless expressed explicitly 
on the plans. If any specialty items are encountered or required, additional costs shall be 
compensated through Project Contingency. 
8. GMP does not include asphalt pavement sealing (fog seal, slurry seal, micro seal, etc.) 
9. Project Contingency funds shall cover material escalation costs related to aggregates, asphalt, 
pipeline, shotcrete, concrete, etc. as compared to vendor/supplier quote. This will be cost 
reimbursable with appropriate back-up documentation showing the cost impacts on the project 
from GMP to construction plus applicable mark-ups, insurance, bond, and taxes per the contract. 
10. Allowance are only anticipated/estimated costs and overruns of the allowances will be 
compensated through Project Contingency. 
11. GMP pricing is based on 24-hour traffic control restrictions on 67th Ave for duration of work scope 
located in the right-of-way on 67th Ave.

ROC089744   |   BFCONTRACTING.COM   |   11011 North 23rd Avenue   |   Phoenix, AZ 85029 
P: 623.582.1170   |   F: 623.582.3761 
 
 
 
12. No weather days have been accounted for in the CPM Schedule. A weather-related delay may be 
claimed on days where rainfall did not actually occur, but follows a day of rain that has impacted 
the schedule. If the project experiences weather-related delays, the CMAR shall be entitled to 
negotiate a commensurate extension of time associated with delays and, if necessary, a Price 
Adjustment for additional costs associated with schedule accelerations.  
 
 
 
Schedule of Value Pay Item Inclusions and Clarifications: 
 
 
 
ITEM # 
DESCRIPTION 
INCLUSIONS & CLARIFICATIONS 
1 
General Conditions 
Inclusion(s): 
•Project Manager for 2.5 months at 25% allocation to this project.  
•Project Engineer for 2.5 months at 40% allocation to this project. 
•Project Superintendent for 2.5 months at 85% allocation to this project. 
•Project sanitation and portable restrooms for 3 months. 
•ST&S, safety supplies, training, and fall protection based on Project’s Direct 
Labor Manhours. 
•Yard lease, field radios, cell phones, tablets, Procore, and storage container. 
 
2 
Mobilization/Demobilization 
Inclusion(s): 
•B&F equipment mobilization to the site and demobilization from the site   
•Unloading and organizing material deliveries 
•Temporary fence delivery, pickup, and rental. 
•Plate and shoring delivery and pickup. 
•Furnishing and installing 2 each project signs. 
•Construction water on the project for all activities including, but not limited to: 
dust mitigation, pipeline testing, etc.  
•Water meter, backflow preventer, and hoses 
•Dust permit fees  
 
Clarification(s): 
•B&F's mobilization costs include a one-time round trip for personnel, 
equipment, and supplies. Project delays that result in demobilization of 
personnel and/or equipment are not included. Any additional costs incurred 
are a change in scope and shall be reimbursed accordingly. 
•GMP pricing is based on equipment being staged in the right-of-way within 
barricade setups during non-work hours to avoid additional costs associated 
with moving the equipment to and from the staging yard before and after each 
shift.

ROC089744   |   BFCONTRACTING.COM   |   11011 North 23rd Avenue   |   Phoenix, AZ 85029 
P: 623.582.1170   |   F: 623.582.3761 
 
 
 
3 
SWPPP 
Inclusion(s): 
•Third-party service to provide the SWPPP project book and complete 
inspections and  
record keeping. 
•SWPPP materials to protect drainage inlets from storm water runoff.   
•Street sweeping 
•AZDEQ notice of intent and permit fees. 
•Labor and equipment to perform setup of SWPPP and routine maintenance of 
the site cleaning and repairing and replacing BMP’s weekly as needed. 
4 
Potholing 
Inclusion(s): 
•13 each standard potholes to locate existing utilities identified on project 
drawings. 
5 
Skunk Creek 
Clearing/Grubbing/Grading/
Restoration 
Inclusion(s): 
•Clear and grub wash area for ingress/egress of equipment required to 
complete installation of steel casing. 
•Grading and leveling existing grade and washed out areas for forklift and 
manlift to ingress/egress under bridge. 
•Restore wash to existing grade and clean-up wash area. 
6 
Remove & Replace AC 
Pavement, COG Std Det G-
319 
 
Inclusion(s): 
•Sawcutting of asphalt for mainline trench operations 
•Asphalt subcontractor costs to perform sawcut 12” on each side of mainline 
trench, remove and haul-off 12” of existing asphalt located on each side of 
trench, perform fine grading, and install replacement asphalt. 
 
Clarification(s): 
•GMP quantities exceed quantities identified on plans because City of 
Glendale’s standard detail indicates a 4’ wide minimum trench. Additional 
asphalt quantities have been included for areas in which remnant asphalt shall 
be removed and replaced. 
7 
Remove & Replace 
Concrete Vertical Curb & 
Gutter to Nearest Joint MAG 
Std Det 220-1, Type A 
Inclusion(s): 
•Sawcut, remove, haul-off, complete subgrade preparation, form, and pour 
new concrete curb and gutter. 
8 
Remove & Reinstall 
Guardrail (ADOT Std Det C-
10.30) 
Inclusion(s): 
•Removal of guardrail for mainline operations and reinstalling existing 
guardrail. 
9 
 
Remove & Replace Sidewalk 
to The Nearest Joint, MAG 
Std Det 230 
Inclusion(s): 
•Sawcut, remove, haul-off, complete subgrade preparation, form, and pour 
new sidewalk. 
10 
Remove & Replace Sidewalk 
Ramp, MAG Std Det 237-2 
Inclusion(s): 
•Sawcut, remove, haul-off, complete subgrade preparation, form, and pour 
new concrete sidewalk ramp.

ROC089744   |   BFCONTRACTING.COM   |   11011 North 23rd Avenue   |   Phoenix, AZ 85029 
P: 623.582.1170   |   F: 623.582.3761 
 
 
 
11 
Abandon Existing 6” WAS 
Line, Fill w/ Grout 
Inclusion(s): 
•Includes labor, equipment, and material to fill existing 6" WAS line with 
flowable grout. 
 
12 
Furnish & Install 12” Steel 
Casing 
Inclusion(s): 
•Concrete scanning, which includes costs for manlift and subcontractor costs 
to scan bridge to ensure pipe hanger anchors do not conflict with existing 
structural infrastructure. 
•Labor and equipment to install pipe hangers. 
•Labor, equipment, and welder to string and weld casing. 
•Crew time for hanging/mounting steel casing. 
•Material costs for pipe hanger hardware, epoxy, steel casing, spacers, and link 
seal. 
  
 
Clarification(s): 
•Costs for performing pull tests of anchors will be invoiced to the Quality 
Control Testing Allowance. 
•Project Documents did not indicate coating of steel casing as required, if such 
coating is required, Project Contingency funds shall be utilized for coating steel 
casing. 
13 
Furnish & Install 6” HDPE 
DR11 
Inclusion(s): 
•Includes labor, equipment, subcontractor/vendor, and material costs to 
perform installation of new 6” HDPE WAS line per project Documents. 
•Includes labor and equipment for fusing and installing new 6” HDPE in 12” 
steel casing. 
•MAG spec ABC for bedding and pipe zone. 
•1/2 Sack ABC Slurry for backfill from 12” above to of pipe to bottom of asphalt.  
•HDPE hydrostatic pressure testing. 
•Includes haul-off of spoils and dump fees associated with said work.  
 
Clarification(s): 
•GMP pricing is based on 24-hour southbound road restrictions on 67th Ave.  
14 
Furnish & Install 2” 
Combination Air Valve & 
Drain Line 
Inclusion(s): 
•Includes labor and equipment required to install 2" Combination Air Valve per 
Det 3, Dwg D1, 
15 
Concrete Encasement, MAG 
Std Dtl 404-1,2,3 
Inclusion(s): 
• Labor, equipment, and materials to install concrete encasements of existing 
utilities and new 6” WAS line. 
16 
Connect to Existing 6” WAS 
Line 
Inclusion(s): 
•Includes crew and material costs for completing connections to existing WAS

ROC089744   |   BFCONTRACTING.COM   |   11011 North 23rd Avenue   |   Phoenix, AZ 85029 
P: 623.582.1170   |   F: 623.582.3761 
 
 
 
line per Project Documents.  
 
Clarification(s): 
•During preconstruction meetings, it was noted that final tie-in configurations 
and tie-in points will be determined based on existing WAS line ductile iron pipe 
condition. If final tie-ins shall be made within vault structures, impacts will 
have to be evaluated and, if agreed that there are cost impacts, costs shall be 
reimbursed through Project Contingency. 
17 
Striping (Min Mob) 
Inclusion(s): 
• Includes subcontractor costs for subcontractor minimum mobilization to 
perform striping replacement of the impacted crosswalk areas at 67th Ave and  
Grovers. 
Allowance 
Traffic Control 
Inclusion(s): 
•This allowance will be utilized to cover anticipated traffic control costs and 
shall be reimbursed via an allowance with appropriate back-up 
documentation. 
•Traffic control plan development 
•Barricade device rental 
•Traffic control subcontractor labor and equipment to deliver, set up, maintain, 
and change/modify traffic control barricades.  
Allowance 
Construction Survey & 
Layout 
Inclusion(s):  
•Surveyor to perform site survey layout/staking and benchmarks with 
remarking as needed 
•Surveyor to record as-builts shots and compile as-built data onto Project 
Drawings 
•Surveyor to provide final signed and sealed as-builts. 
Allowance 
Pump & Transport Waste 
Sludge From ARWRF 
Inclusion(s):  
• Anticipated/estimated costs to perform pumping and transport of sludge 
from ARWRF during MOPO and final new to existing WAS line tie-in efforts. 
Allowance 
Above Ground Pipe 
Protection Cage 
Inclusion(s):  
• Bid item is anticipate/estimate cost only for the furnishing, fabricating, and 
installing of the above ground pipe protection cages.  
Allowance 
Quality Control Testing 
Inclusion(s): 
•Quality control and material testing per MAG testing requirements to be 
performed by a third-party materials testing agency. 
•Pull test of pipe hanger embedded anchors. 
 
Allowance 
Landscape Restoration 
Inclusion(s): 
•This allowance bid item is to-be utilized for reimbursement of any required 
landscape restoration costs associated with construction impacts for the 
installation of the Arrowhead WAS Line. 
•The allowance is an anticipated cost only to include, but not limited to the 
following: labor, equipment, material, and vendors costs for repairing irrigation 
lines, replacing landscape rock, bushes, shrubs, plants, trees, etc.

ROC089744   |   BFCONTRACTING.COM   |   11011 North 23rd Avenue   |   Phoenix, AZ 85029 
P: 623.582.1170   |   F: 623.582.3761 
 
 
 
Allowance 
Flood Control Channel Liner 
Restoration 
Inclusion(s): 
• This allowance bid item is to-be utilized for reimbursement for efforts 
associated with the flood control shotcrete liner restoration.

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
EXHIBIT G 
Schedule of Major Milestones 
(    pages - To be Incorporated by Amendment) 
1

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
T H I S  P A G E  I S  B L A N K

ID
Task Name
Duration
1
Waste Activated Sludge Line Realignment
52 days
2
NTP
0 days
3
MOBILIZATION
2 days
4
SKUNK CREEK CLEARING/GRUBBING/GRADING
2 days
5
BRIDGE CONCRETE REBAR SCANNING & PIPE HANGER LAYOUT
3 days
6
INSTALL PIPE HANGERS
4 days
7
STRING & WELD CASING
1 day
8
FUSE 6" HDPE ABOVE GROUND PIPING ASSEMBLY AND INSTALL IN CASING
2 days
9
MOUNT/HANG STEEL CASING
2 days
10
POTHOLE EXISTING UTILITIES IN ROW
3 days
11
E/L/B STA. 18+82 TO 16+00
4 days
12
E/L/B STA. 20+45 TO 26+98
6 days
13
CONCRETE ENASEMENTS
2 days
14
INSTALL ARV
2 days
15
TRENCH REPLACEMENT ASPHALT RESTORATION
1 day
16
HDPE WAS LINE PRESSURE TEST
2 days
17
WAS LINE TIE-IN PREP & MOPO
2 days
18
ABANDON EXISTING WAS LINE & GROUT FILL
2 days
19
CONCRETE RESTORATION
3 days
20
ASPHALT PATCH BACK
1 day
21
SHOTCRETE CHANNEL
3 days
22
SKUNK CREEK GRADING/RESTORATION & SITE LANDSCAPE RESTORATION
3 days
23
PUNCH LIST
5 days
24
FINAL CLEAN-UP & DEMOBILIZATION
2 days
25
FINAL COMPLETION
0 days
NTP
MOBILIZATION
SKUNK CREEK CLEARING/GRUBBING/GRADING
BRIDGE CONCRETE REBAR SCANNING & PIPE HANGER LAYOUT
INSTALL PIPE HANGERS
STRING & WELD CASING
FUSE 6" HDPE ABOVE GROUND PIPING ASSEMBLY AND INSTALL IN CASING
MOUNT/HANG STEEL CASING
POTHOLE EXISTING UTILITIES IN ROW
E/L/B STA. 18+82 TO 16+00
E/L/B STA. 20+45 TO 26+98
CONCRETE ENASEMENTS
INSTALL ARV
TRENCH REPLACEMENT ASPHALT RESTORATION
HDPE WAS LINE PRESSURE TEST
WAS LINE TIE-IN PREP & MOPO
ABANDON EXISTING WAS LINE & GROUT FILL
CONCRETE RESTORATION
ASPHALT PATCH BACK
SHOTCRETE CHANNEL
SKUNK CREEK GRADING/RESTORATION & SITE LANDSCAPE RES
PUNCH LIST
FINAL CLEAN-UP & DEMOBILIZATION
FINAL COMPLETION
4
7
10
13
16
19
22
25
28
31
3
6
9
12
15
18
21
24
27
30
3
6
9
12
15
18
21
24
27
30
2
5
8
11
14
17
20
23
26
29
y 2025
June 2025
July 2025
August 2025
S
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 1

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
T H I S  P A G E  I S  B L A N K

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
EXHIBIT H 
Dispute Resolution Procedures 
 
1. 
Disputes. 
1.1 
Each Dispute arising out of or related to this Agreement (including Disputes 
regarding any alleged breaches of this Agreement) shall be initiated and decided 
under the provisions of this Exhibit. 
1.2 
CMAR and City shall each designate in writing to the other party, from time to 
time, a member of senior management who shall be authorized to attempt to 
expeditiously resolve any Dispute relating to the subject matter of this Agreement 
in an equitable manner. 
1.3 
A party shall initiate a Dispute by delivery of written notice to the members of 
management designated by the respective parties under Section 1.2 of this Exhibit.   
1.4 
The parties must:   
(A) 
Attempt to resolve all Disputes promptly, equitably and in a good faith 
manner; and  
(B) 
Provide each other with reasonable access during normal business hours to 
any and all non-privileged records, information and data pertaining to any 
such Dispute. 
1.5 
With respect to matters concerning modification of the GMP or any schedule, 
CMAR must first follow the provisions of any Claim procedure established by the 
Design-Build Agreement before seeking relief under these Procedures. 
2. 
Emergency Arbitration. 
2.1 
If the parties are unable to accomplish resolution of a Dispute, the expedited 
resolution of which either party considers necessary to prevent or mitigate a 
material delay to the critical path of the Services (a "Time Sensitive Dispute") 
within two days after the Time Sensitive Dispute has been initiated by a party, either 
party may thereafter seek emergency relief before an emergency arbitrator (the 
"Emergency Arbitrator") appointed as follows:   
(A) 
The parties will exercise best efforts to pre-select an Emergency Arbitrator 
within 20 days after entering into this Agreement;  
(B) 
If the Emergency Arbitrator has not been selected at the time a party delivers 
Notice of a Time Sensitive Dispute, the parties will each select a 
representative within one day after the Notice is delivered and the two 
representatives will then select the Emergency Arbitrator by the third day 
following delivery of the Notice. 
(C) 
The Emergency Arbitrator shall be an attorney with at least ten (10) years’ 
experience with commercial construction legal matters in Maricopa County, 
Arizona, be independent, impartial, and not have engaged in any business 
for or adverse to either party for at least ten (10) years.   
2.2 
The Emergency Arbitrator will conduct a hearing and render a written 
determination on the Dispute to both parties within five business days of the matter 
being referred to him or her, all in accordance with Rules O-1 to O-8 of the

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
American Arbitration Association ("AAA") Commercial Rules-Optional Rules for 
Emergency Protection Commercial Rules ("AAA Emergency Rules"). 
2.3 
Although the hearing will be conducted using AAA rules, unless both parties agree 
otherwise, this dispute process will not be administered by the AAA but will be 
conducted by the parties in accordance with these procedures.  
2.4 
If, however, an Emergency Arbitrator has not selected within three days after 
delivery of the Notice, either party may upon three days additional notice, thereafter 
seek emergency relief before the AAA, in accordance with the AAA Emergency 
Rules, provided that the Emergency Arbitrator meets the qualifications set forth 
above.   
2.5 
All proceedings to arbitrate Time Sensitive Disputes shall be conducted in 
Glendale, Arizona.   
2.6 
Presentation, request for determination (i.e., a party’s prayer), and the Emergency 
Arbitrators decision will adhere to the procedures required in Section 3.6 of this 
Exhibit. 
2.7 
The finding of the Emergency Arbitrator with respect to any Time Sensitive 
Dispute will be binding upon the parties on an interim basis during progress of the 
Services, subject to review de novo by arbitration after the Project Substantial 
Completion Date. 
2.8 
The time and extent of discovery will be as determined by the Emergency 
Arbitrator. 
(A) 
 Discovery orders of the Emergency Arbitrator will consider the time 
sensitivity of the matter and the parties desire to resolve the issue in the 
most time and costs efficient manner; 
(B) 
The parties are obligated to cooperate fully and completely in the provision 
of documents and other information, including joint interviews of 
individuals with knowledge such that the matter moves toward resolution 
in the most time and costs efficient manner and the Emergency Arbitrator 
is empowered to fashion any equitable penalty against a party that fail to 
meet this obligation. 
3. 
Non-Emergency Arbitration. 
3.1 
Except as provided in Section 5 of this Exhibit, any Dispute that is either a non-
emergency Dispute that has not been resolved by negotiation, or a de novo review 
of an AAA emergency arbitration will be decided by binding arbitration by a panel 
of three arbitrators in accordance with, but not necessarily administered by, the 
Construction Industry Rules of the AAA.   
(A) 
The parties shall each select an arbitrator within 15 days after notice that a 
party desires to resolve a dispute by arbitration.   
(B) 
The two arbitrators shall then each select a third arbitrator.  If an arbitrator 
is not selected within any such 15 day period, then the arbitrator shall be 
appointed by the AAA.   
3.2 
The arbitrator(s) shall meet the qualifications of Emergency Arbitrators as provided 
in Section 2 of this Exhibit.

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
3.3 
The arbitrators do not have the authority to consider or award punitive damages as 
part of the arbitrators' award.   
3.4 
In connection with such arbitration, each party shall be entitled to conduct up to 
five depositions, and, no less than 90 days prior to the date of the arbitration hearing, 
each party shall deliver to the other party copies of all documents in the delivering 
party's possession that are relevant to the dispute.   
3.5 
The arbitration hearing shall be held within 150 days of the appointment of the 
arbitrators. 
3.6 
At the arbitration hearing, each party will argue its position to the arbitrators in 
support of one proposed resolution to the dispute (a “Proposed Resolution”).   
(A) 
Each party’s Proposed Resolution must be fully dispositive of the dispute.   
(B) 
The arbitrators must select one Proposed Resolution by majority consent 
and are not free to fashion any alternative resolutions. 
(C) 
The parties must submit their proposed resolution of the matter to the 
arbitrators and the other party 15 days prior to the date set for 
commencement of the arbitration proceeding. 
(D) 
The decision of the arbitrators will be forwarded to the parties within 15 
days after the conclusion of the arbitration hearing. 
(E) 
The decision of the arbitration panel is final and binding on the parties and 
may be entered in any court of competent jurisdiction for the purpose of 
securing an enforceable judgment.   
(F) 
All costs and expenses associated with the arbitration, including the 
reasonable legal fees and costs incurred by the prevailing party, must be 
paid by the party whose position was not selected by the arbitrators. 
4. 
Continuing Work.  Unless otherwise agreed to in writing, CMAR must continue to 
perform and maintain progress of the Work during any Dispute Resolution or arbitration 
proceedings, and City will continue to make payment to CMAR in accordance with the 
Agreement. 
5. 
Exceptions. 
5.1 
Neither City nor CMAR are required to arbitrate any third-party claim, cross-claim, 
counter claim, or other claim or defenses in any action that is commenced by a 
third-party who is not obligated by contract to arbitrate disputes with City and 
CMAR. 
5.2 
City or CMAR may commence and prosecute a civil action to contest a lien or stop 
notice, or enforce any lien or stop notice (but only to the extent the lien or stop 
notice the party seeks to enforce is enforceable under Arizona law), including, 
without limitation, an action under A.R.S. § 33-420, without the necessity of 
initiating or exhausting the procedures of this Exhibit. 
5.3 
This Exhibit does not apply to, and may not be construed to require arbitration of, 
any claims, actions or other process undertaken, filed, or issued by the City of 
Glendale Building Safety Department, Code Compliance Department, Police 
Department, Fire Department, or any other agency of City acting in its

City of Glendale Standard Form Agreement Between Owner and CM@Risk (January 28, 2025) 
 
 
governmental permitting, for the benefit of public health, safety, and welfare, or 
other regulatory capacity. 
5.4 
In connection with any arbitration, the arbitrators do not have the authority to, and 
may not enforce, any provision of the Federal or Arizona Rules of Civil Procedure.