CIOSI – Velma Teague Library 
June 24, 2025

2022 Community Assessment

What the Assessment Entailed

Benchmark Data Analysis - Overview

Benchmark Data Analysis – Cont.

Assessment Survey Results
Community Survey - March 21, 2022 - April 30, 2022
•
1,013 respondents completed the survey

2022 Velma Teague Facility Assessment
•
Library Accessibility
•
Library Visibility
•
Interior Public and Service 
Spaces
•
Technology
•
Staff Areas
•
Experiential Considerations
•
Vistas, Views and Outdoor 
Spaces

2024 Polco Survey - $16,400
Reasons for not regularly visiting Velma Teague Library: 
•
Address-based - lack of time, lack of interest, 
inconvenient location and being unaware of its existence. 
•
Open participation - inconvenient location and lack of 
time.
Main source of information about Velma Teague Library:
•
Glendale Library webpage, e-newsletter and word of 
mouth. 
•
51% of address-based sample and 35% of open 
participation outreach responded they consider 
themselves to be of Hispanic, Latino, or Spanish origin.

2024 Velma Teague - Survey Outreach

2024 Community Forum Announcement

Library Advisory Board Recommendation 
Preliminary Blueprint Mock-Ups Requested for:
• Option 1 - Renovate Existing Building
• Option 4 - Relocate to Promenade

Summary of Options & Probable Cost
12
Option 0
Maintain Existing
15,500 SF
$ 
5,003,527
Option 1
Renovate Existing
15,500 SF
$ 
12,962,539
$ 
2,255,482
$ 
2,435,000
Option 3
New Build in Park
12,000 SF
$ 
13,169,426
$ 
2,291,480
$ 
2,435,000
Option 4*
Promenade TI 
12,000 SF
$ 
7,895,701
$ 
5,003,527
$ 
17,653,020
$ 
17,895,906
$ 
7,895,701
2024-25
2027-28
2027-28
2024-25
2024 Dollars
2028 Dollars (17.4% escalation) 
Maintenance Needed before 2028**
Total Estimate of Probable Cost
Project Year
* Includes $500,000 for demolition and asbestos remediation of VTL and $1,500,000 for increased park scope
** HVAC, electrical, and roof only
City of Glendale 
Engineering Department 
Project Budget Worksheet

Current Infrastructure Concerns
13

14
Questions
Next Steps/Consensus