APC Conflict Evaluation
Extracted text (via pymupdf)
5173 characters
Subject:
Airport Conflict Evaluation
Arizona Commerce Center
Southeast Corner of Arizona Avenue and Ryan Road
Recommendation
Staff recommends the Airport Commission ("Commission") present an Airport Conflict Evaluation (ACE)
report to the Zoning Administrator and City Council with a finding of "no conflict with airport uses" for the
proposed Arizona Commerce Center development.
Background
The project is a six building, light industrial/commerce park development on approximately 41 acres at
the southeast corner of Arizona Avenue and Ryan Road (Exhibit A - Vicinity Map, Exhibit B - Property
Location). The property is zoned AG-1 and the proposed zoning is Planned Area Development.
The site is approximately nine-tenths (0.9) of a mile to the west of the Airport property line (Exhibit A-
Vicinity Map, Exhibit B- Property Location).
The six buildings will consist of approximately 486,000 square feet (SF) (Exhibit C - Site Plan). The
proposed building heights will be 34 feet for Buildings “A” and “D” fronting Arizona Ave with the
remaining four buildings not exceeding 45 feet.
The City of Chandler General Plan designates the property for Employment and Growth Areas. The 2021
Chandler Airpark Area Plan (CAAP) designates the property as Innovation and Light Industrial (Exhibit D –
Chandler Airpark Area Plan Land Use Plan).
Analysis and Stipulations
The proposed development is consistent with the CAAP. Commercial and industrial land uses are
generally compatible with airport operations. The property will experience daily overflights from aircraft
on takeoff and landing (Exhibit E – Flight Tracks).
Based on the proposed building heights, the proposed development does not appear to pose a hazard to
flight safety or be an airspace obstruction. The proposed building height does not appear to impact the
approach and departure surfaces for either runway. Final building structures, including all rooftop objects,
must not impact the approach and departure surfaces for the Airport’s runways.
The owner/applicant must file a Notice of Proposed Construction (FAA Form 7460-1) with the Federal Aviation
Administration (FAA) for the final structure heights, including, without limitation, all rooftop antennas,
parapets, light poles, and other equipment. The form may be submitted online at the FAA’s Obstruction
Evaluation/Airport Airspace Analysis (OE3A) website. The FAA-assigned numbers for all evaluation cases
must be provided to Airport Administration.
The owner/applicant must ensure that its contractors file a Notice of Proposed Construction (FAA Form 7460-1)
with the FAA for temporary construction equipment including, without limitation, cranes, drilling rigs, and
concrete boom pumps and other vertical equipment. The form may be submitted online at the FAA’s
Obstruction Evaluation/Airport Airspace Analysis (OE3A) website. The FAA-assigned numbers for all
evaluation cases must be provided to Airport Administration.
It is strongly recommended that the owner/applicant, or ensure its contractor(s), submits the
7460-1 form for the construction equipment as soon as possible before construction, allowing
for a minimum of sixty (60) calendar days before start of vertical work.
The owner/applicant and its contractors must coordinate directly with Airport Administration at
least thirty (30) calendar days before starting vertical construction.
The proposed project does not indicate the use of rooftop solar panels. If solar panels are anticipated to
be installed, the owner/applicant must complete a solar study and coordinate with Airport Administration
to ensure that glare will not interfere with aircraft on approach or takeoff.
The proposed project’s building design must not create reflectivity issues with aircraft in the traffic
pattern and on approach or takeoff (Exhibit F – Building Elevations). The use of non-reflective glazing and
non-reflective paint is encouraged.
Findings
No Conflict
High Conflict
Moderate Conflict
Low Conflict
Specific Area(s) of Conflict: Not applicable.
Recommended Corrective Actions: Not applicable.
Proposed Motion
Move to present an Airport Conflict Evaluation (ACE) report to the Zoning Administrator and City Council
with a finding of "no conflict with airport uses" for the proposed Arizona Commerce Center development.
Attachments
A. Vicinity Map
B. Property Location
C. Site Plan
D. Chandler Airpark Area Plan Land Use Plan
E. Flight Tracks
F. Building Elevations
N
Exhibit A: Vicinity Map
Property
Location
Property
Location
Exhibit B: Property Location
N
Airpark Area
Property
Location
Exhibit C: Site Plan
Exhibit D: Chandler Airpark Area Plan – Land Use Plan
Property
Location
Above Mean Sea Level / Above Ground Level
Above Mean Sea Level / Above Ground Level
<800’ AGL
>800’ AGL
AMSL
AMSL
N
Queen Creek Rd
Germann Rd
Pecos Rd
Ocotillo Rd
Property
Location
Above Mean Sea Level / Above Ground Level
Exhibit E: Flight Tracks
Loop 202
Airpark Area
(Typical)
Exhibit F: Building Elevations
Exhibit F: Building Elevations