Capital Projects – Design Phase: West Airport Facilities Upgrade: City funded at $3.9 million. Revised scope includes operations garage, parking lot and aircraft observation area. Finalizing plan comments. Evaluating utility relocation options and new phasing plan. Airport Fuel Tank Relocation: City funded at $610,000. Cost negotiation with vendors. Budget transfer under evaluation. Evaluating alternative methods. Runway End Identifier Light (REIL) Installation Runway 4L-22R (North Runway): FAA funding for $110,000. Revising drawings for circuit change for 24/7 REILs. FAA confirmed environmental clearance. Capital Projects - Construction Phase: Hangar Area Pavement Rehabilitation: Completed. Taxiway B Improvements- Phase 1: Completed. Former K&K Site Remediation: City funding for soil remediation near end of Cooper Road north of Queen Creek. 5.8 acre restricted use area remaining. Topographic survey for current site elevations forthcoming. Meeting Date: April 8, 2026 Chandler Municipal Airport Construction Report