Construction Report

City of Chandler — Regular Meeting (2026-05-13)

View PDF Item 9 Meeting page

Extracted text (via pymupdf) 939 characters
Capital Projects – Design Phase:

West Airport Facilities Upgrade: City funded at $3.9 million.  Revised scope includes operations
garage, parking lot and aircraft observation area.  Evaluating proposal for revised design and utility
relocation plan.

Airport Fuel Tank Relocation: City funded at $610,000.  Shift to request for proposals for fuel
branding agreement.  Future removal of underground storage tank.

Runway End Identifier Light (REIL) Installation Runway 4L-22R (North Runway): FAA funding
for $110,000.  Revising drawings for circuit change for 24/7 REILs. FAA confirmed environmental
clearance.
Capital Projects - Construction Phase:

Former K&K Site Remediation: City funding for soil remediation near end of Cooper Road north
of Queen Creek.  5.8 acre restricted use area remaining.  Topographic survey for current site
elevations forthcoming.
Meeting Date:
May 13, 2026
Chandler Municipal Airport
Construction Report