CHANGE ORDER - BOD APPROVAL
Maricopa County Flood Control District

Date: 18/19/2025 Change Order Number:| 4 | Amount:| $600,000.00 Agenda Item No. C-69-22-123-X-01
Contract No:]2021C009 Work Order No:

Consultant Name:]|Wood, Patel & Associates

Project Name:| Paradise Ridge Drainage Improvements

Intial Amount: $2,000,000 Contract Notice to Proceed Date: 8/4/2021 Total Prior Change Orders: $1,000,000.00

By mutual agreement of the parties, the following contract change(s) are incorporated into the above-identified contract. All other contract terms and conditions remain unchanged.

The purpose of Change Order No. 4 for the Paradise Ridge Drainage Improvements to authorize $600,000 to be added to the contract. There is no change to the
Fee Schedule or Scope of Work.

According to A.R.S. 34-605.D, a contract for professional services entered into as the result of a procurement under section 34-603, 34-604 or 34-606 shall have

a term not exceeding five years after the date of contract award by the agent of the first contract under the procurement, except that the contract may continue in
effect after the five year term for professional services on projects on which the rendering of professional services commences within the five year term.

With this Change Order, the total amount of this contract has increased 80.00%

By reason of this change 0 days extension of time will be allowed.

With inclusion of this change, this contract has a revised cumulative performance period of 2522 days.

The contract completion date is: 6/30/2028

The following financial information is submitted:

Initial Contract Amount $2,000,000.00

Amended Contract Amount w/ previous change orders $3,000,000.00

Current Change Order Request $600,000.00

Amended Contract Amount w/ current change order $3,600,000.00

We, the undersigned Consultant, do hereby agree that upon execution of this Change Order that we will perform all work as identified above, and as may be
described in attachment(s) and will accept the above specified amount(s) as full payment thereof.

IN WITNESS WHEREOF, the parties herein have executed this Contract Change Order:

«
Contractor Name: Wood, Patel & Associates Principal (Signature) #v. Wine yd

Address: 2051 W. Northern Avenue, Ste. 100 Printed Name Jeffrey R. Minch
City: Phoenix Title Principal/Vice President
State: AZ Date August 19, 2025
DISTRICT APPROVAL
| certify that this change is required to accomplish the overall task for which this contract is
initiated.
Signed by: DocuSigned by:
Olenia Kingaby It Dow. Kerick
30813689BE24485. 8/19/2025 6FOF4FC16930432 8/19/2025
Project Manager - Obenia Kingsby II Date Division Manager - Don Rerick Date
| certify that funds are available to accomplish this Change Order | certify that this change is within the limits authorized by the Maricopa County

Procurement Code
DocuSigned by: DocuSigned by:

3B47CDBDF603470. 8/19/2025 BRosene Tease 8/20/2025
Finance Manager - Karen Scott Date Contracts Manager- Sharon Rogers Date
FLOOD CONTROL DISTRICT OF MARICOPA COUNTY
RECOMMENDED BY: ACCEPTED AND APPROVED:
Docusigned by:
= 8/20/2025

Flood Control Director - Paul Baughman Date Chairman, Board of Directors - Date
LEGAL REVIEW ATTEST:

Approved as to form and within the powers and authority granted under the laws of the
State of Arizona to the Flood Control District of Maricopa County.
Signed by:

May 6. Caypuelli
Lae C. Camp 8/20/2025

County Attorney - Date Clerk of the Board - Date