IGA FCD 2024A010 
PCN 028.01.30 
PAGE 1 OF 10 
INTERGOVERNMENTAL AGREEMENT 
between  
THE CITY OF TEMPE 
and the 
FLOOD CONTROL DISTRICT OF MARICOPA COUNTY 
for the 
CONSTRUCTION, CONSTRUCTION MANAGEMENT, OPERATION & MAINTENANCE  
of the 
WATSON DRIVE AND BONARDEN LANE PROJECT  
 
IGA FCD 2024A010 
Agenda Item _____________________ 
This Intergovernmental Agreement IGA FCD 2024A010 (Agreement) is entered into by and between the 
City of Tempe, a municipal corporation, acting by and through its City Council and City Manager, hereinafter 
called the CITY, and the Flood Control District of Maricopa County, a political subdivision of the State of 
Arizona, acting by and through its Board of Directors, hereinafter called the DISTRICT. The DISTRICT and 
the CITY may hereinafter individually be called a PROJECT PARTNER, or collectively called the PROJECT 
PARTNERS. 
This Agreement shall become effective as of the date it has been executed by all PROJECT PARTNERS.  
STATUTORY AUTHORIZATION 
1. The DISTRICT is empowered by Arizona Revised Statutes (A.R.S.) Section 48-3603, as revised, to enter 
into this Agreement and has authorized the undersigned to execute this Agreement on behalf of the 
DISTRICT. 
2. The CITY is empowered by A.R.S. § 11-952 and the Tempe City Charter Section 1.03 to enter into this 
Agreement and has authorized the undersigned to execute this Agreement on behalf of the CITY. 
BACKGROUND 
3. The Watson Drive and Bonarden Lane (PROJECT) is located in the developed urban area within the 
City of Tempe (CITY).  The PROJECT is intended to mitigate excess stormwater runoff that impacts 
existing residences by using drainage features to convey stormwater to existing drainage infrastructure in 
the Rural Road drainage system.  
4. The proposed improvements were studied in the Tempe Storm Drainage Management Study prepared 
for the City of Tempe in June 2019.  This followed the Tempe Drainage Master Study prepared by the 
Flood Control District of Maricopa County in September 2016. 
5. On June 12, 2024, the Board of Directors of the DISTRICT adopted Resolution FCD 2024R001 (C-69-
24-075-X-00) authorizing the DISTRICT to negotiate and prepare an Intergovernmental Agreement for 
the cost-sharing, rights-of-way acquisition, utility relocations, design, construction, and construction 
management of the PROJECT. 
         C2024-313

IGA FCD 2024A010 
PCN 028.01.30 
PAGE 2 OF 10 
 
6. This Agreement is for the construction, construction management, operation, and maintenance of the 
PROJECT which will consist of approximately 1,760 feet of 24-inch diameter pipe along the El Paso 
Gasline Trail between Rural Road and Forest Avenue. The intended function of the PROJECT is to 
provide relief to the Rural Road system, thereby reducing the amount of runoff that ponds within the 
Bonarden Lane cul-de-sac area north of Watson Drive as well as improving the rate at which it drains. 
The preliminary PROJECT elements are shown on Exhibit A, attached hereto and made a part hereof. 
PURPOSE OF THE AGREEMENT 
7. This Agreement identifies and defines the responsibilities of the DISTRICT and the CITY, for 
PROJECT activities related to construction, construction management, operation & maintenance.  
TERMS OF AGREEMENT 
8. The PROJECT, as referenced herein, is defined by paragraph 6 of this Agreement.  
9. The PROJECT COST, as referenced herein, solely encompasses the following costs directly associated 
with the PROJECT activities and incurred after the effective date of this Agreement, which are: costs of 
construction, construction management, material testing, post-design services and construction surveying 
support related to the PROJECT. 
9.1 The PROJECT COST for this agreement is estimated to be $2,700,000. This amount is an estimate 
based on the best information available at the time of this Agreement. Upon recognition of 
anticipated costs above this estimated PROJECT COST, the PROJECT PARTNERS shall 
communicate these anticipated increases, and address them in the context of Paragraph 11.3. 
 
10. The following are specifically excluded from the calculation of PROJECT COST: 
10.1 Any costs associated with non-flood control features added to the construction at the CITY’s 
request.  Such costs shall be funded solely by the CITY. 
10.2 The personnel and internal administrative costs associated with this PROJECT incurred by each 
PROJECT PARTNER, including costs associated with the issuance of PROJECT permits, unless 
specifically identified otherwise in this Agreement.  
11. Not later than January 1st of each year during the life of the Project, the CITY shall provide to the 
DISTRICT a written estimate of the funds the CITY anticipates will be needed from the DISTRICT for 
the next fiscal year and for each of the remaining fiscal years of the Project until said Project is 
completed. The County fiscal year commences on July 1 and ends on June 30 of the following calendar 
year. The DISTRICT’S funding as shown in the table below is dependent on the availability of funding. 
The CITY should use these DISTRICT funding figures to derive its cash flow for the PROJECT. 
Depending on funding availability, the Parties may implement a payment plan by mutual agreement. 
11.1 The DISTRICT's total Project funding under this IGA shall not exceed $1,755,000.  
11.2 DISTRICT funding for its cost share of the entire project is contingent on funding availability for 
construction and all related activities, with an overall funding limit of 1,755,000 distributed for the 
DISTRICT fiscal year, as outlined in the table below:

IGA FCD 2024A010 
PCN 028.01.30 
PAGE 3 OF 10 
Fiscal Year 
Not to Exceed 
FY 2026 
$1,755,000 
 
11.3 Funding increases may be negotiated and are subject to written approval from the DISTRICT, 
contingent upon budget availability.  
12. DISTRICT funding for the PROJECT shall be from secondary flood control tax levy revenue and is 
contingent upon funding availability within the DISTRICT’s Capital Improvement Program.  
13. CITY funding for the PROJECT shall be from the CITY’s Capital Improvement Program (CIP) budget. 
14. The CITY shall: 
14.1 Fund 35% of the PROJECT COST, making the CITY’s estimated share $945,000.  
14.2 Prior to the CITY beginning the contracting process for hiring a consultant for design related 
activities, coordinate with the DISTRICT to understand its funding capabilities and timing for 
reimbursement of these PROJECT costs.  
14.3 Beginning three months after the award of the construction contract invoice the DISTRICT every 
quarter for its share of the earned contract costs to date as invoiced to the CITY by the Contractor.  
14.4 Serve as the lead agency for the PROJECT construction, construction management, material 
testing, surveying, and post-design services. 
14.4.1 If the construction management services are provided via CITY staff, then the 
construction management cost shall be assigned a value not to exceed eight percent (8%) 
of the actual construction cost.  
14.5    Serve as the lead agency for any PROJECT public involvement activities. 
14.6 Obtain DISTRICT review and concurrence on construction change orders. 
14.7 Assure the safety and appropriateness of any non-flood control uses of the PROJECT prior to 
offering to make or making the PROJECT available for such uses. 
14.8 Obtain DISTRICT review and comments on the design and construction of any future 
modifications to the PROJECT and resolve and incorporate the DISTRICT’s comments into these 
future PROJECT modifications. 
14.9 Invite the DISTRICT to all progress meetings and inspections. 
14.10 Be responsible for all operations and maintenance of the PROJECT including the development of 
an operation and maintenance plan to be shared with the DISTRICT. 
14.10.1 The maintenance activities to be performed include, but are not limited to, maintaining the 
flood control function of the PROJECT, including sediment and vegetation removal, 
removal of trash and debris, electricity and other operation costs for the facilities,

IGA FCD 2024A010 
PCN 028.01.30 
PAGE 4 OF 10 
vandalism repair and replacement, and structural repair and replacement of the flood 
control structures. 
14.10.2 Schedule, and invite the DISTRICT to participate in, an annual inspection of the 
PROJECT. Any deficiencies relating to flood control for which the CITY is responsible 
shall be corrected by the CITY within 30 calendar days. If the CITY has not taken 
corrective action within this time, the DISTRICT reserves the right to perform the 
corrective action and the CITY shall reimburse the DISTRICT for the total costs incurred 
by the DISTRICT within thirty 30 calendar days of receipt of an invoice from the 
DISTRICT. 
14.10.3 On an annual basis, commencing on the first anniversary date of the completion and 
acceptance of the PROJECT, provide written notification to the DISTRICT that the 
PROJECT has been properly maintained by the CITY over the past year in accordance 
with the PROJECT design and to ensure proper hydraulic function.  
15. The DISTRICT shall: 
15.1 Fund 65% of the PROJECT COST, making the DISTRICT’s estimated share $1,755,000.  
15.2 Subject to the availability of funding, within 30 calendar days of receipt, pay invoices issued by the 
CITY in accordance with the terms of this Agreement. 
15.3 Participate in PROJECT public involvement activities. 
15.4 Participate in a final inspection of the PROJECT with the CITY. 
15.5 Participate, as desired by the DISTRICT, with the CITY in an annual inspection of the PROJECT.  
15.6 Provide review and comments on post-design or post-construction changes or modifications to the 
PROJECT that may affect the hydraulic function of the PROJECT. The DISTRICT will retain 
permitting authority for any modifications or changes that could impact the PROJECTS outfall 
connection to the Salt River or the Salt River Levee. 
16. Each PROJECT PARTNER, and the PROJECT PARTNERS collectively, shall: 
16.1 Comply with A.R.S. Sections 41-4401 and 23-214(A).  
16.1.1 Each party to this Agreement retains the legal right to inspect the records of the CITY’s 
and any contractors’ or subcontractors’ employees performing work under this Agreement 
to verify compliance with Title 34 of the Arizona Revised Statutes, as well as A.R.S. 
Sections 41-4401 (as applicable) and 23-214(A). 
16.1.2 Failure by either party to this Agreement to comply with Title 34 of the Arizona Revised 
statutes, A.R.S. Section 41-4401, or A.R.S. Section 23-214(A) shall be deemed a breach of 
this Agreement and is subject to penalties up to and including termination of the 
Agreement. 
16.2 Require that any contractor selected for the PROJECT: 
16.2.1 Warrant its compliance with all federal immigration laws and regulations that relate to its 
employees and their compliance with A.R.S. Section 23-214(A).

IGA FCD 2024A010 
PCN 028.01.30 
PAGE 5 OF 10 
16.2.2 Agree that a breach of the warranty under paragraph 17.2.1 shall be deemed a material 
breach of contract and is subject to penalties up to and including termination of the 
contract. 
16.2.3 Agree that the PROJECT PARTNERS retain the legal right to inspect the papers of the 
contractor or subcontractor employee(s) who work(s) on this Agreement to ensure that 
contractor or subcontractor is complying with the warranty under paragraph 17.2.1. 
16.2.4 Who engages in for-profit activity and has 10 or more employees, certify it is not currently 
engaged in, and agrees for the duration of this Agreement to not engage in, a boycott of 
goods or services from Israel. This certification does not apply to a boycott prohibited by 
50 U.S.C. Section 4842, or a regulation issued pursuant to 50 U.S.C. Section 4842. 
16.2.5 Warrant and certify that it does not currently, and agrees for the duration of the contract 
that it will not, use: 
The forced labor of ethnic Uyghurs in the People’s Republic of China. 
Any goods or services produced by the forced labor of ethnic Uyghurs in the People’s 
Republic of China. 
Any contractors, subcontractors, or suppliers that use the forced labor or any goods or 
services produced by the forced labor of ethnic Uyghurs in the People’s Republic of 
China. 
If the Contractor becomes aware during the term of the Agreement that the Contractor is 
not in compliance with this paragraph, the Contractor shall notify the County within five 
(5) business days after becoming aware of the noncompliance.  Failure of the Contractor 
to provide a written certification that the Contractor has remedied the noncompliance 
within one hundred eighty (180) days after notifying the public entity of its noncompliance 
shall result in the termination of this Agreement unless the Term of this Agreement shall 
end prior to said one hundred eighty (180) day period.  
16.3 Have the right, when approved by the other PROJECT PARTNER in writing to delegate its 
responsibilities under this Agreement to another party. Any delegation, however, shall not relieve 
the delegating PROJECT PARTNER of its original responsibilities as defined herein. 
16.4 Use their best efforts and enter into good faith negotiations to resolve any disputed items of this 
Agreement. However, this shall not limit the rights of the PROJECT PARTNERS to seek any 
remedies provided by law. 
16.5 Take reasonable and necessary actions within its authority to ensure that only storm water is 
discharged into the PROJECT, and that such discharges into the PROJECT comply at the point of 
discharge with any applicable requirements of the U.S. Environmental Protection Agency Clean 
Water Act, Arizona Pollutant Discharge Elimination System or any other applicable discharge 
requirements, including any permit requirements. 
16.6 Equally share the cost of PROJECT compliance and cost audit to be initiated within 60 days of 
PROJECT completion, if requested by either PROJECT PARTNER. An independent auditing 
firm agreed to by the PROJECT PARTNERS will perform the audit. Any payments or 
reimbursements necessary to bring the PROJECT into compliance with the audit findings shall be

IGA FCD 2024A010 
PCN 028.01.30 
PAGE 6 OF 10 
made within 45 days of the audit findings by the PROJECT PARTNERS and at the agreed upon 
cost chare percentages set forth in Sections 15 and 16. 
17. The PROJECT may be phased due to funding or other coordination issues. Responsibilities of the 
DISTRICT and the CITY shall be phased accordingly, including, but not limited to, invoicing, 
reimbursements, and transfer of land rights.  
18. Each party to this Agreement shall, as “Indemnitor,” to the extent permissible by law, indemnify, defend 
and hold harmless the other PROJECT PARTNER (“Indemnitee”) including agents, officers, directors, 
governors and employees thereof, from and against any and all loss or expense incurred as a result of any 
claim or suit of any nature whatsoever, which arises out of any act or omission of Indemnitor pursuant to 
this Agreement, including but not limited to, reasonable attorneys’ fees, court costs, and other expenses 
relating to the defense against claims or litigation, incurred by the Indemnitee.  Notwithstanding the 
above, Indemnitee shall be liable for its own negligence or wrongful acts as provided by law.  In no event 
shall the Indemnitor owe or be obligated to pay any amounts which the Indemnitee has not actually paid 
or has no actual obligation to pay.  In the event any agreement to pay to resolve issues of liability is not 
enforceable, or any agreement or settlement results in an actual obligation lower than the full amount of 
liability, the Indemnitor’s obligation to pay shall be limited to the amount Indemnitee has paid or would 
be obligated to pay in the absence of any agreement to indemnify. Should any PROJECT PARTNER 
offer to make the PROJECT available for any non-flood control uses, the offering PROJECT 
PARTNER shall, to the extent permissible by law, indemnify, defend and save harmless the DISTRICT, 
including agents, officers, directors, governors and employees thereof, from any and all loss or expense 
incurred as a result of any claim or suit without limitation related solely to the non-flood control use of 
the PROJECT or portions of the PROJECT. Such indemnification obligation is intended to be a specific 
indemnity obligation rather than the general indemnity obligations set forth in this paragraph regarding all 
other types of claims or suits and shall include the obligation to provide reasonable attorneys’ fees, court 
costs, and other expenses relating to the defense of such claims or litigation related solely to the non-
flood control use of the PROJECT or portions of the PROJECT. This paragraph shall survive the 
completion and/or termination of this Agreement. 
19. All notices or demands upon any party to this Agreement shall be in writing and shall be delivered in 
person or sent by mail addressed as follows: 
City of Tempe 
Public Works Director 
31 East 5th Steet, Mail Stop 01-8 
Tempe, Arizona 85281 
 
With a copy to: 
Tempe City Attorney 
P.O. Box 5002 
Tempe, Arizona 85280 
 
Flood Control District of Maricopa County 
 
Chief Engineer and General Manager 
 
 
2801 West Durango Street 
 
 
 
Phoenix, AZ 85009-6399 
 
 
20. This Agreement shall expire either (a) 10 years from the effective date, or (b) upon completion of the 
PROJECT and after all funding obligations and reimbursements have been satisfied in accordance with 
this Agreement, whichever is the first to occur. However, by mutual written agreement of all parties, this 
Agreement may be amended or terminated. The operation, maintenance, and indemnification provisions, 
of this Agreement, shall survive the expiration of this Agreement.  
21. This Agreement is subject to cancellation by any party pursuant to the provisions of A.R.S. Section 38-
511.

IGA FCD 2024A010 
PCN 028.01.30 
PAGE 7 OF 10 
22. Attached to this Agreement or contained herein are the written determinations by the appropriate 
attorneys for the parties to this Agreement, that these agencies are authorized under the laws of the State 
of Arizona to enter into this Agreement and that it is in proper form. 
23. If legislation is enacted after the effective date of this Agreement that changes the relationship or 
structure of one or more parties to this Agreement, the parties agree that this Agreement shall be 
renegotiated at the written request of any party, subject to any additional authorization required by the 
DISTRICT’s Board of Directors or the CITY’s City Council.

IGA FCD 2024A010 
PCN 028.01.30 
PAGE 8 OF 10 
FLOOD CONTROL DISTRICT OF MARICOPA COUNTY 
A Political Subdivision of the State of Arizona 
Recommended by: 
 
 
 
 
 
 
 
 
 
Paul Baughman, Chief Engineer/General Manager   
Date 
 
  
 
Approved and Accepted:  
 
By:  
 
 
 
__________ 
       Chairman, Board of Directors     Date 
 
 
 
 
Attest: 
By:  
 
 
 
__________ 
 
       Clerk of the Board                       Date 
The foregoing Intergovernmental Agreement IGA FCD 2024A010 has been reviewed pursuant to Arizona 
Revised Statutes 11-952, as amended, by the undersigned General Counsel, who has determined that it is in 
proper form and within the powers and authority granted to the Flood Control District of Maricopa County 
under the laws of the State of Arizona. 
 
 
 
 
 
 
 
Flood Control District General Counsel     Date 
C2024-313

IGA FCD 2024A010 
PCN 028.01.30 
PAGE 9 OF 10 
 
CITY OF TEMPE 
A Municipal Corporation, 
 
  
By:   
 
 
 
 
 
 
                                                   
      Corey D. Woods, Mayor 
 
 
Date 
 
 
 
Attest: 
By:   
 
 
 
 
 
 
 
Kara DeArrastia, City Clerk  
 
 
Date 
 
 
The foregoing Intergovernmental Agreement IGA FCD 2024A010 has been reviewed pursuant to Arizona 
Revised Statutes 11-952, as amended, by the undersigned attorney who has determined that it is in proper 
form and within the power and authority granted to the City of Tempe under the laws of the State of 
Arizona.  
By:   
 
 
 
 
 
 
  
Eric C. Anderson 
 
City Attorney 
 
 
 
Date 
C2024-313
s/Eric C Anderson (Dec 4, 2024 09:52 MST)
s/Eric C Anderson
Kara DeArrastia (Dec 6, 2024 10:50 MST)
Kara DeArrastia

IGA FCD 2024A010 
PCN 028.01.30 
PAGE 10 OF 10 
IGA FCD 2024A010 
EXHIBIT “A” 
WATSON DRIVE AND BONARDEN LANE PROJECT 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
*Approximate Locations

2024A010-IGA-WATSON AND BONARDEN
(CONST).DOC
Final Audit Report
2024-12-06
Created:
2024-11-18
By:
Decima Sever (decimase@tempe.gov)
Status:
Signed
Transaction ID:
CBJCHBCAABAA3lIHS17CF-cRy4p0rsnnDCGXrzgfMXZ0
"2024A010-IGA-WATSON AND BONARDEN (CONST).DOC" Hi
story
Document created by Decima Sever (decimase@tempe.gov)
2024-11-18 - 8:03:13 PM GMT- IP address: 164.50.248.105
Document emailed to clerk@tempe.gov for approval
2024-11-18 - 8:10:13 PM GMT
Email viewed by clerk@tempe.gov
2024-11-18 - 8:10:17 PM GMT- IP address: 34.239.14.59
Signer clerk@tempe.gov entered name at signing as Erik Gibson
2024-11-18 - 8:57:12 PM GMT- IP address: 164.50.248.109
Document approved by Erik Gibson (clerk@tempe.gov)
Approval Date: 2024-11-18 - 8:57:14 PM GMT - Time Source: server- IP address: 164.50.248.109
Document emailed to eric_anderson@tempe.gov for signature
2024-11-18 - 8:57:16 PM GMT
Email viewed by eric_anderson@tempe.gov
2024-11-18 - 8:57:19 PM GMT- IP address: 34.194.151.205
Email viewed by eric_anderson@tempe.gov
2024-12-04 - 4:35:46 PM GMT- IP address: 34.194.151.205
Signer eric_anderson@tempe.gov entered name at signing as s/Eric C Anderson
2024-12-04 - 4:52:05 PM GMT- IP address: 164.50.248.106
Document e-signed by s/Eric C Anderson (eric_anderson@tempe.gov)
Signature Date: 2024-12-04 - 4:52:07 PM GMT - Time Source: server- IP address: 164.50.248.106

Document emailed to corey_woods@tempe.gov for signature
2024-12-04 - 4:52:09 PM GMT
Email viewed by corey_woods@tempe.gov
2024-12-04 - 4:52:12 PM GMT- IP address: 34.194.151.205
Signer corey_woods@tempe.gov entered name at signing as Corey D. Woods
2024-12-05 - 6:47:04 PM GMT- IP address: 164.50.248.100
Document e-signed by Corey D. Woods (corey_woods@tempe.gov)
Signature Date: 2024-12-05 - 6:47:06 PM GMT - Time Source: server- IP address: 164.50.248.100
Document emailed to kara_dearrastia@tempe.gov for signature
2024-12-05 - 6:47:08 PM GMT
Email viewed by kara_dearrastia@tempe.gov
2024-12-05 - 6:47:12 PM GMT- IP address: 34.194.151.205
Signer kara_dearrastia@tempe.gov entered name at signing as Kara DeArrastia
2024-12-06 - 5:50:34 PM GMT- IP address: 164.50.248.102
Document e-signed by Kara DeArrastia (kara_dearrastia@tempe.gov)
Signature Date: 2024-12-06 - 5:50:36 PM GMT - Time Source: server- IP address: 164.50.248.102
Document emailed to clerk@tempe.gov for approval
2024-12-06 - 5:50:38 PM GMT
Email viewed by clerk@tempe.gov
2024-12-06 - 5:50:41 PM GMT- IP address: 34.194.151.205
Signer clerk@tempe.gov entered name at signing as Kara DeArrastia
2024-12-06 - 8:00:43 PM GMT- IP address: 164.50.248.102
Document approved by Kara DeArrastia (clerk@tempe.gov)
Approval Date: 2024-12-06 - 8:00:45 PM GMT - Time Source: server- IP address: 164.50.248.102
Agreement completed.