Pavement Management Program/
Arterial Reconstruction Program/Bridge 
Repair Program
June 2, 2022 CTOC Meeting

FY 2022 PMP Activity
2
• ~$12M/$12.2M (invoiced & encumbered)
• Month of March-June Activities
– Slurry/Sealcoat activity, “The Home Stretch”
– Bethany Home Rd (75th Ave to 59th Ave), was in very
bad shape and received a heavy slurry seal treatment

FY 2023 PMP Activity
3

Additional PMP News
4
• The City of Glendale adopted a Pavement 
Preservation Ordinance, Ordinance No. 021-73 in 
October 2021

Additional PMP News
5
Let’s look at in more detail…
Utility Plan Review and Inspection - City of 
Glendale (glendaleaz.com)

PMP Activity
6
For more information go to:
www.GlendalePavementManagement.com
Or call:
PMP Hotline – 602.532.6250

ARP Activity
7
• Glendale Ave (91st Ave – Loop 101)
– Final Design Complete
– Construction Start June 6
– Anticipated Construction Completion September 
2022
– PCI 38 (2019)
– AADT 25,500 (2018)
– A very important economic corridor for the City!

ARP Activity
8
• Cactus Rd (59th Ave – 67th Ave)
– Final design nearing completion
– Anticipated construction start Sept/Oct 2022
• 67th Ave (Greenway Rd – Bell Rd)
– Final design nearing completion
– Anticipated construction start Jan 2023

FY 2023 Bridge Repair Activity
9
• New River Bridge @ Glendale Ave
– Spall repairs on substructure
– Joints repairs
– Reset bearings
• Arizona Canal Bridge @ Cactus Rd
– Replace joints
• Arizona Canal/Diversion Channel Bridge @ 
Cactus Rd
– Repair concrete on superstructure

10
Questions on PMP/ARP/Bridge Repair