07 PMP update

City of Glendale — Regular Meeting (2022-12-01)

View PDF Item 7 Meeting page

Extracted text (via pymupdf) 629 characters
Pavement Management Program/
Arterial Reconstruction Program
December 1, 2022 CTOC Meeting

FY 2023 PMP Activity
2
• $2.69/$13.53M Spent
• Primarily all sealcoat and slurry seal treatments
• ~119 Miles

FY 2023 PMP Activity
3

PMP Activity
4
For more information go to:
www.GlendalePavementManagement.com
Or call:
PMP Hotline – 602.532.6250

ARP Activity
5
• Glendale Ave (91st Ave – Loop 101)
– Substantially complete!
• Cactus Rd (59th Ave – 67th Ave)
– Construction started late Oct 2022
• 67th Ave (Greenway Rd – Bell Rd)
– Final design substantially complete
– Anticipated construction start Feb 2023

6
Questions on PMP/ARP