09 Deputy Director's Report

City of Glendale — Regular Meeting (2023-01-05)

View PDF Item 9 Meeting page

Extracted text (via pymupdf) 500 characters
Deputy Director’s Report
January 5, 2023

Northern Parkway
2
1. El Mirage Alternative Access
– Construction tentative start mid-January 2023
2. 99th Ave – Agua Fria River
– In 60% Design
– Construction tentative start 2026
– Cost inflation workshops
3. 87th Ave – 99th Ave
– In 60% Design
– Construction tentative start 2025
– Cost inflation workshops

Regional Project
3
• I-10 and Loop 101 TI
– Traffic Study Complete
– Design concept report underway
– Public Meeting tentative on February 23, 2023