Streets G.O. Bond Funded Capital Projects
May 16, 2023

Agenda
2
1) Elements of a Capital Improvement Plan
2) Pavement Management Program
a)
Crack seal and fog seal are non-capital
b)
Mill & Overlay, micro seal, and slurry seal are capital and eligible for bond 
funding
3) Arterial Reconstruction Program
a)
Eligible for bond funding
b)
Pavement, sidewalks, landscape, and other improvements
4) GO Bond Funded Streets Capital Projects
5) 2020 GO Bond Election
a)
Ballot Language
b)
Planned Projects

Elements of a Capital Improvement Plan
3
• Assets valued over $50,000 with a useful life of 5+ years
• Land, buildings, streets & improvements, plants, large 
equipment
• Ten-Year Plan (only FY2023-24 is adopted as part of the 
FY2023-24 budget)
Financial Policy:
A. Improve existing assets
B. Replace existing assets as needed
C. Construct new assets

4
Non-Capital Street Maintenance
• Pavement Management Plan
– Repairs usually last less than 5 years
– All roadways in City included in program
– Preservation of Street
– Requires coordination with residents, parking, and utilities
– Examples of non-capital street maintenance not eligible 
for Bond funds
•
Crack seal
•
Fog seal
•
Pothole repairs

Pavement Deterioration & Life Cycle Costs
5
City of Glendale*
*Information based on the 2020 Glendale Pavement Management Analysis

Pavement & Rating System
6
• Glendale Roadways
– 709 Centerline Miles
– 2,532 Lane Miles
• Pavement Rating Categories
– Excellent 85–100 PCI
– Very Good 70–85 PCI
– Good 60–70 PCI
– Fair 50–60 PCI

Pavement Condition & Funding
7
Pavement 
Condition Index
(PCI)
Glendale 
Funding 
Requirement*
83
$45 Million/Year
73
$30 Million/Year
65
$22 Million/Year
57
$13 Million/Year
*Information based on the 2020 Glendale Pavement Management Analysis

8
Arterial Reconstruction Program
• Complete/partial removal and replacement of street 
structure
• Includes improvements to extend life of pavement beyond 
5 years
• ADA ramps brought to current standards
• Requires coordination:
– Business access
– Traffic flow
– Other cities, departments, and utilities

9
Safety
• Ride Quality
• Lane Configuration
• Pavement Markings
• Signage
• Detection
• Roadside Safety
• ADA Ramps
• Cross Walks
• Bike Lanes
• Bus Pullouts

10
Project Safety Components
Lane Markings
Crosswalk
Signage
ADA Ramps
Bike Lanes

11
Projects Requiring Additional Voter Authorization
Project Location
Cost Estimate
67TH AVE - DEER VALLEY RD TO PINNACLE PEAK RD
$4,841,000 
CAMELBACK RD - 67TH AVE TO 75TH AVE
$4,841,000 
CAMELBACK RD - 75TH AVE TO 83RD AVE
$4,326,000 
BETHANY HOME RD - 59TH AVE TO 67TH AVE
$4,986,230 
CAMELBACK RD - 59TH AVE TO 67TH AVE
$4,986,230 
BETHANY HOME RD - 67TH AVE TO 75TH AVE
$4,986,230 
BELL RD - 59TH AVE TO 67TH AVE
$5,135,817 
83RD AVE - GLENDALE AVE TO BETHANY HOME RD
$5,135,817 
67TH AVE - PEORIA AVE TO OLIVE AVE
$5,135,817 
GLENDALE AVE - EL MIRAGE RD TO LITCHFIELD RD (2 MILES)
$10,579,783 
BETHANY HOME RD - 43RD TO 51ST AVE
$4,727,137 
NORTHERN AVE - 43RD TO 51ST AVE
$5,448,588

12
Projects Requiring Additional Voter Authorization
Project Location
Cost Estimate
GLENDALE AVE - 43RD TO 51ST AVE
$5,448,588 
THUNDERBIRD RD - 59TH AVE TO 67TH AVE
$5,448,588 
67TH AVE - DEER VALLEY RD TO BEARDSLEY RD
$5,015,020
All estimates assume a cost inflation of 3% per year

13
Cactus Rd: 59th Ave – 67th Ave

14
Camelback Rd: 83rd Ave – 91st Ave

15
Streets GO Bond Remaining Voter Authorization
4010
Streets
11,355,749
             
11,585,029
             
12,047,311
             
11,502,161
             
6,817,493
               
28,192,255
             
99,191,998
      
4010
Streets
(11,355,749)
           
(22,940,778)
           
(34,988,089)
           
(46,490,250)
           
(53,307,743)
           
(81,499,998)
           
(81,499,998)
    
TOTAL APPROVED PROJECTS BY FUND 
REMAINING VOTER AUTHORIZATION

16
2020 G.O. Bond Election - Ballot Language
• $81.5 million in additional voter authorization
• Constructing and reconstructing major and local 
streets, highways and bridges within the City
• Street signage, lighting, street widening and 
landscaping

17