08 Upcoming projects in Glendale

City of Glendale — Regular Meeting (2023-09-07)

View PDF Item 8 Meeting page

Extracted text (via pymupdf) 4354 characters
UPCOMING PROJECTS IN GLENDALE
CTOC Meeting
By: Tony S. Abbo, P.E., PTOE
09/07/2023

Today’s presentation
2
• Presenting a list of upcoming projects 
in Glendale
– Projects that are in design or are ready to 
be advertised
• Address comments or concerns 
relating to upcoming projects
• The list does not include any roadway 
improvements related to developments 
or projects that are in construction

Signal Detection Upgrade Project
3
• Scope:
– Install signal detection at various 
intersections along Glendale Avenue (19 
int.) and along 59th Ave (25 Int.)
• Stage: construction starts this week
• Estimated Cost: $1.6 M (Grant funded)

Café Light Phase II 
4
• Scope:
– Installation of 
Festoon lighting on 
Glendale Ave: 58th
Ave & 57th Dr
• Stage: Construction 
contract pending 
approval by council
• Estimated Cost: 
$500,000

Flashing Yellow Arrow (FYA) 
Phase IV
5
• Scope:
– Upgrading existing signals to 
accommodate the FYA
• Stage: 
– Post bid - Project ready for construction
• Estimated Cost: 
– $560,000

67th Ave Bike Lane Project 
6
• Scope:
– Addition of a NB and SB bike lanes from 
Missouri Ave to Cholla St 
• Stage: 
– Ready to go out to bid
• Bid opening 9/22/2023. Award 10/20/2023.
• Estimated Cost: 
– $4,100,000
• $3.7 million (94.3%) federal grant funded

Hawk at 53rd Ave & Camelback Rd 
7
• Scope:
– Construction of 
pedestrian activated 
signal
• Stage:
– Bid opening is 
10/5/2024
• Estimated Cost:
– $345,000 (MAG Grant 
funded project)

Hawk at 58th Ave & Bethany 
Home Rd
8
• Scope:
– Construction of 
pedestrian activated 
signal
– Median
• Stage: 90% design 
stage 
• Estimated Cost:
– $500,000 (MAG Grant 
funded project)

Hawk at 59th Ave & Evergreen Rd 
9
• Scope:
– Construction of 
pedestrian activated 
signal
• Stage: 
– 30% design stage 
(60% plans are due in 
October 2023)
• Estimated Cost:
– approx. $300,000

83rd Ave & Bethany Home Rd
10
• Scope:
– Adding a NB to EB 
right turn lane 
– Sidewalk
• Stage: 
– 60% design stage
• Estimated Cost:
– $210,000

59th Ave & Northern Ave 
Intersection Improvement 
11
• Scope:
– Right turn lane on SB 59th Ave in 
advance of Northern Ave 
– Bus bay on SB 59th Ave south of 
the Northern Ave
• Stage: 
– 90% design stage
• Estimated Cost: 
– $1.2 M

Bus Pull outs (CIP project)
12
• Scope:
– Construct bus pull outs
– Phase I
• Bethany Home Rd and 59th Ave – Eastbound
• Glendale And 59th Ave – Eastbound
• Union Hills and 75th Ave – Westbound
• Union Hills and 67th  Ave – Eastbound
• 59th Ave and Bell Rd – Northbound 
• Stage: 60% design stage
• Estimated Cost: $324,000

67th Ave: 
Greenway Rd to Bell Rd
13
• Scope:
– Mill and overlay 
• Stage: 
– 90% design stage
• Estimated Cost: 
– $2,000,000 M

75th Ave: 
Northern Ave to Glendale Ave
14
• Scope:
– Mill and overlay 
• Stage: 
– 90% design stage
• Estimated Cost:
– $1,750,000

83rd Ave: 
Northern Ave to Glendale Ave
15
• Scope:
– Roadway widening and roadway 
reconstruction 
• Stage:
– 90% design stage
• Estimated Cost: 
– TBD

51st Ave:
Olive Ave to Cactus Rd
16
• Scope:
– Mill and overlay 
• Stage:
– 90% design stage
• Estimated Cost: 
– $2,800,000

Scalloped Streets 
17
• Claremont St at 74th Ave 
• Orangewood Ave: 71st Ave to 69th Ave 
• 71st Ave: Bethany Home Rd to Claremont St
• 79th Ave: Glendale Ave to 630’ south
• 55th Ave: Bethany Home Rd to Claremont St
• 63rd Ave: Grand Ave to Northern Ave
• 63 Ave: Northern Ave to Royal Palm Rd

Glendale Ave and Sarival Rd 
Signal
18
• Scope:
– Construct new signal
• Stage: 
– 90% design stage
• Estimated Cost: 
– $600,000 (unfunded)

Bethany Home Road and 
Sarival Rd Signal
19
• Scope:
– Construct new signal
• Stage:
– 90% design stage
• Estimated Cost:
– $600,000 (unfunded)

Lighting on Olive Ave – 59th
Ave to 67th Ave
20
• Scope:
– Placement of streetlights
• Stage: 
– 90% design stage
• Estimated Cost:
– $300,000 (Grant funded)

Signal Improvement
61st Ave & Olive Ave Intersection
21
• Scope:
– Improvements to the 
exiting signal
• Stage: 
– 90% design stage
• Estimated Cost: 
– $300,000 (Grant 
funded)

HAWK at 67th Ave and
Montebello Rd
22
• Scope:
– Install a pedestrian activated signal
• Stage: 
– 100% design stage
• Estimated Cost: 
– $600,000 (HSIP funded)

FYA Phase III
23
• Scope:
– Upgrading existing signals to 
accommodate the FYA
• Stage: 
– 90% design stage
• Estimated Cost: $2.6 M (Grant funded)

Questions
24