Loop 101, 75th Avenue to I-17 Widening Project 
Glendale Citizens Transportation Oversight Commission
October 5, 2023
Rashidul Haque, P.E., ADOT Senior Project Manager
Gary J. Melita, P.E., Senior Project Manager, Stanley 
Consultants

Project Background and Need
•
Loop 101 is a vital transportation corridor 
•
Population growth is increasing traffic congestion
•
ADOT completed a study in 2021
– Additional lanes were recommended

Major Project Elements
•
Widen Loop 101 for additional GP 
lanes in each direction
•
Modify exit/entrance ramps
•
Widen frontage roads approaching 
crossroads
•
Widen bridges over 51st,  35th, and 
31st Ave
•
Improve 75th Ave interchange
•
Convert the I-17 / SR 101 ramp from 
1-lane to 2-lanes

Additional Project Elements
•
Construct retaining, noise, and 
screen walls
•
Resurface freeway pavement 
(diamond grinding)
•
Place freeway signing and striping
•
Install FMS elements
•
Convert freeway and ramp lighting 
to LED
•
Restore landscaping and irrigation

Loop 101 Improvements: 75th - 67th Avenue

Loop 101 Improvements: 63rd - 55th Avenue

Loop 101 Improvements: 51st - 43rd Avenue

Loop 101 Improvements: 43rd - 31st Avenue

Loop 101 Improvements: 31st - 19th Avenue

75th Avenue Crossroad Improvements
• Add third left turn lane from SB 75th Ave to EB Loop 101
• Modify existing 75th Ave median islands, traffic signals, signing and pavement markings
• Maintain pedestrian and bike access on existing 75th Ave sidewalks

Noise Wall Locations
Presented at February 2022 public meeting
For additional information, the Noise Analysis Report can be found on the Loop 101 project website.

Wall Improvements 59th to 51st Ave
Adjacent to Arrowhead Lakes
●State Legislature approved funding to add wall 
improvements to the project. 

Raise Existing Walls

Remove and Replace Existing Walls

Construct New Screen Wall (not noise wall)

Existing Wall – Not Impacted
Existing Wall – Raised 
Existing Wall – Reconstructed
New Wall
LEGEND
51st Avenue
59th Avenue
54th Avenue
53rd Avenue
WB Frontage Rd
N
SR 101L
Arrowhead Lakes 
Screen Walls

Schedule
•
Project is currently in final design phase (95% complete)
•
Anticipated construction start in fall 2024
•
Estimated construction duration is 30 months

During Construction
• Freeway traffic maintained except for weekend and night time 
closures.
• No freeway closures during special events or holidays.
• Ramp closures and lane restrictions on cross streets and 
frontage roads.
• Notifications and additional information will occur prior to and 
during construction. Subscribe for  updates: 
azdot.gov/projects/central-district-projects/loop-101-75th-ave-i-17

Questions?