Presentation on Flood Control Projects

City of Glendale — Regular Meeting (2025-06-25)

View PDF Item 5 Meeting page

Extracted text (via pymupdf) 2647 characters
Flood Control G.O. Bond Funded Capital Projects
June 25, 2025

Purpose of Flood Control
2
City’s Responsibility To Provide Infrastructure for: 
• Protect residential/private property from costly 
repairs due to storm events
• Protect businesses from interruptions due to 
storm events
• Protect the traveling public during storm events

Flood Control Projects Needing Voter Authorization
3
• Bethany Home Rd – 43rd Ave to 51st Ave 
                                     
• Camelback Rd – 51st St to 58th St
• 83rd Ave, Bethany Home Rd to Camelback Rd
• 59th Ave & Thunderbird Intersection
• Glenn Drive – 59th St – 52nd St
City Share
$     13.6M
$       4.3M
$       4.3M
$       2.8M
$       5.3M

4
On-Going Stormwater Project

5
Bethany Home RD – 43rd Ave to 51st Ave

Bethany Home RD – 43rd Ave to 51st Ave Phasing
6
Phase/
Increment
City Construction
Cost
Grants / Participation
Total Estimated 
Const. Cost
Outcome
A
$5.32M
$9.88M FCDMC
$15.20M
Resolves ~70% of the historical 
flooding.
B1 (BHR)1
$4.83M
$5.84M FCDMC
$2.00M USACE
$12.67M (ROM)
Mitigates the flooding at the 
51/BHR/Grand intersection.
B2 (Rose Lane)2
$1M
$6.50M FDMC
$2.00M USACE
$9.50M (ROM)
Routes stormwater away from the 
51/BHR/Grand intersection through 
the Rose Lane basin to 47th Avenue. 
C
$2.45M
$4.55M FCDMC
$7.00M (ROM)
Routes stormwater away from the 
51/BHR/Grand intersection to Rose 
Lane Park to 47th Avenue.
USACE 
Participation 
(20%)
$1.00M USACE
$1.00M
USACE Participation for Increments B1 
& B2.
Total
$13.6M
$26.77M FCMCD
$5M USACE
$45.37M

7
Future Stormwater Projects

8
Camelback Rd, 51st St to 58th St

9
Estimated Start Date
Fiscal Year 
2028
Estimated Project Cost
$4.31M 
Camelback Rd, 51st St to 58th St

10
83rd Ave, BHR to Camelback Rd

11
Estimated Start Date
Fiscal Year 
2029
Estimated Project Cost
$4.25M 
83rd Ave, BHR to Camelback Rd

12
Glenn Dr – 52nd to 59th
Estimated Start Date
Fiscal Year 
2030
Estimated Project Cost
$2.75M

13
Estimated Start Date
Fiscal Year 
2031
Estimated Project Cost
$2.64M 
59thAve, Thunderbird Rd Storm Drain

14
GO Funded Flood Control Project Summary
PROJECT #
PROJECT NAME
2026
2027
2028
2029
2030
2031
Grand Total
CIPDR19040
CAMELBACK RD, 51ST TO 58TH
4,313,920 
4,313,920 
CIPDR19078
83RD AVE, BETHANY HM TO CAMELBACK
4,251,520 
4,251,520 
CIPDR19079
59TH AVE & T-BIRD RD STORM DRAIN
2,635,360 
2,635,360 
CIPDR21019
DRAINAGE IMP. GLENN DR., 59TH-52ND
2,749,760 
2,749,760 
CIPDR21034
BETHANY HOME SD, 43RD TO 51ST AVE
6,936,640 
4,884,444 
1,740,000 
13,561,084 
Grand Total
$          6,936,640 
$    4,884,444 $  6,053,920 $  4,251,520 
$  2,749,760 
$  2,635,360 
$  27,511,644

15
Questions?