Presentation on Operations Campus Projects
Extracted text (via pymupdf)
874 characters
Glendale Operations Campus June 2025 Bond Committee Presentation 2 Operations Campus Location 3 4 Fleet Services 5 Traffic Signs/Signals 6 Graffiti Removal 7 Parks Maintenance 8 Water Services 9 Streets and Transportation 10 Warehousing 11 Warehousing 12 Other Warehouse / Storage 13 Spring City 14 Obsolete Structures Transfer Station Paint Booth 15 Inadequate Space Staff Training 16 Phased Plan: Phase 1 – Field Staff Building Option 1 Option 2 17 Phased Plan: Phase 2 – Adaptive Re-Use Adaptive Re-Use 18 Example of Possible Adaptive Re-Use 19 Possible Future Campus S Option 1 Option 2 20 Capital Cost Estimate Fund Cost Estimate Spring City Demolition $ 2.4 million Field Staff Bldg $30.2million Adaptive Reuse – Remodel Existing $ 7 million Total $39.6 million Enterprise Fund Component to be determined as part of the programming phase in FY26