FY2027-2036 Capital Improvement Plan
Bond Committee
March 4, 2026

Agenda
2
• Capital Improvement Plan (CIP) Overview
• Capital Improvement Plan Bond Funding

Capital Improvement Plan 
Overview
3

What is a Capital Improvement Plan (CIP)?
4
• 10-Year “roadmap” for creating, maintaining and paying for 
current and future capital needs
• CIP Projects are:
• Cost $50,000 or more 
• Useful life of 5+ years
• Examples of CIP Projects:
• Fire and Police Stations
• City Buildings (Libraries, Court Facilities, Office Buildings)
• Parks, Recreation Centers, Libraries 
• Water and Wastewater Treatment Plants
• Streets, Bridges, Traffic Signals
• Flood Control (Storm Drains, Retention Basins)
• Major Equipment Purchases (Fire Trucks, Street Sweepers, etc.)

Life Cycle of a CIP Project
5
Study
Design
Construction
Furniture, 
Fixtures and 
Equipment 
(Vertical 
Construction)
Project 
Completion
Life Cycle of a Vertical Construction Project

Life Cycle of a CIP Project
6
Life Cycle of a Horizontal Construction Project 
Study
Design
Construction
Project 
Completion

Examples of CIP Projects
7

Examples of CIP Projects
8

Examples of CIP Projects
9

Examples of CIP Projects
10

Why Do We Do Capital Planning?
11
• Strategic Planning
• Fiscal Management
• Community Improvement
• Transparency and Accountability
• Risk Management
• Leveraging Funding

Why Do We Do Capital Planning?
12
• City Council Financial Policy on Capital Asset and Debt 
Management
A. Improve existing assets
B. Replace existing assets as needed
C. Construct new assets
• Government Finance Officers Association (GFOA) 
Best Practice

CIP Process
13
Staff Develops       
5-year Financial 
Forecasts
Departments work 
with Engineering 
on Project 
Scope/Timelines
Projects are 
Submitted to 
Budget and 
Finance
Budget and 
Finance Evaluates 
Funding Sources 
for Projects
Proposed CIP 
Presented to 
Council
Budget and 
Finance Evaluates 
Funding Sources 
for Projects
Council Adopts 
10-Year CIP 
(Year 1 
Appropriated)

How is the CIP Funded?
14
• Year 1 (FY27) is appropriated as part of the budget
• Funding Sources:
• Cash (Fund Balance + Revenue)
• Bonds (Debt)
• General Obligation Bond funded projects in Library, Government 
Facilities, and Parks require additional voter authorization
• Grants
• Carryover

What is Carryover?
15
• Carryover is funding that is “carried over” from one fiscal to the next 
• Carryover occurs when a project takes more than one budget year
• Budget and Finance works with Departments during budget 
development to estimate carryover from current fiscal year (FY26) to 
upcoming fiscal year (FY27)
• If a project has carryover, the carryover funds remain in the same 
project/funding source
• Carryover is adjusted after the fiscal year is closed, when all prior 
fiscal year expenses have been recorded.

CIP Funding Sources
16
• Development Impact Fees 
• One-time charges to developers for new development
• Can only be used for new or expanded infrastructure
• General Obligation Bonds
• Debt issuance must be authorized by Voters 
• Streets, Public Safety, Parks, Government Facilities, Open 
Space/Trails, Libraries, and Flood Control
• Parks, Government Facilities, Libraries and Flood Control require 
additional voter authorization via special bond election
• Debt service paid by Secondary Property Tax

CIP Funding Sources
17
• Grants
• Federal or state grant funding
• Often require a match contribution to the project
• Pay-As-You-Go
• Cash funded projects

CIP Funding Sources
18
• Special Revenue Funds
• Transportation Sales Tax
• Half cent sales tax 
• Improve service for all modes of transportation
• Highway User Revenue Funds
• Restricted Special Revenue Fund
• Right of Way acquisition, construction, reconstruction, maintenance, and repair 
• Enterprise Funds
• Water/Sewer
• Funding can come from G. O. Bonds, revenue bonds, revenue obligations or cash 
financing
• Debt service paid from future water/sewer fee revenue
• Landfill – paid by Landfill user fees
• Solid Waste – paid by Solid Waste user fees

FY2026 10-Year Adopted CIP By Project Type
19
Water
$736.8M
Streets
$481.2M
Public Safety
$323.0M
Wastewater
$297.1M
Facility Maintenance
$169.0M
Parks
$136.8M
Solid Waste
$57.6M
Drainage
$56.1M
Airports
$52.8M
Landfill
$42.1M
Library
$36.7M
Parking Lots
$21.8M
Tranist
$11.1M
Arts
$1.0M
Total FY26-35 CIP 
$2.4B

FY2027 10-Year Proposed CIP By Project Type
20
Water 
$851.8M
Streets
$672.9M
Public Safety 
$373.9M
Wastewater 
$289.1M
Parks 
$186.5M
Facility Maintenance 
$122.6M
Solid Waste 
$67.8M
Drainage 
$58.4M
Airport 
$52.7M
Library 
$52.1M
Landfill 
$49.5M
Parking Lots 
$21.0M
Transit 
$10.6M
Arts 
$1.0M
Total FY27-36 CIP 
$2.8B

10-Year Proposed CIP by Funding Source
21
Enterprise Funds 
$1,271.2M
Bond Funds
$646.1M
Special Revenue 
Funds
$433.7M
Grants
$159.1M
Pay-As-You-Go
$219.7M
DIF
$80.0M
Total FY27-36 CIP 
$2.8B

One-Year Proposed Capital Improvement Plan
22
Streets 
$93.4M
Water 
$79.3M
Public Safety 
$71.6M
Wastewater 
$38.3M
Drainage 
$34.1M
Parks 
$31.4M
Facility Maintenance 
$28.9M
Parking Lots 
$16.5M
Airport 
$10.1M
Solid Waste 
$8.3M
Library
 $7.8M
Landfill 
$7.6M
Transits 
$5.7M
Arts
$1.0M
Total FY26-27 CIP 
$430M

Bond Funding
23

24
FY27-36 Bond Funding by Bond Type
Bond Fund Source
FY2027
FY2028
FY2029
FY2030
FY2031
FY 2032-2036
TOTAL
Flood Control Constr. Bonds
5,005,701
6,053,920
4,251,520
5,385,120
0
0
20,696,261
Government Facilities Bonds
1,410,954
6,335,160
524,000
391,400
3,900,200
0
12,561,714
Library Construction Bonds
0
15,470,000
6,049,800
9,156,000
1,500,000
12,200,000
44,375,800
Open Space/Trail Constr. 
Bonds
11,311,861
0
0
0
0
0
11,311,861
Parks Construction Bonds
0
7,165,000
24,139,699
46,445,100
66,082,569
11,259,380
155,091,748
Public Safety Bonds
12,170,737
30,314,857
51,041,148
32,872,980
22,398,300
72,594,129
221,392,151
Streets Construction Bonds
4,127,652
36,490,834
19,118,924
11,505,550
7,923,314
17,935,156
97,101,430
Grand Total
34,026,905
101,829,771
105,125,091
105,756,150
101,804,383
113,988,665
562,530,965

25
FY27-36 Bond Funding by Project Type
Project Type
FY2027
FY2028
FY2029
FY2030
FY2031
FY2032-2036
TOTAL
Drainage
5,005,701
6,053,920
4,251,520
5,385,120
0
0
20,696,261
Facility Maintenance
1,410,954
6,335,160
524,000
391,400
3,900,200
0
12,561,714
Library
0
15,470,000
6,049,800
9,156,000
1,500,000
12,200,000
44,375,800
Parks
11,311,861
7,165,000
24,139,699
46,445,100
66,082,569
11,259,380
166,403,609
Public Safety
12,170,737
30,314,857
51,041,148
32,872,980
22,398,300
72,594,129
221,392,151
Streets
4,127,652
36,490,834
19,118,924
11,505,550
7,923,314
17,935,156
97,101,430
Grand Total
34,026,905
101,829,771
105,125,091
105,756,150
101,804,383
113,988,665
562,530,965

Remaining Bond Authorization
26
Bond Fund Program
Authorization
FY2027
FY2028
FY2029
FY2030
FY2031
FY2032-2036
Total
Streets
76,293,969 
72,166,317 
35,675,483 
16,556,559 
5,051,009 
(2,872,305)
(83,229,844)
(20,807,461)
Public Safety
111,903,962 
99,733,225 
69,418,368 
18,377,220 
(14,495,760)
(36,894,060)
(434,952,756)
(109,488,189)
Parks
-   
-   
(7,165,000)
(31,304,699) (77,749,799)
(143,832,368)
(607,344,492)
(155,091,748)
Government Facilities
3,172,786 
1,761,832 
(4,573,328)
(5,097,328)
(5,488,728)
(9,388,928)
(37,555,712)
(9,388,928)
Cultural Facility
2,087,625 
2,087,625 
2,087,625 
2,087,625 
2,087,625 
2,087,625 
8,350,500 
2,087,625 
Open Spaces & Trails
25,935,998 
16,124,137 
16,124,137 
16,124,137 
16,124,137 
16,124,137 
64,496,548 
16,124,137 
Library
6,193,165 
6,193,165 
(9,276,835)
(15,326,635) (24,482,635)
(25,982,635)
(152,730,540)
(38,182,635)
Flood Control
30,000,000 
24,994,299 
18,940,379 
14,688,859 
9,303,739 
9,303,739 
37,214,956 
9,303,739

27
Flood Control Bond Projects

FY27-36 Flood Control Bond Projects
28
PROJECT
FY2027
FY2028
FY2029
FY2030
FY2031 FY2032-2036
TOTAL
CIPDR19040 - CAMELBACK ROAD, 51ST TO 58TH
0 4,313,920 
0 
0 
0 
0 
4,313,920 
CIPDR19078 - 83RD AVE, BETHANY HM TO CAMELBACK
0 
0 4,251,520 
0 
0 
0 
4,251,520 
CIPDR21019 - DOWNTOWN REGIONAL DRAINAGE PROJECT
0 
0 
0 2,749,760 
0 
0 
2,749,760 
CIPDR21034 - BETHANY HOME SD, 43RD TO 51ST AVE
4,904,701 1,740,000 
0 
0 
0 
0 
6,644,701 
CIPDR27043 - BETHANY HOME ROAD DRAINAGE, 79TH - 51ST AVE
101,000 
0 
0 2,635,360 
0 
0 
2,736,360 
Grand Total
5,005,701 6,053,920 4,251,520 5,385,120 
0 
0 20,696,261

29
Government Facilities 
Bond Projects

FY27-36 Government Fac. Bond Projects
30
PROJECT
FY2027
FY2028
FY2029
FY2030
FY2031
FY2032-2036
TOTAL
CIPFC19016 - GLENDALE OPS CAMPUS-FIELD STAFF BLD
1,410,954 
6,335,160 
524,000 
0 
0 
0 
8,270,114 
CIPFC23041 - GLENDALE OPS CAMPUS RENOVATION
0 
0 
0 
391,400 
3,900,200 
0 
4,291,600 
Grand Total
1,410,954 
6,335,160 
524,000 
391,400 
3,900,200 
0 
12,561,714

31
Library Bond Projects

FY27-36 Library Bond Projects
32
PROJECT
FY2027
FY2028
FY2029
FY2030
FY2031
FY 2032-2036
TOTAL
CIPLB19046 - MAIN LIBRARY RENOVATION
0 
2,160,000 
6,049,800 
7,651,000 
0 
0 
15,860,800 
CIPLB19066 - FOOTHILLS LIBRARY RENOVATION
0 
0 
0 
1,505,000 
1,500,000 
12,200,000 
15,205,000 
CIPLB25081 - MAIN LIBRARY ROOF PROJECT
0 
1,310,000 
0 
0 
0 
0 
1,310,000 
CIPLB27044 - VELMA TEAGUE REDEVELOPMENT
0 
12,000,000 
0 
0 
0 
0 
12,000,000 
Grand Total
0 
15,470,000 
6,049,800 
9,156,000 
1,500,000 
12,200,000 
44,375,800

33
Open Space/Trails
Bond Projects

FY27-36 Open Space/Trails Bond Projects
34
PROJECT
FY2027
FY2028
FY2029
FY2030
FY2031
FY2032-2036
TOTAL
CIPPK19077 - THUNDERBIRD CONSV. PARK IMPS.
11,311,861 
0 
0 
0 
0 
0 
11,311,861 
Grand Total
11,311,861 
0 
0 
0 
0 
0 
11,311,861

35
Park Bond Projects

FY27-36 Park Bond Projects
36
PROJECT
FY2027
FY2028
FY2029
FY2030
FY2031
FY 2032-2036
TOTAL
CIPPK21033 - HEROES PARK REC AND AQUATICS CENTER
0 
2,500,000 
5,000,000 
38,799,000 
36,701,000 
0 83,000,000 
CIPPK21042 - PARK RESTROOM REPLACEMENT
0 
900,000 
0 
0 
0 
0 
900,000 
CIPPK22011 - MARY SILVA PARK IMPROVEMENTS
0 
0 
0 
555,000 
0 
0 
555,000 
CIPPK22013 - HERITAGE PARK IMPROVEMENTS
0 
0 
0 
252,300 
0 
0 
252,300 
CIPPK22016 - MISSION PARK IMPROVEMENTS
0 
0 
0 
0 
0 
399,000 
399,000 
CIPPK22022 - COUNTRY GABLES PARK IMPROVEMENTS
0 
0 
75,000 
0 
0 
0 
75,000 
CIPPK22023 - SUNNYSIDE PARK IMPROVEMENTS
0 
0 
1,138,440 
0 
0 
0 
1,138,440 
CIPPK22024 - TARRINGTON RANCH PARK 
IMPROVEMENTS
0 
0 
0 
0 
555,880 
0 
555,880 
CIPPK22025 - FOOTHILLS PARK IMPROVEMENTS
0 
0 
0 
950,000 
0 
0 
950,000 
CIPPK22026 - NORTHERN HORIZON PARK 
IMPROVEMENTS
0 
0 
0 
1,500,000 
0 
0 
1,500,000

FY27-36 Park Bond Projects
37
PROJECT
FY2027
FY2028
FY2029
FY2030
FY2031
FY2032-2036
TOTAL
CIPPK22027 - MYRTLE PARK IMPROVEMENTS
0 
0 
50,000 
0 
0 
0 
50,000 
CIPPK22028 - CLAVELITO PARK IMPROVEMENTS
0 
0 
442,010 
0 
0 
0 
442,010 
CIPPK22029 - BUTLER PARK IMPROVEMENTS
0 
415,000 
0 
0 
0 
0 
415,000 
CIPPK22030 - CHOLLA PARK IMPROVEMENTS
0 
0 
0 
0 
344,900 
0 
344,900 
CIPPK23004 - PLAZA ROSA PARK IMPROVEMENTS
0 
0 
380,949 
0 
0 
0 
380,949 
CIPPK23005 - KINGS PARK IMPROVEMENTS
0 
0 
716,900 
0 
0 
0 
716,900 
CIPPK23006 - DESERT VALLEY PARK IMPROVEMENTS
0 
0 
0 
915,000 
0 
0 
915,000 
CIPPK23007 - DESERT ROSE PARK IMPROVEMENTS
0 
0 
900,000 
0 
0 
0 
900,000 
CIPPK23027 - CHAPPARAL PARK IMPROVEMENTS
0 
0 
1,450,000 
0 
0 
0 
1,450,000 
CIPPK24002 - ADA UPGRADES
0 
0 
1,000,000 
0 
0 
0 
1,000,000

FY27-36 Park Bond Projects
38
PROJECT
FY2027
FY2028
FY2029
FY2030
FY2031
FY2032-2036
TOTAL
CIPPK24003 - PARKING LOT IMPROVEMENTS
0 
700,000 
0 
0 
0 
0 
700,000 
CIPPK25014 - HORIZON PARK IMPROVEMENTS
0 
0 
277,650 
0 
0 
0 
277,650 
CIPPK25016 - UTOPIA PARK IMPROVEMENTS
0 
0 
0 
656,300 
0 
0 
656,300 
CIPPK25017 - FOOTHILLS PARK SKATE PARK RENOVATIO
0 2,500,000 
0 
0 
0 
0 
2,500,000 
CIPPK25018 - SUNSET VISTA PARK IMPROVEMENTS
0 
0 
267,550 
0 
0 
0 
267,550 
CIPPK25019 - GREENWAY GRANADA PARK IMPROVEMENTS
0 
0 
0 
817,500 
0 
0 
817,500 
CIPPK25020 - SUNSET RIDGE PARK IMPROVEMENTS
0 
0 
267,550 
0 
0 
0 
267,550 
CIPPK25068 - SAHUARO RANCH PARK BUILDOUT
0 
0 
0 
0 27,627,489 
0 27,627,489 
CIPPK26004 - PARK SIGNAGE IMPROVEMENTS
0 
150,000 
0 
0 
0 
1,011,880 
1,161,880 
CIPPK26010 - DOS LAGOS PARK IMPROVEMENTS
0 
0 
955,000 
0 
0 
0 
955,000

FY27-36 Park Bond Projects
39
PROJECT
FY2027
FY2028
FY2029
FY2030
FY2031
FY2032-2036
TOTAL
CIPPK27012 - LAWRENCE PARK IMPROVEMENTS
0 
0 
0 
0 
0 
660,000 
660,000 
CIPPK27013 - SONORITA PARK IMPROVEMENTS
0 
0 
0 
0 
0 
350,000 
350,000 
CIPPK27014 - VETERANOS PARK IMPROVEMENTS
0 
0 
0 
0 
0 
65,000 
65,000 
CIPPK27015 - WINDSOR PARK IMPROVEMENTS
0 
0 
0 
0 
0 
75,000 
75,000 
CIPPK27016 - GARDENWOOD PARK
0 
0 
0 
0 
0 
45,500 
45,500 
CIPPK27017 - OCOTILLO ROSE PARK IMPROVEMENTS
0 
0 
0 
0 
0 
531,000 
531,000 
CIPPK27018 - DESERT GARDEN PARK IMPROVEMENTS
0 
0 
0 
0 
0 
500,000 
500,000 
CIPPK27019 - ORANGEWOOD PARK IMPROVEMENTS
0 
0 
0 
0 
0 
730,000 
730,000 
CIPPK27023 - TRIANGLE PARK IMPROVEMENTS
0 
0 
0 
0 
0 
50,000 
50,000 
CIPPK27024 - BONSALL PARK SOUTH IMPROVEMENTS
0 
0 
0 
0 
0 
1,575,000 
1,575,000

FY27-36 Park Bond Projects
40
PROJECT
FY2027
FY2028
FY2029
FY2030
FY2031
FY2032-2036
TOTAL
CIPPK27025 - MEMMINGEN PARK IMPROVEMENTS
0 
0 
0 
0 
0 
903,000 
903,000 
CIPPK27026 - PASEO NEIGHBORHOOD PARK IMPROVEMENTS
0 
0 
0 
0 
0 
352,000 
352,000 
CIPPK27027 - ORANGEWOOD VISTA PARK IMPROVEMENTS
0 
0 
0 
0 
0 
500,000 
500,000 
CIPPK27028 - TIERRA BUENA PARK IMPROVEMENTS
0 
0 
0 
0 
853,300 
0 
853,300 
CIPPK27029 - BICENTENNIAL PARK IMPROVEMENTS
0 
0 
0 
0 
0 
525,000 
525,000 
CIPPK27030 - MARYLAND LAKES PARK IMPROVEMENTS
0 
0 
0 
0 
0 
532,000 
532,000 
CIPPK27031 - ROVEY PARK IMPROVEMENTS
0 
0 
0 
0 
0 
55,000 
55,000 
CIPPK27032 - MANISTEE RANCH PROPERTY IMPROVEMENTS
0 
0 
0 
0 
0 
50,000 
50,000 
CIPPK27033 - GLENDALE ADULT CENTER
0 
0 
0 
2,000,000 
0 
0 
2,000,000 
CIPPK27034 - ADULT CENTER PARKING IMPROVEMENTS
0 
0 
365,000 
0 
0 
0 
365,000

FY27-36 Park Bond Projects
41
PROJECT
FY2027
FY2028
FY2029
FY2030
FY2031
FY2032-2036
TOTAL
CIPPK27035 - BRIDLE PATH IMPROVEMENTS
0 
0 
0 
0 
0 
100,000 
100,000 
CIPPK27036 - GLEN LAKES PARK IMPROVEMENTS
0 
0 
0 
0 
0 
300,000 
300,000 
CIPPK27037 - MORCOMB PARK IMPROVEMENTS
0 
0 
0 
0 
0 
250,000 
250,000 
CIPPK27038 - FOOTHILLS SPORTS COMPLEX
0 
0 
0 
0 
0 
1,500,000 
1,500,000 
CIPPK27039 - ROSE LANE POOL REPLACEMENT
0 
0 
10,000,000 
0 
0 
0 
10,000,000 
CIPPK27040 - BRIAN ANDERSON FIELD IMPROVEMENTS
0 
0 
0 
0 
0 
200,000 
200,000 
CIPPK27041 - OASIS PARK IMPROVEMENTS
0 
0 
450,000 
0 
0 
0 
450,000 
CIPPK73576 - FOOTHILLS PARK PICKLEBALL COURTS
0 
0 
403,650 
0 
0 
0 
403,650 
Grand Total
0 
7,165,000 24,139,699 46,445,100 66,082,569 
11,259,380 155,091,748

42
Public Safety Bond Projects

FY27-36 Public Safety Bond Projects
43
PROJECT
FY2027
FY2028
FY2029
FY2030
FY2031
FY2032-2036
TOTAL
CIPPS19041 - MAIN PUBLIC SAFETY BLDG RENOVATION
0 
2,319,994 
17,730,006 
0 
0 
0 
20,050,000 
CIPPS19043 - GATEWAY POLICE STATION RENOVATION
0 
0 
0 
3,116,834 
12,883,166 
0 
16,000,000 
CIPPS19044 - FIRE STATION #154 CONSTRUCTION
6,413,737 
7,179,803 
0 
0 
0 
0 
13,593,540 
CIPPS19049 - FIRE STATION - WESTERN AREA
0 
0 
0 
0 
0 
20,000,000 
20,000,000 
CIPPS19051 - FIRE STATION #156 RENOVATION
0 
0 
482,759 
4,344,833 
0 
0 
4,827,592 
CIPPS19052 - FIRE STATION #157 RENOVATION
0 
0 
0 
0 
560,000 
5,094,129 
5,654,129 
CIPPS23031 - POLICE CRIME LABORATORY
4,545,000 
13,120,060 
24,879,940 
7,500,000 
0 
0 
50,045,000 
CIPPS24050 - FIRE STATION - 1510
0 
7,195,000 
5,590,000 
10,315,000 
0 
0 
23,100,000 
CIPPS26005 - FIRE RESOURCE CENTER REPLACEMENT
0 
0 
0 
0 
0 
45,000,000 
45,000,000 
CIPPS26007 - FIRE STATIONS INGRESS & EGRESS ENHA
1,212,000 
500,000 
500,000 
500,000 
500,000 
2,500,000 
5,712,000 
CIPPS26017 - FOOTHILLS PUBLIC SAFETY BLDG RENO
0 
0 
1,858,443 
7,096,313 
8,455,134 
0 
17,409,890 
Grand Total
12,170,737 30,314,857 
51,041,148 32,872,980 22,398,300 
72,594,129 221,392,151

44
Streets Bond Projects

FY27-36 Streets Bond Projects
45
PROJECT
FY2027
FY2028
FY2029
FY2030
FY2031 FY2032-2036
TOTAL
CIPST24068 - 67TH AVE - BEARDSLEY TO PINNACLE PK
0 
6,508,637 
0 
0 
0 
0 
6,508,637 
CIPST25049 - MOUNTAIN VIEW RD, 43RD TO 59TH
118,333 
2,204,250 
0 
0 
0 
0 
2,322,583 
CIPST25050 - ST RECON, 75TH AVE & NORTHERN AREA
0 
6,636,112 
0 
0 
0 
0 
6,636,112 
CIPST25052 - ST RECON, 75TH AVE & DENARO DR AREA
0 
209,846 
0 
0 
0 
0 
209,846 
CIPST25053 - 46TH AVE, McLENNAN TO OCOTILLO
0 
0 
106,400 
0 
0 
0 
106,400 
CIPST25054 - ST RECON, 59TH AVE & BETHANY AREA
0 
0 
6,692,271 
0 
0 
0 
6,692,271 
CIPST25056 - ST RECON, 47TH AVE & NORTHERN AREA
0 
0 
0 
3,381,193 
0 
0 
3,381,193 
CIPST25058 - ST RECON, 71ST AVE & NORTHERN AREA
0 
0 
0 
2,430,441 
0 
0 
2,430,441 
CIPST25059 - ST RECON, 79TH AVE & BETHANY AREA
0 
0 
602,916 
602,916 
0 
0 
1,205,832 
CIPST25060 - ST RECON, 75TH AVE & GLENDALE AREA
0 
0 
0 
0 
851,543 
0 
851,543

FY27-36 Streets Bond Projects
46
PROJECT
FY2027
FY2028
FY2029
FY2030
FY2031
FY2032-2036
TOTAL
CIPST25061 - UNION HILLS, 51ST AVE TO 59TH AVE
0 
0 
0 
250,000 
4,716,000 
0 
4,966,000 
CIPST25062 - 59TH, DEER VALLEY TO PINNACLE PEAK
0 
0 
0 
125,000 
2,096,000 
0 
2,221,000 
CIPST25063 - RECON BELL RD, 67TH AVE TO 75TH AVE
0 
0 
0 
0 
259,771 
4,935,650 
5,195,421 
CIPST25064 - ST RECON, 55TH AVE & BELL RD AREA
0 
0 
0 
0 
0 
2,576,344 
2,576,344 
CIPST25065 - ST RECON, 79TH AVE & GLENDALE AREA
0 
0 
0 
0 
0 
4,318,081 
4,318,081 
CIPST25066 - NEW RIVER, GLENDALE TO CUL-DE-SAC
0 
0 
0 
0 
0 
466,995 
466,995 
CIPST25067 - ST RECON, OLIVE AVE & 51ST AVE AREA
0 
0 
0 
0 
0 
4,318,185 
4,318,185 
CIPST25070 - ST RECON BETHANY HM - 43RD TO 51ST
0 
0 
4,965,160 
0 
0 
0 
4,965,160 
CIPST25072 - ST RECON GREENWAY - 59TH TO 51ST
0 
0 
200,000 
4,716,000 
0 
0 
4,916,000 
CIPST25073 - ST RECON CAMELBACK - 59TH TO 83RD
0 
5,533,500 
0 
0 
0 
0 
5,533,500

FY27-36 Streets Bond Projects
47
PROJECT
FY2027
FY2028
FY2029
FY2030
FY2031
FY2032-2036
TOTAL
CIPST25075 - ST RECON 75TH-DEER VLLY TO BEARDSLY
1,376,220 
0 
0 
0 
0 
0 
1,376,220 
CIPST26018 - LITCHFIELD-MISSOURI TO NORTHERN
969,600 
5,283,900 
0 
0 
0 
0 
6,253,500 
CIPST26019 - GLENDALE-EL MIRAGE TO LITCHFIELD
136,350 
3,786,000 
0 
0 
0 
0 
3,922,350 
CIPST26020 - 67TH, DEER VALLEY TO PINNACLE PEAK
424,200 
3,052,500 
0 
0 
0 
0 
3,476,700 
CIPST27020 - 59TH AVE - CAMELBACK RD - LOOP 101
1,102,949 
3,276,089 
6,552,177 
0 
0 
0 
10,931,215 
CIPST27022 - 67TH AVE - OLIVE - PINNACLE PEAK RD
0 
0 
0 
0 
0 
1,319,901 
1,319,901 
Grand Total
4,127,652 36,490,834 19,118,924 11,505,550 7,923,314 
17,935,156 97,101,430

48
 
 
 
 
 
 
 