TT0651
Contract Amendment 02
Project No.: TT0651
Contract No.: 2020-020
Revised: 7/19/2022
July 19, 2022
Mr. Ben Markert, P.E.
Maricopa County Department of Transportation
Project Management
2901 West Durango Street
Phoenix, Arizona 85009-6357
Serv
ices
Project Name: MC 85 – 95th Avenue to 87th Avenue
Final Design
, Utility Construction,
and Post Design
Services
MC 85
–
95
TH
AVENUE TO 87
TH
AVENUE
David Rutkowski, P.E.
Scope of Services
Final Design, Utility Construction, and Post Design
Services
MC 85 – 95TH AVENUE TO 87TH AVENUE
Project No:
Contract No.:
TT0651
2020-020
Maricopa County
Department of Transportation
2901 W. Durango Street
Phoenix, AZ 85009
JULY 2022
Scope of Services
Project Specific
Project No.: TT0651
Contract No.: 2020-020
Revised: July 2022
Page 2 of 8
Table of Contents
SCOPE OF SERVICES – PROJECT SPECIFIC .............................................................................................. 4
Project Overview .................................................................................................................................... 4
Project Location .................................................................................................................................. 4
Project Background ............................................................................................................................ 4
Project Purpose ................................................................................................................................... 4
Length of Services .................................................................................................................................. 4
SECTION 100
PROJECT MANAGEMENT ............................................................................................. 4
SECTION 200
DATA ACQUISITION ..................................................................................................... 5
200.4
Site Visit and Project Research ......................................................................................... 5
SECTION 300
LAND SURVEY .............................................................................................................. 5
300.3
Supplemental Field Survey .............................................................................................. 5
SECTION 400
PROJECT COORDINATION ........................................................................................... 5
SECTION 500
UTILITIES AND RAILROAD ........................................................................................... 5
500.5
Pothole Data on Plans, Profiles and Cross-Sections ......................................................... 5
500.5.2
Update Plans ..................................................................................................................... 5
500.6
Proposed Utility Data on Plans, Profiles and Cross-Sections ........................................... 5
500.7
Utility Relocation Concepts with R/W and Easement Requirements ............................... 6
500.7.1
Utility Plans Review ......................................................................................................... 6
500.11
Utility Relocation Plans .................................................................................................... 6
500.11.1
Miscellaneous Exhibits and Correspondence.................................................................... 6
500.13
Utility Special Provisions.................................................................................................. 6
500.16
Utility Clearance Letter ..................................................................................................... 6
SECTION 600 ENVIRONMENTAL ............................................................................................................ 6
SECTION 700
ALTERNATIVE ANALYSIS ............................................................................................. 6
SECTION 800
TECHNICAL MEMORANDA AND REPORTS .................................................................. 6
SECTION 900
RIGHT OF WAY ............................................................................................................. 7
900.17
Annexation ........................................................................................................................ 7
SECTION 1000 PLANNING .................................................................................................................... 7
SECTION 1100 PLANS, SPECIFICATIONS, AND ESTIMATE .................................................................. 7
1100.7
Sealed Plans ..................................................................................................................... 7
Scope of Services
Project Specific
Project No.: TT0651
Contract No.: 2020-020
Revised: July 2022
Page 3 of 8
SECTION 1200 VALUE ENGINEERING ................................................................................................. 8
SECTION 1300 BIDDING PHASE ........................................................................................................... 8
SECTION 1400 CONSTRUCTION PHASE ............................................................................................... 8
Scope of Services
Project Specific
Project No.: TT0651
Contract No.: 2020-020
Revised: July 2022
Page 4 of 8
SCOPE OF SERVICES – PROJECT SPECIFIC
Project Overview
Project Location
This project is located within Maricopa County along Maricopa County Highway 85 (MC 85) from 95th
Avenue to 87th Avenue (approximately 1 mile).
Project Background
MC 85 currently varies between a 4-lane and a 5-lane Arterial street section throughout the project
corridor. There are SRPI and private irrigation facilities located throughout the project limits along the
north and south sides of MC85. The project was originally split up into two phases.
•
TT0345-MC85, 95th Avenue to 75th Avenue
•
TT0511-MC85, 107th Avenue to 95th Avenue
The Consultant previously developed project plans up to the sealed stage for TT0345. TT0345 recently
completed construction east of 91st Avenue. West of 91st Avenue the remaining portion of TT0345 is
being repackaged as a new project that will be bid separately under TT0651-MC85, 95th Avenue to 87th
Avenue. In addition, a new development (Logic Park 91) was approved at the southwest corner of MC85
and 91st Avenue. This development is adding driveways and right turn bays along the south side of MC85
and constructing right turn bays and driveways along the west side of 91st Avenue.
TT0651 connects the ultimate improvements at 91st Avenue to the existing roadway condition at 95th
Avenue and will complete portions of the TT0345 improvements that were omitted from 91st Avenue to
87th Avenue and incorporates overlapping developer improvements. 95th Avenue to 107th Avenue will be
improved with future MCDOT project TT0511. TT0511 is planned to be constructed after TT0651 is
constructed.
Project Purpose
The purpose of this contract amendment is to add additional scope to the design services for TT0651.
Throughout the course of the project additional survey was necessary, extensive developer coordination
was needed and construction support for SRP Irrigation dry-up relocation and overhead distribution and
transmission coordination was found to be necessary.
Length of Services
No additional time is required to accommodate the additional services outlined within this contract
amendment.
SECTION 100 PROJECT MANAGEMENT
Additional project management services are not included in this scope of work.
Scope of Services
Project Specific
Project No.: TT0651
Contract No.: 2020-020
Revised: July 2022
Page 5 of 8
SECTION 200 DATA ACQUISITION
200.4 Site Visit and Project Research
Site Visits
Additional site visits were necessary for reviewing field constraints for utility relocations and tracking
the progress of the relocations during construction. The estimated effort associated with meeting
attendance, preparation, and note compilation is provided in the attached fee estimate.
If necessary, additional site visits during post design will be completed under Task 1400.
SECTION 300 LAND SURVEY
300.3
Supplemental Field Survey
Additional survey requests were necessary for accurately portraying the existing conditions in the project
plans and re-designing the connections to the changing existing conditions. The estimated effort
associated with preparing requests, coordination (meetings, phone calls, emails), and incorporating the
survey into the project plans is provided in the attached fee estimate.
Additional survey requests are not included in this scope of work.
SECTION 400 PROJECT COORDINATION
Additional coordination meetings are not included in this scope of work.
SECTION 500 UTILITIES AND RAILROAD
500.5 Pothole Data on Plans, Profiles and Cross-Sections
500.5.2 Update Plans
Additional utility survey was necessary to accurately portray the newly installed utilities in the project
plans and back check the design against where the utilities were installed. The estimated effort associated
with processing the audit shots, displaying the audit shots, sharing the data with stakeholders, updating
the plans and profiles with the newly installed utilities, and coordination (meetings, phone calls, emails)
is provided in the attached fee estimate.
Additional audit shot processing and coordination is not included in this scope of work.
500.6 Proposed Utility Data on Plans, Profiles and Cross-Sections
Additional elevation information to stake where the finished grade would be in relation to the new utility
(also known as bluetopping) was necessary during construction. The estimated effort associated with
coordinating the bluetopping information, calculating the information, packaging the information, and
quality control is provided in the attached fee estimate.
Additional bluetopping calculations and coordination is not included in this scope of work.
Scope of Services
Project Specific
Project No.: TT0651
Contract No.: 2020-020
Revised: July 2022
Page 6 of 8
500.7 Utility Relocation Concepts with R/W and Easement Requirements
500.7.1 Utility Plans Review
Additional utility plan reviews were necessary. The estimated effort associated with reviewing the plans,
providing comments, and coordinating any questions or concerns regarding the comments is provided in
the attached fee estimate.
Additional utility plan reviews are not included in this scope of work.
500.11 Utility Relocation Plans
500.11.1
Miscellaneous Exhibits and Correspondence
Additional exhibits and coordination were necessary for MCDOT’s JOC to accurately bid the construction
required for early utility relocations. Estimates and Special Provisions were also necessary. The estimated
effort associated with preparing and coordinating these documents with MCDOT is provided in the
attached fee estimate.
Additional exhibits, special provisions, and estimates are not included in this scope of work.
500.13 Utility Special Provisions
APS and City of Tolleson manhole abandonment/removal information was requested by the MCDOT RE
to be added to the special provisions. The estimated effort associated with the investigation and
coordination of this information is shown in the attached fee estimate.
Additional Utility Special Provisions and Investigations are not included in this scope of work.
500.16 Utility Clearance Letter
Additional submittals and coordination with utility companies was necessary for utility clearance letters.
The estimated effort associated with the submittals and coordination is provided in the attached fee
estimate.
Additional utility coordination for clearance letters or licenses is not included in this scope of work.
SECTION 600 ENVIRONMENTAL
Additional environmental coordination is not included within this scope of services.
SECTION 700 ALTERNATIVE ANALYSIS
Alternative analysis is not anticipated for this project and is not included with this scope of services.
SECTION 800 TECHNICAL MEMORANDA AND REPORTS
Additional technical memoranda and reports are not included within this scope of work.
Scope of Services
Project Specific
Project No.: TT0651
Contract No.: 2020-020
Revised: July 2022
Page 7 of 8
SECTION 900 RIGHT OF WAY
900.17 Annexation
A COP annexation exhibit was necessary to coordinate the City of Tolleson’s utilities and easements that
are in the City of Phoenix’s annexation limits. The estimated effort associated with the coordination and
exhibit is provided in the attached fee estimate.
Additional annexation exhibits are not included in this scope of work.
SECTION 1000 PLANNING
Planning is not anticipated for this project and is not included with this scope of services.
SECTION 1100 PLANS, SPECIFICATIONS, AND ESTIMATE
1100.7
Sealed Plans
The effort associated with updating the CAD files, plan sheets, estimate, and specifications is provided in
the attached fee estimate for the following tasks that were not captured in the previous scopes of work.
In addition to these new work items, the original items estimated to complete and bid the TT0651 project
evolved over the course of the project and required additional effort as noted in the attached fee estimate.
Roadway
•
A fencing design for the First Fleet property was requested by the MCDOT RE during design.
•
Fencing and gate construction for the A1 property was completed during design to clear the
property of its R/W requirements.
•
A roadway mill and overlay project along MC85 occurred during design which raised the grade
of the roadway.
•
A re-display of the existing ground profiles was necessary to accurately portray the cut/fill
condition of the roadway in the roadway profiles because of the changes to the existing ground
from the mill and overlay project, Logic Park grading, and MCDOT JOC grading. This included
combining the various existing ground surfaces, creating the new profiles, and updating the plan
sheets to reflect the change in existing conditions.
•
Including new survey benchmarks in the plans was requested by MCDOT survey.
•
A re-design of the eastern tie-in including a milling operation to fix a ponding issue that was
created with the interim tie-in of the TT0345 project was requested by the MCDOT RE during
design.
•
An earthwork report was requested by MCDOT Engineering during design which was not
captured in the previous scope of work. Earthwork report calculations were completed to
account for the changing existing ground conditions accordingly.
•
Moving the First Fleet mailbox was necessary during construction to prevent accidentally
damaging it while building the driveways to the site which changed the existing conditions.
Utilities
•
Displaying the pipe collars installed by SRPI in the plan sheets was requested by the MCDOT
RE during design to reflect the change in existing conditions.
Scope of Services
Project Specific
Project No.: TT0651
Contract No.: 2020-020
Revised: July 2022
Page 8 of 8
Drainage
•
Constructing the ultimate scupper east of the 91st Ave intersection was decided by MCDOT RE
during construction which required removing the scupper from to reflect the change in existing
conditions.
Lighting
•
Constructing the ultimate pull boxes and routing temporary conduit through them to the existing
light poles to prepare for the ultimate light poles was decided by MCDOT RE during
construction requiring an update to reflect the change in existing conditions.
•
The City of Phoenix requested additional changes to the lighting design to salvage existing
luminaires on power poles, change mast arm lengths and reposition poles to provide required
clearances to wet utilities.
Traffic Signals
•
Constructing one of the ultimate traffic signals and most of the ultimate signal conduit was
decided by the MCDOT RE during construction which required updating the design to reflect
the change in existing conditions.
Pavement Marking and Signing
•
Constructing the remaining temporary driveways to the Logic Park site and installing temporary
signing was decided by the MCDOT RE during construction which required updating the
design to reflect the change in existing conditions.
Specifications
•
A pedestrian access plan from 95th Ave to 99th Ave was requested by the MCDOT RE to be
added to the special provisions.
•
A driveway closure plan for the Pima Road driveway was requested by the MCDOT RE to be
added to the special provisions.
Estimates
•
Unit costs have been fluctuating drastically based on recent global economic changes. The cost
associated with checking the unit costs against recent bids for the 100% and sealed submittal is
shown in the attached fee estimate.
SECTION 1200 VALUE ENGINEERING
Value Engineering is not anticipated for this project and is not included with this scope of services.
SECTION 1300 BIDDING PHASE
Additional bidding support is not included in this scope of work.
SECTION 1400 CONSTRUCTION PHASE
Additional construction phase support is not included in this scope of work.
MC85 Additional Final Design Services
Kimley-Horn and Associates
PROJECT NO. TT0651
Contract No. 2020-020
ESTIMATED DIRECT LABOR
PERSON
BILLING
Scope of
Services
Principal/QC
F
inal Design
, Util
ity Construction,
and Post Design
45
Servi
ces
Project Engineer - Sr
MC
8
5
–
95
TH
AVENUE TO 87
T
H
A
VENUE
Designer
43.31
$
Administrative
-
42.16
$
-
$
656
Hours
Estimated Labor Cost
30,881.00
$
Overhead
194.28%
59,995.61
$
Subtotal
90,876.61
$
ESTIMATED DIRECT EXPENSES
(Listed By Item At Estimated Actual Cost - NO MARKUP)
Travel
-
$
Plotting
-
$
Miscellaneous Expenses
-
$
Total Estimated Expenses
-
$
ESTIMATED OUTSIDE SERVICES AND CONSULTANTS
Firm
Cost
-
$
-
$
-
$
-
$
-
$
-
$
-
$
Total Estimated Outside Services
-
$
PROFIT (Direct Labor +Overhead)
10%
9,087.66
$
TOTAL ESTIMATED FEE
99,964.27
$
CONTRACT TIME
N/A
Calendar Days
Consultant Firm Signature
Date
July 19, 2022
DERIVATION OF COST PROPOSAL SUMMARY
K:\PHX_Roadway\191850000-MC 85\Contract\5 - Contract Amendments\CA02_TT0651 95th to 87th\ TT651_CA02_Fee_V1.xlsx
Table A
Page 1 of 3
Updated: 7/19/2022 1:21 PM
David
Rutkowski
MC85 Additional Final Design Services
Kimley-Horn and Associates
PROJECT NO. TT0651
Contract No. 2020-020
TASK
Scale
No Sheets
Hours/Sheet
Principal/QC
Project Manager - Sr Project Engineer -
Sr
Engineer
Designer
Environmental
Manager
Administrative
Total
SUBTOTAL
$ 101.93 $ 73.91 $ 71.69 $ 49.74 $ 43.31 $ 62.95 $ 42.16
Task 100 - Project Management
-
-
-
-
-
-
-
-
-
Task 200 - Data Acquisition
1,329.90
-
1
-
-
29
-
-
30.00
200.4 - Site Visit and Project Research
-
-
Site Visits (Previously Completed) (7 total) (1 attendee)
-
-
Preparation (1 hr/person)
420.39
1
8
9.00
Attendance (4 hrs/person)
606.34
14
14.00
Notes (1 hr/visit)
303.17
7
7.00
Task 300 - Land Survey
364.37
-
2
-
-
5
-
-
7.00
300.3 - Supplemental Field Survey
-
-
Processing/Combining Survey Data
129.93
3
3.00
Additional Survey Request Forms and Exhibits
234.44
2
2
4.00
Task 400 - Project Coordination
-
-
-
-
-
-
-
-
-
Task 500 - Utilities and Railroad
15,450.24
-
16.00
15.00
31.00
269.00
-
-
331.00
500.5 - Pothole Data on Plans, Profiles and Cross-Sections
-
-
500.5.2 - Update Plans
-
-
Audit Shot Updates
866.20
20
20.00
500.6 - Proposed Utility Data on Plans, Profiles and Cross-Sections
-
-
Bluetopping
389.79
9
9.00
QC
73.91
1
1.00
500.7 - Utility Relocation Concepts with R/W and Easement Requirements
-
-
Additional Utility Plan Reviews
519.72
12
12.00
500.11 - Utility Relocation Plans
-
-
500.11.1 - Miscellaneous Exhibits and Correspondence
-
-
Additional Exhibits
9
3.00
1,367.82
4
2
3
18
27.00
JOC Estimates
73.91
1
1.00
JOC Specs
203.84
1
3
4.00
Additional Services (Coordination)
11,361.42
8
13
28
195
244.00
500.13 - Utility Special Provisions
-
-
RE Manhole Specifications Request
160.53
1
2
3.00
500.16 - Utility Clearance Letter
-
-
95%, 100% (30% was included)
433.10
10
Task 600 - Environmental
-
-
-
-
-
-
-
-
-
Task 700 - Alternative Analysis
-
-
-
-
-
-
-
-
-
Task 800 - Technical Memoranda and Reports
-
-
-
-
-
-
-
-
-
Task 900 - Right-of-Way
117.22
-
1
-
-
1
-
-
2.00
900.3 - Right-of-Way Limit Requirements
-
-
900.17 - Annexation
-
-
COT Utility Exhibit for Ben
117.22
1
1
2.00
Task 1000 - Planning
-
-
-
-
-
-
-
-
-
Task 1100 - Plans Specifications and Estimate
13,619.27
-
25.00
9.00
33.00
219.00
-
-
286.00
1100.7 - Sealed Plans
-
-
Roadway
-
-
RE Request - First Fleet Fencing
259.86
6
6.00
Existing Condition Change - A1 Fence
43.31
1
1.00
Existing Condition Change - Taper Tie-Ins
346.48
8
8.00
Re-displaying Existing Ground Profile
173.24
4
4.00
Added survey Benchmarks to Roadway Sheets
216.55
5
5.00
RE Request - Added Mill and Fill to Correct Bird Bath
303.17
7
7.00
Earthwork Report
519.72
12
12.00
Existing Condition Change - Moved Mailbox and Moved back
43.31
1
1.00
Additional Design Services
5,427.16
15
25
71
111.00
Utilities
-
-
RE Request - Add Pipe Collars per RE Redlines
822.89
19
19.00
Additional Design Services
375.01
1
1
2
3
7.00
Drainage
-
-
Removed scupper that banicki rebuilt
129.93
3
3.00
Lighting
-
-
Existing Condition Change - AJP installing a portion of the Light Poles
86.62
2
2.00
COP Lighting Change Internal Coordination
507.01
1
10
11.00
Traffic Signals
-
-
Revising plans for Early AJP Signal Work
848.61
4
15
19.00
Additional Design Services
722.08
1
3
10
14.00
Pavement Marking and Signing Items
-
-
Logic Park Signs Update
374.86
1
7
8.00
Additional Design Services
852.16
2
3
2
9
16.00
ESTIMATED STAFF HOURS - DESIGN PHASE
7/19/2022
2 of 3
TASK
Scale
No Sheets
Hours/Sheet
Principal/QC
Project Manager - Sr Project Engineer -
Sr
Engineer
Designer
Environmental
Manager
Total
SUBTOTAL
$ 101.93 $ 73.91 $ 71.69 $ 49.74 $ 43.31 $ 62.95 $ 42.16
Specifications
-
-
Writing/Investigation per RE Request
247.15
1
4
5.00
Estimates
-
-
Roadway
-
-
Fencing addition and removals per RE Request
43.31
1
1.00
Unit Cost Updates and Comparisons
277.75
2
3
5.00
Pavement Marking and Signing Items
-
-
Unit Cost Updates
43.31
1
1.00
Traffic Signals
-
-
Unit cost updates
86.62
2
2.00
Updates for AJP early work
43.31
1
1.00
Drainage
-
-
95% and Sealed Unit Cost update
86.62
2
2.00
Lighting
-
-
AJP Lighting Quantity Update
201.62
1
3
4.00
Unit cost updates
86.62
2
2.00
Additional Design Services
450.99
2
7
9.00
Task 1200 - Value Engineering
-
-
-
-
-
-
-
-
-
Task 1300 - Bidding Phase
-
-
-
-
-
-
-
-
-
Task 1400 - Construction Phase
-
-
-
-
-
-
-
-
-
KIMLEY-HORN SERVICES
-
SUBTOTAL (KIMLEY-HORN SERVICES)
30,881.00
-
7/19/2022
3 of 3