11
Date:
7/19/2022
Amount:
$400,000.00
File No:
XXXXX
PCN No:
207.01.31
Initial   
Amount:
Contract NTP 
Date:
9/9/2009
$3,570,000.00
1096
days extension of time will be allowed.
12/31/2026
.
2,000,000.00
$        
5,570,000.00
$        
400,000.00
$           
5,970,000.00
$      
Principal 
(Signature):  
Printed Name:
Title:
Date:
Date
Date
Date
Date
Date
Date
ATTEST:
Date
Clerk of the Board
Date
Change Order Number:
Contract No:
Consultant Name:
Contract Title:
Approval of this change order establishes a new contract amount of  $5,970,000 and a new completion date of December 31, 2026.
We, the undersigned Contractor, having given careful consideration to the change(s) proposed, hereby agree that upon execution of this change order that we will
provide all equipment, furnish all material (except as noted in the bid line item sheet), perform all work specified in the bid line item sheet; and we will accept as full
payment therefore the prices shown in the bid line item sheet.
The contract completion date is: 
$2,000,000.00
Total Previous Change Orders:
By reason of this proposed change
Initial Contract Amount:
Amended Contract Amount w/ previous change orders:
The following financial information is submitted:
Copy to:  Contract File, Finance, Division Manager, Project Manager
CONSULTANT CHANGE ORDER - BOD APPROVAL
FCD 2009C005
Tetra Tech Inc.
Buckeye FRS No. 1 Rehabilitation Project
Flood Control District of Maricopa County
By mutual agreement of the parties, the following contract change(s) are incorporated into the above-identified contract.  Approval of this change order will establish a 
new contract amount.  All other contract terms and conditions remain unchanged.
With this Change Order, Cumulatively, the total amount of this contract has increased 198.5%.
Change Order No. 11 for On-Call Contract FCD2009C005 adds $400,000 to the existing contract increasing its value from $5,570,000 to $5,970,000. This change 
order will also add 1096 days to the contract changing its end date from December 31, 2023 to December 31, 2026.
Current Change Order Request:
Amended Contract Amount w/ current change order:
Consultant Name:
Tetra Tech, Inc.
800 E. Wetmore, Suite 230
Douglas G. Lantz
7/21/2022
DISTRICT APPROVAL
Tucson, AZ 85719
Principal Project Manager
Consultant Address:
Division Concurrence
I certify that this change is required to accomplish the overall task for which this 
contract is initiated.
Project Manager
Division Manager
ACCEPTED AND APPROVED:
I certify that funds are available to accomplish this Change Order
I certify that this change is within the limits authorized by the Maricopa County 
Procurement Code.
Controller
FLOOD CONTROL DISTRICT OF MARICOPA COUNTY
RECOMMENDED BY:
Contracts Branch
General Counsel, District
Michael A. Fulton
Chairman, Board of Directors
Director
LEGAL REVIEW
Approved as to form and within the powers and authority
granted under the laws of the State of Arizona to the Flood
Control Dist. of Maricopa Cnty.
Change Order form revised 08/06/2010
DocuSign Envelope ID: DE019028-21EA-4B54-941E-5BFD2ECA70AE
7/21/2022
7/21/2022
7/21/2022
7/22/2022
7/22/2022
7/22/2022