11 Date: 7/19/2022 Amount: $400,000.00 File No: XXXXX PCN No: 207.01.31 Initial Amount: Contract NTP Date: 9/9/2009 $3,570,000.00 1096 days extension of time will be allowed. 12/31/2026 . 2,000,000.00 $ 5,570,000.00 $ 400,000.00 $ 5,970,000.00 $ Principal (Signature): Printed Name: Title: Date: Date Date Date Date Date Date ATTEST: Date Clerk of the Board Date Change Order Number: Contract No: Consultant Name: Contract Title: Approval of this change order establishes a new contract amount of $5,970,000 and a new completion date of December 31, 2026. We, the undersigned Contractor, having given careful consideration to the change(s) proposed, hereby agree that upon execution of this change order that we will provide all equipment, furnish all material (except as noted in the bid line item sheet), perform all work specified in the bid line item sheet; and we will accept as full payment therefore the prices shown in the bid line item sheet. The contract completion date is: $2,000,000.00 Total Previous Change Orders: By reason of this proposed change Initial Contract Amount: Amended Contract Amount w/ previous change orders: The following financial information is submitted: Copy to: Contract File, Finance, Division Manager, Project Manager CONSULTANT CHANGE ORDER - BOD APPROVAL FCD 2009C005 Tetra Tech Inc. Buckeye FRS No. 1 Rehabilitation Project Flood Control District of Maricopa County By mutual agreement of the parties, the following contract change(s) are incorporated into the above-identified contract. Approval of this change order will establish a new contract amount. All other contract terms and conditions remain unchanged. With this Change Order, Cumulatively, the total amount of this contract has increased 198.5%. Change Order No. 11 for On-Call Contract FCD2009C005 adds $400,000 to the existing contract increasing its value from $5,570,000 to $5,970,000. This change order will also add 1096 days to the contract changing its end date from December 31, 2023 to December 31, 2026. Current Change Order Request: Amended Contract Amount w/ current change order: Consultant Name: Tetra Tech, Inc. 800 E. Wetmore, Suite 230 Douglas G. Lantz 7/21/2022 DISTRICT APPROVAL Tucson, AZ 85719 Principal Project Manager Consultant Address: Division Concurrence I certify that this change is required to accomplish the overall task for which this contract is initiated. Project Manager Division Manager ACCEPTED AND APPROVED: I certify that funds are available to accomplish this Change Order I certify that this change is within the limits authorized by the Maricopa County Procurement Code. Controller FLOOD CONTROL DISTRICT OF MARICOPA COUNTY RECOMMENDED BY: Contracts Branch General Counsel, District Michael A. Fulton Chairman, Board of Directors Director LEGAL REVIEW Approved as to form and within the powers and authority granted under the laws of the State of Arizona to the Flood Control Dist. of Maricopa Cnty. Change Order form revised 08/06/2010 DocuSign Envelope ID: DE019028-21EA-4B54-941E-5BFD2ECA70AE 7/21/2022 7/21/2022 7/21/2022 7/22/2022 7/22/2022 7/22/2022