Presentation

City of Glendale — Regular Meeting (2022-02-24)

View PDF Item 4 Meeting page

Extracted text (via pymupdf) 6122 characters
WOOLF CROSSING PAD 
AMENDMENT 
ZON21-29
Planning Commission – February 24, 2022
Alex Lerma 
Planning Project Manager

Request
2
Request to amend the Woolf Crossing PAD building 
development standards for parcel K, L and M of the 
PAD site. 
Applicant:  Cindy Paddock, on behalf of 
HilgartWilson, representing Woolf Family 
Enterprises Limited Partnership

3
CITY 
HALL
SITE
Vicinity Map
Located at the 
southeast corner of 
Olive Avenue and Loop 
303.

4
Zoning Map

5
Aerial

6
LAFB LDN

7
PAD Development Plan

8
Project Details 
• Amend existing development standards for 
Parcel K, L and M. 
• Amendment will allow compatibility with 
LCLU and consistency with previous PAD 
amendments to Parcel C through J.
• Amendment will meet needs of industrial uses 
withing site.

9
Development Standards 
DEVELOPMENT 
STANDARD
EXISTING PAD 
(2006)
PROPOSED PAD 
AMENDMENT
Minimum Building Setback1
Front Setback 
25 feet2
30 feet
Rear Setback
60 feet2
15 feet
Street Side 
Setback 
60 feet2
30 feet – arterial 
street
20 feet – all other 
streets
Maximum 
Structure Height 
30 feet3
100 feet
Maximum FAR
0.30
1.0

10
Development Standards 
PARKING 
STANDARDS
EXISITNG PAD 
(2006)
PROPOSED PAD 
AMENDMENT 
Section 6.11 © -
LCLU Parking 
Standards 
(Original PAD) 
Parking will be in 
compliance with
Section 7.400 of 
Glendale Zoning 
Ordinance 
1 space per 2,000 
Square Feet. 
1Building setback for arterial streets shall be a minimum of one foot for each 
foot of building height. 
260 feet to residential uses. 15 feet to non-residential uses. 
3Maximum height of accessory structures is 15 feet. 
Note: Development standards denoted by footnotes 1 & 3 are being removed.

11
Public Involvement
• Notice mailed October 26th.
• Virtual neighborhood meeting was held on 
November 10th.  
• Request advertised in The Arizona Republic on 
February 2nd.
• Hearing notices mailed on February 4th. 
• Property posted on-site February 3rd.

12
• The PAD zoning amendment will remain 
consistent with the RMU and LCLU land use 
designations. The proposed amendments 
will maintain the overall development 
unified by having a consistency in building 
and design. 
Finding & Analysis

13
Finding & Analysis 
•Proposed amendments will be exclusive 
to Parcel K, L and M. 
•Amended development standards will 
facilitate development of a rage of 
industrial and manufacturing project 
supported by the size and type of 
buildings currently being constructed in 
the area.

14
Finding & Analysis 
• Amended development standards create 
compatibility with adjacent employment 
facilities in Woolf Logistics PAD to the east. 
• Development will require a FAA Form 7460 
to the FAA Regional Office prior to onsite 
improvements.

15
• No TIS was required based on minor 
modification to the PAD building standards. 
• All applicable city departments have reviewed 
the application and have recommended 
approval. 
• Stipulations have been added to ensure 
quality development. 
Finding & Analysis

16
Should the Planning Commission motion to 
recommend approval of ZON21-29, it should be 
subject to the following stipulations:
1. Development shall be in substantial 
conformance to the PAD Booklet entitled 
“Woolf Crossing PAD Amendment Narrative,” 
date stamped December 22, 2021.
Recommendation

Continued:
17
2. Prior to issuance of a permit for vertical 
construction or other improvements, the 
developer shall submit FAA Form 7460 to the 
FAA Regional Office.

Continued:
18
3.
Dedication of additional right-of-way for 
Northern Avenue to provide for a total half 
width of 55 feet, except within 250 feet of a 
major intersection where the right-of-way 
dedication shall increase to 65 feet. Except for 
the area between Sarival Avenue and Loop 
303, the half street right-of-way in this area 
shall be 65 feet and increase to 75 feet within 
250 feet of a major intersection. Such 
dedication shall be made at the time of 
development of adjacent parcel.

Continued:
19
4. Dedication of additional right-of-way for 
Sarival Avenue to provide for a total half-street 
width of 65 feet, except within 250 feet of a 
major intersection where the right-of-way 
dedication shall increase to 75 feet. Such 
dedication shall be made at the time of 
development of adjacent parcel.

Continued:
20
5. Dedication of additional right-of-way for 
Reems Road, south of Northern Parkway, to 
provide for a total half-width of 55 feet, except 
within 250 feet of a major intersection where 
the right-of-way dedication shall increase to 
65 feet. Such dedication shall be made at the 
time of development of adjacent parcel.

Continued:
21
6. Dedication of additional right-of-way for all 
collector streets to provide for a total width of 
70 feet (90 feet with medians). Such 
dedication shall be made at the time of 
development of adjacent parcel.
7. Dedication of additional right-of-way for all 
local streets to provide for a total width of 50 
feet shall be made before issuing any building 
permits for any part of the project.

Continued:
22
8. No parallel utilities will be located in the 
Northern Parkway right-of-way.
9. All half-street improvements on Northern 
Avenue, Reems Road, and Sarival Avenue, 
which are adjacent to the parcel to be 
developed, shall be completed prior to 
Certificate of Occupancy for said development. 
Required improvement standards are 
determined by the City of Glendale Engineering 
Design Construction Standards.

Continued:
23
10.Maricopa County Department of Transportation 
(MCDOT) operates and controls Olive Avenue 
adjacent to the development. The developer 
shall coordinate with MCDOT on the right-of-
way and roadway section requirements as well 
as the timing and required half-street 
improvements for Olive Avenue. Also, the 
developer shall be required to coordinate with 
MCDOT all items related to access to and from 
the proposed development(s) onto Olive 
Avenue.

Continued:
24
11.All irrigation ditches located on the property 
shall be tiled or abandoned.

WOOLF CROSSING PAD 
AMENDMENT 
ZON21-29
Planning Commission – February 24, 2022
Alex Lerma 
Planning Project Manager