Date: April 29, 2026 for May 6, 2026 scheduled meeting Page: 1 of 8 To: Planning Commission From: Koren Manning, Director of Planning and Development Services, and Executive Secretary Subject: C8-25-04 Large-Scale Data Center Regulations Unified Development Code Amendment (Citywide) Issue – This study session item is being held to present a proposed code amendment to the Unified Development Code (UDC) to establish regulations and standards for large-scale data centers. This amendment was initiated by Mayor and Council during their August 6, 2025 study session (see Attachment A for the Legal Action Report from that meeting). At that time, Mayor and Council directed City staff to develop regulations for this use. This request was part of the motion Mayor and Council adopted to not consider the proposed Project Blue data center annexation and Development Agreement. A second Mayor and Council Study Session was held on April 7, 2026. during which Mayor and Council provided additional feedback on the proposed code amendment (see Attachment B). The proposed code amendment would establish a definition of large-scale data centers and establish use- specific standards. The proposed code amendment has been developed with input from a Technical Advisory Committee (TAC), four community engagement meetings and community survey, and Mayor and Council feedback. Staff Recommendation – Staff recommends the Planning Commission set the Unified Development Code Amendment to establish regulations for Large-Scale Data Centers for a public hearing on June 3, 2026. Background – At the August 6, 2025, Mayor and Council study session regarding the proposed “Project Blue” annexation, Mayor and Council directed staff to develop zoning regulations for large-scale data centers. Staff then brought this request before the Planning Commission for an initial Study Session, and formed a Technical Advisory Committee to inform the development of the proposed standards, as detailed below. On September 9, 2025, the Zoning Administrator issued a Determination which established large-scale data centers as the most appropriately classified use per the Unified Development Code as a Generating System land use (see Attachment C). This use is not currently permitted by-right in any zone, has no use-specific standards, and may only be developed through a rezoning process to a Planned Area Development (PAD). This Determination anticipated a later UDC code amendment process to establish a new defined use, development standards, and review process for large-scale data centers. xz Attachment I Page: 2 of 8 PLANNING COMMISSION MEMORANDUM C8-25-04 Large-Scale Data Center Regulations UDC Amendment Study Session (Citywide) On September 17, 2025, Planning and Development Services Department (PDSD) presented preliminary information at a study session to the Tucson Planning Commission (See Attachment D). That presentation included an overview of the demand for data centers, how facilities are currently classified in the UDC, and potential regulatory components such as definitions, zoning classifications, use-specific standards, and review procedures. PDSD staff also requested and received initial feedback on potential regulations for large-scale data centers from Planning Commission members. Community Outreach and Stakeholder Engagement Following direction from Mayor and Council and the Planning Commission study session, staff initiated research and analysis of regulatory approaches used in other jurisdictions and formed a Technical Advisory Committee (TAC) to provide subject matter expertise. The TAC was formed with input from the City Manager’s office, Mayor and Council, the Planning Commission, and suggestions from local experts on Data Centers operations, Water, Environmental, and Energy issues. The TAC met four times over a three-month period to identify key issues, review best practices, and provide recommendations related to land use compatibility, infrastructure impacts, and environmental considerations associated with large-scale data center development. Membership of the TAC and meeting notes are provided in Attachment E. In addition to convening a Technical Advisory Committee (TAC), PDSD staff sought input and feedback on the proposed regulations through public outreach efforts. Staff held four public community meetings in February and March 2026, offered in both in-person and virtual formats. More than 200 participants attended the four meetings, and more than 1,100 comments were received through surveys, discussions, and written feedback. Each meeting included presentations, open discussion, and opportunities for participants to provide input. Please see the Compilation of All Public Comments (see Attachment F) for additional information on public feedback. Throughout the process, there has been coordination between the development of standards for large- scale data centers and the City’s Large Quantity Water User Ordinance, with overlap between the staff as well as stakeholders involved in each process. Initial Technical Advisory Committee Meetings As noted above, a Technical Advisory Committee (TAC) was organized by PDSD to provide technical expertise and stakeholder input during development of the proposed amendment. The TAC included representatives from utilities, environmental organizations, the technology sector, planning professionals, and community organizations. A total of four meetings were held, with the initial three taking place between November 2025 and January 2026 to review draft concepts, discuss potential regulatory approaches, and identify key land-use considerations associated with large-scale data centers. During the first meeting on November 17, 2025, staff provided background on the Mayor and Council direction to develop regulations for large-scale data centers and reviewed the scope of the code amendment process. TAC members discussed the current regulatory context, including the role of zoning in addressing land use impacts and the limitations of zoning related to regulating water and energy consumption directly. Members also reviewed examples from other Arizona jurisdictions and identified priority issues for the Tucson ordinance, including noise impacts, water use considerations, energy infrastructure, design compatibility, and public engagement. The second meeting on December 15, 2025, focused on the discussion of potential regulatory topics and approaches for the amendment. TAC members reviewed possible definitions and size thresholds for Page: 3 of 8 PLANNING COMMISSION MEMORANDUM C8-25-04 Large-Scale Data Center Regulations UDC Amendment Study Session (Citywide) large-scale data centers, zoning districts in which such use may be permitted, and potential review processes. The group also discussed expanded public notice requirements and the role of development agreements as a tool to address considerations that cannot be regulated through zoning. Members emphasized the importance of clear public communication and robust notification processes for future proposals. The third meeting on January 12, 2026, continued the discussion of potential development standards, including setbacks; noise mitigation measures; generator operation and backup power systems; landscaping and heat mitigation strategies; wildlife and environmental protections; and design considerations. Members also discussed approaches for addressing community concerns related to water and energy use through coordination with other City policies and ordinances, including the Large Quantity Water User Ordinance and relevant sustainability plans. Feedback from the first three TAC meetings helped inform the proposed standards. These proposed standards were then presented to the public in February and March. For the meeting notes and presentations from all TAC meetings please see Attachment E. Public Meetings and Community Feedback Staff conducted four public meetings in February and March 2026 to present proposed regulations for large-scale data centers and gather community feedback. The meetings included two in-person sessions held at Pueblo High School (February 19) and Rincon/University High School (March 5), as well as two virtual meetings (February 23 and March 4). Across all meetings, more than 200 individuals participated, and hundreds of written comments were submitted through surveys, meeting discussions, and follow-up feedback. Each meeting included a staff presentation providing an overview of the proposed regulations, followed by opportunities for public input. Engagement formats varied by session and included open comment periods, small group discussions to facilitate dialogue, and structured question-and-answer segments to allow for more detailed feedback and clarification. 1. February 19 (In-Person): Approximately 51 attendees; included a mix of previously engaged community members, students, and residents seeking information. 2. February 23 (Virtual): Approximately 61 attendees; many participants new to the topic. 3. March 4 (Virtual): Approximately 48 attendees; greater participation from professionals and retirees, with more detailed, technical feedback. 4. March 5 (In-Person): Approximately 40 attendees; including many attendees familiar with the topic who may have participated previously. Overall, the primary themes raised during the outreach process included concerns related to water availability, energy consumption, noise and generator operations, environmental impacts, and transparency regarding potential community benefits (See Attachment F for comments received as of April 27, 2026). Feedback generally fell into the following categories: 1. Water Scarcity (most frequently raised concern) - The overwhelming sentiment was that Tucson does not have adequate water to support large-scale data centers. Residents repeatedly questioned where the water will come from, argued that "adequate water supply" in the desert is impossible long-term, and called for a strengthened Large Quantity Water User Ordinance. Many stated that only recycled water, not potable or groundwater, should be permitted, with some calling for mandatory closed-loop cooling systems. Page: 4 of 8 PLANNING COMMISSION MEMORANDUM C8-25-04 Large-Scale Data Center Regulations UDC Amendment Study Session (Citywide) 2. Energy Demands & Utility Costs - Residents are concerned that data centers will strain the existing electrical grid, force construction of new natural gas generation, and raise utility rates for existing customers. Multiple commenters specifically cited Project Blue as an example of ratepayers potentially subsidizing a data center. Many stated that 100% renewable energy with no offsets or credits be required, and that data center developers, not ratepayer, bear the full cost of new infrastructure. 3. Opposition to Data Centers - A significant portion of comments stated they are opposed to any data centers in Tucson at all. Common refrains included "No data centers, period," "ban hyperscale data centers," "full moratorium." Some framed this as a resource issue, others as an environmental or political one (surveillance, AI, corporate interest, etc.). 4. Setbacks - Many commenters stated the proposed 400-foot setback from residential areas is far too small. Requests ranged from 1,000 feet to 2 miles. Commenters cited noise, air quality, heat island effects, and visual impact on Tucson's natural views. 5. Definition & Size Threshold – Many commenters stated that the proposed 50,000 sq ft threshold for defining a "large-scale data center" is too high. They further stated that the definition should be based on energy consumption (e.g., megawatts) or water use rather than square footage alone, since technology changes and smaller facilities can still have enormous resource impacts. 6. Noise and Generator Use – Significant concern was voiced about generator noise and air quality impacts. Commenters asked for strict, clearly defined noise standards with enforceable limits that address sound frequency and duration. Many voiced outright opposition to any diesel backup generators in favor of battery only backup. 7. Neighborhood Notification Process – Commenters felt that the proposed expanded public notification process for large-scale data centers is inadequate and should be expanded beyond the proposed quarter-mile. Commenters also suggested a citywide public notice of the neighborhood meeting, and mailed notification to renters as well as property owners. 8. Enforcement & Accountability – Recurring concerns were voiced about what happens if a data center operator violates the City’s zoning regulations or conditions of the data center’s approval. Many commenters asked for stronger, clearly defined enforcement measures, such as ongoing monitoring requirements, utility shutoffs, or other meaningful consequences, rather than relying solely on fines. 9. Climate & Environmental Compatibility - Commenters stated that large data centers conflict with Tucson's Climate Action Plans, contribute to heat island effects, increase ozone and particulate pollution from generators, and destroy natural habitat. Fourth Technical Advisory Committee Meeting A fourth TAC meeting was held on March 9, 2026, focused on reviewing feedback received during the February–March 2026 community outreach process and discussing potential revisions to the proposed large-scale Data Center regulations. Staff presented an overview of the draft regulations previously shared with the public and summarized comments received from four community meetings, with concerns primarily focused on water availability, energy use, noise, air quality, equity considerations, and broader issues related to technology and artificial intelligence. TAC members mainly discussed the following topics: 1. Challenges of addressing some concerns through zoning regulations, particularly those related to energy generation and water consumption, and emphasized the importance of clearly communicating the role and limitations of zoning. 2. Potential modifications to the proposed standards in several areas, including the use definition Page: 5 of 8 PLANNING COMMISSION MEMORANDUM C8-25-04 Large-Scale Data Center Regulations UDC Amendment Study Session (Citywide) and size threshold, expanded public notice requirements, separation from residential and commercial areas, noise mitigation measures, and standards for backup power systems such as generators and battery storage. 3. Energy implications, including generator operations, potential impacts on air quality, and coordination with utility providers during maintenance or emergency events. Feedback from the fourth TAC meeting helped inform the refinement of the proposed development standards (see Attachment E for a full summary of the TAC materials). Mayor and Council Study Session On April 7, 2026 Mayor and Council held a study session on the proposed regulations for large-scale data centers. During this study session, PDSD staff presented an update on the development of the proposed regulations. These included a summary of the TAC's work, engagement with community members, and key takeaways from public outreach. The proposed regulations and options for revisions to specific standards were also presented. Mayor and Council conveyed that they were in support of the potential revisions suggested by staff and informed by public feedback. They also acknowledged the concerns that community members expressed during the engagement process with regard to the amount of water and energy required for a large-scale data center to operate, with unknown community benefits. However, it was also acknowledged that technology is changing rapidly and conditions for development may be more favorable sometime in the future. Furthermore, Arizona State Statute limits the City’s ability to place a moratorium on large-scale data centers for longer than 120 days without justifying the prohibition or risk legal action from potential developers. Mayor and Council offered several notes for revisions to the first draft of the amendment language: 1. Several council members supported the inclusion of an energy consumption threshold as part of the definition of a large-scale Data Center 2. There was consensus on enhanced public notice standards 3. Several council members supported limiting large-scale data centers to PAD or PCD applications instead of allowing them within the I-2 zone due to environmental justice concerns. 4. Several council members requested that staff continue to investigate what other localities have done to regulate large-scale data centers. Mayor and Council then directed staff to present their findings and draft materials to the Planning Commission for additional feedback and consideration. Present Consideration(s) – The proposed amendment to the Unified Development Code would establish a regulatory framework for large-scale data centers. The proposal introduces a definition for large-scale data centers and establishes where and how these facilities may be permitted, along with use- specific standards intended to address land use compatibility, environmental impacts, and operational considerations (see Attachment G, Proposed Code Amendment Fact Sheet). Large-Scale Data Centers Unified Development Code Proposal Throughout the process of research, advisory input from the TAC, and public input, staff developed a proposal for UDC code changes. The proposal is based on best practices, regional considerations, and precedents already established in the UDC. Below is an overview of the proposed regulations (see draft code amendment in Attachment H). Page: 6 of 8 PLANNING COMMISSION MEMORANDUM C8-25-04 Large-Scale Data Center Regulations UDC Amendment Study Session (Citywide) Definition and Size Threshold Proposed Regulation: The proposed definition includes both a square footage and a power consumption threshold, minimum floor area of 25,000 square feet, or power consumption of 50 Megawatts. The proposed definition for a large-scale data center is as follows: A facility, multiple facilities, or portion of a facility on a contiguous site with the same controlling ownership interest, and a gross floor area greater than 25,000 square feet or uses greater than 50 megawatts (MW) of energy, housing networked computer systems and/or telecommunications equipment used for remote storage, processing, and distribution of data. In addition to the regulations proposed below, any large-scale data center would need to comply with all existing Commercial Rainwater Harvesting Standards, Environmental Resource Zone (ERZ), and Watercourse Amenities, Safety, and Habitat (WASH) regulations contained within the Unified Development Code. Review Process and Zoning Proposed Regulation: Large-Scale Data Centers are permitted through adoption or major amendment of a Planned Area Development (PAD) or a Planned Community Development (PCD). Large-Scale Data Centers are not permitted as of right or through a special exception in any other zone. Establishing or amending a PAD or PCD is a rezoning process subject to Mayor and Council review. Separation from Residential and other Non-Industrial Uses Proposed Regulation: Must be located a minimum of 1,320 feet (one quarter mile) from residential zones as well as certain uses (nursing home, residential care facilities, educational uses) and 600 feet from commercial or office zones. Public Notice Proposed Regulation: Require an enhanced public notice of all property owners within a half mile, and all Neighborhood Associations within 2 miles, which is consistent with Planned Community Development notice requirements, for the required neighborhood meeting and public hearing before the Zoning Examiner. Additional notice is being proposed due to the broader impacts of large-scale data centers, and the typically low-density surrounding areas where large-scale data centers are likely to be proposed. Water Supply Certification and Restriction on Potable Water Use Proposed Regulation: Reaffirm requirements to comply with the City’s Large Quantity Water User Ordinance. Additionally, if an applicant is not subject to the Large Quantity Water User Ordinance, the use of potable water for data center cooling is prohibited and an applicant is required to demonstrate access to an adequate water supply. A mitigation plan may also be required to address impacts during drought or local water emergency. Energy Disclosure Proposed Regulation: At the time of application, require that applicants demonstrate access to an adequate energy supply and disclose their proposed amount of energy and energy mix, including renewables. Page: 7 of 8 PLANNING COMMISSION MEMORANDUM C8-25-04 Large-Scale Data Center Regulations UDC Amendment Study Session (Citywide) Noise and Generators Proposed Regulation: Applicants must provide an independent noise study as well as a noise mitigation plan at the time of application. The code establishes strict decibel limits at the property line and requires annual monitoring. For generators, only Tier IV or natural gas/dual-fuel generators would be permitted, with requirements for “battery-first” backup systems, limits on hours of maintenance testing, and prohibition of “load shifting”. Additionally, data center operators could be required, at the City’s discretion, to identify a point of contact for community concerns about noise or other negative impacts. This stipulation was added after receiving feedback from both the public at large and Mayor and Council. Development Standards Proposed Regulation: Require a 20-foot enhanced landscaping border and right-size parking standards to reduce paved surfaces and mitigate urban heat island effects. Require sound blocking and screening for generators and other noise-producing mechanical equipment through solid screened walls or rooftop screening. Lot coverage is restricted to 40% where the remaining area must be dedicated to natural open space and any disturbed land not included in project site must be revegetated with native plantings. Plan Tucson Consideration(s) – Plan Tucson does not specifically address the location of large-scale data centers, as this land use had not been defined in Tucson even during the outreach and drafting of the recently adopted Plan Tucson 2025. The General Plan does speak to what should be considered with regard to the impacts of large-scale Data Centers. Government 4: Provide diverse, well-resourced opportunities for productive public engagement throughout the planning and decision-making process of City initiatives that respect and accommodate disabilities and diverse cultural needs by implementing a variety of interactive methods and communication tools to maximize inclusive participation. Climate 3: Use a variety of strategies to ensure that all residents benefit from initiatives aimed at resilience and sustainability. Climate 6: Develop a regional collaborative approach with public and private partnerships to reduce energy consumption and transition to renewable energy sources. Water 3: Encourage appropriate use of reclaimed water and other potable water alternatives. Water 7: Encourage increased water efficiency in both existing and new private and public developments, promoting user-level conservation practices across all water use contexts by expanding effective water efficiency and conservation programs across all sectors. Environment 8: Promote the designs of buildings and use of materials that mitigate or reduce noise pollution Economy 13: Create a business supportive climate through investment in public infrastructure and services, through its regulations and policies, and in building public-private partnerships. Land Use 6: Create a business supportive climate through investment in public infrastructure and services, through its regulations and policies, and in building public-private partnerships. Page: 8 of 8 PLANNING COMMISSION MEMORANDUM C8-25-04 Large-Scale Data Center Regulations UDC Amendment Study Session (Citywide) Land Use 12: Apply the Guidelines for Development Review to the appropriate Building Blocks in the Future Growth Scenario Map, included in chapter four, to evaluate and provide direction for annexations, plan amendments, rezoning requests and special exception applications, Board of Adjustment appeals and variance requests, and other development review applications that require plan compliance. Land Use 25: Work collaboratively with Arizona State Land Department, Pima County, and nearby major land users to identify strategic and appropriate land uses within the Southlands and Houghton Corridor area. Attachments: A. August 6, 2025 Mayor and Council Legal Action Report B. April 7, 2026 Mayor and Council Legal Action Report C. Zoning Administrator Determination Letter for Large-Scale Data Centers D. Planning Commission Study Session Materials, September 17, 2025 E. Technical Advisory Committee Membership, Meeting Summaries, and Presentations F. Compilation of Public Comments G. Proposed Code Amendment Fact Sheet H. Draft Regulations for Large-Scale Data Centers