Construction Report

City of Chandler — Regular Meeting (2026-04-08)

View PDF Meeting page

Extracted text (via pymupdf) 1079 characters
Capital Projects – Design Phase: 
 
West Airport Facilities Upgrade: City funded at $3.9 million.  Revised scope includes operations 
garage, parking lot and aircraft observation area.  Finalizing plan comments. Evaluating utility 
relocation options and new phasing plan. 
 
Airport Fuel Tank Relocation: City funded at $610,000.  Cost negotiation with vendors.  Budget 
transfer under evaluation.  Evaluating alternative methods. 
 
Runway End Identifier Light (REIL) Installation Runway 4L-22R (North Runway): FAA funding 
for $110,000.  Revising drawings for circuit change for 24/7 REILs. FAA confirmed environmental 
clearance. 
 
Capital Projects - Construction Phase: 
 
Hangar Area Pavement Rehabilitation:  Completed. 
 
Taxiway B Improvements- Phase 1:  Completed. 
 
Former K&K Site Remediation: City funding for soil remediation near end of Cooper Road north 
of Queen Creek.  5.8 acre restricted use area remaining.  Topographic survey for current site 
elevations forthcoming. 
 
Meeting Date:  
April 8, 2026 
Chandler Municipal Airport 
Construction Report