D2 NL SPLASH - BUDGET PROPOSAL 091824.PDF
Extracted text (via pymupdf)
1151 characters
Scope/Description
Budget
Estimated Timeline/Duration*
FY Expenditure
Splash Pad Repairs and Improvements
$85,000.00
11 Weeks
Expended in FY25
Splash pad improvemetns Design and Permitting
Included above
Included Above
Expended in FY25
Replacement of splashpad holding/recirculating tanks and equipment upgrades
Included above
Included Above
Expended in FY26
Pump and circulation equipment upgrades
Included above
Included Above
Expended in FY27
Tuff Coat Safety Surfacing
Included above
Included Above
Expended in FY25
Facilities Management project management time
$6,000.00
N/A
Expended in FY25
Contingency
$17,000.00
N/A
Expended in FY25
TOTAL
$108,000.00
11 Weeks
Expended in FY25
*Items are concurrent and non-concurrent with other scopes of work
La Mesita - New Leaf
Splash Pad Improvements
CSF-Proposed Budget Summary
Construction Start Date: 10/28/2024
Construction Completion Date: 1/13/2025