MARS PROJECT GAP ANALYSIS 
REF 
NO.
CURRENT STATE
DESIRED STATE
DESCRIPTION / NOTES
PROPOSAL
OUTCOME
1
Competent technical experts 
assigned to project; Team is 
focused on resolving short-term 
urgent issues, with no true critical 
path defined or managed.Global 
strategy for project 
accomplishment needed
Global strategy for project 
accomplishment drives daily tasks of 
technical experts.
Technical experts contribute exceptional value to the quality of the daily development of 
the project, but cannot themselves define the critical path, anticipate future problems, 
problem solve at a global level, and remove barriers for the team. There is no shortage 
of detail-level tasks that must be accomplished to successfully implement a project of 
this scope and scale.  However the approach MUST be outcome-oriented: fully define 
the project scope and stakeholder roles, establish the critical path, define the steps and 
timelines required to accomplish the milestones on the critical path, and THEN define 
and accomplish the associated tasks.
MC & ESRI-C hire/retain experienced project 
managers with a history of demonstrated 
success in managing complex, large scale IT 
applications.
Both MC & ESRI-C hired experienced PMs 
freeing up technical experts to perform 
essential tasks. Team is solidifying the critical 
path and associated strategies.
2
"Go-Live" functionality limited to 
one seasonal function with future 
development of some statutorily 
required calendar functions to be 
developed on a "Just In Time" 
basis, and others listed as "Road 
Map" items with no funding or 
plan established.
All statutory and constitutional 
requirements need to be developed, 
tested, implemented, and fully 
functional for "Go Live."
February 2021 "Go Live" date reflects the ability to accomplish only those tasks 
required by statute to be accomplished in February.  Development of critical 
functionality, such as notices of change, would not even begin until after this date, with 
the hope of completing the development and implementing the functionality in time to 
meet the statutory deadlines.  Essential elements, such as in appeals and legal 
classification verification (LCV) are no longer included in the project scope but are 
instead listed as "Road Map" items with no funding or plan.
Establish a project plan and corresponding 
contract amendment to efficiently and 
effectively develop ALL essential functionality. 
Reserve post Go Live activities for 
configuration, enhancement, and 
complementary functionality, and Road Map for 
future desired enhancements.
PCR 05 to be considered by BOS will 
establish a new Go Live date of February 
2022 and contain all essential elements
3
Project team dedicated to project 
but isolated from business 
operations
Project team dedicated to project 
AND connected to business 
operations, ensuring effective 
representation of business needs.
Dedicated resources for project development are key to ensuring a successful project 
implementation.  Those same resources must be in tune with the business operations to 
effectively represent and advocate on their behalf.
Continue to dedicate staff to project success, 
while actively engaging business units in 
process mapping and testing.
Business units now involved and advocating 
for their business needs. Mission specialists, 
identified for each line of service, are actively 
testing and resolving business concerns. 
System gaps are being identified and 
addressed.
4
Business Analysis is completed 
on a Just-In-Time basis
Business Analysis is a critical 
development resource and MUST be 
made a priority
Business Analysis provides critical information on remaining effort so we can identify 
needs.  Story points are growing and need to have this completed or much further 
ahead of development to accurately reflect outstanding work.  The team is identifying 
data to support the effort required and want to ensure if any contract amendment is 
completed a date is agreed upon for when this will be done.  
EC to hire one BA; County hire one additional 
BA using ACRO contract for 3-4 months to 
help complete work.
Business Analysis (BA) schedule now 
required from ESRI-C by Release 19 delivery 
to be approved by MC. During six week period 
while technical teams addressed known 
deficiencies, BA team worked ahead of 
development. Continues to be a watch item.
5
As Business Analysis 
progresses, EC often wants to 
rework an area previously 
completed.
Accomplish BA work in advance to 
minimize the need for rework
As business analysis continues, at times, EC wants to re-work an area which has been 
previously completed.  Our teams work together and many times the idea does help 
support the product.  As this work increases it does cause changes to our release plan.  
But again, if analysis is done early this category should decrease.
Allocate sufficient BA resources and analyze 
remaining functionality to minimize the need for 
rework.
Allocated additional business analysis 
resources.  Business Review Team now 
evaluates each new software function to 
ensure accurate reflection of business needs 
and priorities.
6
Development: Business analysis 
trend to date would indicate 
remaining effort will be greater 
than anticipated.
Accurate projection of remaining 
effort and assignment of sufficent 
resources to accomplish with great 
quality.
Allocation of additional BA resources would result in information on remaining effort to 
help identify needs.   Quality is still tracking with the new release with a few days of 
testing.  Additional resources should help increase velocity. It was noted by EC some of 
the areas in the prior release became more complicated than originally thought which 
took longer for development.
Hire two additional BAs and two new 
developers to have time to train while the BA 
work continues. 
EC hired three new developers to address 
Azure, quality control, and business function 
development, one additional BA, and a new 
PM, allowing the Subject Matter Expert (SME) 
more time to dedicate to business analysis 
work.
7
Current resources may be 
insufficient for timely deployment 
given realistic projection of 
necessary effort
Accurately estimate the required level 
of effort and allocate sufficient 
resources (quantity, roles, and 
skillset) for successful and timely 
deployment
Workied with OET to compile needs.  Identified need for two oversight positions. One 
would be a PM coordinator who is responsible for contract monitoring, meetings, 
documenting progress, etc.  This would encompass the day-in day-out activities of the 
project with the releases, sprints and documentation.  Another position would be a 
project manager who specializes in strategic planning for future activities.  This would 
include but not be limited to deployment, training, testing, etc.  This would allow us to 
capture some of the future risks on the project so the core team can concentrate on the 
development area.
County to hire 1 project manager to monitor 
project and add additional resource for 
strategic planning.  
Retained exceptional talent: PM on temporary 
assignment from OET and new project 
coordinator hired.

MARS PROJECT GAP ANALYSIS 
REF 
NO.
CURRENT STATE
DESIRED STATE
DESCRIPTION / NOTES
PROPOSAL
OUTCOME
8
Development of training materials 
removed from scope of contract
Fully developed materials, training 
plan, and strategy to provide excellent 
training for entire staff
With the changes brought about by the pandemic, less of the training is expected to be 
conducted through live, instructor-led courses. Assessor training division is proficient in 
developing online, computer-based training. 
Training will be a hybrid of workflow and 
software "button" training, resulting in a much 
more engaged workforce and much earlier 
identification of problems.
Assigned training development to Assessor 
training analyst, project coordinator and 
agency "mission specialists" (subject matter 
experts from each business unit). Leveraging 
County HUB resources and tools.
9
User documentation removed 
from scope of contract
Comprehensive user documentation 
provided in tandem with training
Can be done in combination with creating training documents but need to finalize User 
Interface in some areas.  EC has hired 2 UI staff to ensure all areas in the application 
are consistent with the same look & feel.  As part of the training program the user 
documentation can be created in tandem with training.
Working the vendor creating training programs 
would help to ensure product is delivered and 
core team remains focused on project.
Coordinating delivery of user documentation 
with training solution outlined above, and will 
be tailored specifically to Maricopa County.
10
Support: County has agreed to 
pay a substantial fee for software 
support, but  Service Level 
Agreement (SLA) lacks desired 
specificity regarding performance 
expectations or plan for support
Comprehensive Service Level 
Agreement depicting expectations 
and agreed upon service levels
Need to work with IT and MARS team on support or "Life after MARS" for our 
organization and with vendor. Some work has been done previously but needs to be 
updates. The new project manager activity will be to work with EC new PM for creation 
of support model.
Clarify the Service Level Agreement for post 
Go Live support of the software. The new MC 
PM will work with the EC PM to ensure the 
development plan identified in the contract is 
completed. Create change review board 
internally to determine which requests would 
be considered bug or defect vs enhancement.
SLA has been reviewed and updated for the 
proposed PCR 05 to adequately support the 
business into the future.
11
"Go Live" date of February 2021 
misleading (referring only to 
partial functionality) and even so, 
highly unlikely.  Remaining level 
of effort cannot be accomplished 
by February 2021 with existing 
allocation of resources
Realistic and transparent timeline, 
consistent progress and momentum, 
allocation of sufficient resources, and 
continued high quality of deliverables
Required functionality and user stories remain largely unchanged. Recognizing that the 
required level of effort is much greater than originally anticipated, project scope (desired 
future state) has been largely reduced through PCR 4, primarily in removing training, 
reports, and user documentation. As Business Analysis is conducted on these user 
stories, EC is recognizing that they underestimated the level of effort as reflected in the 
number of story points. Maricopa is not adding additional functionality but ensures the 
needs of the current system are being developed in the new system.
Considerations need to be given to PCR 05 to 
identify dates in the contract for items included 
in the releases, and recognizing go-live will 
occur February 2022 rather than February 
2021.  This would provide time to complete 
ALL development and provide some parallel 
testing with current 6i system.  This includes 
having a deadline date for BA work.
PCR 05 to be considered by BOS will 
establish a new Go Live date of February 
2022.  It contains dates for each delivery, 
deadlines for BA, improved estimates for level 
of effort, and additional releases to 
accomplish all required functionality.
12
Legislative requirements: 
statutory requirements and 
corresponding dates have not yet 
been aligned with calendar
All statutory requirements need to be 
documented as part of the calendar 
and incorporated into the release plan
EC is concentrating on valuation material.  We have many items in which we are 
required by statute.  All items need to be documented as part of the calendar to ensure 
they are included in a release plan. Having PM’s coordinate this effort will help all 
understand need of development
Identify all legislative items and ensure these 
items are included in releases. 
PCR 05 includes additional releases to 
address required functionality and to include 
retainage that is tied to delivery of critical 
business processes for the entire business 
cycle calendar.  Business Review Team has 
tightened up the review process to ensure 
legislative items prioritized in delivery.
13
Reports were removed from 
scope of contract with PCR 4
Identify resources and develop plan 
to successfully develop statutory and 
user defined reports
The MARS product is more fully developed now, allowing for a more effective use of 
report development resources.
Engage application development team and 
dedicate resources to ensure development of 
quality reports.
Recruitment underway for SQL report writer.
14
No plan exists to develop 
interfaces with ancillary systems, 
such as the Assessor website 
and the Treasurer's and 
Recorder's systems.
Smooth transition with external 
parties, ensuring accurate and timely 
information across platforms.
Parcel data is essential to the functionality of a multitude of systems and functions, from 
property tax to ownership.  Functionality must be developed to ensure all related 
systems reflect matching accurate data.
Develop a plan to address all relevant 
applications and ensure accurate data is 
shared across external systems and agencies.
Project budget request includes funding to 
develop interfaces.
15
Current Oracle 6i system no 
longer supported, and could not 
be rebuilt upon failure
Sustainable ability to accomplish 
required functions while building the 
new system, and to retrieve historical 
data for 6-7 years post Go Live
The Oracle 6i system currently in place was established in 1992, and last upgraded in 
2009.  The hardware and database alike are no longer supported or serviceable. Fully 
upgrading the database would be an endeavor of similar effort to building the new 
system. Data is backed up and protected, but the database itself could not be rebuilt in 
the case of catastrophic failure, rendering the backed up data inaccessible.
Replace the server hardware and upgrade the 
database to Oracle 10.2.5, the lowest level still 
currently supported by Oracle that is still 
compatible with the existing front end forms.
Purchased hardware, upgraded and tested a 
single node successfully.  Currently testing 
solution within a high availability environment. 
Oracle 10.2.5 upgraded week of October 27, 
2020 in test environment; production to be 
upgraded upon successful testing completion.