TT0345_CHANGE_ORDER_14_BOS.PDF

Maricopa County — Formal (2020-08-19)

View PDF Item 102 Meeting page

Extracted text (via pymupdf) 7209 characters
14
7/30/2020
79,786.87
$           
C-64-18-007-5-00-14
TT0345
9/12/2018
($2,579,347.21)
Date
Date
Date
Date
Date
Date
Date
Deputy County Attorney
Distribution:  Originals - Contractor, Contract Services, Clerk of the Board                Copies - Chief Construction Manager, Consultant (if applicable), City Partner (if applicable), Finance
Date
ATTEST:
LEGAL REVIEW
Approved as to form and within the powers and authority granted under the              laws of 
the State of Arizona to the Maricopa County Department of Transportation.
Clerk of the Board
Date
COUNTY APPROVAL
RECOMMENDED BY:
ACCEPTED AND APPROVED:
Transportation Director/County Engineer
Chairman, Board of Supervisors
CIP Cash Flow Manager
I certify that this change is within the limits authorized by the Maricopa County 
Procurement Code
Contract Services
 
I certify that this change is required for this contract
Consultant (if applicable)
Field Manager
I certify that funds are available to accomplish this Change Order
Branch Manager
CITY of  XXXXXXXXXX APPROVAL
I certify  that this change is required for this contract.
Project Manager:                                                            
Date:
MARICOPA COUNTY DEPARTMENT OF TRANSPORTATION
Printed Name Michael Sullivan
Title: Vice President
Date: 7/30/2020
Principal (Signature)
Federal Tax ID Number:          86-0744516
Amended Contract Amount w/ current change order
17,570,147.19
$                          
We, the undersigned Contractor, having given careful consideration to the change(s) proposed, hereby agree that upon execution of this change order that we will provide all equipment, furnish all
material (except as noted in the Bid Line Item Sheet), perform all work specified in Bid Line Item Sheets; and we will accept as full payment therefore the prices shown in Bid Line Item Sheet.
IN WITNESS WHEREOF, the parties herein have executed this Contract Change Order:
Initial Contract Amount
20,069,707.53
$                          
Amended Contract Amount w/ previous change orders
17,490,360.32
$                          
Current Change Order Request
79,786.87
$                                 
The Contractor, by mutual agreement of the parties, shall make the herein described changes to the plans and specifications or do the following described work not included in the plans
and specifications on the above-identified contract.  All other contract terms and conditions remain unchanged.   
Approval of this change order establishes a new contract amount of  $17,570,147.19 and a new completion date of 11/30/2020.
To Establish Change Order No. 13 to provide full and complete compensation to the Contractor for cost to complete the project within the time extension established in 
Change Order 11. Change Order 13 costs will be compensated by new Allowance and Lump Sum items which are based upon material and unit price increases; 
supervision and Site Special Conditions; additional subcontractor mobilizations; and daily traffic control cost during this time extension as detailed in Attachment A.
The following financial information is submitted:
Initial   Amount:
$20,069,707.53
Contract Award Date:
Total Prior Change Orders:
Contract No:
2018-034
Work Order No:
Contractor Name:
Combs Construction Company, Inc.
CONSTRUCTION CHANGE ORDER - BOS APPROVAL
Maricopa County Department of Transportation
Change Order Number:
Date:
Amount:
Agenda Item No.
Project Name:
MC85 - 95th Avenue to 83rd Avenue
Revised:  7/30/2020

Sheet 1 of 1
Bid Item No.
Unit
Estimated 
Quantity
As-Built    
Quantity
Difference    (+/-)
Unit Price
Difference   (+/-)
109.00050-14
LS
0
1
1.00 
 $                   79,786.87  $                                79,786.87 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Total this Sheet
79,786.87
$                    
Contract No. 2018-034
Bid Line Items Sheet
CONSTRUCTION CHANGE ORDER NO. 14
Provide description of work to be done, estimate of quantities, and prices to be paid, segregate between additional work at contract price, agreed price and
actual cost. Unless otherwise stated, rates for rental of equipment on actual cost work cover only such time as equipment is actually used and no allowance
will be made for idle times.
Description
Negotiated Settlement for Utility 
Relocation Delay Costs (6/17/2020-
7/12/2020)
Maricopa County Department of Transportation
Revised:  7/30/2020

INITIALS 
 
SUPPORT DOCUMENTATION 
 
 
 
 
 
 
 
 
 
To accompany CHANGE ORDER   14  
 
 /  
 
 
 
 
 
 
 
Page 
1 
 of 
1 
 
Maricopa County Department of Transportation 
ATTACHMENT “A” (Change Order Scope) 
Project#:  TT0345  
Project Name: MCDOT TT0345 – MC 85 at 83rd 
Avenue and Center Turn Lane Expansion 
Contract #: 2018-034 
 
Change Order #: 14 
Request: To Establish Change Order No. 14 for negotiated compensation to the Contractor, inclusive of 
all subcontractors, for claimed delay and standby cost incurred between June 17, 2020 and 
July 12, 2020. This change order shall be full and complete compensation for all direct cost, 
(Labor, vehicles and equipment standby), and indirect cost, (Corporate overhead) submitted 
by and negotiated with the Contractor.  This date range covers utility relocation work that was 
ongoing as of June 17, 2020 and prevented the continuation of work by the Contractor up to 
and including the date of July 12, 2020 
 
 
Change 
Order 
Reason: 
Within the Project limits and along the north side of MC 85 between 91st Avenue and 87th 
Avenue, there was an existing overhead, multi-circuit 12kV powerline supported on a dozen 
wood poles which was intended to remain. For reasons described in Change Order 13, it 
became necessary during construction of the project for this existing overhead power to be 
relocated and converted to an underground facility.  This relocation work by SRP took from 
April 14, 2020 to July 12, 2020 to complete.  Meanwhile, progress on the rest of the project 
continued and was completed on June 17, 2020.  The only area of remaining Contract work 
was westbound MC85 between 91st and 87th Avenues where the SRP power relocation was 
occurring.  As a result, the Contractor was delayed from performing any Contract work from 
June 17th to July 12th in this area of the project and is entitled to compensation for the delays 
in accordance with MAG Specification 109.8.2, Contracting Agency Delay. 
 
 
Action 
Item No. 
Item Description 
Unit 
Quantity Unit Price 
Extended 
Amount 
Create 
109.00050-14 
Negotiated Settlement for Utility 
Relocation Delay Costs (6/17/2020 – 
7/12/2020) 
LS 
1 
$79,786.87 
$79,786.87 
 
 
 
Total 
 
 
$79,786.87 
 
 
 
 
 
 
 
Cost: 
$79,786.87 
Time: 
None 
 
 
 
 
Specifications: 
None. 
 
 
Subcategories:  
Preventable 
☒Utility Conflict 
☐Right-Of-Way Conflict 
☐Quantity Adjustment 
☐Work out of Scope (MCDOT) 
☐Work out of Scope (Other Jurisdiction) 
☐Plans Revisions 
☐Change Physical Condition 
☐Environmental 
☐Value Engineering 
☐Other:   
 
 
 
 
 
 
Contacts: 
 
 
 
Alana Lewicki, PE 
Interim PC&I Division Manager 
MCDOT 
 
David Hopper, PE 
Chief Construction Engineer 
MCDOT 
Concurred 07/29/2020 
Lisa Ruane, PE 
Construction Engineer 
MCDOT 
Concurred 07/27/2020