PROJECTS EXHIBIT A 2021 COPS.PDF
Extracted text (via pymupdf)
1024 characters
Proposed COP Series 2021
FY21 Tentative Capital Projects
FY21
FY22
FY23
Total
Function
Human Resources Information System
4,000,000
6,000,000
5,000,000
15,000,000
GGOV
Equipment Services Downtown Fueling Station
3,700,000
3,700,000
GGOV
South Block
14,000,000
14,000,000
GGOV
Equipment Services Center Buckeye
5,400,000
5,400,000
GGOV
Electronic Court Recording System Project*
15,000,000
15,000,000
30,000,000
GGPS
Superior Court Central Building
1,000,000
1,000,000
GGPS
Superior Court Central Building 11th Floor
1,400,000
6,000,000
7,400,000
GGPS
Total Projects
39,100,000
32,400,000
5,000,000
76,500,000
76,500,000
7,800,000
*The Electronic Court Recording System Project will need an additional $7.8m of funding identified in the future.
Proposed Debt Issuance
Cash to be covered in future