Scope of Services  
Final Design 
MC 85 – 95TH AVENUE TO 87TH AVENUE 
 
 
 
 
 
Project No: 
Contract No.: 
TT0651 
TBD 
 
 
 
 
 
 
 
Maricopa County 
Department of Transportation 
2901 W. Durango Street 
Phoenix, AZ 85009 
 
 
 
APRIL 2020

Scope of Services 
Project Specific 
 
Project No.: TT0651 
 
Contract No.: 20xx-xxx 
Revised: April 2020 
 
Page 2 of 15 
Table of Contents 
SCOPE OF SERVICES – PROJECT SPECIFIC .............................................................................................. 4 
Project Overview .................................................................................................................................... 4 
Project Location .................................................................................................................................. 4 
Project Background ............................................................................................................................ 4 
Project Purpose ................................................................................................................................... 4 
Length of Services .................................................................................................................................. 4 
SECTION 100 
PROJECT MANAGEMENT ............................................................................................. 5 
100.1.1 
 Matrix of Responsibilities ................................................................................................ 5 
100.1.2 
 Matrix of Deliverables ..................................................................................................... 5 
100.2     
 Kick-Off Meeting ............................................................................................................. 5 
100.6 
 Project Progress Meetings ................................................................................................ 6 
100.12 
 Project Administration ..................................................................................................... 6 
100.13 
 Quality Assurance/Control ............................................................................................... 7 
SECTION 200 
DATA ACQUISITION ..................................................................................................... 7 
200.1  
 Project Research / Data Collection .................................................................................. 7 
200.2  
 Review Acquired Data ..................................................................................................... 7 
200.3  
 Identify Additional Information Needs ............................................................................ 7 
200.4 
Site Visit and Project Research ......................................................................................... 7 
SECTION 300 
LAND SURVEY .............................................................................................................. 7 
300.3  
 Supplemental Field Survey .............................................................................................. 7 
SECTION 400 
PROJECT COORDINATION ........................................................................................... 8 
400.1 
 Stakeholder Meetings ....................................................................................................... 8 
SECTION 500 
UTILITIES AND RAILROAD ........................................................................................... 8 
500.1 
 Verification of Existing Utility Base Map ....................................................................... 8 
500.2 
 Utility and Railroad Conflict Identification ..................................................................... 8 
500.5 
Pothole Data on Plans, Profiles and Cross-Sections ......................................................... 8 
500.5.1 
Test Hole List .................................................................................................................... 8 
500.5.2 
Update Plans ..................................................................................................................... 9 
500.6  
Proposed Utility Data on Plans, Profiles and Cross-Sections ........................................... 9 
500.7  
Utility Relocation Concepts with R/W and Easement Requirements ............................... 9 
500.7.1 
Utility Plans Review ......................................................................................................... 9 
500.8 
Private irrigation Relocation Concepts ............................................................................. 9 
500.11  
 Utility Relocation Plans ................................................................................................... 9 
500.11.1  
Miscellaneous Exhibits and Correspondence.................................................................... 9 
500.11.2 -  Establishing Utility Service Connection ........................................................................... 9

Scope of Services 
Project Specific 
 
Project No.: TT0651 
 
Contract No.: 20xx-xxx 
Revised: April 2020 
 
Page 3 of 15 
500.13  
Utility Special Provisions.................................................................................................. 9 
SECTION 600  ENVIRONMENTAL ......................................................................................................... 10 
SECTION 700 
ALTERNATIVE ANALYSIS ........................................................................................... 10 
SECTION 800 
TECHNICAL MEMORANDA AND REPORTS ................................................................ 10 
800.1.2 
 Drainage Memorandum/Report ..................................................................................... 10 
SECTION 900 
RIGHT OF WAY ........................................................................................................... 10 
SECTION 1000 
  PLANNING ................................................................................................................ 10 
SECTION 1100 
  PLANS, SPECIFICATIONS, AND ESTIMATE ............................................................. 11 
1100.1 
 60% Plans, Specifications, and Estimate Development ................................................. 11 
1100.2 
 60% PS&E Submittal ..................................................................................................... 11 
1100.3 
 95% Plans, Specification, and Estimate Development .................................................. 11 
1100.4 
 95% PS&E Submittal ..................................................................................................... 11 
1100.5 
 100% Plans, Specification, and Estimate Development ................................................ 11 
1100.6 
 100% PS&E Submittal ................................................................................................... 11 
1100.7 
 Sealed Plans ................................................................................................................... 11 
1100.8  
 Constructability Review ................................................................................................. 12 
1100.9  
 Construction Phasing ..................................................................................................... 13 
1100.10  
Sealed PS&E Submittal .................................................................................................. 13 
SECTION 1200 
  VALUE ENGINEERING ............................................................................................. 14 
SECTION 1300 
  BIDDING PHASE ....................................................................................................... 14 
1300.1 
 Prepare Advertisement Package ..................................................................................... 14 
1300.5 
 Pre-Bid Conference ........................................................................................................ 14 
1300.6 
 Preparation of Addenda ................................................................................................. 14 
1300.7 
 Bid Opening ................................................................................................................... 14 
SECTION 1400 
  CONSTRUCTION PHASE .......................................................................................... 14 
1400.1 
 Pre-Construction Conference ......................................................................................... 14 
1400.2  
 Requests for Information (RFI’s) ................................................................................... 14 
1400.3 
 Begin Construction ........................................................................................................ 15 
1400.5 
 Project Close-Out ........................................................................................................... 15 
 
List of Tables 
 
Table 1 – Matrix of Responsibilities 
5 
Table 2 – Matrix of Deliverables 
5 
Table 3 – Project Submittals Table 
13

Scope of Services 
Project Specific 
 
Project No.: TT0651 
 
Contract No.: 20xx-xxx 
Revised: April 2020 
 
Page 4 of 15 
SCOPE OF SERVICES – PROJECT SPECIFIC 
Project Overview 
Project Location 
This project is located within Maricopa County along Maricopa County Highway 85 (MC 85) from 95th 
Avenue to 87th Avenue (approximately 1 mile). 
Project Background 
MC 85 currently varies between a 4-lane and a 5-lane Arterial street section throughout the project 
corridor. There are SRPI and private irrigation facilities located throughout the project limits along the 
north and south sides of MC85. The project was originally split up into two phases.   
 
• 
TT0345-MC85, 95th Avenue to 75th Avenue 
• 
TT0511-MC85, 107th Avenue to 95th Avenue 
 
The Consultant has developed project plans up to the sealed stage for TT0345.  TT0345 is currently 
under construction east of 91st Avenue.  West of 91st Avenue the contractor has not been provided a notice 
to proceed for construction due to delays with the Bureau of Reclamation (BOR) clearance which is 
necessary to relocate SRP irrigation facilities.  West of 91st Avenue the remaining portion of TT0345 is 
being repackaged as a new project that will be bid separately under TT0651-MC85, 95th Avenue to 87th 
Avenue.  In addition, a new development (Logic Park 91) has been approved at the southwest corner of 
MC85 and 91st Avenue.  This development is planning to add driveways and right turn bays along the 
south side of MC85, widen the west side of 91st Avenue, install median islands on 91st Avenue south of 
MC 85, and construct right turn bays and driveways along the west side of 91st Avenue. 
 
This project connects the ultimate improvements at 91st  Avenue to the existing roadway condition at 95th 
Avenue and will complete portions of the TT0345 improvements that were omitted from 91st Avenue to 
87th Avenue. 95th Avenue to 107th Avenue will be improved with future MCDOT project TT0511. 
 
TT0511 was planned to be constructed once the construction of TT0345 was near completion; however, 
with the area west of 91st Avenue being delayed and repackaged TT0511 will now be bid after TT0651 is 
constructed.   
Project Purpose 
The purpose of this contract is to complete design services for TT0651.  The TT0651 plans, specifications 
and estimate will be updated to reflect new utility base mapping, changes requested by utility companies, 
developers, right-of-way negotiations, new design standards/specifications and to prepare the plans for 
bidding which includes the incorporation of lessons learned from the TT0345 project.  This contract will 
also provide post design services for TT0651 consisting of bidding phase assistance, preparing addenda, 
responding to RFIs, answering questions that may arise and reviewing design changes as dictated by 
changes in the field conditions.  
Length of Services 
The estimated contract time for this task shall be 1100 days from NTP. The Consultant shall deliver the 
Sealed submittal for TT0651 by April 2021.

Scope of Services 
Project Specific 
 
Project No.: TT0651 
 
Contract No.: 20xx-xxx 
Revised: April 2020 
 
Page 5 of 15 
SECTION 100 PROJECT MANAGEMENT 
100.1.1  
Matrix of Responsibilities 
The following table summarizes the project specific responsibilities for the Consultant and MCDOT: 
Table 1 – Matrix of Responsibilities 
Scope Section 
Item 
Consultant 
MCDOT 
300.3 
Supplemental Field Survey  
Request Only 
X 
400.10 
Intergovernmental Agreements (IGA) 
 
COMPLETED 
500.16 
Utility Clearance 
 
X 
600.12 
Environmental Clearance 
 
X 
900.3 
Right-of-Way and Easement 
Requirements 
 
X 
1100.1, 1100.3, 1100.5, 
1100.7  
Plans 
X 
 
1100.1, 1100.3, 1100.5, 
1100.7  
Specifications 
X 
 
1100.1, 1100.3, 1100.5, 
1100.7  
Estimates 
X 
 
1300.5 
Pre-Bid Conference 
Attend 
X 
1300.6 
Preparation of Addenda 
X 
X 
1300.7 
Bid Opening 
X 
X 
1400.1 
Pre-Construction Conference 
Attend 
X 
1400.2 
Requests for Information (RFIs) 
X 
X 
1400.5 
Project Close-out 
X 
X 
 
100.1.2  
Matrix of Deliverables 
The deliverables for this project are in the table below: 
Table 2 – Matrix of Deliverables 
Supplier 
Deliverable 
Scope Section 
Consultant 
60% Plans, Specifications, and Estimate 
1100.1 
Consultant 
95% Plans, Specifications, and Estimate 
1000.3 
Consultant 
100% Plans, Specifications, and Estimate 
 1100.5  
Consultant 
Sealed Plans, Specifications, and Estimate 
1100.7 
 
100.2     
Kick-Off Meeting 
At the beginning of the project, a kick-off meeting will be held and shall include the Project Manager, 
the Project Team, the Design Team, and any other necessary parties. The Consultant shall work with 
Project Manager and staff to schedule a project kick-off meeting following the NTP to the Consultant. 
The Consultant shall be responsible for preparing the kick-off meeting agenda, sign-in sheet, 
presentation, handout material, attending and facilitating the kick-off meeting, and submitting notes of 
the meeting to MCDOT. MCDOT will schedule the conference room and review meeting material and

Scope of Services 
Project Specific 
 
Project No.: TT0651 
 
Contract No.: 20xx-xxx 
Revised: April 2020 
 
Page 6 of 15 
notes. The Consultant shall prepare and send meeting notes to the Project Manager within five (5) 
business days of the actual meeting occurrence for review.  The Consultant shall be responsible for 
distributing the meeting notes after the Project Manager’s review and approval as deemed appropriate 
by the Project Manager. Meeting attendees shall have an additional five (5) business days to comment 
on the submitted meeting notes, after which time the notes will be considered final. 
One kick-off meeting is assumed.  The estimated effort associated with meeting attendance, preparation, 
and note compilation time is provided in the attached fee estimate.    
100.6  
Project Progress Meetings 
Meeting assumptions are as follows: 
• 
Progress Meetings – The Consultant will attend progress meetings as estimated in the attached 
fee estimate.  
• 
Technical Group Meetings – The Consultant will attend meetings with various technical teams 
at MCDOT as estimated in the attached fee estimate.  
• 
Comment Resolution Meetings – The Consultant will attend comment resolution meetings as 
estimated in the attached fee estimate.   
If additional meetings for this task are necessary, the Consultant will notify the Project Manager and 
request additional services be added to this scope of work. 
For each of these meetings the consultant will prepare agendas, sign-in sheets and meeting notes. 
100.8  
Field Walk with Project Team 
The Project Team will visit the field site to acquaint key personnel with the details and features of the 
project and to gather input on issues, concerns and opportunities. The field walks will be scheduled and 
the team notified at least two weeks prior to the visit. The field walk will be held shortly after 95% Plans 
are complete and are in the process of review. The Consultant shall comply with applicable local, state 
and public laws for the safety and health of its employees and sub-consultant.  The estimated effort 
associated with meeting attendance, and preparation time is provided in the attached fee estimate.    
The Consultant will also visit the site early in the project to document existing features such as signing 
and marking placement, utility appurtenance locations and other existing conditions under section 200.4. 
100.12  
Project Administration 
This task includes the administrative and coordination tasks required for coordinating the work of the 
team members with MCDOT staff and other project stakeholders. This task coordinates and administers 
the day-to-day operations of the project, including preparing the internal production work plan, organizing 
and filing project data and communication files, responding to project correspondence including emails, 
preparation of regular monthly progress reports, performance of monthly budget updates, and schedule 
monitoring. This task also includes the management of sub-consultants, interfacing and communication 
necessary to keep stakeholders fully and accurately informed.  The assumed effort for this task is shown 
within the attached fee estimate.  As the full effort for this task is unknown, any efforts necessary above 
and beyond the estimated effort will be considered additional services.  If additional services for this task 
are necessary, the Consultant will notify the Project Manager in advance of continuing services above 
and beyond the estimated effort. 
The Consultant shall submit invoices for progress payments using the MCDOT payment request form.

Scope of Services 
Project Specific 
 
Project No.: TT0651 
 
Contract No.: 20xx-xxx 
Revised: April 2020 
 
Page 7 of 15 
100.13  
Quality Assurance/Control 
All engineering calculations submitted to MCDOT shall be complete in detail and shall be checked.  The 
person checking the calculations shall not be the originator and shall be equally or better qualified than 
the originator. All calculation sheets shall be initialed and dated by both the originator and the checker.  
Discipline specific QA/QC is accounted for under the respective sections for each deliverable throughout 
this scope of services.  
The Consultant will follow the guidelines, processes, and quality control checklists for project 
development as per the current Project Development Manual. 
 
SECTION 200 DATA ACQUISITION 
200.1   
Project Research / Data Collection 
The Consultant shall obtain available relative and relevant information impacting the project. This 
information will include copies of design standards and guidelines, quarter section maps, as-builts within 
the project area, previously prepared reports and studies, and other relevant documents (electronic or hard 
copies).  The assumed effort for this task is shown within the attached fee estimate.  As the full effort for 
this task is unknown, any efforts necessary above and beyond the estimated effort will be considered 
additional services.  If additional services for this task are necessary, the Consultant will notify the Project 
Manager in advance of continuing services above and beyond the estimated effort. 
The effort for this task includes TCE expiration research. Research and updates to the legal documents 
shall be performed by MCDOT. Updates to the plans and estimate shall be performed by Consultant.  
200.2   
Review Acquired Data 
No additional data is anticipated for this project but if new data is acquired that affects the project is 
provided by MCDOT the Consultant will evaluate the extent of the changes or review necessary and 
advise the Project Manager of the additional services required.  
200.3   
Identify Additional Information Needs 
It is not anticipated that additional information will be needed for the project.  No additional services are 
included under this section. 
200.4 Site Visit and Project Research 
Site Visits 
Site visits will be used for specific discipline research to gather additional field data that was not 
acquired or may have changed since the field walks. The estimated effort associated with meeting 
attendance, preparation, and note compilation time is provided in the attached fee estimate. 
 
SECTION 300 LAND SURVEY 
300.3   
Supplemental Field Survey 
The Consultant shall request supplemental survey services performed by MCDOT for features that may 
have been recently constructed since the original survey or if the project scope or limits have been 
increased.  It is assumed that up to two supplemental field survey requests will be prepared and submitted 
by the Consultant.  MCDOT survey effort will consist of surveying the TT0345 tie-in and the Logic Park 
development frontage.  Additional survey requests will be considered additional services.  If additional

Scope of Services 
Project Specific 
 
Project No.: TT0651 
 
Contract No.: 20xx-xxx 
Revised: April 2020 
 
Page 8 of 15 
services for this task are necessary, the Consultant will notify the Project Manager in advance of 
continuing services above and beyond the estimated effort. The Consultant shall prepare the survey 
request form and exhibits to communicate the topographic survey needs. 
 
SECTION 400 PROJECT COORDINATION 
400.1  
Stakeholder Meetings 
The Consultant will attend coordination meetings with the developments under construction on the SE 
and SW corners of the 91st Avenue intersection as part of the estimated effort in the attached fee estimate. 
Additional developments are anticipated along this phase of the project. The Consultant will attend 
coordination meetings with future Developers as estimated in the attached fee estimate. In addition, the 
Consultant will attend coordination meetings with property owners to discuss driveway construction 
requirements and alternate access points as estimated in the attached fee estimate. 
The Consultant will attend agency stakeholder coordination meetings with the City of Phoenix to discuss 
the project details and construction.  
The Consultant will meet with various utility companies including but not limited to SRP-I, SRP-D, 
SRP-T, Cox, Century Link, AT&T and Southwest Gas.   
If additional stakeholder meetings are required beyond what is provided in the attached fee estimate, the 
Consultant will notify the Project Manager and request additional services be added to this scope of 
work. 
 
SECTION 500 UTILITIES AND RAILROAD 
500.1  
Verification of Existing Utility Base Map  
MCDOT will contact Arizona 811 to obtain current utility maps in the project limits and provide the 
maps to the Consultant. MCDOT will contact the surrounding agencies for utility maps and as-builts not 
found in the Arizona 811 coordination. If additional effort is required by the Consultant to find the 
necessary as-built information, the Consultant will notify the Project Manager and request additional 
services be added to this scope of work.  
MCDOT will provide the Consultant with an updated CAD utility base map.  The base map will be 
developed by MCDOT’s on-call utility locator using designation and locating techniques consistent with 
Quality Level B.  The Consultant will verify the utility locations in the utility base file against the current 
utility maps provided by MCDOT. 
500.2  
Utility and Railroad Conflict Identification 
The Consultant shall identify existing utility facilities that may conflict with the proposed 
improvements and prepare a utility conflict spreadsheet as outlined in the project development manual.  
In cases where direct conflict exists between existing utilities and proposed MCDOT work, the Consultant 
shall indicate the proposed solution of the conflict on the plans. The Consultant will update the utility 
basefile to show the conflicts in question.   
500.5 Pothole Data on Plans, Profiles and Cross-Sections 
500.5.1 Test Hole List 
The Consultant will prepare SUE request forms and plan exhibits and QC the documents prior to 
submittal. The Consultant will submit the forms and exhibits to MCDOT  who will procure and manage 
all utility locating services and subcontractors necessary for this project. The estimated number of

Scope of Services 
Project Specific 
 
Project No.: TT0651 
 
Contract No.: 20xx-xxx 
Revised: April 2020 
 
Page 9 of 15 
conflicts/potholes that will be needed are unknown. If the conflict resolution/pothole requests require 
more effort than shown in the attached fee estimate, the Consultant will notify the Project Manager and 
request additional services. 
500.5.2 Update Plans 
The Consultant will review the test hole report and update the utility basefile based on test hole findings 
and perform a QC to ensure the utility basefile correctly matches the data from the test hole reports.  
500.6  Proposed Utility Data on Plans, Profiles and Cross-Sections 
The Consultant will update the proposed utility basefiles for TT0651 with new designs received from 
utility companies once the final design is approved by MCDOT. 
500.7  Utility Relocation Concepts with R/W and Easement Requirements 
500.7.1 Utility Plans Review 
The Consultant will provide high level reviews of the final designs from all utility companies yet to 
complete their design.  This includes SRP distribution, SRP Transmission, SRP Irrigation, COX and 
Century Link.  For each utility the Consultant will provide two reviews. If additional reviews are 
necessary, the Consultant will notify the Project Manager in advance of continuing services above and 
beyond the estimated effort and request additional services. 
500.8 Private irrigation Relocation Concepts 
The Consultant will coordinate with SRP-I and provide them CAD files of the updated designs for review 
and comment.  The original design from TT0345 will be extended further south as detailed in the Logic 
Park 91 development plans.  The Consultant will provide high level reviews of the final designs from 
SRP Irrigation.  The Consultant will provide two reviews. If additional reviews are necessary, the 
Consultant will notify the Project Manager in advance of continuing services above and beyond the 
estimated effort and request additional services. 
500.11   
Utility Relocation Plans 
The Consultant will submit 60%, 95%, 100%, and sealed design plans to all utility companies for review 
and archiving. The Consultant will be responsible for addressing comments from the utility companies. 
500.11.1  
Miscellaneous Exhibits and Correspondence   
The Consultant shall prepare miscellaneous exhibits as part of the finalization of utility relocations.  
These exhibits may include depictions of relocation alignments, locations for easements, locations for 
stubs and service requests, etc.  The assumed effort for this task is shown within the attached fee estimate.  
As the full effort for this task is unknown, any efforts necessary above and beyond the estimated effort 
will be considered additional services.  If additional services for this task are necessary, the Consultant 
will notify the Project Manager in advance of continuing services above and beyond the estimated effort. 
500.11.2 -  
Establishing Utility Service Connection 
The Consultant shall review and update utility service request letters and resend to MCDOT for submittal 
to the utility companies. 
500.13  Utility Special Provisions 
The Consultant will update the utility special provisions to comply with changes made with the TT0345 
project and updates to the TT0651 project.

Scope of Services 
Project Specific 
 
Project No.: TT0651 
 
Contract No.: 20xx-xxx 
Revised: April 2020 
 
Page 10 of 15 
The Consultant will review the status of the SRP license process. The Consultant will perform 
coordination to license the construction of the TT0651 improvements. The Consultant will include 
licenses and license requirements in the special provisions.  
 
SECTION 600  ENVIRONMENTAL 
MCDOT is responsible for providing Environmental Clearance.  It is assumed that all environmental 
clearance efforts are completed except for updating the PISA which will need to be incorporated into the 
project specifications and reviewing the extended project limits on the south end of 91st Avenue.  The 
Consultant will coordinate with MCDOT to include additional environmental language in the 
specifications if additional evaluations are completed.  If additional efforts are identified as a necessity 
during the plan update MCDOT will provide these services accordingly.  This task also includes the 
coordination effort between the Consultant and MCDOT to determine how to incorporate Asbestos 
Concrete Pipe (ACP) considerations into the special provisions to ensure the contractor has enough 
information for the NESHAP report, should ACP be encountered in this phase of the project. 
 
SECTION 700 ALTERNATIVE ANALYSIS  
Alternative analysis is not anticipated for this project and is not included with this scope of services. 
 
SECTION 800 TECHNICAL MEMORANDA AND REPORTS 
800.1.2  
Drainage Memorandum/Report 
The Consultant will finalize the drainage report and design exceptions previously completed based on 
the comments received prior to 8/17/18.  If additional comments received after this date require significant 
changes to the documents additional services will be requested. The Consultant will revise the report to 
be a standalone report for this project. 
No other technical memoranda and/or reports are anticipated or included within this scope of services. 
 
SECTION 900 RIGHT OF WAY 
It is assumed that the acquisition process is complete and that no additional meetings will be necessary to 
coordinate the R/W acquisition process.  No additional meetings are included within this scope of work. 
It is assumed that changes to the design based on comments from property owners will not be necessary.  
Therefore, no additional services are included within this scope of work for such revisions.  This includes 
design updates for driveway and all other roadway and landscape appurtenances.  It is also assumed that 
no additional R/W will be required or coordinated with private utility companies. 
MCDOT will update R/W documents based on current understanding of property ownership and 
linework. The Consultant will review the R/W documents and update the plans and CAD files to match. 
If ownership changes before construction, MCDOT will be responsible for updating the R/W documents 
and informing the Consultant. The Consultant will update the plans for the R/W documents to the 
amount shown in the attached fee estimate. If the revisions necessary require more effort than shown in 
the attached fee estimate, the Consultant will notify Project Manager and request additional services.    
SECTION 1000  PLANNING 
Planning is not anticipated for this project and is not included with this scope of services.

Scope of Services 
Project Specific 
 
Project No.: TT0651 
 
Contract No.: 20xx-xxx 
Revised: April 2020 
 
Page 11 of 15 
 
SECTION 1100   PLANS, SPECIFICATIONS, AND ESTIMATE 
1100.1  
60% Plans, Specifications, and Estimate Development 
See Section 1100.7 
1100.2  
60% PS&E Submittal 
See Section 1100.10 
1100.3  
95% Plans, Specification, and Estimate Development 
See Section 1100.7 
1100.4  
95% PS&E Submittal 
See Section 1100.10 
1100.5  
100% Plans, Specification, and Estimate Development 
See Section 1100.7 
1100.6  
100% PS&E Submittal 
See Section 1100.10 
1100.7  
Sealed Plans 
The CAD format for the Plans will follow the MCDOT format used on earlier submittals.  The number 
of plan sheets anticipated for the project are expected to increase.  If no work appears on a plan sheet after 
a revision is requested, the sheet will not be deleted from the plan set.  However, a note will be added to 
alert the contractor that no work is required in that area.  Revisions to the plans will be necessary to match 
revisions completed on the TT0345 project, updated utility alignments, early private irrigation relocation 
construction and constructability comments which are anticipated once MCDOT selects a Construction 
Manager.  The estimated number of plan sheets that will need to be updated are unknown since final utility 
plans and constructability comments have not been received.  If the revisions necessary require more 
effort than shown in the attached fee estimate, the Consultant will notify Project Manager and request 
additional services.    
The Consultant will check the design against the current design standards at the time of the submittal and 
update the plans to work with the latest construction details for all disciplines.  
Specific design changes that are anticipated with the update of the plans are as follows: 
• 
The Consultant shall coordinate to finalize the lighting plans as estimated in the attached fee 
estimate. The lighting plans may need to be updated to match Phase 1 fixtures and poles which 
will be coordinated with the maintaining agencies during the final update of the plans.  
• 
TT0651 plans will be checked against Logic Park and Phoenix Logistics as-builts and survey to 
ensure compliancy with design. If design changes require more effort than shown in the 
attached fee estimate, the Consultant will notify Project Manager and request additional 
services.  
• 
TT0651 plans will be checked against TT0345 tie-in as-builts and supplemental survey. If 
design changes require more effort than shown in the attached fee estimate, the Consultant will 
notify Project Manager and request additional services.

Scope of Services 
Project Specific 
 
Project No.: TT0651 
 
Contract No.: 20xx-xxx 
Revised: April 2020 
 
Page 12 of 15 
The Consultant will update the project plans based on future developments that start construction during 
the design phase of the project.  The estimated number of future developers that will need plan reviews is 
unknown. If the plan revisions or reviews of the proposed development plans necessary require more 
effort than shown in the attached fee estimate, the Consultant will notify Project Manager and request 
additional services.  
TT0651 plans will be checked to ensure detail is added for lessons learned in TT0345 post design provided 
by the County’s construction manager. Effort for this task and specific breakdown of hours can be seen 
in the attached fee estimate.  
The Consultant will revise the sign summary based on field visit findings before the 60% submittal which 
will document if the existing conditions have changed.  
Each revised sheet will go through the Consultants standard QC process. 
Specifications 
Special Provisions will be updated based on input from the utility companies, MCDOT and MCDOT’s 
Construction Manager.  Updates to the specifications based on revised standards are included within this 
scope of work. Specifications will be revised to account for lessons learned on TT0345 post design. 
Specifications will be revised to enhance clarity and ease of use during post design. The effort for updating 
the specifications is unknown since final utility plans and constructability comments have not been 
received.  If the revisions necessary require more effort than shown in the attached fee estimate, the 
Consultant will notify Project Manager and request additional services.    
Estimates 
Estimates of probable cost will be updated based on input from the utility companies, MCDOT and 
MCDOT’s Construction Manager.  Updates to the probable costs based on revised standards are included 
within this scope of work.  Estimates of probable cost will be revised to account for lessons learned on 
TT0345 post design.  The effort for updating the estimates is unknown since final utility plans and 
constructability comments have not been received.  If the revisions necessary require more effort than 
shown in the attached fee estimate, the Consultant will notify Project Manager and request additional 
services.   If the revisions necessary require more effort than shown in the attached fee estimate, the 
Consultant will notify Project Manager and request additional services.    
MCDOT will provide estimates for proposed utility relocations to be included within the final 
construction cost estimate.  If the detail provided by the agency is not enough for inclusion, MCDOT will 
request additional detail from the utility company accordingly. 
The Consultant shall address comments as necessary and re-submit documents as needed to address 60% 
comments.  
The Consultant shall address comments as necessary and re-submit documents as needed to address 95% 
comments.  
The Consultant shall address comments as necessary and re-submit documents as needed to address 
100% comments.  
The Consultant shall prepare the engineers estimate using MCDOT’s cost estimation tool. 
1100.8   
Constructability Review 
The Consultant will coordinate with the County’s selected construction manager during their 
constructability review.  The Consultant will answer questions and coordinate plans, specifications and 
estimate updates as needed.  The effort for this coordination is unknown since constructability comments 
have not been received.  If the coordination necessary requires more effort than shown in the attached fee 
estimate, the Consultant will notify Project Manager and request additional services.

Scope of Services 
Project Specific 
 
Project No.: TT0651 
 
Contract No.: 20xx-xxx 
Revised: April 2020 
 
Page 13 of 15 
1100.9   
Construction Phasing 
Revisions to construction phasing for this project will be reviewed during the constructability review.    
Changes to the specifications will be made to account for information that needs to be communicated to 
the contractor.  Construction phasing plans are not anticipated or included within this scope of services. 
1100.10  
Sealed PS&E Submittal 
The following table provides the submittal requirements: 
Table 3 – Project Submittals Table 
 
Legend: 
H# - Number of Hard Copies Requested 
E - Indicates Electronic Submittal is Requested 
 
Ben Markert 
(Project Manager) 
Total Number of Hard Copies 
Submittal Document 
 
60% PS&E 
 
 
60% Plans 
H1, E 
1 
60% Specifications 
H1, E 
1 
60% Estimate and Bid Schedule 
H1, E 
1 
60% CD (CAD and pdf files) 
H1 
1 
95% PS&E 
 
 
95% Plans 
H1, E 
1 
95% Specifications 
H1, E 
1 
95% Estimate and Bid Schedule 
H1, E 
1 
95% CD (CAD and pdf files) 
H1 
1 
100% PS&E 
 
 
100% Plans 
H1, E 
1 
100% Specifications 
H1, E 
1 
100% Estimate and Bid Schedule 
H1, E 
1 
100% CD (CAD and pdf files) 
H1 
1 
Sealed PS&E 
 
 
Sealed Plans 
H1, E 
1 
Sealed Specifications 
H1, E 
1 
Sealed Estimate and Bid Schedule 
H1, E 
1 
Sealed CD (CAD and pdf files) 
H1 
1 
 
The Consultant shall submit 60%, 95%, 100%, and sealed PS&E. It is anticipated that these submittals 
will be reviewed by a select number of MCDOT staff members as opposed to a normal plan review cycle.

Scope of Services 
Project Specific 
 
Project No.: TT0651 
 
Contract No.: 20xx-xxx 
Revised: April 2020 
 
Page 14 of 15 
SECTION 1200  VALUE ENGINEERING 
Value Engineering is not anticipated for this project and is not included with this scope of services. 
 
SECTION 1300  BIDDING PHASE 
The assumed effort for all tasks under this section is shown within the attached fee estimate.  As the full 
effort for this task is unknown, any efforts necessary above and beyond the estimated effort will be 
considered additional services.  If additional services for this task are necessary, the Consultant will 
notify the Project Manager in advance of continuing services above and beyond the estimated effort. 
1300.1  
Prepare Advertisement Package 
The Consultant shall provide technical assistance and respond to design questions during the preparation 
of the advertisement by MCDOT.  
1300.4   
Advertisement 
The Consultant will track and respond to questions received during bidding. 
1300.5  
Pre-Bid Conference 
Attendance at a pre-bid conference is included within this scope of services.  A planning meeting is also 
assumed as part of this scope of work.  Exhibits for the pre-bid conference are not assumed or included 
within this scope of work beyond the standard roll plot prepared as part of the design phase efforts. 
1300.6  
Preparation of Addenda 
Addenda is anticipated based on input from MCDOT and bidding contractors.  The Consultant will track 
questions received during bidding and formulate the items included in each addendum.  MCDOT will 
prepare and distribute the official addenda.  
1300.7  
Bid Opening 
The Consultant will combine bids into a spreadsheet and analyze the differences between the various 
bidders. Results will be shared with the Project Manager. The Consultant will answer questions and 
perform additional analysis up to the amount in the attached fee estimate.  
 
SECTION 1400  CONSTRUCTION PHASE 
The assumed effort for all tasks under this section is shown within the attached fee estimate.  As the full 
effort for this task is unknown, any efforts necessary above and beyond the estimated effort will be 
considered additional services.  If additional services for this task are necessary, the Consultant will 
notify the Project Manager in advance of continuing services above and beyond the estimated effort. 
1400.1  
Pre-Construction Conference 
Attending a preconstruction conference is included within this scope of services as detailed in the 
attached fee estimate. 
1400.2   
Requests for Information (RFI’s) 
Requests for Information 
The Consultant will provide technical assistance by explaining design intent and specifications in 
response to Requests for Information (RFI’s).  The estimated number of requests for information is 
shown in the attached fee estimate.

Scope of Services 
Project Specific 
 
Project No.: TT0651 
 
Contract No.: 20xx-xxx 
Revised: April 2020 
 
Page 15 of 15 
 
Shop Drawings 
Shop drawing reviews are included in this scope of services. 
 
Plan Revisions 
Plan revisions for field conditions that dictate the need for the Contractor to deviate from the proposed 
design are included in this scope of services.  The estimated number of revisions is shown in the attached 
fee estimate.  
1400.3  
Begin Construction 
The Consultant will attend construction meetings as estimated in the attached fee estimate. If additional 
meetings for this task are necessary, the Consultant will notify the Project Manager and request 
additional services be added to this scope of work.  
1400.5  
Project Close-Out 
This task includes the administrative and coordination tasks required for coordinating the work of the team 
members with MCDOT staff and other project stakeholders. This task coordinates and administers the day-
to-day operations of the project, including documenting all post design requests/communications, organizing 
and filing project data and communication files, preparation of regular monthly progress reports, performance 
of monthly budget updates and schedule monitoring. This task also includes the management of sub-
consultants, interfacing and communication necessary to keep stakeholders fully and accurately informed and 
full close-out of the project documents.

MC85 Update Docs., Bidding Assist., and Post Design
Kimley-Horn and Associates
PROJECT NO. TT0651
Contract No. TBD
ESTIMATED DIRECT LABOR
PERSON
BILLING
CLASSIFICATION
HOURS
RATE/HOUR
TOTAL
Principal/QC
-
                         
101.93
$                 
-
$                  
Project Manager - Sr
550
                        
73.91
$                   
40,650.50
$        
Project Engineer - Sr
396
                        
71.69
$                   
28,389.24
$        
Engineer
663
                        
49.74
$                   
32,977.62
$        
Environmental Manager
2
                            
62.95
$                   
125.90
$             
Designer
2,030
                     
43.31
$                   
87,919.30
$        
Administrative
81
                          
42.16
$                   
3,414.96
$          
3,722
                     
  Hours
Estimated Labor Cost
193,477.52
$      
Overhead
194.28%
375,888.13
$      
Subtotal
569,365.65
$      
ESTIMATED DIRECT EXPENSES
(Listed By Item At Estimated Actual Cost - NO MARKUP)
Travel
224.00
$                 
Plotting
255.00
$                 
Miscellaneous Expenses
100.00
$                 
Total Estimated Expenses
579.00
$             
ESTIMATED OUTSIDE SERVICES AND CONSULTANTS
Firm
Cost
-
$                       
-
$                       
-
$                       
-
$                       
-
$                       
-
$                       
-
$                       
Total Estimated Outside Services
-
$                  
PROFIT (Direct Labor +Overhead)
10%
56,936.56
$        
TOTAL ESTIMATED FEE
626,881.21
$      
CONTRACT TIME 
1,100
     
Calendar Days
Consultant Firm Signature
Date
April 2, 2020
DERIVATION OF COST PROPOSAL SUMMARY
K:\PHX_Roadway\191850000-MC 85\Contract\5 - Contract Amendments\CA##_TT0651 95th to 87th\      TT651_Fee_V3.xlsx
Table A
Page 1 of 14
Updated: 4/2/2020   5:58 PM
David
Rutkowski

MC85 Bidding Assistance and Post Design Services
Kimley-Horn and Associates
PROJECT NO. TT0651
Contract No. TBD
TASK
Scale
No Sheets
Hours/Sheet
Principal/QC
Project Manager - Sr Project Engineer -
Sr
Engineer
Designer
Environmental 
Manager
Administrative
 Total 
 SUBTOTAL 
 $            101.93  $                      73.91  $                71.69  $        49.74  $          43.31  $              62.95  $              42.16 
Task 100 - Project Management
22,061.13
                             
-
                    
153
                            
60
                       
42
                
54
                  
-
                    
48
                      
357.00
                                                         
100.1- Project Work Plan
-
                                        
-
                                                              
100.1.1 - Matrix of Responsibilities
-
                                        
-
                                                              
100.1.2 - Matrix of Deliverables
-
                                        
-
                                                              
100.2- Project Initiation
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
100.3- Kick-Off Meeting  (1 total) (2 attendees)
-
                                        
-
                                                              
Preparation (2 hrs/mtg/person)
234.44
                                  
2
2
4.00
                                                             
Attendance (3 hrs/person)
351.66
                                  
3
3
6.00
                                                             
Notes (2 hr/mtg)
117.22
                                  
1
1
2.00
                                                             
100.4- Design Criteria
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
100.5- Design Exceptions
-
                                        
-
                                                              
See Task 800.1.2
-
                                        
-
                                                              
100.6 - Project Progress Meetings 
-
                                        
-
                                                              
Progress Meetings (4 total) (2 attendees)
-
                                        
-
                                                              
Preparation (1 hrs/mtg/person)
468.88
                                  
4
4
8.00
                                                             
Attendance (3 hrs/person)
1,406.64
                               
12
12
24.00
                                                           
Notes (2 hr/mtg)
468.88
                                  
4
4
8.00
                                                             
Technical Group Meetings (3 total) (2 attendees)
-
                                        
-
                                                              
Preparation (1 hrs/mtg/person)
436.80
                                  
3
3
6.00
                                                             
Attendance (3 hrs/person)
1,310.40
                               
9
9
18.00
                                                           
Notes (2 hr/mtg)
436.80
                                  
3
3
6.00
                                                             
Comment Resolution Meeting (3 total) (2 attendees)
-
                                        
-
                                                              
Preparation (15 hrs/person)
5,826.90
                               
15
45
30
90.00
                                                           
Attendance (4 hrs/person)
1,406.64
                               
12
12
24.00
                                                           
Notes (2 hr/mtg/person)
703.32
                                  
6
6
12.00
                                                           
100.7 - Determine VE Study Recommendation
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
100.8 - Field Walk with Project Team
-
                                        
-
                                                              
Field Walks (1 total) (5 attendees) (4hrs/meeting/person)
1,065.76
                               
4
12
4
20.00
                                                           
100.9- Project Implementation Master Schedule
-
                                        
-
                                                              
Develop and maintain project Schedule
481.59
                                  
3
6
9.00
                                                             
100.10- Project Delivery Method Recommendation
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
100.11- Team input for Seasonal limitations (dry-ups, monsoon, special event, etc.).
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
100.12 - Project Administration
-
                                        
-
                                                              
Project Administration and Management (2 hrs/month for duration of project)
3,547.68
                               
48
48.00
                                                           
Invoicing
3,797.52
                               
24
48
72.00
                                                           
ESTIMATED STAFF HOURS - DESIGN PHASE
4/2/2020
2 of 14

TASK
Scale
No Sheets
Hours/Sheet
Principal/QC
Project Manager - Sr Project Engineer -
Sr
Engineer
Designer
Environmental 
Manager
Administrative
 Total 
 SUBTOTAL 
 $            101.93  $                      73.91  $                71.69  $        49.74  $          43.31  $              62.95  $              42.16 
Task 200 - Data Acquisition
1,821.56
                               
-
                    
2
                                
16
                       
8
                  
2
                    
-
                    
1
                       
29.00
                                                           
200.1 - Project Research / Data Collection
-
                                        
-
                                                              
Data Collection
352.50
                                  
1
2
1
1
1
6.00
                                                             
200.2 - Review Acquired Data
-
                                        
-
                                                              
Review Data
503.46
                                  
1
4
2
1
8.00
                                                             
200.3 - Identify Additional Information Needs
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
200.4 - Site Visit and Project Research
-
                                        
-
                                                              
Site Visits (3 total) (1 attendee)
-
                                        
-
                                                              
Preparation (1 hr/person)
193.12
                                  
2
1
3.00
                                                             
Attendance (4 hrs/person)
772.48
                                  
8
4
12.00
                                                           
Notes (EXCLUDED)
-
                                        
-
                                                              
Task 300 - Land Survey
1,014.32
                               
-
                    
4
                                
-
                      
4
                  
12
                  
-
                    
-
                    
20.00
                                                           
300.1 - Results of Survey, Section Control, Exst R/W Base Map
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
300.2 - Establish Coordinate System per RDM
-
                                        
-
                                                              
By MCDOT
-
                                        
-
                                                              
300.3 - Supplemental Field Survey
-
                                        
-
                                                              
Processing/Combining Survey Data
693.26
                                  
2
4
8
14.00
                                                           
Additional Survey Request Forms and Exhibits (2 additional)
321.06
                                  
2
4
6.00
                                                             
Task 400 - Project Coordination
3,507.29
                               
-
                    
31
                              
-
                      
14
                
12
                  
-
                    
-
                    
57.00
                                                           
400.1 - Stakeholder Meetings (9 total)
-
                                        
-
                                                              
Current Developer  Meetings  (2 total) (1 attendees)
-
                                        
-
                                                              
Preparation (1 hr)
117.22
                                  
1
1
2.00
                                                             
Attendance (2 hrs)
234.44
                                  
2
2
4.00
                                                             
Notes (2 hr/mtg)
234.44
                                  
2
2
4.00
                                                             
Future Developer Meetings  (1 total) (1 attendee)
-
                                        
-
                                                              
Preparation (1 hr/mtg)
73.91
                                    
1
1.00
                                                             
Attendance (2 hrs)
147.82
                                  
2
2.00
                                                             
Notes (2 hr/mtg)
147.82
                                  
2
2.00
                                                             
Agency Stakeholder Meetings  (2 total) (2 attendee)
-
                                        
-
                                                              
Preparation (1 hr/mtg)
117.22
                                  
1
1
2.00
                                                             
Attendance (2 hrs)
468.88
                                  
4
4
8.00
                                                             
Notes (2 hr/mtg)
234.44
                                  
2
2
4.00
                                                             
Utility Coordination Meetings (4 total) (2 attendees)
-
                                        
-
                                                              
Preparation (1 hr/mtg)
247.30
                                  
2
2
4.00
                                                             
Attendance (2 hrs)
989.20
                                  
8
8
16.00
                                                           
Notes (2 hr/mtg)
494.60
                                  
4
4
8.00
                                                             
400.2 - Public Involvement Plan
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
400.3 - Public Involvement Activities
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
400.4 - Public Involvement Summary
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
400.5 - Public Meeting Summary and Comments
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
400.6 - 60% Public Project Update Activity and Feedback
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
400.7 - 95% Public Outreach Materials
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
400.8 - Project Specific Partnering Special Provisions
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
400.9 - Intergovernmental and Maintenance Agreements Identification
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
400.10 - Intergovernmental Agreements (IGA)
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
4/2/2020
3 of 14

TASK
Scale
No Sheets
Hours/Sheet
Principal/QC
Project Manager - Sr Project Engineer -
Sr
Engineer
Designer
Environmental 
Manager
Administrative
 Total 
 SUBTOTAL 
 $            101.93  $                      73.91  $                71.69  $        49.74  $          43.31  $              62.95  $              42.16 
Task 500 - Utilities and Railroad
14,099.46
                             
-
                    
39.00
                         
13.00
                  
78.00
           
144.00
           
-
                    
4.00
                   
278.00
                                                         
500.1 - Verification of Existing Utility Base Map
-
                                        
-
                                                              
Data Acquisition (By MCDOT)
-
                                        
-
                                                              
Utility Verification
891.92
                                  
4
16
20.00
                                                           
QA/QC
272.87
                                  
1
4
5.00
                                                             
500.2 - Utility and Railroad Conflict Identification
-
                                        
-
                                                              
Identify Utility Conflicts
1,262.72
                               
2
5
20
27.00
                                                           
Utility Conflict QC
198.96
                                  
4
4.00
                                                             
500.3 - Utility Prior Rights
-
                                        
-
                                                              
By MCDOT
-
                                        
500.4 - Utility Company Review of Recommended Alternative
-
                                        
-
                                                              
By Utility Companies
-
                                        
500.5 - Pothole Data on Plans, Profiles and Cross-Sections
-
                                        
-
                                                              
500.5.1 - Test Hole List
-
                                        
-
                                                              
Prepare Test Hole List
359.34
                                  
2
6
8.00
                                                             
Test Hole List QC
49.74
                                    
1
1.00
                                                             
Review Test Hole Data
680.40
                                  
2
2
10
14.00
                                                           
Revise Plan Sheets (See Task 1100)
-
                                        
-
                                                              
Revise Designs (See Task 1100)
-
                                        
-
                                                              
500.5.2 - Update Plans
-
                                        
-
                                                              
Update Existing Utility Base File Based on MCDOT Locating
346.48
                                  
8
8.00
                                                             
Update Utility Test Hole Base File Based on MCDOT Locating
173.24
                                  
4
4.00
                                                             
Utility Base File QC
173.39
                                  
1
2
3.00
                                                             
500.6 - Proposed Utility Data on Plans, Profiles and Cross-Sections
-
                                        
-
                                                              
Update TT651 Proposed Utility Base
866.20
                                  
20
20.00
                                                           
QC
247.30
                                  
2
2
4.00
                                                             
500.7 - Utility Relocation Concepts with R/W and Easement Requirements
-
                                        
-
                                                              
500.7.1 - Utility Plans Review (2 Each)
-
                                        
-
                                                              
Century Link Plan Reviews
520.02
                                  
2
4
4
10.00
                                                           
SRP Distribution Plan Reviews
693.26
                                  
2
4
8
14.00
                                                           
SRP Transmission Plan Reviews
693.26
                                  
2
4
8
14.00
                                                           
COX Plan Reviews
520.02
                                  
2
4
4
10.00
                                                           
500.8 - Private Irrigation Relocation Concepts
-
                                        
-
                                                              
Prepare Plans and CAD File Digital Package
381.21
                                  
1
1
4
2
8.00
                                                             
Courier CDs and Hard Copy plans to Utility Companies
127.63
                                  
1
2
3.00
                                                             
SRP Irrigation Plan Reviews
346.63
                                  
1
2
4
7.00
                                                             
500.9 - Utility Relocation Cost Estimates and Schedule
-
                                        
-
                                                              
By MCDOT
-
                                        
500.10 - Proposed Utility Data on Plans, Profiles and Cross-Sections
-
                                        
-
                                                              
See Task 500.6
-
                                        
500.11 - Utility Relocation Plans
-
                                        
-
                                                              
500.11.1 - Miscellaneous Exhibits and Correspondence
-
                                        
-
                                                              
  Exhibits (4 at 2 hours each)
468.88
                                  
4
4
8.00
                                                             
  Correspondence (2 hours per month for 12 months)
1,071.59
                               
5
19
24.00
                                                           
500.11.2 - Establishing Utility Service Connection
-
                                        
-
                                                              
Review and update Service Request Letters
490.01
                                  
1
2
2
4
9.00
                                                             
500.12 - Private Irrigation Relocation Plans
-
                                        
-
                                                              
By SRP
-
                                        
500.13 - Utility Special Provisions
-
                                        
-
                                                              
Update Special Provisions
2,450.80
                               
10
10
20
40.00
                                                           
Review License Status
395.12
                                  
4
2
6.00
                                                             
Coordinate License for SRPI Crossings for Lighting and Signal Conduit
418.47
                                  
2
1
4
7.00
                                                             
500.14 - Utility Relocation Cost Estimates
-
                                        
-
                                                              
By MCDOT
-
                                        
500.15 - Utility and Railroad Agreements
-
                                        
-
                                                              
By MCDOT
-
                                        
500.16 - Utility Clearance Letter
-
                                        
-
                                                              
By MCDOT
-
                                        
4/2/2020
4 of 14

TASK
Scale
No Sheets
Hours/Sheet
Principal/QC
Project Manager - Sr Project Engineer -
Sr
Engineer
Designer
Environmental 
Manager
Administrative
 Total 
 SUBTOTAL 
 $            101.93  $                      73.91  $                71.69  $        49.74  $          43.31  $              62.95  $              42.16 
Task 600 - Environmental
421.54
                                  
-
                    
4
                                
-
                      
-
               
-
                 
2
                       
-
                    
6.00
                                                             
600.1 - Environmental Document Tech Memo
-
                                        
-
                                                              
600.1.1 - Public/Agency Scoping
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.1.2 - Biological Resources
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.1.3 - Hazardous Materials
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.1.4 - Cultural Resources
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.1.5 - Air Quality
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.1.6 - Noise
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.1.7 - Preliminary Jurisdictional Delineation
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.2 - Environmental Inventory and Fatal Flaw Documentation
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.3 - Determine Environmental Impacts
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.4 - Identify Environmental Items for Evaluation Matrix
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.5 - Complete Title VI, Limited English Proficiency and Environmental Justice Assessment
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.6 - Document Anticipated Environmental Permits with Associated Schedule Requirements
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.7 - Geotechnical Environmental Clearance
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.8 - Utility Pothole Environmental Clearance
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.9 - Environmental Document (ED)
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.10 - Environmental Document (CE)
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.11 - Environmental Permits Approved
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
600.12 - Environmental Clearance Letter (With Mitigation Measures)
-
                                        
-
                                                              
Text provided by MCDOT Environmental
-
                                        
-
                                                              
Coordination
210.77
                                  
2
1
3.00
                                                             
Incorporation into the special provisions
210.77
                                  
2
1
3.00
                                                             
4/2/2020
5 of 14

TASK
Scale
No Sheets
Hours/Sheet
Principal/QC
Project Manager - Sr Project Engineer -
Sr
Engineer
Designer
Environmental 
Manager
Administrative
 Total 
 SUBTOTAL 
 $            101.93  $                      73.91  $                71.69  $        49.74  $          43.31  $              62.95  $              42.16 
Task 700 - Alternative Analysis
-
                                        
-
                    
-
                             
-
                      
-
               
-
                 
-
                    
-
                    
-
                                                              
700.1 - Conceptual Alternative Plans Development
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
700.2 - Alternatives Plans Development
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
700.3 - Evaluation Criteria Matrix
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
700.4 - Evaluate Candidate Alternatives
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
700.5 - Select Recommended Alternative - Project Team
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
700.6 - Approve Recommended Alternative - Management Committee
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
700.7 - Draft Scoping Document (with TMs) Submittal
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
700.5 - Constructability Review
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
700.6 - Final Scoping Document - Final Scoping Plans Submittal
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
4/2/2020
6 of 14

TASK
Scale
No Sheets
Hours/Sheet
Principal/QC
Project Manager - Sr Project Engineer -
Sr
Engineer
Designer
Environmental 
Manager
Administrative
 Total 
 SUBTOTAL 
 $            101.93  $                      73.91  $                71.69  $        49.74  $          43.31  $              62.95  $              42.16 
Task 800 - Technical Memoranda and Reports
2,809.97
                               
-
                    
3
                                
21
                       
-
               
25
                  
-
                    
-
                    
49.00
                                                           
800.1 - Traffic Analysis
-
                                        
-
                                                              
800.1.1 - Traffic Memorandum/Report
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
800.2 - Drainage Report
-
                                        
-
                                                              
Update Drainage Report
2,447.82
                               
2
20
20
42.00
                                                           
Revise report to be a standalone for TT0651
362.15
                                  
1
1
5
7.00
                                                             
Update Drainage Design Exception (EXCLUDED)
-
                                        
-
                                                              
QC
-
                                        
-
                                                              
800.3 - Structures
-
                                        
-
                                                              
800.3.1 - Wall Selection Report
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
800.3.1 - Bridge Selection Report
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
800.4 - Geotechnical and Pavement Design Report
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
800.5 - Alternatives Analysis
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
800.5.1 - ADA Memorandum
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
800.6 - Utilities Report
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
800.7 - Right-of-way Report
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
4/2/2020
7 of 14

TASK
Scale
No Sheets
Hours/Sheet
Principal/QC
Project Manager - Sr Project Engineer -
Sr
Engineer
Designer
Environmental 
Manager
Administrative
 Total 
 SUBTOTAL 
 $            101.93  $                      73.91  $                71.69  $        49.74  $          43.31  $              62.95  $              42.16 
Task 900 - Right-of-Way
963.18
                                  
-
                    
6
                                
-
                      
-
               
12
                  
-
                    
-
                    
18.00
                                                           
900.1 - Identify Open & Declare Right-of-Way (R/W) Status
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
900.2 - R/W Base Map
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
900.3 - Right-of-Way Limit Requirements
-
                                        
-
                                                              
900.3.1 - Coordination with MCRED
-
                                        
-
                                                              
Identify Additional TCE's
321.06
                                  
2
4
6.00
                                                             
Coordination with MCRED
642.12
                                  
4
8
12.00
                                                           
900.4 - Land Value Estimate
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
900.5 - Acquisition Timeline Estimate
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
900.6 - Identify Unique Ownerships with project budget and schedule requirements
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
900.7 - Title Reports
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
900.8 - Right-of-Entry (Environmental, Geotechnical, Potholing)
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
900.9 - Identify & Map Prior Right Conflicts
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
900.10 - Initiate and Complete Open & Declare Right-of-Way (R/W)
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
900.11 - Contact Letters to Property Owners
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
900.12 - Title Reports
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
900.13 - Right-of-Entry (Environmental, Geotechnical, Potholing)
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
900.14 - Research & Evaluate Prior Rights Claims
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
900.15 - Right-of-Way Strip Map (Note: No R/W or Easement changes after 60%)
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
900.16 - Right-of-Way Clearance Letter
-
                                        
-
                                                              
By MCRED
-
                                        
-
                                                              
Task 1000 - Planning
-
                                        
-
                    
-
                             
-
                      
-
               
-
                 
-
                    
-
                    
-
                                                              
1000.1 - Identification of ADA facilities/conformance
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1000.2 - Identification of bicycle and pedestrian facilities
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1000.3 - Traffic Volume Projections
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1000.4- Ultimate Roadway Classification
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1000.5 - Project Rating Score
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1000.6 - Federal Aid recommendation
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
4/2/2020
8 of 14

TASK
Scale
No Sheets
Hours/Sheet
Principal/QC
Project Manager - Sr Project Engineer -
Sr
Engineer
Designer
Environmental 
Manager
Administrative
 Total 
 SUBTOTAL 
 $            101.93  $                      73.91  $                71.69  $        49.74  $          43.31  $              62.95  $              42.16 
Task 1100 - Plans Specifications and Estimate
126,833.87
                           
-
                    
203.00
                       
252.00
                
456.00
         
1,614.00
        
-
                    
28.00
                 
2,553.00
                                                      
1100.1 - 60% Plans, Specifications, and Estimate Development
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1100.2 - 60% PS&E Submittal
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1100.3 - 95% Plans, Specifications, and Estimate Development
-
                                        
-
                                                              
See 1100.7
-
                                        
-
                                                              
1100.4 - 95% PS&E Submittal 
-
                                        
-
                                                              
See 1100.10
-
                                        
-
                                                              
1100.5 - 100% Plans, Specifications, and Estimate Development
-
                                        
-
                                                              
See 1100.7
-
                                        
-
                                                              
1100.6 -100% PS&E Submittal
-
                                        
-
                                                              
See 1100.10
-
                                        
-
                                                              
1100.7 - Sealed Plans
-
                                        
-
                                                              
Roadway
-
                                        
-
                                                              
Revise and Replot for 60% Submittal
-
                                        
-
                                                              
Cover Sheet
1
1.00
43.31
                                    
1
1.00
                                                             
General Notes Sheet
1
3.00
136.36
                                  
1
2
3.00
                                                             
Quantity Summaries
21
2.00
1,896.18
                               
12
30
42.00
                                                           
Typical Sections
4
10.00
1,796.70
                               
10
30
40.00
                                                           
Geometric Data Sheets
4
2.00
372.20
                                  
4
4
8.00
                                                             
Mass Diagram
1
15.00
746.10
                                  
15
15.00
                                                           
MC 85 Paving Plans
10
8.00
3,625.55
                               
25
55
80.00
                                                           
MC 85 Paving Profiles
8
10.00
3,593.40
                               
20
60
80.00
                                                           
91st Avenue Paving Plans (New)
1
30.00
1,331.45
                               
5
25
30.00
                                                           
91st Avenue Paving Plans  (Revise Existing)
9
8.00
3,214.77
                               
15
57
72.00
                                                           
91st Avenue Paving Profiles (New)
2
25.00
2,294.10
                               
20
30
50.00
                                                           
91st Avenue Paving Profiles (Revise Existing)
5
8.00
1,796.70
                               
10
30
40.00
                                                           
Intersection Grading
1
2.00
93.05
                                    
1
1
2.00
                                                             
Driveway Plan & Profiles (New)
4
25.00
4,427.45
                               
15
85
100.00
                                                         
Driveway Plan & Profiles (Revise Existing)
2
10.00
898.35
                                  
5
15
20.00
                                                           
Median Details (New)
3
15.00
1,981.10
                               
5
40
45.00
                                                           
Median Details (Existing) 
2
6.00
532.58
                                  
2
10
12.00
                                                           
Miscellaneous Details
2
2.00
186.10
                                  
2
2
4.00
                                                             
Check and revise plans against current design standards (0.5hr/sheet)
72
0.50
1,623.46
                               
10
26
36.00
                                                           
Update plans to comply with TT0345 Lessons Learned
72
1.00
3,246.92
                               
20
52
72.00
                                                           
Revise and replot sheets for utility updates
72
0.50
1,623.46
                               
10
26
36.00
                                                           
Update Earthwork Model and Cross Sections
2,783.75
                               
5
5
50
60.00
                                                           
Revise and Replot for Future Development Plans
2
5.00
507.16
                                  
2
2
6
10.00
                                                           
Revise and Replot for 60% Comments
81
1.00
3,965.10
                               
8
33
40
81.00
                                                           
Revise and replot sheets for 95% comments
81
0.51
2,000.99
                               
4
16
21
41.00
                                                           
Utilities
-
                                        
-
                                                              
Revise and Replot for 60% Submittal
-
                                        
-
                                                              
Cover
1
1.00
43.31
                                    
1
1.00
                                                             
Notes
2
1.50
136.36
                                  
1
2
3.00
                                                             
DIP Details
1
2.00
93.05
                                    
1
1
2.00
                                                             
Relocation Table
1
6.00
272.72
                                  
2
4
6.00
                                                             
Misc. Details
1
8.00
359.34
                                  
2
6
8.00
                                                             
MC 85 Removal Sheets 
10
5.00
2,229.80
                               
10
40
50.00
                                                           
91st Avenue Removal Sheets (New)
1
20.00
879.06
                                  
2
18
20.00
                                                           
91st Avenue Removal Sheets (Revise Existing)
7
8.00
2,489.66
                               
10
46
56.00
                                                           
Private Irrigation Details
1
6.00
272.72
                                  
2
4
6.00
                                                             
Check and revise plans against current design standards (0.5hr/sheet)
24
0.50
539.01
                                  
3
9
12.00
                                                           
Update plans to comply with TT0345 Lessons Learned
24
1.00
1,078.02
                               
6
18
24.00
                                                           
Revise and replot sheets for utility updates
24
0.50
539.01
                                  
3
9
12.00
                                                           
Revise and Replot for Future Development Plans
4
2.00
389.94
                                  
1
2
5
8.00
                                                             
Revise and Replot for 60% Comments
25
1.00
1,256.59
                               
4
8
13
25.00
                                                           
Revise and replot sheets for 95% comments
25
0.52
649.95
                                  
2
4
7
13.00
                                                           
4/2/2020
9 of 14

TASK
Scale
No Sheets
Hours/Sheet
Principal/QC
Project Manager - Sr Project Engineer -
Sr
Engineer
Designer
Environmental 
Manager
Administrative
 Total 
 SUBTOTAL 
 $            101.93  $                      73.91  $                71.69  $        49.74  $          43.31  $              62.95  $              42.16 
Drainage
-
                                        
-
                                                              
Revise and Replot for 60% Submittal
-
                                        
-
                                                              
Scupper Design Summary
2
8.00
806.48
                                  
4
12
16.00
                                                           
Drainage Details
3
8.00
1,209.72
                               
6
18
24.00
                                                           
Storm Drain Design Summary
3
4.00
604.86
                                  
3
9
12.00
                                                           
MC 85 Drainage Plans
9
4.00
1,814.58
                               
9
27
36.00
                                                           
91st Avenue Drainage Plans (New)
4
20.00
3,748.60
                               
10
70
80.00
                                                           
91st Avenue Drainage Plans (Revise Existing)
3
8.00
1,096.20
                               
2
22
24.00
                                                           
Drainage Profiles
3
5.00
734.79
                                  
3
12
15.00
                                                           
91st Avenue Basin Grading (NW Corner)
1
2.00
115.00
                                  
1
1
2.00
                                                             
Check and revise plans against current design standards (0.5hr/sheet)
24
0.50
576.48
                                  
2
10
12.00
                                                           
Update plans to comply with TT0345 Lessons Learned
24
1.00
1,152.96
                               
4
20
24.00
                                                           
Revise and replot sheets for utility updates
24
1.00
1,152.96
                               
4
20
24.00
                                                           
Revise and Replot for Future Development Plans
3
2.00
347.22
                                  
1
2
3
6.00
                                                             
Revise and Replot for 60% Comments
28
1.00
1,562.12
                               
4
8
16
28.00
                                                           
Revise and replot sheets for 95% comments
28
0.50
781.06
                                  
2
4
8
14.00
                                                           
ITS
-
                                        
-
                                                              
Revise and Replot for 60% Submittal
-
                                        
-
                                                              
Splice Point Plan
1
2.00
115.00
                                  
1
1
2.00
                                                             
Splice Detail Sheet
1
2.00
115.00
                                  
1
1
2.00
                                                             
ITS Plan
2
4.00
403.24
                                  
2
6
8.00
                                                             
Check and revise plans against current design standards (1hr/sheet)
4
1.00
230.00
                                  
2
2
4.00
                                                             
Update plans to comply with TT0345 Lessons Learned
4
1.50
345.00
                                  
3
3
6.00
                                                             
Revise and replot sheets for utility updates
4
3.00
690.00
                                  
6
6
12.00
                                                           
Revise and Replot for Future Development Plans
1
3.00
188.91
                                  
1
1
1
3.00
                                                             
Revise and Replot for 60% Comments
4
2.00
460.00
                                  
4
4
8.00
                                                             
Revise and replot sheets for 95% comments
4
1.00
230.00
                                  
2
2
4.00
                                                             
Lighting
-
                                        
-
                                                              
Revise and Replot for 60% Submittal
-
                                        
-
                                                              
Cover Sheet
1
2.00
115.00
                                  
1
1
2.00
                                                             
MC 85 Lighting Plan
3
8.00
1,209.72
                               
6
18
24.00
                                                           
91st Lighting Plan (New)
1
15.00
791.55
                                  
5
10
15.00
                                                           
91st Lighting Plan (Revise Existing)
1
6.00
316.62
                                  
2
4
6.00
                                                             
Lighting Detail
1
6.00
316.62
                                  
2
4
6.00
                                                             
Check and revise plans against current design standards (1hr/sheet)
6
1.00
316.62
                                  
2
4
6.00
                                                             
Update plans to comply with TT0345 Lessons Learned
6
1.50
474.93
                                  
3
6
9.00
                                                             
Revise and replot sheets for utility updates
6
1.00
316.62
                                  
2
4
6.00
                                                             
Revise and Replot for Future Development Plans
6
2.00
576.48
                                  
2
10
12.00
                                                           
Revise and Replot for 60% Comments
7
1.00
388.31
                                  
3
4
7.00
                                                             
Revise and replot sheets for 95% comments
7
0.57
230.00
                                  
2
2
4.00
                                                             
Traffic Signals
-
                                        
-
                                                              
Revise and Replot for 60% Submittal
-
                                        
-
                                                              
Removal Plan
1
2.00
93.05
                                    
1
1
2.00
                                                             
Signal Plan
1
4.00
179.67
                                  
1
3
4.00
                                                             
Pole and Conductor Schedule
1
4.00
186.10
                                  
2
2
4.00
                                                             
Check and revise plans against current design standards (4hr/sheet)
3
4.00
545.44
                                  
4
8
12.00
                                                           
Revise and replot sheets for utility updates
3
5.00
688.23
                                  
6
9
15.00
                                                           
Revise and Replot for 60% Comments
3
2.00
272.72
                                  
2
4
6.00
                                                             
Revise and replot sheets for 95% comments
3
1.00
136.36
                                  
1
2
3.00
                                                             
Pavement Marking and Signing Items
-
                                        
-
                                                              
Revise and Replot for 60% Submittal
-
                                        
-
                                                              
Cover
1
2.00
115.00
                                  
1
1
2.00
                                                             
Notes
1
1.00
43.31
                                    
1
1.00
                                                             
MC 85 Plans
3
4.00
604.86
                                  
3
9
12.00
                                                           
91st Avenue Plans (New)
1
20.00
1,008.10
                               
5
15
20.00
                                                           
91st Avenue Plans (Revise Existing)
2
8.00
749.72
                                  
2
14
16.00
                                                           
Signing Summary
3
10.00
1,384.44
                               
3
27
30.00
                                                           
Check and revise plans against current design standards (2hr/sheet)
10
2.00
979.72
                                  
4
16
20.00
                                                           
Update plans to comply with TT0345 Lessons Learned
10
1.00
489.86
                                  
2
8
10.00
                                                           
Revise and Replot for Future Development Plans
6
2.00
576.48
                                  
2
10
12.00
                                                           
Revise and Replot for 60% Comments
11
2.00
1,123.10
                               
6
16
22.00
                                                           
Revise and replot sheets for 95% comments
11
1.55
821.41
                                  
3
14
17.00
                                                           
Plan Sheet Quality Control (0.5 hrs/sheet/submittal) (60% & 95%)
159
0.96
9,325.71
                               
25
60
36
32
153.00
                                                         
4/2/2020
10 of 14

TASK
Scale
No Sheets
Hours/Sheet
Principal/QC
Project Manager - Sr Project Engineer -
Sr
Engineer
Designer
Environmental 
Manager
Administrative
 Total 
 SUBTOTAL 
 $            101.93  $                      73.91  $                71.69  $        49.74  $          43.31  $              62.95  $              42.16 
Specifications
-
                                        
-
                                                              
Roadway
1,161.84
                               
4
20
24.00
                                                           
Pavement Marking and Signing Items
286.76
                                  
4
4.00
                                                             
Sequence of Construction and Temporary Traffic Control 
198.96
                                  
4
4.00
                                                             
Traffic Signals
198.96
                                  
4
4.00
                                                             
ITS
286.76
                                  
4
4.00
                                                             
Drainage
286.76
                                  
4
4.00
                                                             
Landscape Architectural Practice and Design
147.82
                                  
2
2.00
                                                             
Structures (EXCLUDED)
-
                                        
-
                                                              
Lighting
286.76
                                  
4
4.00
                                                             
Geotechnical
321.06
                                  
2
4
6.00
                                                             
Add COC requirements to the specs
219.51
                                  
2
1
3.00
                                                             
Update specs to comply with TT0345 Lessons Learned
3,579.10
                               
20
8
22
10
60.00
                                                           
Discuss process of getting green tags, SRP inspection, LOA, Letters to De-energize
286.76
                                  
4
4.00
                                                             
Combine Document (All Submittals)
886.92
                                  
12
12.00
                                                           
Specifications Quality Control
2,956.40
                               
40
40.00
                                                           
Estimates
-
                                        
-
                                                              
Roadway
-
                                        
-
                                                              
Update Quantities for Logic Park Revisions
965.98
                                  
2
6
12
20.00
                                                           
Estimate Roadway Excavation vs. Subgrade Preparation
346.63
                                  
1
2
4
7.00
                                                             
Revise P1243 Driveway Wings to 9" thick sidewalk
136.36
                                  
1
2
3.00
                                                             
Estimate Lime under sidewalk
210.27
                                  
1
1
2
4.00
                                                             
Estimate Driveway structural section to 10" with Fiber Mesh
136.36
                                  
1
2
3.00
                                                             
Rectify subgrade prep in areas of lime stabilization
210.27
                                  
1
1
2
4.00
                                                             
Insert estimate into MCDOT cost estimation tool
645.63
                                  
3
2
8
13.00
                                                           
Geotechnical (Earthwork/Over excavation)
755.71
                                  
1
5
10
16.00
                                                           
Pavement Marking and Signing Items
-
                                        
-
                                                              
Sequence of Construction and Temporary Traffic Control 
-
                                        
-
                                                              
Update Quantities for Logic Park Revisions
979.72
                                  
4
16
20.00
                                                           
Verify temp striping and seal coating (Edge line, DY, Stop bars) is incidental to Traffic Control
684.68
                                  
4
8
12.00
                                                           
Traffic Signals
-
                                        
-
                                                              
Update Quantities for Logic Park Revisions
272.72
                                  
2
4
6.00
                                                             
ITS
-
                                        
-
                                                              
Update Quantities for Logic Park Revisions
158.31
                                  
1
2
3.00
                                                             
Revise estimate duct plugs, remove/replace, and new fiber
387.72
                                  
1
2
5
8.00
                                                             
Drainage
-
                                        
-
                                                              
Update Quantities for Logic Park Revisions
489.86
                                  
2
8
10.00
                                                           
Landscape Architectural Practice and Design
-
                                        
-
                                                              
Update Quantities for Logic Park Revisions
316.62
                                  
2
4
6.00
                                                             
Structures (EXCLUDED)
-
                                        
-
                                                              
Lighting
-
                                        
-
                                                              
Update Quantities for Logic Park Revisions
316.62
                                  
2
4
6.00
                                                             
Quantify splice points underneath SRP
416.10
                                  
2
2
4
8.00
                                                             
Utilities
-
                                        
-
                                                              
Update Quantities for Logic Park Revisions
831.02
                                  
8
10
18.00
                                                           
Split and quantify remove hydrant and install hydrant separately
179.67
                                  
1
3
4.00
                                                             
Add Temporary Tap and Lateral pipe contingency items for water service connections
49.74
                                    
1
1.00
                                                             
Review and update Quantify ACP removal
99.48
                                    
2
2.00
                                                             
Environmental - Coordinate with MCDOT to Update Mitigation Costs
123.65
                                  
1
1
2.00
                                                             
Combine Estimates (All Submittals)
2,038.40
                               
10
30
40.00
                                                           
Estimate Quality Control
1,773.84
                               
24
24.00
                                                           
1100.8 - Constructability Review
-
                                        
-
                                                              
Address Comments from Constructability Review
2,102.70
                               
10
10
20
40.00
                                                           
1100.9 - Construction Phasing
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1100.10 - Sealed PS&E Submittal
-
                                        
-
                                                              
Submittal Preparation (60%, 95%, 100% and Sealed)
2,300.68
                               
8
20
20
48.00
                                                           
4/2/2020
11 of 14

TASK
Scale
No Sheets
Hours/Sheet
Principal/QC
Project Manager - Sr Project Engineer -
Sr
Engineer
Designer
Environmental 
Manager
Administrative
 Total 
 SUBTOTAL 
 $            101.93  $                      73.91  $                71.69  $        49.74  $          43.31  $              62.95  $              42.16 
Task 1200 - Value Engineering
-
                                        
-
                    
-
                             
-
                      
-
               
-
                 
-
                    
-
                    
-
                                                              
1200.1 - Select Value Engineering Team
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1200.2 - Value Engineering Study Plan
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1200.3 - Value Engineering Meeting Setup 
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1200.4 - Design Team Presentation
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1200.5 - Value Engineering Analysis
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1200.6 - Assess Impacts of Value Engineering Recommendations
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1200.7 - Initial Dispositions of Value Engineering Recommendations
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1200.8 - Draft Value Engineering Study Report
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1200.9 - Management Committee Presentation
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1200.10 - Final Value Engineering Study Report
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1200.11 - Update Draft Scoping document and Recommended Alternative Plans
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1200.12 - Final Dispositions of Value Engineering Recommendations
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1200.13 - Implementation
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
Task 1300 - Bidding Phase
5,829.92
                               
-
                    
32
                              
-
                      
-
               
80
                  
-
                    
-
                    
112.00
                                                         
1300.1 - Prepare Advertisement Package
-
                                        
-
                                                              
Technical Assistance
642.12
                                  
4
8
12.00
                                                           
1300.2 - Submit Obligation Package
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1300.3 - Receive Federal Funding Authorization
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
1300.4 - Advertisement
-
                                        
-
                                                              
Answer Questions
1,284.24
                               
8
16
24.00
                                                           
1300.5 - Pre-Bid Conference
-
                                        
-
                                                              
Planning Meeting (1 total) (1 attendee)
221.73
                                  
3
3.00
                                                             
Pre-bid Meeting (1 total) (1 attendee)
221.73
                                  
3
3.00
                                                             
1300.6 - Preparation of Addenda
-
                                        
-
                                                              
Addenda Preparation
2,471.50
                               
10
40
50.00
                                                           
1300.7 - Bid Opening
-
                                        
-
                                                              
Bid Analysis
988.60
                                  
4
16
20.00
                                                           
1300.5 - Hand-off Meeting with Construction
-
                                        
-
                                                              
EXCLUDED
-
                                        
-
                                                              
4/2/2020
12 of 14

TASK
Scale
No Sheets
Hours/Sheet
Principal/QC
Project Manager - Sr Project Engineer -
Sr
Engineer
Designer
Environmental 
Manager
Administrative
 Total 
 SUBTOTAL 
 $            101.93  $                      73.91  $                71.69  $        49.74  $          43.31  $              62.95  $              42.16 
Task 1400 - Construction Phase
14,115.28
                             
-
                    
73
                              
34
                       
61
                
75
                  
-
                    
-
                    
243.00
                                                         
1400.1- Pre-Construction Conference (1 meeting) (1 attendee)
-
                                        
-
                                                              
Preparation (1 hr)
117.22
                                  
1
1
2.00
                                                             
Attendance (3 hrs)
221.73
                                  
3
3.00
                                                             
1400.2 - Requests for Information (RFIs)
-
                                        
-
                                                              
1400.2.1 - TT0651 Requests for Information (RFIs)
-
                                        
-
                                                              
RFI's (60 @ 2 hrs/each)
6,448.85
                               
15
20
35
50
120.00
                                                         
Shop Drawings (5 reviews) (4 hours per review)
1,153.56
                               
4
4
8
4
20.00
                                                           
Material Reviews (3 Reviews) (2 hours per review)
443.46
                                  
6
6.00
                                                             
Plan Revisions
5
10.00
2,819.60
                               
10
10
10
20
50.00
                                                           
1400.3 - Construction Start
-
                                        
-
                                                              
Meetings (5 meetings) (1 attendees)
-
                                        
-
                                                              
Preparation (1 hr/mtg)
369.55
                                  
5
5.00
                                                             
Attendance (2 hrs/mtg)
739.10
                                  
10
10.00
                                                           
1400.4 - Complete Construction
-
                                        
-
                                                              
As-Builts (EXCLUDED)
-
                                        
-
                                                              
AOC (EXCLUDED)
-
                                        
-
                                                              
1400.5 - Project Close-Out
-
                                        
-
                                                              
Administration and Management
1,108.65
                               
15
15.00
                                                           
Close-Out
693.56
                                  
4
8
12.00
                                                           
KIMLEY-HORN SERVICES
-
                                                              
SUBTOTAL (KIMLEY-HORN SERVICES)
193,477.52
                           
-
                                                              
4/2/2020
13 of 14

MC85  Update Docs., Bidding Assist., and Post Design
Kimley-Horn and Associates
PROJECT NO. TT0651
Contract No. TBD
Travel
A. Local Mileage at
0.56
$                  
400
                    
miles
Subtotal Travel
224
$                  
Plotting
B.  Exhibits at
0.25
$                  
20
                      
exhibits
5.00
$                 
C.  Plots at
1.00
$                  
per LF
100
                    
plots
100
$                  
D.  Plan Submittals
Half Size Bond Copies at
0.10
$                  
500
                    
Copies
Full Size Bond Copies at
1.00
$                  
100
                    
Copies
Subtotal Plotting
255.00
$             
Miscellaneous Expenses
C. Messenger
100
$                  
Subtotal Miscellaneous Expenses
100
$                  
ESTIMATED OUTSIDE SERVICES & CONSULTANTS
-
$                   
TOTAL ESTIMATED OUTSIDE SERVICES
-
$                   
TOTAL ESTIMATED EXPENSES  
579
$                  
ESTIMATE OF DIRECT EXPENSES
 3/26/2013
Page 14 of 14