BWS Architects 
Elections Project No. 1925.000 
Recorders Project No. 1925.100 
 
 
Maricopa County Elections and Recorders 
Safety and Security Improvements    
 
 
Meeting Date:    
Thursday, October 3, 2019 @ 1:00 pm 
Meeting Purpose:    
SD Estimate Review 
Location:   
 
Facilities Management Department 
Liberty Conference Room 
 
Attendees: 
Maricopa County: Paul Corens, Seth Bouman, Rich Wegele 
 
Elections & Recorders: Scott Hadley, Keely Varvel, Richard Greene 
 
BWS Architects: Sue Gray, Erin Giles 
 
SD Estimate Meeting Minute 10 
  
10.0 
Budgets for the Security Hardening project’s and the schematic design documents were 
reviewed. 
a.   The projects were priced as separate elements within a cost range. 
b.   Soft Costs, Furniture, Fixtures and Equipment are included in the numbers. 
c.  Escalation is not included in these costs.  If elements are deferred to another fiscal year, 
current escalation rates are trending at 3.5% to 4%. 
 
10.1 
Election’s Ballot Vault and New Server Room Documents 
a. Dry suppression requires these two rooms be sealed and doors swing out.  
b. Security camera locations are shown as a place holder for pricing. Moving forward, we will 
get feedback if they can tie into the existing analog system or if they will be on an upgraded 
digital system. 
c. The existing wall in the BTC may be removed.  Outlets have been shown – moving forward, 
we will need to coordinate outlets at the Duplication Stations.  Outlets will be added to the 
Ballot Vault. 
d. Space for 61 pallets are shown.  The County anticipates they will need space for the storage 
of 2.3 million ballots over the next 4‐6 years.  Ballots are getting smaller. 
 
10.2 
Election’s Lobby: North and South 
a. Hardening extent was reviewed.  Secure pass‐throughs are included at the counter.   
b. The extent of bullet proof glass at the counter was priced with a cost deduct to reduce the 
amount of glass.  Since the price was nominal, the cost shown today reflects the preferred 
option that is like the current condition.

10.3 
Recorder’s Lobby 
a. Two smaller offices are preferred to an open space or one large office. 
b. Panic buttons are included at all counter stations, including the Election’s lobbies. 
 
10.4 
BWS will send the County an Executive Summary and Abridged version of the documents for 
Elections and Recorders review. 
a. They will review and provide comments and direction by October 15th. 
 
10.5 
Next Meeting:  October 15th, 2019.  Time to be Determined. 
 
10.6 
Attachments:  County Cost Memo 
 
 
 
 
 
 
 
These notes were taken by Sue Gray; they reflect her understanding of the meeting. Please contact us if you have any 
comments and/or changes.

401 West Jefferson Street 
Phoenix, AZ  85003-2143 
Phone: 602-506-8194 
Fax: 602-506-7292 
www.maricopa.gov 
 
Maricopa County 
Facilities Management Department 
October 3, 2019 
 
 
 
To: 
 
Scott Hadley, Recorder’s Office 
 
From:  
Paul Corens, Facilities Management 
 
 
RE: 
 
Budgets for Security Hardening Projects 
 
 
 
 
Scott, 
 
 
In conjunction with BWS Architects, Facilities Management has compiled the 
following rough order of magnitude budgets for the four requested security design 
projects.   
 
These are estimates based on schematic designs.  Final costs may change due to 
changes in scope, design, and/ or final contractor estimates.  Cost savings might be 
realized if projects are authorized at the same time. 
 
 
 
1) Election’s vault and new server room: 
 
$657,000 - $723,000 
 
2) Election’s North lobby: 
 
 
 
$449,000 – $501,000 
 
3) Election’s South lobby: 
 
 
 
$180,000 – $203,000 
 
4) Recorder’s lobby: 
 
 
 
 
$496,000 – $550,569 
 
 
 
Facilities is aware that, if these construction projects are authorized, certain areas may 
only be available for short periods of time during the calendar year. 
 
Next steps may include authorizing BWS Architects to complete aspects of the 
various designs and engaging a contractor for estimating and scheduling.