Staff Report

Town of Fountain Hills — Town Council (2026-06-16)

View PDF Meeting page

Extracted text (via pymupdf) 7241 characters
ITEM 9.c. 
 
TOWN OF FOUNTAIN HILLS 
 
STAFF REPORT 
 
Meeting Date: 
6/16/2026 
Meeting Type: 
Town Council Regular Meeting 
Submitting Department: 
Public Works 
Prepared by: 
Justin Weldy, Public Works Director 
Staff Contact Information: Phone: 480-816-5133 
Email: jweldy@fountainhillsaz.gov 
 
Request to Town Council Regular Meeting (Agenda Language) 
CONSIDERATION AND POSSIBLE ACTION: Regarding a budget authority transfer for 
additional design costs for the Downtown Streetscape Capital Improvement Project 
 
Staff Summary (background) 
Recommended Action 
Staff recommends that the Town Council authorize the use of $133,605 from the previously 
approved FY 2027 Downtown Streetscape Improvements construction budget to complete 
additional drainage design services for the Parkview Avenue portion of the project. 
 
Summary 
The Downtown Streetscape Improvements Project is currently in the design phase and 
includes planned pedestrian safety, accessibility, lighting, landscaping, and streetscape 
improvements along Verde River Drive and Parkview Avenue. 
During the 30 percent design review for Parkview Avenue, the project engineer identified 
drainage issues that were not known during the original grant application or concept 
development phase. The analysis determined that stormwater runoff could negatively affect 
the proposed improvements by trapping water within parking areas and restricting stormwater 
flows from areas west of La Montana Drive. 
To address these issues, a new storm drain system must be designed along Parkview Avenue 
between La Montana Drive and Saguaro Boulevard. The additional drainage design services 
total $133,605. 
No new appropriation is being requested. Staff is requesting authorization to use a portion of 
the already-approved FY 2027 Downtown Streetscape Improvements construction budget so 
the design work can continue without interruption. 
 
Background 
In October 2024, Town Council approved staff’s submission of an application to the 
Maricopa Association of Governments for Federal Fiscal Year 2025 Closeout Funds through 
the Design Assistance Program. The project, titled Downtown Sidewalk Gap Elimination and 
Lighting Improvements, was developed to evaluate and address missing sidewalk segments 
and insufficient pedestrian-scale lighting in the Downtown area, with a focus on the Verde 
River Drive and Parkview Avenue corridors. 
The Town was successful in securing the grant award and received $100,000 in federal 
funding. 
To maintain project momentum while the design concept phase was underway, the Town 
released a Request for Qualifications on May 8, 2025, for final design services. One proposal 
was received, and Kimley-Horn and Associates was selected to complete the design.

The project scope includes: 
• Construction of ADA-compliant sidewalks and curb ramps; 
• Installation of pedestrian-scale street lighting; 
• Trees and landscape buffers; 
• Street furniture, including benches, waste receptacles, and bicycle racks; 
• Pedestrian wayfinding signage; and 
• Crosswalk enhancements. 
 
Drainage Design Need 
As part of the final design process, a drainage analysis was completed for the Parkview 
Avenue corridor. At the 30 percent design milestone, the analysis identified stormwater 
conditions that must be addressed before the Parkview Avenue improvements can advance. 
Specifically, the analysis found that stormwater runoff would negatively affect the proposed 
improvements by trapping water within parking areas and limiting stormwater flows 
originating west of La Montana Drive. To correct these conditions and ensure the long-term 
functionality of the streetscape improvements, a new storm drain system is needed along 
Parkview Avenue between La Montana Drive and Saguaro Boulevard. 
This drainage infrastructure was not identified during the initial grant application or concept 
development phases. It was discovered through the more detailed engineering analysis 
completed as part of final design. 
 
Project Schedule 
The Verde River Drive design portion of the project remains on schedule for completion by 
June 30. Construction for Verde River Drive is currently included in the FY 2027 Budget in 
the amount of $2,003,000. 
The Parkview Avenue design will extend into FY 2027 due to the additional drainage design 
requirements. Authorizing the additional design services now will allow the design team to 
continue work without interruption and help avoid delays that could affect future construction 
timing and costs. 
 
Financial Impact 
The additional drainage design services total $133,605. Staff is requesting authorization to 
use a portion of the approved FY 2027 Downtown Streetscape Improvements construction 
budget for this work. 
These funds were originally planned for Verde River Drive construction. No additional 
budget appropriation is being requested at this time. Staff will seek bids for the next phase of 
Verde River Drive construction before requesting any additional budget authority. 
Staff Recommendation 
Staff recommends approval of the request to authorize $133,605 in existing FY 2027 budget 
authority for additional drainage design services. Approval will allow the Town to complete 
the Parkview Avenue design, maintain project momentum, reduce the risk of schedule delays, 
and help minimize potential cost increases associated with delaying the work. 
 
Related Ordinance, Policy or Guiding Principle 
• Downtown Sidewalk Gap Elimination and Lighting Improvements Project 
• FY 2027 Capital Improvement Program (CIP) 
• Town Strategic Plan – Transportation and Infrastructure 
• MAG Regional Transportation Improvement Program (TIP) and Design Assistance 
Program

• Council Goal of maintaining and improving pedestrian safety, accessibility, and 
multimodal connectivity within the Downtown area 
 
Risk Analysis 
If the requested funding authorization is not approved, completion of the Parkview Avenue 
drainage design will be delayed. This delay will impact the overall project schedule, postpone 
construction activities, and increase project costs due to inflation and changing market 
conditions. In addition, delaying the drainage design may require redesign or re-evaluation of 
completed project elements, resulting in inefficiencies and potential schedule impacts. 
Approval of this request allows staff to maintain project momentum, complete the necessary 
engineering analysis, and advance the project toward construction without interruption. 
 
Recommendation(s) by Board(s) or Commission(s) 
N/A 
 
Staff Recommendation(s) 
Staff recommends that the Town Council authorize the use of $133,605 from the approved 
FY 2027 Downtown Streetscape Improvements construction budget to complete additional 
design services associated with the Parkview Avenue drainage improvements. 
 
Suggested Motion 
MOVE TO APPROVE the transfer of $133,605 budget authority from the FY 2027 
Downtown Streetscape Improvements construction budget for additional drainage design 
services on Parkview Avenue and authorize staff to proceed with the work. 
 
FISCAL IMPACT 
Fiscal Impact: $133,605 
Budget Reference: FY 27 Budget 
Funding Source: Capital Improvement Fund 
 
ATTACHMENTS 