PRESENTATION

Town of Fountain Hills — Town Council (2026-05-05)

View PDF Meeting page

Extracted text (via pymupdf) 5581 characters
FY2027 Tentative Budget
Paul Soldinger, Chief Financial Officer
May 5, 2026

Key Updates from 
Proposed Budget

Key Updates from Proposed Budget
• Added $80,000 of budgeted expenditures for Arizona 
Office of Tourism (AOT) grant (Prop 302)
• Budget increased $80K in Tourism Fund
• Added $1 million of budget contingency in Capital Projects 
Fund for possible new FY27-FY28 project to be presented 
to Council on 6/2/2026
• Budget increase $1M in Capital Projects Fund (up to $1.7M)

FY2027 Tentative Budget Comparison - Revenues
No changes made from 
FY27 Proposed Budget
FY2027
FY2027
Changes
Proposed Budget Tentative Budget
from Proposed
Revenues by Fund
General Fund
$26,800,894
$26,800,894
$0
Streets Fund
4,516,381
4,516,381
0
Capital Projects Fund
2,668,068
2,668,068
0
Facilities Reserve Fund
144,302
144,302
0
Special Revenue Fund
1,755,660
1,755,660
0
Economic Dev Funds
820,259
820,259
0
10 Nonmajor Funds
1,772,039
1,772,039
0
Total Expenditures:
$38,477,603
$38,477,603
$0
Major Fund Groups

FY2027 Tentative Budget Comparison - Expenditures
Additional $1M for CIP 
contingency
General Fund Contingency
FY2027
FY2027
Changes
Proposed Budget Tentative Budget
from Proposed
Expenditures by Fund
General Fund
$26,800,894
$26,800,894
$0
Streets Fund
8,269,842
8,269,842
0
Capital Projects Fund
10,000,000
11,000,000
1,000,000
Facilities Reserve Fund
600,000
600,000
0
Special Revenue Fund
1,755,660
1,755,660
0
Economic Dev Funds
989,190
1,069,190
80,000
10 Nonmajor Funds
789,478
789,478
0
Total Expenditures:
$49,205,064
$50,285,064
$1,080,000
FY2027
FY2027
Changes
Proposed Budget Tentative Budget
from Proposed
General Gov Contingency
$1,002,316
$1,002,316
$0
Major Fund Groups
General Fund Contingency
Added $80K of budget 
to account for AOT grant

Expenditure Limitation for FY2027 Tentative
FY27 Expenditure Limit
$38,178,069
FY27 Proposed Budget
$49,205,064
Less Grants
(1,760,660)
Less HURF
(1,810,740)
Less Investment Income
(840,962)
Less Other Exclusions
(2,175,700)
Less Using Prior Years’ Carryforward
(5,518,934)
FY27 Expenditures Subject to Limit
$38,178,068
$1
FY27 - $6.7M exclusions
Budgeted to be $1 
under the FY2027 
expenditure limitation

General Fund

General Fund Past Performance
*FY23 Expenditures do not include about $4.2 million of ARPA grants that paid for 
Public Safety out of another fund instead of the General Fund
Without those grants, the General Fund expenditures would have been about $19.9 
million in FY23

General Fund - Expenditures
*Administration Department includes Town Manager, Information Technology, Town Clerk, Administrative Services, Finance, Public Information, Legal 
Services and Purchasing divisions
** Includes MCSO Patrol/Jail costs, and animal control services
FY2026
FY2027
FY2027
Changes
% Change
Adopted Budget
Proposed Budget
Tentative 
Budget
from FY27 
Proposed to 
Tentative
from FY2026 Adopted 
to FY27 Tentative
Expenditures by Department
Mayor and Council
$73,455 
$80,442
$80,442
$0
9.5%
Administration*
3,252,618
3,459,977
$3,459,977
0
6.4%
General Government
1,899,944
1,745,819
$1,745,819
0
-8.1%
Municipal Court
548,969
574,919
$574,919
0
4.7%
Public Works
2,488,886
2,516,325
$2,516,325
0
1.1%
Development Services
1,532,513
1,568,863
$1,568,863
0
2.4%
Community Services
4,427,565
4,580,916
$4,580,916
0
3.5%
Fire & Emergency Med
5,966,584
6,477,777
$6,477,777
0
8.6%
Law Enforcement**
5,861,005
5,795,856
$5,795,856
0
-1.1%
Total Expenditures:
$26,051,539 
$26,800,894
$26,800,894
$0
2.9%
General Fund

All Other Funds

All Other Funds - Expenditures
FY2026
FY2027
FY2027
Changes
% Change
Adopted Budget
Proposed Budget
Tentative 
Budget
from FY27 
Proposed to 
Tentative
from FY26 Adopted 
to FY27 Tentative
Funds other than General Fund
Streets Fund
$7,244,627 
$8,269,842
$8,269,842
$0
14.2%
Capital Projects Fund
12,712,800
10,000,000
11,000,000
1,000,000
-13.5%
Facilities Reserve Fund
1,000,000
600,000
600,000
0
-40.0%
Special Revenue Fund
4,690,000
1,755,660
1,755,660
0
-62.6%
Economic Development Funds*
970,003
989,190
1,069,190
80,000
10.2%
All Nonmajor Funds**
727,429
789,478
789,478
0
8.5%
Total Expenditures:
$27,344,859 
$22,404,170
$23,484,170
$1,080,000
-14.1%
Total Budgeted Expenditures:
$53,396,398
$49,205,064
$50,285,064
Major Fund Groups
*”Economic Development Funds” includes the Downtown Strategy, Economic Development, and Tourism Funds
** Nonmajor Funds include the Public Art, Court Enhancement, GO Bond Debt Service, MPC Debt Service, Cottonwoods Maintenance District, 
Fire/Streets/Parks Impact Fee, Technology Replacement, and Vehicle Replacement Funds
Added $1M (up to $6M) for road 
paving projects
Additional $1M for CIP contingency
Added $80K of budget to account 
for AOT grant

Proposed Transfers

Proposed Transfers*
• $150,000 from Economic Development Fund to Tourism Fund to cover non-grant 
funded FY27 operations
• Up to $35,000 from Court Enhancement Fund to General Fund to cover actual part-time 
Court operation staff costs
• Up to $1,400,000 from Facilities Reserve Fund to Capital Projects Fund (matched to 
actual Lake Liner Design and Air Handler project costs, as planned and discussed with 
Council)
• Up to $1,900,000 ($1.6M Parks & $0.3M Streets) from Development Impact Fee Funds 
to Capital Projects Fund for actual costs for Skyview Park and Shea Blvd Widening capital 
projects (reimbursements from impact fee funds, as planned and discussed with 
Council)
*Funding transfers of General Fund excess reserves will be presented to Council in Fall 2026, after the financial audit is completed.

Council Direction 
for Final Budget