FY2026 Community Services CIP update april

Town of Fountain Hills — Town Council (2026-04-21)

View PDF Meeting page

Extracted text (via pymupdf) 1449 characters
Presented by
Kevin Snipes, Community Services Director
FY26 Capital Projects Update

Golden Eagle Park Playground Replacement
Complete, Carry Over from Last Year
2
Budgeted   
$150,000 
Expended 
 
$152,555
Over Budget  
$   -2,555

Avenue Linear Park Improvements
(Multi-Year 2 of 3)
Complete
Budgeted 
 
$200,000
Expended 
 
$193,305 
Remaining Budget $    6,695

COMMUNITY CENTER LIGHTING AND FANS
BEFORE
AFTER
AFTER

Budgeted                    $550,000
Ceiling Fans                   $49,100
Motorized Roller Blinds         $46,500
Light Fixtures in the Lobby    $115,203
Divider Walls in the Ballrooms  $332,873
Expended                    $543,676
Under Budget                   $6,324
COMMUNITY CENTER DIVIDER WALLS, 
BLINDS, LIGHTING AND FANS

Skyview Park 
Out For Bid Construction

Skyview Park 
Development Fees 
Budgeted  
 
  $700,000 
Expended For Design   $36,348

• Budgeted      
  $50,000
• Encumbered   $40,213
Budget Remaining $   9,787
Centennial Pavilion Shade Lighting

Fountain Park Ramada Replacement
Out for Bid

Fountain Park Splash Pad Shade Lighting- Met with vendor design In Process
Budgeted      $50,000 
Expended     $0
Desert Vista Dog Park Improvements- Work to begin end of May-June
Budgeted      $50,000 
Expended     $0
Desert Vista Pumphouse and Four Peaks Electrical Room Design-
 
Met with contractor and working on design/build to save 100,000 design
Budgeted      $50,000 Each  
Expended     $0

Questions