FY2026 Public Works Capital Projects Update - 4-21-2026

Town of Fountain Hills — Town Council (2026-04-21)

View PDF Meeting page

Extracted text (via pymupdf) 2571 characters
Presented by
Justin T. Weldy, Public Works Director
Town Council Meeting
April 21, 2026
FY26 Public Works 
Capital ProjectsUpdate

Public Works
FY 2026
Capital Projects
2

S6058 – Shea Boulevard Widening
South Side Between Palisades Blvd & FHBLVD
State Funding (Prop 400)
UNDER CONSTRUCTION
FY26 Budget 
$3,525,000
Expended 
$170,371.35
Available  
$3,354,628.65
Development Fee Eligible
MAG Grant 
$2,100,000
3

S7003 – Palomino Boulevard Full Depth
Pavement Reconstruction
4
Budgeted -  $5,400,000.00
Construction bid - $3,176,633.92
Expended - $ 1,304,057.59
Budget Available - $4,095,942.41

5
Pedestrian Marked Crosswalks/Sidewalk Infill – Town-Wide
S7002 - Crosswalks
Budgeted: $152,900.00
Expended: $140,803.77
Encumbered: $12,096.23
(Saguaro & Monterey)
Budget Available: $0
S6061 - Sidewalks
Budgeted: $325,000.00
Expended: $237,261.66
Encumbered: $54,230.72
(Saguaro & Monterey)
Budget Available: 
$33,507.62
Crosswalk Locations Completed 
in FY26:
•
El Lago Mid-Block Crossing 
(between Saguaro & La 
Montana) 
•
Golden Eagle Blvd & 
Brittlebush Dr
•
La Montana Dr & Cambria Dr
•
La Montana & Hamilton Dr
Sidewalk Infill Completed in 
FY26: 
 
•
La Montana between 
Hamilton Dr and Saguaro 
Blvd
•
Sidewalk on Hamilton Dr

S6068 – Town wide Guardrail replacement 
Guardrail Locations Completed in FY26:
•
McDowell Mountain Road – Milepost 2
6
Budgeted: $50,000
Expended: $14,261
Encumbered: $29,140
(for Palisades Blvd)
Budget Available: $6,599

S6059 - Wayfinding Signs
Installation Nearly Complete
7
Budgeted: $88,194
Expended: 54,704.31
Encumbered: $33,263.50
Budget Available: $226.19

D6057 - Golden Eagle Impoundment Area  - Phase 2 
(Golden Eagle Dam Improvements Only)
                   
Design almost complete – Coord. with ADEQ
Construction anticipated for FY27
75% Grant Funded from Flood Control 
District of Maricopa County for Construction
8
Budgeted (FY26): $300,000.00
Expended:             $291,2333.55
FY26 Budget Available: $8,766.45

D6060 – Stormwater Infrastructure Rehabilitation
Projects Completed in FY26 – Wendover 
Court Spillway
Currently Underway – Nelson Drainage 
Channel
9
Budgeted: $150,360.00
Expended: $150,354.59

E-8506 - Downtown Streetscape Improvements – Phase I
(Verde River Dr and Parkview Ave)
MAG Design Assistance Grant
Work Completed in September 2025
(15% Plan and Project Assessment Report)
Public Meeting Held – April 9, 2026
Design of Verde River & Parkview Underway – 
30% Completion by June
10
Budgeted:      $515,000
Expended:      $88,529.29
Encumbered: $407,908.40
Budget Available: $18,562.31

Questions