Staff Report

Town of Fountain Hills — Town Council (2026-02-03)

View PDF Meeting page

Extracted text (via pymupdf) 1405 characters
Presented by
Kevin Snipes, Community Services Director
FY26 Capital Projects Update

Golden Eagle Park Playground Replacement
Complete, Carry Over from Last Year
2
Budgeted   
$150,000 
Expended 
 
$152,555
Over Budget  
$   -2,555

Avenue Linear Park Improvements
(Multi-Year 2 of 3)
In progress
Budgeted 
 
$200,000
Expended 
 
$193,305 
Remaining Budget $    6,695

Pleasantville Park 
100% Design Submitted

Pleasantville Park 
100% Design Submitted
Development Fees 
Budgeted  
 
$700,000 
Expended 
 
$7,704

COMMUNITY CENTER LIGHTING AND FANS
BEFORE
AFTER

Budgeted                    $550,000
Ceiling Fans                   $49,100
Motorized Roller Blinds         $46,500
Light Fixtures in the Lobby    $109,826
Divider Walls in the Ballrooms  $332,873
Expended                    $538,299
Under Budget                 $11,701
COMMUNITY CENTER LIGHTING AND FANS

Fountain Park Splash Pad Shade Lighting- Met with vendor design In Process
Budgeted      $50,000 
Expended     $0
Centennial Pavilion Shade Lighting- Met with vendor Design In Process 
Budgeted      $50,000 
Expended     $0
Desert Vista Dog Park Improvements- In Process
Budgeted      $50,000 
Expended     $0
Desert Vista Pumphouse and Four Peaks Electrical Room Design- Not Started
Budgeted      $50,000 
Expended     $0
Fountain Park Ramada Replacement- Met with Multiple Vendors
Budgeted      $320,000 
 Expended     $0

Questions