Staff Report

Town of Fountain Hills — Town Council (2026-02-03)

View PDF Meeting page

Extracted text (via pymupdf) 6293 characters
ITEM 8.a. 
 
TOWN OF FOUNTAIN HILLS 
 
STAFF REPORT 
 
Meeting Date: 
2/3/2026 
Meeting Type: 
Town Council Regular Meeting 
Submitting Department: 
Public Works / Streets 
Prepared by: 
Jeff Pierce, Streets Superintendent 
Staff Contact Information: Phone: 480-816-5129 
Email: jpierce@fountainhillsaz.gov 
 
Request to Town Council Regular Meeting (Agenda Language) 
CONSIDERATION AND POSSIBLE ACTION: Regarding Pavement Management Options for 
Thistle Drive and Funding Allocation. 
 
Staff Summary (background) 
On December 16, 2025, staff presented alternative pavement treatment options for 
Richwood Avenue between Golden Eagle Boulevard and Boulder Drive. These options 
included use of the Town’s pilot chip seal/cape program as well as full reconstruction of the 
roadway. Following discussion, the Mayor and Council reviewed the alternatives, selected a 
preferred approach, and directed staff to use funds for a full reconstruction of Richwood 
Avenue. 
Concurrently, the Mayor and Council directed staff to also evaluate Thistle Drive, from 
Palisades Boulevard to just east of Mountainside Drive at the roadway terminus, for similar 
alternative pavement treatment options, while also preparing cost evaluation for full 
roadway reconstruction. 
 
Evaluation and Findings  
Since the last meeting, staff reached out to the paving contractor to secure a quote for the 
same treatment options, both a lower-cost alternative and a full roadway reconstruction as 
presented on Richwood Avenue. 
 
Thistle Drive Treatment Approach 
 
Lower-Cost Alternative- Chip Seal w/ Cape 
 
1. Localized Asphalt Removal and Replacement 
-Approximately 400 square yards of asphalt will be removed and replaced in sections where 
the pavement cannot be salvaged. 
 
2.Micro Milling 
-A micro mill of ½ inch to ¾ inch will be performed across the roadway surface to remove 
high spots, address raveling areas, and improve bonding for subsequent treatments. 
 
3. Type III Micro Seal Scratch Course 
-Apply a micro-seal scratch coat to level minor surface imperfections and provide a uniform

base for sealing. 
 
4.Crack Sealing 
-Seal all remaining cracks to prevent water intrusion and extend pavement life. 
 
5. Chip Seal with Cape Seal Overlay 
-Apply a chip seal (liquid asphalt and embedded aggregate) followed by a cape seal to 
provide a smooth, sealed, durable finish. 
-This treatment combination has proven successful in extending service life 7–10 years, 
depending on weather conditions. 
 
Estimated Cost Summary 
Component                                                                                Estimated Cost 
 
Asphalt Removal/Replacement, Chip Seal w/ Cape                 $623,000 of which includes 15% 
                                                                                                                                owners allowance 
Concrete Repairs (curb, gutter, panels, etc.)                            $284,000 of which includes 15% 
                                                                                                                                owners allowance 
Total Project Cost $907,000.00 
 
Full Reconstruction Alternative 
 
Asphalt reconstruction is the process of completely removing and replacing the full 
pavement structure—including the surface, base, and, when necessary, the sub-base, to 
create a new pavement that is equivalent to or stronger than the original. It is used to 
correct major structural failures or functional obsolescence and differs from resurfacing, 
which only treats the surface. Reconstruction is a long-term solution followed by the 
placement of new pavement layers to produce a durable, renewed roadway. 
 
Estimated Cost Summary 
Component                                                                                        Estimated Cost 
3” AC on 5” ABC (see estimate)                                                         $1,304,000.00 
Concrete Repairs (curb, gutter, panels, etc.)                                     $284,000 of which includes 
15% 
                                                                                                                                owners allowance      
                 
Total Project Cost $1,600,000.00 
 
Related Ordinance, Policy or Guiding Principle 
N/A 
 
Risk Analysis 
If no action is taken on Thistle Drive, pavement distress will continue to deteriorate. As 
pavement conditions decline, the cost of rehabilitation increases significantly. Temporary or 
surface-level treatments address only visible symptoms—such as cracking, potholes, and 
surface wear—and do not correct underlying structural deficiencies within the roadway 
base, drainage system, or sub-grade. Consequently, these treatments have a limited-service 
life and require frequent repeat applications. Over time, the cumulative cost of multiple 
temporary repairs often exceeds the cost of a single full reconstruction, while providing 
inferior long-term performance and reliability.

Recommendation(s) by Board(s) or Commission(s) 
N/A 
 
Staff Recommendation(s) 
Staff recommend that the Mayor and Council approve the full reconstruction option for the 
Thistle Drive pavement treatment as outlined above. This recommendation is consistent 
with Council’s direction from December 16th, 2025, to pursue a full roadway reconstruction 
rather than a lower-cost, temporary repair. 
Although full reconstruction requires a higher initial investment, it results in a lower life-
cycle cost by providing a durable, long-term solution. In contrast, temporary repairs would 
require repeated funding allocations while only postponing inevitable pavement failure. 
For these reasons, staff conclude that full reconstruction is the most effective option to 
ensure the long-term performance, safety, and fiscal sustainability of the town’s roadway 
system. 
 
Suggested Motion 
MOVE TO APPROVE Proceeding with Pavement Management Options for Thistle Drive and 
Funding Allocation 
 
FISCAL IMPACT 
Fiscal Impact: $1,600,000.00 
Budget Reference: FY 25/26 Budget for Pavement Management Program 
Funding Source: Streets Fund 
 
ATTACHMENTS 
1. 
THISTLE DRIVE- CHIP SEAL WITH CAPE QUOTE 
2. 
THISTLE DRIVE-FULL RECON QUOTE 
3. 
THISTLE DRIVE-CONCRETE REPLACEMENT QUOTE