CIP List for FY 2025-26

Town of Wickenburg — Regular Meeting (2025-05-19)

View PDF Meeting page

Extracted text (via pymupdf) 9631 characters
Department
Account
Request Title
ApproFY2025
FY2026
FY2027
FY2028
FY2029
Total
Airport Expense
580-580-580-60305
Hangar Development Area Design Only
N/A
$200,000.00
$200,000.00
580-580-580-60603
Replace AWOS system
N/A
$350,000.00
$350,000.00
580-580-580-90923
Airport Master Plan Update
N/A
$425,000.00
$425,000.00
580-580-580-90915
Design of Taxiway A
N/A
$300,000.00
$300,000.00
580-580-580-90912
Taxilane Rehabilitation (Grant)
Yes
$1,125,000.00
$1,125,000.00
580-580-580-90917
Covered Tie Downs
N/A
$250,000.00
$250,000.00
Total Airport Expense
$250,000.00
$1,125,000.00
$300,000.00
$775,000.00
$200,000.00
$2,650,000.00
Court Expense
418-418-125-69999
Video Appearance
Yes
$0.00
$25,000.00
$25,000.00
Total Court Expense
$0.00
$25,000.00
$0.00
$0.00
$0.00
$25,000.00
Electric Utility Expense
510-510-500-90912
LaGolondrina Overhead/Underground Electric
N/A
$800,000.00
$800,000.00
510-510-500-90912
Adams/Jefferson St Alley OH/UG Electric Upgrades
Yes
$800,000.00
$800,000.00
510-510-500-90912
South Tegner Overhead/Underground Upgrades
N/A
$1,200,000.00
$1,200,000.00
510-510-500-90912
Jackson/Mohave St Overhead/Underground Upgrades
N/A
$800,000.00
$800,000.00
510-510-500-90912
Madison/Lincoln Alley OH/UG Electric Upgrades
N/A
$1,200,000.00
$1,200,000.00
Total Electric Utility Expense
$800,000.00
$800,000.00
$800,000.00
$1,200,000.00 $1,200,000.00
$4,800,000.00
Fire Expense
100-170-165-60603
VHF System Upgrades
Yes
$75,000.00
$100,000.00
$100,000.00
$100,000.00
$375,000.00
100-170-165-90908
Ladder 751 Replacement
Yes
$1,573,000.00
$1,573,000.00
100-170-165-90912
Cardiac monitor replacement
N/A
$48,000.00
$48,000.00
100-170-165-90908
Type 6 Fire Engine Upfit
N/A
$35,000.00
$35,000.00
Fire Station 751 Remodel
N/A
$2,200,000.00
$2,200,000.00
Total Fire Expense
$2,283,000.00
$1,648,000.00
$100,000.00
$100,000.00
$100,000.00
$4,231,000.00
Information Technology
700-700-700-90904
Network Refresh
N/A
$25,000.00
$25,000.00
100-170-165-60603
Mobile data terminals replacements
Yes
$8,600.00
$8,600.00
$17,200.00
100-142-142-90912
Police Server Refresh
N/A
$60,000.00
$60,000.00
100-142-142-90912
New Workstations
Yes
$10,000.00
$20,000.00
$50,000.00
$10,000.00
$90,000.00
100-142-142-90912
Building Low Voltage Cabling
N/A
$200,000.00
$200,000.00
100-142-142-90912
Voting/Request to Speak Software
No
$40,000.00
Total Information Technology
$25,000.00
$18,600.00
$228,600.00
$50,000.00
$70,000.00
$432,200.00
Library Expense
450-450-145-90905
Remodel of Conference & Study Room
Yes
$35,000.00
$35,000.00
Total Library Expense
18,746 GF, 16,254 Lib Recip
$0.00
$35,000.00
$0.00
$0.00
$0.00
$35,000.00
Maintenance Shop Expense
600-600-600-90912
Forklift
Yes
$50,000.00
$50,000.00
600-600-600-90905
Shade Structure
N/A
$180,000.00
$180,000.00
600-600-600-90912
Hose machine
N/A
$10,000.00
$10,000.00
Total Maintenance Shop Expense
$10,000.00
$50,000.00
$180,000.00
$0.00
$0.00
$240,000.00
Parks & Facilities Expense
750-750-750-90904
Rodeo Grounds Lighting & Electrical Upgrades
Yes
$25,000.00
$25,000.00
100-150-150-90905
Sunset Pickleball Restrooms
Yes
$250,000.00
$250,000.00
Block Grant
LED Lighting Improvement Grant
Yes
$173,476.00
$173,476.00
750-750-750-90904
Rodeo Grounds Road / Parking Upgrades
Yes
$48,000.00
$48,000.00
100-150-150-90905
Refurbish / Paint Sunset Concession Stand
Yes
$36,500.00
$36,500.00
100-150-150-90905
PSC Repair
Yes
$75,000.00
$75,000.00
100-150-150-90905
Replace Aging HVAC RTU's
Yes
$275,000.00
$100,000.00
$100,000.00
$100,000.00
$575,000.00
100-150-150-90904
Seal / Stripe Sunset Parking Lots
No
$75,000.00
$75,000.00
100-150-150-90904
Resurface Coffinger Tennis Courts
No
$38,000.00
$38,000.00
100-150-150-90904
Irrigation Upgrades at Sunset & Coffinger
Yes
$22,000.00
$22,000.00

Department
Account
Request Title
ApproFY2025
FY2026
FY2027
FY2028
FY2029
Total
100-150-150-90904
ADA Safety Upgrades at Town Parks
Yes
$48,000.00
$48,000.00
750-750-750-90904
Rodeo Grounds RV Hookups (10)
No
$25,000.00
700-700-700-90943
Rodeo Grounds Waterline Design
No
$300,000.00
700-700-700-90943
Rodeo Grounds Waterline Construction
No
$1,500,000.00
100-150-150-90905
Smoke Eaters Renovation
No
$450,000.00
$450,000.00
100-150-150-90912
Lawn Mower, Gator and Attachments
Yes
$53,600.00
$53,600.00
320-135-135-90905
Pool Heater & Covers
Yes
$142,000.00
$142,000.00
700-700-700-90961
Sunset Ball Park - Design / Engineering
N/A
$462,000.00
$462,000.00
700-700-700-90961
Sunset Ball Park Construction - Phase 1
N/A
$1,600,000.00
$1,600,000.00
700-700-700-90961
Sunset Ball Park Construction - Phase 2
N/A
$1,500,000.00
$1,500,000.00
100-150-150-90904
Sunrise Ball Park - Design / Engineering
Yes
$650,000.00
$472,000.00
$1,122,000.00
100-150-150-90904
Sunrise Ball Park Construction - Phase 1
N/A
$5,000,000.00
$5,000,000.00
100-150-150-90904
Sunrise Ball Park Construction - Phase 2
N/A
$6,000,000.00
$6,000,000.00
100-150-150-90904
Sunrise Ball Park Construction - Phase 3
N/A
$2,500,000.00
$2,500,000.00
700-700-700-90902
Coffinger Dog Park
N/A
$50,000.00
$50,000.00
700-700-700-90902
Coffinger Baseball / Football Field Renovation
Yes
$125,000.00
$125,000.00
100-150-150-90905
Community Center Renovation Design
Yes
$300,000.00
$300,000.00
100-150-150-90905
Community Center Construction
Yes
$1,500,000.00
$3,500,000.00
$5,000,000.00
700-700-700-90943
Constellation RV Park
N/A
$1,000,000.00
$1,000,000.00
750-750-750-90904
Constellation Park Trailhead Event Space
N/A
$350,000.00
750-750-750-90904
Rodeo Grounds Trailhead Parking
N/A
$650,000.00
$650,000.00
Total Parks & Facilities Expense
$0.00
$3,723,576.00
$10,097,000.00
$8,750,000.00 $4,750,000.00
$29,495,576.00
Recreation Expense
100-135-135-90912
LED Balloon Lights
N/A
$9,000.00
$9,000.00
100-135-135-90912
Sound System
N/A
$5,000.00
$5,000.00
100-135-135-90912
Portable Stage
No
$21,000.00
320-135-135-90905
Pool Remodel/Improvement
Yes
$80,000.00
$80,000.00
Total Recreation Expense
$14,000.00
$80,000.00
$0.00
$0.00
$0.00
$115,000.00
Sanitation Utility Expense
520-520-500-90908
Sanitation truck
Yes
$600,000.00
$600,000.00
520-520-500-90908
Sanitation Trucks
$1,000,000.00
$1,000,000.00
$2,000,000.00
Total Sanitation Utility Expense
$1,000,000.00
$600,000.00
$0.00
$1,000,000.00
$0.00
$2,600,000.00
Streets Expense
300-300-300-90904
Lewis Addition
Yes
$200,000.00
$200,000.00
$200,000.00
$200,000.00
$800,000.00
300-300-300-90904
Multi use path
Yes
$80,000.00
$80,000.00
300-300-300-60605
Bass Rd. rock wall retention
Yes
$70,000.00
$70,000.00
300-300-300-90904
Constellation Road repaving
Yes
$1,200,000.00
$1,200,000.00
300-300-300-90904
Coconino Parking Lot Upgrade
N/A
$500,000.00
$500,000.00
Dump Truck 10-Wheeler (Ttl $200k-300/500/501/530/531)
N/A
$30,000.00
300-300-300-90912
Lift gate
N/A
$8,000.00
$8,000.00
300-300-300-90904
N. Vulture Mine Rd.
N/A
$1,700,000.00
$1,700,000.00
300-300-300-90904
Tegner Street Phase 2
Yes
$900,000.00
$900,000.00
Total Streets Expense
$8,000.00
$2,450,000.00
$2,400,000.00
$200,000.00
$200,000.00
$5,288,000.00
Wastewater 1 Utility Expense
530-530-530-90914
Aztec Lift Station Odor Control
Yes
$160,000.00
$160,000.00
530-530-500-90912
Truck Crane
Yes
$11,000.00
$11,000.00
ARPA
383-383-383-90914
South WWTP Headworks Upgrade
Yes
$1,000,000.00
$1,000,000.00
530-530-500-90914
South WWTP Clarifier
N/A
$900,000.00
$900,000.00
WIFA
530-530-500-90914
UV and EPS
Yes
$800,000.00
$800,000.00
WIFA
530-530-500-90914
South WWTP Grit Removal Improvements
Yes
$300,000.00
$1,000,000.00
$1,300,000.00
WIFA
530-530-500-90914
South WWTP Solids Handling Improvements
N/A
$1,850,000.00
$1,850,000.00
530-530-500-90914
Sunset Terrace Lift Station Upgrade
N/A
$108,000.00
$108,000.00

Department
Account
Request Title
ApproFY2025
FY2026
FY2027
FY2028
FY2029
Total
WIFA
530-530-500-90914
South WWTP- Digester Improvements Design/ Permitting & Construction N/A
$200,000.00
$1,250,000.00
$1,450,000.00
WIFA
530-530-500-90914
South WWTP - Intensification Expansion Construction & Engineering 
Yes
$160,000.00
$3,000,000.00
$4,425,000.00
WIFA
530-530-500-90914
South WWTP- RAS Pit Structural and Mechanical Improvement
N/A
$350,000.00
$350,000.00
Total Wastewater 1 Utility Expense
$1,468,000.00
$5,971,000.00
$2,050,000.00
$1,600,000.00
$0.00
$11,089,000.00
Wastewater 2 (WR) Utility Exp
531-531-500-90912
Truck Crane (WW2)
Yes
$11,000.00
$11,000.00
Total Wastewater 2 (WR) Utility Exp
$0.00
$11,000.00
$0.00
$0.00
$0.00
$11,000.00
Water 1 Utility Expense
500-500-500-90914
Vulture Mine Booster Station
Yes
$200,000.00
$200,000.00
500-500-500-90912
Utility Storage
N/A
$200,000.00
$200,000.00
WIFA
500-500-500-90914
Monitoring Wells
Yes
$500,000.00
$500,000.00
$500,000.00
$1,500,000.00
500-500-500-90905
Shade Structures and Fencing Improvements
Yes
$75,000.00
$75,000.00
$75,000.00
$225,000.00
500-500-500-90905
Listening Hills Booster Station MCC and SCADA Upgrade
N/A
$80,000.00
$80,000.00
500-500-500-90912
Skid Steer Hydraulic Hammer Attachment
N/A
$9,000.00
$9,000.00
WIFA (CDBG- $340,000.00)
500-500-500-90914
Adams/Santa Cruz Waterline Replacement
Yes
$164,968.00
$1,570,000.00
$1,734,968.00
500-500-500-90914
El Pajarito Waterline Project 
N/A
$200,000.00
$1,400,000.00
$1,600,000.00
500-500-500-90914
LaGolondrina/La Paloma Waterline Project Design
N/A
$200,000.00
$200,000.00
WIFA 
500-500-500-90914
Mariposa Well Replacement
Yes
$200,000.00
$1,370,000.00
$1,570,000.00
Total Water 1 Utility Expense
$528,968.00
$2,545,000.00
$2,145,000.00
$1,900,000.00
$200,000.00
$7,318,968.00
Water 2 (WR) Utility Expense
$0.00
Total Water 2 (WR) Utility Expense
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Total Departments
$6,386,968.00
$19,082,176.00
$18,300,600.00 $15,575,000.00 $6,720,000.00
$68,330,744.00