Memo to Mayor and Council

Town of Wickenburg — Study Session (2025-10-20)

View PDF Meeting page

Extracted text (via pymupdf) 2729 characters
TOWN OF WICKENBURG 
          155 N. Tegner, Ste. A -  Wickenburg, Arizona 85390  
(928) 684-5451            FAX (602) 506-1580 
 
 
 
MEMORANDUM 
 
TO: 
 
Mayor and Council  
 
 
THRU:   
Andy Granger, Interim Town Manager 
 
FROM:  
Todd Wallace, Project Manager  
 
DATE:  
August 22, 2024 
 
 
SUBJECT: 
Wickenburg Community Center Estimates 
 
 
Town staff requested estimates from two contractors to either remodel or build the 
Community Center. Remodeling the Community Center would involve bringing the 54 
year old facility up to current building and safety codes. This would include adding ADA 
restrooms, a fire alarm and fire sprinkler system, upgraded HVAC, electrical and 
plumbing equipment, as well as minor cosmetic repairs. The same two contractors also 
provided estimates for building an entirely new and redesigned Community Center. For 
estimating purposes, the new construction was based on the 11,000 sqft conceptual 
Community Center plan found on the Town of Wickenburg website at: 
https://www.wickenburgaz.gov/1475/Wickenburg-Community-Center 
 
The rough estimates to remodel the existing facility range from $5.6 million to $7.5 
million and the estimates to build an entirely new Community Center range from $8.1 
million to $10.5 million.

Based on the above estimates, the cost to build an entirely new Community Center 
would require an additional $2.5 million to $3 million versus the cost to remodel the 
existing building. However, this additional investment would provide a custom-built 
facility, tailored to meet the current and future needs of our growing community. 
 
Recently, Town staff engaged an engineering firm to review the structural integrity of the 
trusses and roof system of the Community Center. The engineer identified a number of 
deficiencies as well as the fact that the truss system does not meet current building 
code requirements (see below). 
 
 
 
Town staff requested a rough estimate from Caliente Construction to remedy the 
deficiencies identified by Kimley Horn. Using the engineer’s long-term recommendations 
(see below), their high-level estimate came in at $512,462.

It is important to note that Caliente’s estimate only includes the section of roof above the 
main hall and stage area. Also, the costs associated with remedying the deficiencies 
identified by the engineer are in addition to the base remodel estimate that Caliente 
provided. The estimate does not include any items that would be included in a potential 
future remodel, such as a fire sprinkler system, new lighting and sound system. 
 
If you have any questions, comments or concerns, please do not hesitate to contact me 
at 928-232-2634 or twallace@wickenburgaz.gov. 
 
Thank you.