TOWN OF WICKENBURG
Adams/Jefferson Alleyway –
Overhead/Underground Electrical Upgrade
Cason Chambers, Public Works Director
March 2, 2026

Background
• This is the 8th electric utility improvement project to be completed in a
span of 5 years.
• These projects align with guiding principle #3 under Infrastructure Assets
in the Town’s Strategic Plan.
• Pricing was based on the previous Jackson/Madison Alleyway Project from
FY25
• The project was originally scheduled to be completed in FY26, but will now
be phased between FY26 and FY27
2

Projects to Date
FY 21/22 - Oxbow OH/UG 
FY 22/23 - N Jackson/ Madison OH/UG
and the Grid Feeder Upgrade for
Cobblestone Hotel and Jones Ford
FY 23/24 - La Paloma/La Golondrina
OH/UG and  Vai Corte/ Avispa OH/UG
FY 24/25 - Jackson/ Mohave OH/UG  and
Jackson/Madison Alley OH/UG
FY 25/26 - Adams/Jefferson Alley
OH/UG Conduit Installation
FY 26/27 – Adams/Jefferson Alley OH/UG
Utility Migration
This would be the 8th project in 5 years
3

Phased Project Plan
• This project will be done in two phases
•
Phase I – FY26, install underground conduit in preparation for utility
migration
•
Phase II – FY27, migrate overhead utilities underground
• Why two phases?
•
Total project came in $500,000 over projected cost at $1.2 million
•
Original $800,000 that was budgeted was expended on FY25 APS invoice

4
Why Overhead Utilities Are an Issue
• Safety Risks
• Reliability Problems
• Space Constraints
• Maintenance Challenges
• Aesthetic Concerns

What We Hope to Accomplish
• Public Safety
• Improved Reliability
• Accessibility
• Long-Term Cost Savings
• Aesthetics and Development
5

•
$800,000 originally budgeted
•
FY26 funds used to pay FY25 APS Invoice
•
$732,237 Total
•
$700,000 is needed for FY26
 
•
The Electrical Utility Fund (510)
•
$2,126,846 in contingency
•
$1,020,000 in capital reserves
This request is to use contingency funds in the
amount of $700,000
6
Project Funding – Phase I

Why Total Project Cost Increased
• Age and accessibility of infrastructure
• Multipack residential service
      SES – Service Entrance Section
• Electric meter locations
• Additional site walks with stakeholders
• Dirt work (boulders present) and added
streetlights
7

Summary
• $700,000 is being requested from the Electrical Fund contingency to
replenish Council’s FY26 authorization for phase I of the project
• Additional funds are needed to replenish the Council authorized funding
for this project, due to an accounting issue with a FY25 invoice
• The original project scope has become more complex due to multiple
factors
• The project has been split into two separate years due to increased cost

Questions & Council Discussion