A. CALL TO ORDER – Mayor Bratcher called the meeting to order at 3:01 PM
B. ROLL CALL
Present:
Mayor BG Bratcher
Vice Mayor Brian Jones
Councilmember Kristy Bedoian
Councilmember Shawn Clark
Councilmember Margaret Nyberg
Councilmember Rebecca Rovey
Councilmember Art Rubash
Staff Present:
Troy Smith, Town Manager
Trish Stuhan, Town Attorney
Steve Boyle, Community Development Director
Amy Brown, Town Clerk
Cason Chambers, Public Works Director
Les Brown, Police Chief
Robert Martinez, Finance Director
Tarah Mayerhofer, Human Resources Director
Ed Temerowski, Fire Chief
C. ITEMS OF BUSINESS
1. Discussion and Direction to Staff Regarding FY27 Budget Preparation, Session
#3
Troy Smith, Town Manager, stated that this is the third budget study session that
will include the Town Manager’s budget. The tentative budget is scheduled for
May 4th, so if the Council doesn’t finish the discussion by 5:00, we plan to take a
break and conduct the regular meeting. We will then reconvene this meeting to
finish the discussion tonight. If not, there will need to be a special meeting
scheduled to finish the budget discussions. This is a financial plan, so there will
be changes from tonight’s budget to the tentative budget. This is the largest
policy the Council has to decide each year.
Town Council Minutes of April 20, 2026
Page 2 of 11
Mayor Bratcher wanted to discuss the Council liaison assignments to emphasize
that it is important to go to the meetings and report back to the Council. Below
are the current assignments and these will come back in December, when the
new Council is seated. All members were fine with keeping the current
assignments.
Tarah Mayerhofer, HR Director, stated that she received a request for the
Council to look at the idea of PHI Air Medical (PHI Cares) membership for town
residents or town employees. This same request was heard by the Council on
December 20, 2021, and June 19, 2023, without it being approved either time.
Option 1 is to cover all households in the town limits. This will cover PHI air
transports from Maricopa and Yavapai Counties but will not have national
coverage. Membership isn’t insurance and residents on AHCCS/Medicaid are
excluded. The cost is $7 per household annually at an estimated cost of $24,290-
27,118. The town will have to provide PHI membership cards to residents and
provide an annual resident roster.
Option 2 is to cover full-time town employees at a cost of $60 per employee to
cover their household. This is a national plan and is estimated to cost
approximately $7,380 for 123 employees. There is a business benefit plan which
would just be adding another benefit for employees while they are employed or
there is a business gift plan which means the membership will remain with the
employee even if they leave employment with the town.
The Council needs to consider if this is a core municipal service and appropriate
to use General Fund resources to pay for this as it will be an ongoing annual
funding commitment or would the Council like to add this benefit to employees.
Consensus of Council was that this is not the town’s responsibility as it is not a
core municipal service.
Maya Kwiedacz, Management Intern, presented information on the three grants
the town has talked about offering. The town currently has the Commercial
Façade Grant and Tourism Marketing Grant. The addition is the Community
Town Council Minutes of April 20, 2026
Page 3 of 11
Support Grant that has $50,000 designated for it which will give a process for the
non-profit support grants as the Council requested that come at budget time
instead of throughout the year from contingency. The Council heard a
presentation from the Arizona Community Foundation about them managing the
Community Support Grant or does the Council want to keep this with the town
managing the grant. Does the Council want to only offer the grants one time per
year? If they are all town managed grants, does the Council want to designate
the Economic Development and Transportation Advisory Committee (EDTAC) as
having the awarding authority or the Council want to take that back as a Council
decision?
Mayor Bratcher stated that having the Arizona Community Foundation manage
the grant allows residents to put in money to help fund the grants.
Consensus of Council was to have the town manage the Community Support
Grant, have one cycle per year per grant, and have EDTAC manage the
awarding of the grants.
Cason Chambers, Public Works Director, presented the five-year Capital
Improvement Projects (CIP) list with a discussion on the FY27 items only.
• Airport Taxiway A Rehabilitation - Grant funded and underway with some of
the project rolling over into next fiscal year
• Adams/Jefferson Undergrounding of the Electric - Some of the project rolled
over to next year with Phase 2 that came to the Council on March 2, 2026
• Fire VHF System Upgrades - Spread over several years to get radios and
some of the issues are the availability of the equipment. Town Manager Smith
stated that the town has a very good deal by working with other municipalities
to share the costs as radio towers are very expensive.
• Fire Ladder Truck Replacement – Cost is $1.57 million with expected
delivery of November or December
Town Council Minutes of April 20, 2026
Page 4 of 11
• IT Police Mobile Data Terminal Replacements – New fire workstations out of
the fire department budget
• IT New Workstations – Replace aging stations
• IT Building Low Voltage Cabling – Replacing internal cables
• Library Children’s Room Expansion – Easier access from the Library
Reciprocal Fund
• Maintenance Shop Door Rehabilitation and Motor Replacement
• Sunset Pickleball Restrooms – This will be a 140 square foot building with
one unisex bathroom and a utility room. The location will be across the
parking lot due to easier access to utilities. A drinking fountain will be on the
exterior of the building for filling water bottles. The cost is closer to $130,000
but the question is whether the Council wants one or two restrooms. Two
restrooms will result in a redesign being needed along with additional costs
and more time. The current design is estimated to be completed by August
2026. Consensus was to keep it at one restroom.
• LED Lighting Improvement Grant – Upfit town facilities
• Replace Aging HVAC Units
• Seal/Stripe Sunset Park Parking Lots
• ADA/Safety Upgrades at Town Parks
• Pool Heaters and Covers – This is not being recommended to continue with
this project as the cost is now at $202,000, so much higher than originally
projected. Consensus of Council was to not do this project.
• Sunset and Sunrise Park Design/Engineering – It is being recommended to
move forward with getting 60% plans at a cost of $500,000 so that the town
will know the costs and be able to apply for grants.
• Coffinger Baseball/Football Field Renovations – Rolling forward some of the
project budget into next year as it will not be finished by July 1
• Community Center Construction – The renovations are estimated to be
between $5-7 million with 100% plans not yet received in order to get an
accurate estimate. This building was built in 1970 with 10,000 square feet of
usable space. Significant repairs are needed in equipment upgrades, HVAC,
electrical, plumbing, roof structure & trusses, ADA access, ADA restrooms
and fire sprinkler system. In addition to the structure issues, there will also be
some remodel work to maximize the usable spaces including a commercial
kitchen, removable stage, exterior cosmetic repairs, and enclose the patio
and lobbies. The remodel will add 3,806 square feet of new usable space.
There is $5 million in next year’s budget for this project with $1 million this
year’s budget.
• Shade Sail Repair on Playgrounds
• Replace Turf at Sunset Park
• Garbage Can Replacement Downtown
• CAP Building Demolition and Parking Lot – This building was built in 1979
and is the old Community Action Program (CAP) office building. There was an
assessment of the building with it receiving a 30 out of 100 score. Less than a
score of 35 means that it is urgent as the building needs to either be
Town Council Minutes of April 20, 2026
Page 5 of 11
stabilized or replaced. The plan is to demolish the building and make it into a
parking lot for the town building next door that was the temporary fire station
(TFS). The TFS will be turned into the Emergency Operations Center and be
used as a large conference room/training center with the remodel of that
building in FY28. Town Manager Smith added that this building is not a good
look for the town and this demolition is critical since the town hasn’t been
keeping up on the maintenance of the building.
• Smoke Eater Renovation – This has been moved back a year but is another
example of the town not keeping up on the maintenance of buildings. This
was constructed in 1906 and is on the National Register of Historic Places. It
was deeded to the town in 1984 by the volunteer fire department as a youth
center and is currently used for police virtual training. The interior and exterior
are in poor condition. The idea is to create ADA restrooms in the rear of the
building and create a meeting space for youth or public safety in the front of
the building.
• Paint the Exterior of the Train Depot – It was suggested to let the Chamber of
Commerce do this for less money and pay them.
• Lewis Addition Streets – Chip seal
• Coconino Parking Lot Upgrade – This project can start once the construction
vehicles for the museum are moved as this is their staging area. Dan Finley,
Sigler Western Museum, stated that they expect to have the building
complete by August 2027 and then hopefully open December 2027. The
pavilion will seat 300 people for dinner. Community Development Director
Steve Boyle stated that the town doesn’t have a parking requirement for
downtown so businesses can use the streets and town parking areas.
Consensus was to keep it as a public parking lot in next year’s budget.
MOVED BY Councilmember Margaret Nyberg to recess at 5:04 PM until after the
regular Council meeting
SECONDED BY Councilmember Rebecca Rovey
VOTE: 7 – 0 (Yes – Mayor Bratcher, Vice Mayor Jones, Councilmembers
Bedoian, Clark, Nyberg, Rovey, and Rubash)
Council restarted the meeting at 6:00 PM.
Public Works Director Cason Chambers continued presenting on the CIP list.
• Tegner Street Phase 3 – South Tegner and expand the road
• Community Center Parking Lot Rehabilitation – Pave the dirt lot next to the
Community Center Parking lot and work on the Community Center Parking
Lot
• Wastewater (WW) 1 Headworks Upgrade, UV and EPS, Grit Removal
Improvements and Intensification – Rolled over from the current fiscal year as
project waiting for permits to start project – These are paid by WIFA and
ARPA funds.
Town Council Minutes of April 20, 2026
Page 6 of 11
• Lead Service Line Inventory Program – This is waiting for federal
requirements regarding inspecting lines to see if there is lead for homes built
before 1990 that is from the shut off valve of the home.
• Utility Room at the Airport is split between WW1 and WW2 – Adding a
restroom to the metal structure
• Water 1 Land Acquisition – Future well site on state land north of the airport
runway
• Monitoring Wells – To test water
• Shade Structures and Fencing Improvements – To protect pumps and other
equipment to extend their life and make them secure
• Adams/Santa Cruz Waterline Replacement – Rolled over but the project is
underway and has CDBG funding
• El Pajarito Waterline Project
• Mariposa Well Replacement – Engineered this year with rehabilitation next
year
• Fuel Tank Cleaning at the Fuel Facility – There is water in the bottom, so this
needs to be completed.
• Public Works Copier – Matching Town Hall’s copier and purchased outright
• Police Vehicle Bay Power Run – There is no power to their vehicle bay for
charging.
Town Manager Smith stated that there are $24 million in projects on the list for
next fiscal year, but those will probably not all be completed in one fiscal year.
There were $19 million in last fiscal year with many of those rolling over. He does
not expect that we will get all the projects that are budgeted done this fiscal year.
Finance Director Martinez stated that the Council already had a discussion
regarding the funding agreements. Currently the town looks at the actual bed tax
revenues collected from the previous fiscal year and subtract the operating
expenses and planned expenditures designated by Town Council. Then the town
sets aside 15% for contingency. The remainder is then divided into three equal
parts, and 33.3% will be paid to the Chamber of Commerce, Del E Webb Center
and Sigler Western Museum. The summary of the actual amounts is below:
• FY25 Revenue - $260,803
• Operating Expenses - $130,500
✓ Other Contract Services - $90,000
➢ Chamber of Commerce Sponsorship Agreement $60,000
➢ Wasatch Mountain Media $30,000
✓ Marketing II - $10,000
✓ Matching Improvements - $25,000
✓ Devore Statues - $5,500
• 15% Contingency - $19,546
• Marketing - $110,757
✓ 3 Funding Agreements
• Each of the three organizations will receive $36,919
Town Council Minutes of April 20, 2026
Page 7 of 11
Since the pool heater and cover project will not happen, that will put money back
into the bed tax contingency.
Consensus of Council was to keep the Bed Tax Contingency at 15% and split at
33% for the 3 entities.
Director Martinez then reviewed the state shared revenue and local tax. Last
year the town lowered the expected revenue by $1 million. This year staff is
recommending that it be dropped by another $500,000, bringing it to $8 million.
This is due to the downward trends that have been seen this year as well as less
state shares being received due to the addition of San Tan Valley. Council gave
staff direction to keep the property tax levy relatively flat at $628,450 which
reduced the rate to .3856. Below is the breakdown for General Fund revenues:
Our largest IGA (Fire) is created based on budget amounts and actual
expenditures. For right now we show facility rentals down 12.7%, as we know
this will be down due to the community center being closed due to construction.
The Other Revenues category includes interest income which will be lower based
on this budget as we have a lesser amount of cash invested into LGIP, which
means we will earn less interest. The transfer out includes the fire station loan
and $2.4 million to streets.
Town Manager Smith stated that he told management not to submit any
personnel requests this year and to continue with a five-year CIP plan. The
budget process this year was a hybrid base budget approach where finance built
the budgets for the departments based on historic spending and encouraged the
reduction in operating expenses. This budget includes a 9.5% increase in health
insurance benefits and a 5% increase in wages for all employees. Last year
employees received a 4% increase as that was all that the town could afford. The
5% increase is on the low end of the expected 5-8% increase of other
Town Council Minutes of April 20, 2026
Page 8 of 11
municipalities. This is paid for primarily because the town saved about $891,000
by not having an unfunded amount for the Public Safety Personnel Retirement
System and it was budgeted. Staff has looked at other options to try to stay
competitive and within budget.
Tarah Mayerhofer, HR Director, stated that the Council’s compensation
philosophy target was at 50th percentile (market median). The town is currently
10% below the market for salary and 13% below the market for total
compensation, so we are not meeting our compensation philosophy. She
participated in an El Mirage class and compensation study, which means that
she gets the results to know where we stand and their compensation philosophy
is to be at 65th percentile. Other target cities are at 55th-75th percentile and are
implementing a 5-8% total compensation increase. The town’s Employee
Advisory Committee recommends having a 2% employee match to the 457b
retirement accounts. The town currently offers a 457b plan though Nationwide
with 36% of employees enrolled or 44 employees. The estimate is that 75% of
the employees will do a match of 2% so the cost is about $150,000. This can be
looked at annually to see if the Council wants to continue to provide this match.
There are tax incentives to putting the money in a retirement plan instead of in a
paycheck. This benefit would be for full-time employees only, including public
safety. This benefit increase is not included in the budget yet.
Consensus of Council was to keep the employee increase at 5% and add the
benefit of a 2% employee match in a 457 plan.
Finance Director Martinez then reviewed the department budgets. All
departments include the 5% wage increase and the 9.5% health insurance
increase. Departments with an asterisk have a CIP project that will also increase
their budget. Departments did very good at increasing their budgets this year. As
a summary, below are some reasons some of the budgets might be increase
•
General Services includes increases for Genysis, $120,000 for FSL, and
$50,000 for ACF or Town Grant Funding
•
Human Resources includes increases for employee development and
employee benefit portal
•
Town Clerk includes increases for short term rental and elections
•
Town Attorney includes increases for flat fee due to FY25 Actual if it had been
billed by the hour, 5% indirect
•
Economic Development includes increases for Placer AI and Canva
•
IT - $20,000 workstations and $200,000 low voltage cabling
•
Public Services - $8,000 New Copy Machine
•
Police - $35,000 Vehicle Bay Power
•
Fire - $100,000 VHF System Upgrades, $1,573,000 Ladder 751
Replacement, $8,600 Mobile Data Terminals
Town Council Minutes of April 20, 2026
Page 9 of 11
Contingencies and reserves are for emergencies, mid-year requests, and
unanticipated expenditures. The General Fund Reserve will be maintained in an
amount not less than 15% of new General Fund revenues for the budgeted fiscal
year. Contingency will be established for all other applicable funds of at least
10% and the equity of all funds will be maintained to meet the objectives of the
fund. $100,000 will be budgeted under General Services each year to indemnify
the town of unanticipated insurance claims. Expenditures may be made from
contingencies only upon approval by the Town Council. Below show the
balances for the contingencies and reserves:
• Restricted Projected End of Year Fund Balance – $21,778,705
✓ Contingency $1,201,535 at 10%
✓ Capital Reserve $1,000,000
✓ Reserve $5,283,553 at 30%
• Unrestricted Fund Balance - $14,293,617
The enterprise fund budget is below with the ones with asterisk’s have CIP
projects.
Town Council Minutes of April 20, 2026
Page 10 of 11
The Enterprise Funds contingency and reserves are below:
The expenditure limitation for FY26 was $63,473,203 and FY27 will be at
$66,901,115. There are certain items that are excluded from calculating the
expenditure limitation including:
• Debt Service
• Dividends, interest, or gains
• Grants, aid, or contributions
• Funds received from State of Arizona
• Contracts with other political subdivisions
• Refunds, reimbursements, and other recoveries
Town Council Minutes of April 20, 2026
Page 11 of 11
Below shows the last two completed years with their expenditure limitation
compared to home much we actually use by showing the amount that we were
under the limitation.
The timeline for the budget is:
• Tentative Budget Resolution and Adoption – May 4
• Policy Review – May 18
• Final Budget and Tax Levy – June 1
• Final Budget Adoption (Special Meeting) – June 1
• Property Tax Rate Adoption – July 6
D. EXECUTIVE SESSION - (Council May Vote to Go Into Executive Session Pursuant
to A.R.S §38-431.03(A)(3) to Receive Legal Advice from the Town Attorney on Any
of the Above Agenda Items.)
E. ADJOURNMENT
MOVED BY Councilmember Margaret Nyberg to adjourn at approximately 7:17 PM
SECONDED BY Councilmember Rebecca Rovey
VOTE: 7 – 0 (Yes – Mayor Bratcher, Vice Mayor Jones, Councilmembers Bedoian,
Clark, Nyberg, Rovey, and Rubash)
ATTEST:
BG Bratcher, Mayor
Amy Brown, Town Clerk
CERTIFICATION
I, Amy Brown, the duly appointed and qualified Town Clerk of the Town of Wickenburg,
do hereby certify that the foregoing minutes are a true and correct copy of the minutes
of the study session of the Town Council of Wickenburg, Arizona held on April 20, 2026.
I further certify the meeting was duly called and held and that a quorum was present.
Amy Brown, MMC