TOWN OF WICKENBURG 
TRANSPORTATION AREA MASTER 
PLAN
Town Council Briefing
June 15, 2026
1

© 2026, All Rights Reserved
© 2026, All Rights Reserved
2
METROPOLITAN 
PLANNING 
ORGANIZATION
United States Department of 
Transportation designation.
Responsible for carrying out 
the transportation planning 
and programming in the 
metropolitan area. 
Set priorities for projects and 
their implementation.

© 2026, All Rights Reserved
3

© 2026, All Rights Reserved
© 2026, All Rights Reserved
4
STUDY OVERVIEW
4
Type:
Transportation Area Master Plan
Overview:
Roadway classification, 
multimodal transportation network 
analysis, safety and resiliency 
improvements, and ultimate ROW 
requirements
Planned Duration:
13 months
Stakeholders:
Wickenburg, ADOT, Maricopa 
County, and Yavapai County
Estimated Completion:
February 2027

© 2026, All Rights Reserved
© 2026, All Rights Reserved
5
A.
US 93 Incident/Secondary Emergency 
Response Route Analysis
B.
Jack Burden Road Resiliency
C.
Grade Separated Railroad Crossing Feasibility
D.
North Tegner Street Road Diet/ Repurposing
E.
Evaluate Possible Jake Brake Free Zone
F.
Freight Traffic 
G.
Multi-Use Path Extension
H.
Bureau of Land Management (BLM)/ASLD 
Trailhead Concept Design
I.
Kerkes Street ATV Access/Travel
STUDY FOCUS 
AREAS
A
A
B
C
D
E
F
G
H
I

© 2026, All Rights Reserved
2026 PM LOS
2050 PM LOS
TRAFFIC LEVEL OF SERVICE (LOS)
6
Bidirectional PM LOS

© 2026, All Rights Reserved
© 2026, All Rights Reserved
7
SAFETY FOCUS
5-year Crash Analysis Period
➢1,228 total collisions
➢
14 fatalities
➢
48 suspected serious injuries
➢
7 involving a non-motorist
➢74% of crashes occur on US 60, 
US 93, and SR 89

© 2026, All Rights Reserved
8
Task 1
• Project 
Management
Task 3
•Data Collection & 
Forecasting
Task 4 
•Vision & Goals
Task 5
•Alternatives 
Development
Task 6
•Implementation & 
Funding
Task 7
•Final TAMP
We’re here
Task 2: Public & Stakeholder Engagement
Technical Advisory Group (TAG) 
Meeting 1
Public 
Meeting 1
TAG 
Meeting 2
TAG 
Meeting 3
TAG 
Meeting 4
Public 
Meeting 2
TAG 
Meeting 5
TAG 
Meeting 6
January
2026
February 
2027
STUDY PROCESS & DELIVERABLES
Town Council 
Briefing
Town Council 
Briefing
8
8

© 2026, All Rights Reserved
►TAG 1:1 Interviews
►Field Review
►Community Survey
►Tech Memo #1 – Existing & Forecasted 
Conditions
►Public Open House Meeting #1
9
NEXT STEPS
9

© 2026, All Rights Reserved
© 2026, All Rights Reserved
10
Tim Strow, MAG Major Projects Manager 
TStrow@azmag.gov
 
Brian Snider, Consultant Project Manager 
Brian.Snider@mbakerintl.com
 
THANK YOU!

© 2026, All Rights Reserved
11
STUDY OVERVIEW
Type:
Transportation Area Master Plan
Overview:
Roadway classification, 
multimodal transportation network 
analysis, safety and resiliency 
improvements, and ultimate ROW 
requirements
Planned Duration:
13 months
Stakeholders:
Wickenburg, ADOT, Maricopa 
County, and Yavapai County
Estimated Completion:
February 2027
11