Resolution No. 2021-124 
RFLS #7885 
Rev 08/21 
RESOLUTION # 2021-124 
 
A RESOLUTION OF THE MAYOR AND COUNCIL OF THE CITY 
OF SURPRISE, ARIZONA, TO CONDITIONALLY ACCEPT THE 
STREET 
AND 
PUBLIC 
UTILITY 
IMPROVEMENTS 
AND 
COMMENCE MAINTENANCE AFTER TWO YEAR WARRANTY 
AT ZANJERO TRAILS PHASE 2 PARCEL 11A, GENERALLY 
LOCATED AT N. 189TH AVENUE AND W. LAUREL LANE. 
 
WHEREAS, the Mayor and City Council of the City of Surprise approved a final 
plat entitled “Zanjero Trails Phase 2 - Parcel 11A” on, February 12th, 2019; 
 
WHEREAS, Lennar Arizona Incorporated, an Arizona Corporation, the developer 
of Zanjero Trails Phase 2 Parcel 11A, dedicated to the City the street and public utility 
improvements, generally located at N. 189th Avenue and W. Laurel Lane; 
 
WHEREAS, on or about September 29, 2020, the City of Surprise Public Works 
Department Engineering Division completed an inspection of the public improvements 
described in this resolution and found the improvements to be in substantial compliance 
with the approved plans and specifications; 
 
WHEREAS, the City of Surprise notes that the two-year warranty period will 
commence upon conditional acceptance by the City; and 
 
WHEREAS, after the conclusion of the two-year warranty period, the City of 
Surprise will release the warranty and begin maintenance of the street and public utility 
improvements. 
 
NOW, THEREFORE, BE IT RESOLVED by the Mayor and Council of the City of 
Surprise, Arizona, as follows. 
 
Section 1.  The City of Surprise conditionally accepts the street and public utility 
improvements generally located as depicted on the map attached as Exhibit A and listed 
on Exhibit B. 
 
Section 2.  Upon final acceptance by the City Engineer, the City Council hereby 
directs the City to release warranty and begin maintenance of the street and public utility 
improvements. 
 
 
SIGNATURES ON THE FOLLOWING PAGE

Resolution No. 2021-124 
RFLS #7885 
Rev 08/21 
 
APPROVED AND ADOPTED this  
_day of ____  
, 2021. 
 
 
 
 
 
 
 
Skip Hall, Mayor 
 
Attest:  
 
Approved as to form: 
 
 
Sherry Aguilar, City Clerk 
 
Robert Wingo, City Attorney

Resolution No. 2021-124 
RFLS #7885 
Rev 08/21 
 
 
Exhibit A 
 
 
Map of Infrastructure

Zanjero Trails Phase 2 Parcel 11A Phase 1 
 
 
   INFRASTRUCTURE TO BE ACCEPTED 
                         SEWER 
                         STORM DRAIN 
                         ROADWAY 
Laurel Lane
Poinsettia Drive
190th Drive
188th Drive
189th Court
189th Lane
Jenan Drive

Zanjero Trails Phase 2 Parcel 11A Phase 2 
 
 
   INFRASTRUCTURE TO BE ACCEPTED 
                         SEWER 
                         STORM DRAIN 
                         ROADWAY 
Desert Hills Drive
189th Ave
190th Ave
Shaw Butte Drive
188th Drive

Resolution No. 2021-124 
RFLS #7885 
Rev 08/21 
 
EXHIBIT B 
 
List and Cost of Improvements

EXHIBIT B 
Memorandum 
 
 
To: 
City of Surprise City Council 
From: Public Works – Engineering Services 
Date:  8/11/2021 
Re:  
Zanjero Trails Phase 2 Parcel 11A  
 
 
The public improvements for the above project have been completed and are tentatively scheduled 
for the September 7, 2021 council agenda for acceptance. The amounts for the infrastructure have 
been provided by a third party and not the City of Surprise. The following are the infrastructure 
improvements included with this acceptance and the corresponding valuation that the City will be 
accepting: 
City Paving - $533,517.01 
City Concrete - $722,863.58 
City Storm Drain - $275,881.93 
City Sewer - $408,535.40 
 
Total: $1,940,797.92