Total Capital Cost:
$100,000.00
Department:
Water
Type:
Capital Improvement
Request Groups:
CIP
Timeline:
07/01/2025
to
06/30/2026
Request description:
Capital Costs
FY2026
Total
Planning
$0.00
Design
$0.00
Engineering
$0.00
Land/Right-of-way
$0.00
Construction/Maintenance
$100,000.00
$100,000.00
Equipment/Vehicle/Furnishings
$0.00
Other
$0.00
Total
$100,000.00
$100,000.00
Funding Source
FY2026
Total
149 - Special Projects
$0.00
511 - Water
$100,000.00
$100,000.00
513 - Ranchettes
$0.00
541 - Sewer
$0.00
148 - CDBG
$0.00
111 - General
$0.00
Total
$100,000.00
$100,000.00
Type of Project
Strategic Priority
Bond Eligible
Grant Funding
Project Status
No
No
Unmodified
Alto Well Site Discharge Pipe Replacement
This request is to replace the discharge piping at the Alto well site.  The discharge piping has never been replaced, and the site is over 40 years old.  The discharge piping 
takes drinking water directly from the booster pump and into the public distribution system.  The approximate useful life of this asset ranges from 30 to 50 years.  The water 
division is recommending replacement because of the condition of the current pipe and leaking due to internal corrosion.  The benefits of replacing this pipe are a higher 
quality product being discharged to the distribution system along with an improvement in water loss.
Additional Information
Improvement
Superior Infrastructure
91