FCI Constructors proposal

City of El Mirage — Regular Meeting (2026-01-06)

View PDF Meeting page

Extracted text (via pymupdf) 15724 characters
Estimate Clarifications, Qualifications & Assumptions 
Project Name: El Mirage YMCA Flooring Replacement & Resurfacing 
Project Location: 12450 W Cinnabar Ave, El Mirage, AZ 85335 
 
 
Date: 10/3/2025 
Page 1 of 4 
 
Scope of the Project 
▪ 
Project Type, size, components 
o 
14540 SqFt Renovation 
▪ 
The Construction Manager’s general conditions and general requirements are included, based on a period 
of seven (7) weeks, and is based on a December 3, 2025 start date. 
▪ 
Project to be conducted during normal working hours. 
 
Basis of the Construction Estimate 
▪ 
The Estimate has been prepared based on the following documents: 
o 
Site walk held on 9/24/25 and sketch of rooms with images (Exhibit A) 
o 
Addendum #1 dated 9/22/2025 as prepared by Valerie Ojeda. 
o 
Addendum #2 dated 9/22/2025 as prepared by Valerie Ojeda. 
o 
Addendum #3 dated 9/25/2025 as prepared by Valerie Ojeda. 
o 
FCI’s Proposal dated 10/3/2025. 
▪ 
The sizes, quantities and descriptions indicated within the Estimate are part of these clarifications, 
qualifications and assumptions. 
▪ 
These clarifications, qualifications and assumptions are intended to supplement the Estimate and are an 
attempt to inform the Owner and the Architect of the Construction Manager’s interpretation of the scope 
items which are included or excluded, and which may not be clearly shown or defined by specification, 
plan, elevation, detail, section, schedule or schematic. 
▪ 
Allowances – The following Allowances have been included within the estimate. Costs associated with 
these allowances will be tracked on a time and material basis and if the actual cost comes under budget, 
those savings will be returned to owner. If actual costs exceed the stated allowance, a request for change 
order will be submitted. 
# 
Title 
Description 
Value ($) 
#1 
Clean Exposed Ductwork 
Cleaning of the Exposed ceiling ductwork in all 3 
rooms 
$5415 
 
General Notes 
▪ 
The Estimate includes the following Contingency amounts. 
o 
0% Design Contingency shall be used to resolve unforeseen issues that are not currently 
addressed in the design, and other items such as project requirements, building permit 
comments and changes, inaccurate project information, or other items not identified when this 
GMP was developed.   
o 
0% Contractor Contingency is to be used for any costs which are properly reimbursable as cost of 
the work, but not the basis for a change order.  These may include but not be limited to: costs 
attributable to errors and omissions by the Construction Manager; errors not due to the 
negligence of the Contractor; Contractor coordination issues; costs generated from the 
clarification of the contract documents; costs for code changes or upgrades required by 
governmental agencies which are not otherwise the basis for a change order; costs for overtime 
and acceleration required to meet contract schedules; and costs including legal fees for 
contractual disputes with parties other than the owner. 
▪ 
Impacted Materials - Certain construction material markets are experiencing or expected to experience 
significant, industry-wide fluctuation during the performance of the Work that may impact price, 
availability, and delivery time frames. If during the performance of the Work an Impacted Material item 
experiences an increase in price or a delay in delivery, beyond the control of and without the fault of the 
Contractor, its Subcontractors and suppliers, the Contractor may notify the Owner in writing within 
twenty-one (21) days from the date the basis for an equitable adjustment to the Contract Price, or a 
change to the Contract Schedule and shall provide appropriate documentation substantiating such 
adjustment.  Payment for an adjustment shall be made in accordance with the terms of the Agreement

Estimate Clarifications, Qualifications & Assumptions 
Project Name: El Mirage YMCA Flooring Replacement & Resurfacing 
Project Location: 12450 W Cinnabar Ave, El Mirage, AZ 85335 
 
 
Date: 10/3/2025 
Page 2 of 4 
 
concerning payment of agreed change orders. The Contractor shall not be liable to the Owner for any 
expenses, losses or damages arising from a delay in the delivery of an Impacted Material. Owner agrees it 
will not withhold or seek payment of liquidated damages pursuant to the terms of the agreement for 
material delays beyond the control of and without the fault of the Contractor. 
▪ 
Due to the timeframe between FCI’s assembly of the estimate, presentation to the owner, and 
acceptance and execution of the contract, this estimate is based on FCI’s ability to execute subcontracts 
identified within the estimate at the stated amounts. Should an unexpected event occur that precludes 
subcontract execution, FCI will immediately notify Owner and either submit a revised estimate prior to 
contract execution or if the contract has been previously executed, a change order with justification will 
be issued and executed to update the Subcontract amount(s) to the extent they are higher than those 
included.  Any issues arising from this must be identified by FCI and communicated to the Owner within 
60 days of Notice to Proceed. Owner and FCI will work diligently together to resolve these items in an 
expedited manner. 
▪ 
The Owner shall pay for all regulatory permits and plan review fees including Building and Environmental 
permits (if required). 
▪ 
Sales Tax is included as point of sale (MRRA). 
▪ 
Diversity business goals do not apply to this project.  
▪ 
Davis Bacon or other Prevailing wages do not apply to this project. 
▪ 
This Estimate represents specifically identified construction costs only. Therefore, all other “Owner’s 
Costs” are not included. The following items are considered “Owner’s Costs”: 
o 
Owner administrative costs or fees. 
o 
Legal fees or expenses. 
o 
F.F.&E. items (Furniture, Fixtures and Equipment). 
o 
Artwork, murals, or exhibits. 
o 
Owner’s Contingency.  
o 
Architectural/Engineering Design costs. 
o 
Material Testing or Special Inspections costs. 
o 
Third Party commissioning, air leakage or blower door testing, water infiltration testing costs. 
o 
Moving expenses 
o 
Others noted in Divisional sections below. 
▪ 
Electronic, CAD or BIM “As-Builts” are not included. FCI Constructors will maintain “As-Built” drawings at 
the jobsite throughout the construction phase and provide copies to the Architect and Owner at Final 
Completion. 
▪ 
The Estimate is based on the premise and understanding that FCI Constructors will have full control to 
reallocate any funds and/or budgets within the Estimate (excluding allowances, lump sum General 
Conditions and Contingency unless approved by the Owner) as determined necessary in the execution of 
the CM Contract. 
▪ 
General Conditions costs are based upon a continuous workflow throughout the project; unforeseen work 
stoppages that may necessitate a re-mobilization have not been included in the project schedule or 
pricing. 
▪ 
Weather protection costs (if any) included in the GMP are based on the construction start date noted 
above.  Should construction commencement be delayed due to reasons outside of FCI’s control, FCI 
reserves the right to request a revision to the construction schedule and costs accordingly. 
 
Division 01 – General Requirements 
▪ 
Payment and Performance Bonds are included at the fixed percentage of 0.83% and will be invoiced as a 
lump sum amount in the first pay application.  
▪ 
General Liability Insurance is included at the fixed percentage of 1.0% and will be invoiced as a lump sum 
amount in the first pay application.

Estimate Clarifications, Qualifications & Assumptions 
Project Name: El Mirage YMCA Flooring Replacement & Resurfacing 
Project Location: 12450 W Cinnabar Ave, El Mirage, AZ 85335 
 
 
Date: 10/3/2025 
Page 3 of 4 
 
▪ 
Builder’s Risk Insurance is included at the fixed percentage of 0.025% and will be invoiced as a lump sum 
in the first pay application. 
o 
Should a Builder’s Risk claim occur, any deductibles or uncovered costs will be treated as a 
change order to the Construction Manager’s Contract. 
▪ 
The costs associated with temporary water, sewer, and electrical utilities will be paid for by the Owner. 
▪ 
We have included a one (1) year workmanship warranty. 
▪ 
We have not included costs associated with sustainable building programs (such as LEED, Green Globes, 
etc.) as they do not apply to this project. 
▪ 
Any down payment requirements from suppliers or subcontractors are assumed to qualify as billable 
materials.  
▪ 
Building mock-ups are not included. 
 
Division 02 – Existing Conditions 
▪ 
Removal of existing flooring materials in the Group Fitness and Teen Center Rooms. 
▪ 
Removal of cove base in Gymnasium 
 
Division 03 – Concrete 
▪ 
No scope of work included. 
 
Division 04 - Masonry 
▪ 
No scope of work included. 
 
Division 05 – Steel 
▪ 
No scope of work included. 
 
Division 06 – Carpentry 
▪ 
No scope of work included. 
 
Division 07 – Thermal and Moisture Protection 
▪ 
No scope of work included. 
 
Division 08 – Doors and Windows 
▪ 
No scope of work included. 
 
Division 09 – Finishes 
▪ 
We have included 6” cove base in all three rooms.  
▪ 
We have included the new cushioned wood-style flooring per Shaw: Rexcourt Rubber Flooring in standard 
manufacturer color for the Fitness Room. 
▪ 
We have included the new LVP flooring per Patcraft: Forest Highland 6”x48” LVT Flooring in standard 
manufacturer color for the Teen Room and Teen Room Office. 
▪ 
We have included the resurfacing of the wood gym floor and repairing of dead spots, along with the new 
court markings consisting of (1) full court basketball, (1) full court volleyball, (2) cross court basketball, 
logos, and pickleball court. 
▪ 
We have not included cost premiums for product and or procedures necessary to address moisture 
mitigation of concrete sub-surfaces prior to flooring. 
▪ 
We have included the painting of the walls within the Fitness Room, Teen Room, and Gymnasium to 
match existing. 
▪ 
We have included the painting of the door frames in the Gymnasium to match existing. 
 
Division 10 – Specialties 
▪ 
No scope of work included.

Estimate Clarifications, Qualifications & Assumptions 
Project Name: El Mirage YMCA Flooring Replacement & Resurfacing 
Project Location: 12450 W Cinnabar Ave, El Mirage, AZ 85335 
 
 
Date: 10/3/2025 
Page 4 of 4 
 
 
Division 11 – Equipment 
▪ 
 No scope of work included. 
 
Division 12 – Furnishings 
▪ 
No scope of work included. 
 
Division 13 – Special Systems 
▪ 
No scope of work included. 
 
Division 14 – Conveyance 
▪ 
No scope of work included. 
 
Division 21 – Fire Suppression  
▪ 
No scope of work included. 
 
Division 22 - Plumbing  
▪ 
No scope of work included. 
 
Division 23 - HVAC  
▪ 
No scope of work included. 
 
Division 26 - Electrical  
▪ 
No scope of work included. 
 
Division 27 – Communications 
▪ 
No scope of work included. 
 
Division 28 – Electronic Safety and Security 
▪ 
No scope of work included. 
 
Division 31 – Earthwork 
▪ 
No scope of work included. 
 
Division 32 – Exterior Improvements  
▪ 
W No scope of work included. 
 
Division 33 – Utilities 
▪ 
No scope of work included. 
 
 
END OF CLARIFICATIONS, QUALIFICATIONS & ASSUMPTIONS

FCI Constructors, Inc.
El Mirage YMCA Flooring Replacement & Resurfacing
October 3, 2025
Estimate
Scope of Work
Cost
Notes
Div 01 - General Requirements
48,754
$       
7 Week Duration
Div 02 - Selective Demo
-
$             
Included with Flooring
Div 03 - Concrete
-
$             
N/A - Excluded
Div 04 - Masonry
-
$             
N/A - Excluded
Div 05 - Steel
-
$             
N/A - Excluded
Div 06 - Rough Carpentry
-
$             
N/A - Excluded
Div 07 - Thermal / Moisture Protection
-
$             
N/A - Excluded
Div 08 - Openings
-
$             
N/A - Excluded
Div 09 - Finishes
87,518
$       
Flooring and Painting
Div 10 - Specialties
-
$             
N/A - Excluded
Div 11 - Equipment
-
$             
N/A - Excluded
Div 12 - Furnishings
-
$             
N/A - Excluded
Div 13 - Special Construction
-
$             
N/A - Excluded
Div 14 - Vertical Transportation
-
$             
N/A - Excluded
Div 21 - Fire Suppression
-
$             
N/A - Excluded
Div 22 - Plumbing
-
$             
N/A - Excluded
Div 23 - HVAC
-
$             
N/A - Excluded
Div 26 - Electrical
-
$             
N/A - Excluded
Div 27 - Low Voltage Systems/Access Control
-
$             
N/A - Excluded
Div 28 - Life Safety / Security Systems
-
$             
N/A - Excluded
Div 31 - Earthwork
-
$             
N/A - Excluded
Div 32 - Exterior Improvements
-
$             
N/A - Excluded
Div 33 - Utilities
-
$             
N/A - Excluded
Allowances
5,415
$         
Cleaning of Ductwork
Subtotal - Direct Cost
141,687
$     
Construction Contingency
-
$             
N/A - Excluded
Insurance and Bonds
2,931
$         
Sales Tax / OH&P
14,462
$       
Overall Total Construction Cost
159,081
$     
Clarifications 
- Sales tax has been included as MRRA being that the project value is under $750,000.

Activity Name
Remaining
Duration
Start
Finish
El Mirage YMCA Flooring Replacemen
82
02-Oct-25
02-Feb-26
Pre-Construction
50
02-Oct-25
12-Dec-25
City of El Mirage
20
02-Oct-25
29-Oct-25
Review Proposal
5
02-Oct-25
08-Oct-25
Move Furniture from Teen Rm to Fitness Rm
1
02-Oct-25
02-Oct-25
Move Furniture from Fitness Rm to Teen Rm
1
02-Oct-25
02-Oct-25
Issue NTP
0
08-Oct-25
Review and Approve Submittals
5
23-Oct-25*
29-Oct-25
FCI Constructors, Inc.
50
02-Oct-25
12-Dec-25
Submit Proposal
0
02-Oct-25*
Write Subcontracts
5
09-Oct-25
15-Oct-25
Request/Review Submittals
5
16-Oct-25
22-Oct-25
Lead Times
30
30-Oct-25
12-Dec-25
Teen Rm & Office Flooring Materials
15
30-Oct-25
19-Nov-25
FItness Room Flooring Materials
30
30-Oct-25
12-Dec-25
Construction
35
03-Dec-25
27-Jan-26
FCI Constructors, Inc.
35
03-Dec-25
27-Jan-26
Mobilize
0
03-Dec-25*
Teen Rm Demo & Prep Floor
1
03-Dec-25
03-Dec-25
Teen Rm Install New Flooring
4
04-Dec-25
09-Dec-25
Teen Rm Clean Duct Work
1
10-Dec-25
10-Dec-25
Teen Rm Prep & Paint Walls
2
11-Dec-25
12-Dec-25
Fitness Rm Demo & Prep Floor
1
15-Dec-25
15-Dec-25
Fitness Rm Install New Flooring
3
16-Dec-25
18-Dec-25
Fitness Rm Clean Duct Work
1
19-Dec-25
19-Dec-25
Fitness Rm Prep & Paint Walls
2
22-Dec-25
23-Dec-25
Gym Clean & Remove Dust from Duct Work
2
22-Dec-25
23-Dec-25
Gym Prep & Paint Walls
4
24-Dec-25
31-Dec-25
Gym Flooring, Patchwork & Refinish
15
05-Jan-26
23-Jan-26
Punch Walk
1
26-Jan-26
26-Jan-26
Substantial Completion
0
27-Jan-26
Closeout
5
27-Jan-26
02-Feb-26
Complete Punch Items
5
27-Jan-26
02-Feb-26
Complete Closeout Documents
5
27-Jan-26
02-Feb-26
Final Acceptance
0
02-Feb-26
29
06
13
20
27
03
10
17
24
01
08
15
22
29
05
12
19
26
02
09
16
23
02
October
November
December
January
February
March
2025
2026
Review Proposal
Move Furniture from Teen Rm to Fitness Rm
Move Furniture from Fitness Rm to Teen Rm
Issue NTP
Review and Approve Submittals
Submit Proposal
Write Subcontracts
Request/Review Submittals
Teen Rm & Office Flooring Materials
FItness Room Flooring Materials
Mobilize
Teen Rm Demo & Prep Floor
Teen Rm Install New Flooring
Teen Rm Clean Duct Work
Teen Rm Prep & Paint Walls
Fitness Rm Demo & Prep Floor
Fitness Rm Install New Flooring
Fitness Rm Clean Duct Work
Fitness Rm Prep & Paint Walls
Gym Clean & Remove Dust from Duct Work
Gym Prep & Paint Walls
Gym Flooring, Patchwork & Refinish
Punch Walk
Substantial Completion
Complete Punch Items
Complete Closeout Documents
Final Acceptance
EL MIRAGE YMCA FLOORING REPLACEMENT & RESURFACING
02-Oct-25 17:05
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 1
TASK filter: All Activities
© Oracle Corporation