PLANNING AND ZONING 
 Development Services Department 
10000 N. El Mirage Road, El Mirage, Arizona 85335 
623-876-2996; Fax 623-876-4605; TDD 623-933-3258 
www.elmirageaz.gov 
 
1  
 
 
MEMORANDUM 
Technical Advisory Committee  
Review Comments  
TO: 
 
Richard South, DLR Group  
FROM: 
Jose A. Macias, Senior Planner 
 
 
Development Services Department, Planning & Zoning  
RE: 
SP250003 Cavco Manufacturing Facility  
DATE:  
August 28, 2025 
Mr. South,   
Please see the review comments from the El Mirage Technical Advisory Committee (TAC) for the site 
plan approval zoning application mentioned above.      
 
BUILDING & SAFETY – Brigham Bennett, Building Official  
1. No comments. 
ECONOMIC DEVELOPMENT – Tom Doyle, Economic Development Manager 
2. Great company and project for the City of El Mirage. This really complements the diversity at the 
LogistiCenter, reducing employee turnover. 
ENGINEERING – Bryce Christo, Asst. City Engineer 
3. See the attached memorandum. 
FIRE DEPARTMENT – Jason Napier, Fire Marshall   
4. See the attached memorandum. 
PLANNING & ZONING – Jose A. Macias, Senior Planner 
5. See the attached memorandum.  
POLICE DEPARTMENT – Chris Culp, Police Sergeant  
6. No comments. 
PUBLIC WORKS – Scott Ketchmark, Utilities Superintendent  
7. No comments. 
 
If you have any questions regarding these comments or would like to set up a follow-up, please feel free 
to contact my office.

Engineering 
Development Services Department 
10000 N El Mirage Road, El Mirage, AZ 85335 
623-972-8116; Fax 623-876-4605; TDD 623-933-3258 
www.elmirageaz.gov 
 
 
MEMORANDUM  
 
TO: 
 
Jose Macias, Planner/GIS 
FROM: 
Bryce Christo, P.E., Assistant City Engineer 
SUBJECT: 
Cavco Manufacturing Facility Site Plan Application Review  
DATE: 
08-25-25 
 
Below are the Engineering Division’s comments for the above referenced submittal prepared in 
August 2025. These items will have to be addressed prior to the Planning and Zoning 
Meeting 
 
1. None. 
 
The below items will have to be addressed during the Construction Plan Submittal. 
 
Project Narrative 
2. No comments. 
 
Design Exception Requests 
3. Design Exception No. 1 – Number of Driveways – This request has been approved. 
4. Design Exception No. 2 – Driveway Width – This request has been approved. 
5. Design Exception No. 3 – Parking Waiver – Parking Waivers are not requested through a 
Design Exception. The City will use Response #2 to the Planning & Zoning Comments 
from the DLR letter dated 08-11-25 as the waiver request. 
 
Preliminary Site Plan (C1.0 & C1.1) and Enlarged Site Plans (AS1.0 – AS1.3) 
6. Show the address of the property. 
7. Show the building setback lines.  
8. The project is responsible for a six-foot-wide detached (meandering where possible) 
sidewalk and landscaping/irrigation along the Ramirez Road frontage. The project will 
also be responsible for any associated right of way/easement revisions.  
9. The sidewalk shall be within the right of way, not the PUE, if possible. The sidewalk may 
be attached to the curb to avoid obstructions (streetlights, electrical equipment, etc.). If 
the sidewalk cannot fit within the right of way (i.e. areas around the proposed driveways), 
a Pedestrian Access Easement shall be dedicated to the City in these locations.  
10. Site Data – The Parking Required does not match the number on the Context Pan. Which 
is correct? 
11. The proposed driveways shall be per MAG or City standards. Stop signs are 
recommended at each driveway.

2 
 
12. If a driveway is either designated for truck entry or prohibits use by trucks, please 
provide the necessary signage. Verify that any driveway to be used by a truck can 
accommodate a WB-67 vehicle without encroaching into the adjacent lane. 
13. Show the sight distance requirements at each proposed driveway per City Detail EM-
158.  
14. Any fire lane/emergency access road shall be designed to handle 75,000 lbs. A 
Geotechnical Report will be required for this project, and it should provide a 
recommended design section for the access road(s) and any other onsite pavement 
section. 
15. Curb that carries drainage shall include a gutter. Sheet Note S3 of the Enlarged Site Plans 
calls out curb and gutter but none of the details show gutter. The curbing shall be no 
closer than 3 feet to any property line. 
16. It is noted that  “spaces adjacent to landscape or sidewalk are 16’ with a 2’ overhang”. 
This does not appear to pertain to this Site Plan any longer.  
17. Buildings 3 and 4 are shown as 30 feet tall while Sheet AS1.1 shows them as 25 feet tall. 
Which is correct? 
18. Are there any issues with the spacing between Building 1 and Buildings 5-8 or between 
Building 2 and Building 3? Or do the overhead doors align to allow for maneuverability. 
19. Sheet AS1.2 
a. Detail 1A – Show that the curb is 6 inches tall. 
b. Detail 1E – The refuse container slab is recommended to be 6 inches thick. 
c. Detail 4C – The sign will have to be specific to El Mirage and reference A.R.S. 
Section 28-884. 
 
Context Plan and Enlarged Site Plans (AS1.0 – AS1.3) 
20. 455 parking spaces requires a minimum of 9 ADA spaces including 7 standard and 2 van 
accessible spaces. 
 
Preliminary Grading Plans 
21. The proposed retention basins shall not be located within any building setbacks, 
easements, or fire lanes. The basins along Ramirez Road appear to encroach into the front 
setback and the southern basin appears to encroach into the rear setback. 
22. If any existing dry well is removed, it will need to be abandoned per EPA requirements. 
23. Side slopes adjacent to the public right to way or within the PUE, including within any 
basins, shall be 6:1 or flatter. There shall be at least two feet of level ground between any 
sidewalk, wall or vertical obstruction and the top of any side slope grading.  
24. Verify no portion of the fire lane has a longitudinal slope over 10% or a cross slope over 
5%. 
25. Headwalls require safety rail and trash racks. 
26. The City does not typically allow the co-mingling of offsite flows with on-site flows. 
However, per Section 4-3(B)(6)(c)(1) of the City’s DDSM,  “upon written request, off-
project flows, which historically flowed through the project, may be routed through the 
storm water storage facilities. The applicant shall provide specific written request 
submitted to the City Engineer and receive written acknowledgment of approval by the 
City.” 
27. Show utility clearance/crossing information per MAG Detail 404 and City Detail EM-
402. 
28. Plans shall include applicable City Notes. Call out MAG, City, etc. details to be used. 
Use the City’s Design & Development Standards Manual (DDSM) as a guide for the final 
design.

3 
 
 
Preliminary Utility Plans 
29. This site is located within the EPCOR Water and Sewer Service Area. Any water 
improvements between the main in Ramirez Road and the backflow preventer will be 
reviewed by EPCOR. Any sewer improvements within Ramirez Road right of way will 
be reviewed by EPCOR. All onsite water and sewer improvements will be reviewed by 
the City. 
30. Backflow preventers shall be placed on private property, not within the right of way or 
PUE. 
31. See City Water Note #21 and City Sewer Note #13 for pavement restoration within 
Ramirez Road. Trench Backfill within the City’s right of way shall adhere to City Detail 
EM-406. 
32. Show utility clearance/crossing information per MAG Detail 404 and City Detail EM-
402. 
33. Water valves are recommended along the fire line, approximately every 500 feet, and at 
locations so that the maximum number of hydrants to be out of service is two. 
34. Hydrants shall be installed per City Details EM-360, 361 and 362. Bollards, which are 
recommended around the hydrant when they are not protected by curbs, shall adhere to 
City Detail EM-364. 
35. Hydrants shall be spaced at a maximum of 300 feet or as approved by the Fire 
Department. 
36. All water and sewer mains and services within the site will be considered private. Any 
hydrants within the project site will be private and painted red per City Detail EM-360. 
All hydrants require markers per MAG Detail 122. 
37. There is an existing irrigation pipe that runs from the Arcadia property into the Cavco 
property. Verify whether or not this irrigation pipe active? If not, the pipe shall be 
removed from the City right of way or capped and filled with slurry. 
 
Preliminary Landscaping Plans 
38. The City Landscaping and Irrigation Notes (Detail EM-101-4) are not the most current. 
39. Landscaping and irrigation within the right of way of Ramirez Road will be required 
along the project frontage.  
40. Show the sight distance requirements at the proposed driveways per City Detail EM-
158. Verify that landscaping will not block any views.  
41. All plantings at maturity shall maintain a minimum of 3 feet of clearance from all fire 
hydrants and fire suppression devices per City Detail EM-361. Show the hydrants on the 
plans. 
42. No walls or trees shall be placed within the Public Utility Easements (PUE).  
43. Trees shall not be placed within 5 feet of any City curb or sidewalk or within 6 feet of 
any public utility. 
44. DG is required on all non-paved areas both on site and within the right of way adjacent to 
the project site. 
45. Add a note to the plans that the maintenance for all landscaping and irrigation shown on 
the plans will be the responsibility of the property owner. 
46. Irrigation plans will be required. 
 
Exterior Elevations (A4.1 – A4.10) 
47. No comments.

4 
 
Electric Plans (ES101 – ES104) 
48. No comments. 
 
Final Drainage Report   
49. This report should labeled as “Preliminary”. The Final Report shall be submitted with the 
civil plans. 
50. Section 6.0 – Note the location and elevation of the ultimate outfall.  
51. Figure 3 – The drainage arrows for Ramirez Road appear to be incorrect (they appear to 
be correct on the Preliminary Grading Plan). OFF-1 appears to drain to RB-3 and OFF-2 
appears to drain to RB-5. Verify and update the calculations accordingly. 
52. Weighted Runoff Calculations – The Cw for basins should be 1.0. 
53. Calculations for the on-site storm drain will be required. 
54. Provide stage-storage calculations for the basins. 
55. Appendix C - Verify how much offsite flow reaches the site from the north, how much 
will overflow to the south and how it will reach the CarMax site.  More recent Drainage 
Reports from CRI, TI Cold (Arcadia), Copperwing Spur Extension Phase II and CarMax 
can be obtained through a Public Records Request.  
 
Preliminary Water Report 
56. This report shall be reviewed by EPCOR. 
57. Table 1 
a. EPCOR has their own criteria and may require those numbers to be used. 
b. Note 3 – Should this be a 75% reduction? 
58. Table 3 – Include the office portion for Building 1 as well.  
59. Section 5.1 
a. The static pressure is noted as 81.9 psi. Individual pressure reducing valves sized 
equivalent to the meter size shall be installed on private services where static 
pressures will exceed 80 psi. 
b. The 1,513 gpm flow is not adequate to accommodate the max day plus fire flows 
for Building 1. This site will require a tank and pump. 
 
Preliminary Wastewater Report 
60. This report shall be reviewed by EPCOR. 
61. Table 1  
a. Maximum manhole spacing onsite shall be 400 feet. 
b. There shall be 0.2 feet of drop through the onsite manholes 
62. Table 2 – Include the office portion for Building 1 as well.  
63. Section 4.2 – The first sentence of the second paragraph is not accurate. There is an 8-
inch main in Ramirez Road that runs to a 12-inch main within Dysart Road. 
 
Traffic Impact Statement (TIS) 
64. Existing Traffic Conditions – The traffic volume data was collected when school was not 
in session. An adjustment factor shall be included. 
65. Trip Generation and Distribution Section - If there is only one shift, is it likely that the 
peak hour traffic will be 455 entering the site in the am and 455 exiting in the pm rather 
than the trips shown in Table 2? 
66. Will left turns into the driveways be accommodated within the existing TWLTL? Provide 
calculations that show this.   
67. Provide a crash summary and identify any trends and/or potential safety hazards.

5 
 
68. Due to the increase in traffic, do any of the below turn lane lengths at the Ramirez 
Road/Dysart Road intersection need to be increased? Provide calculations: 
a. NB left turn lane 
b. SB right turn lane 
c. EB left turn lane 
d. EB right turn lane 
e. What happens if the traffic signal is not installed by the time Cavco opens? 
See the City’s Auxiliary Lane Criteria for turn lane requirements.  
69. Provide an exhibit that shows the distances between the driveways (existing and 
proposed) from nearest face of curb to nearest face of curb. 
 
Title Report 
70. No comments. 
 
ALTA Survey 
71. No comments. 
 
Phase I Environmental Site Assessment 
72. Section 2.2 – The Water and Sewer Provider is EPCOR. 
73. Section 2.4 – CarMax is to the south. 
74. Section 4.0 – There are drywells in the existing on site basins. It is possible they were 
never registered. Cavco will have to register them in their name as part of their project. 
 
Miscellaneous 
75. A Final Plat will be required to show any right of way and/or easement dedications. The 
Plat shall be reviewed and approved by the City and recorded prior to Certificate of 
Occupancy.  
76. The project is responsible for reimbursement of ½ of the southbound deceleration lane at 
Dysart Road and Ramirez Road. The estimated fee is $38,000 and would be due to the 
City prior to release of the Certificate of Occupancy.  The fee is subject to change and 
will be finalized after the one year warranty period for Dysart Road (approximately 
August 2026). 
77. A Geotechnical Report will be required to provide on-site pavement sections. Verify the 
proposed pavement sections can handle 75,000 lbs. for the fire lane. 
78. A Stormwater Pollution Prevention Plan (SWPPP) will be required per the City’s SWPPP 
Guidelines document. A Notice of Intent (NOI) from ADEQ will be required prior to 
release of any Engineering permit. 
79. An Approval to Construct (ATC) will be required from MCESD for the water and sewer 
line extensions. A copy shall be provided to the City prior to the release of any 
Engineering permit. 
80. A Haul Permit will be required if 500 cubic yards or more of material will be brought 
into or out of the site. This will require a separate application, an exhibit showing the haul 
route and insurance from the company performing the haul. The fee is $300. 
81. Any cutting of the pavement in Ramirez Road will require Pavement Cut Fees per the 
most current Fee Schedule. 
82. A Dust Control Permit from the County will be required prior to the release of any 
Engineering permit. 
83. Any modifications to the farmer’s irrigation system would be an agreement between the 
developer and the property owner but the modifications may be reviewed by the City.

6 
 
84. The City will not release any permits until EPCOR provides the City with their approval 
of the water and sewer plans and reports. The applicant is responsible for submitting 
plans to EPCOR for review and approval. 
 
The above comments are meant to be general in nature and are not considered to be all inclusive. 
Additional comments will arise during the formal permit submittal.

DEVELOPMENT SERVICES  
ENGINEERING DIVISION 
10000 N. El Mirage Road 
 
 
El Mirage, AZ 85335 
Phone:  623-876-2974 
www.elmirageaz.gov 
 
 
REQUEST FOR DESIGN EXCEPTION 
 
Applicant Information  
 
Name: 
 Telephone:_
 
Address:_
 City:_
 State:
 
E-mail:
 
Name of Development: 
 Permit No.:
 
Describe the Request:  
 
1. Cite City of El Mirage Design & Development Standard or condition of approval that you are requesting the 
Design Exception for. 
 
 
 
2. Reason that the Exception is needed. 
 
 
 
3. Impacts of granting the Exception. 
 
 
 
4. Alternatives to granting the Exception. 
 
 
 
 
 
 
____
 
Applicant 
 
 
 
 
 
 
 
Date 
 
 
 
For Office Use Only 
 APPROVED            DENIED 
Comments:_
 
____
 
____
 
____
 
____
 
City Engineer or Assigned Designee 
 
 
 
 
Date 
 
08-25-25
X
Tim Thielke
602-794-2180
6225 N 24th St # 250
Phoenix
AZ
tthielke@dlrgroup.com
CAVCO Manufacturing Facility
PA250010
We are requesting a Design Exception to City of El Mirage Detail EM-259, “Maximum Number of Driveways for Commercial/Industrial Projects,” which limits the number of
driveways per street frontage to two (2). This request seeks approval for three (3) driveways along Joe Ramirez Road to accommodate the operational needs of the proposed
manufacturing facility.
The proposed facility is a manufacturing plant for the production of manufactured homes, requiring distinct access points for different vehicle types to maintain safe and efficient
operations. The easternmost driveway will serve inbound material delivery trucks, the westernmost driveway will serve outbound transport of completed homes and associated
delivery vehicles, and the center driveway will be reserved for passenger vehicles, including employees and visitors. This separation of traffic types will reduce potential conflicts, i
Approval of this exception will enhance operational efficiency and traffic safety by providing dedicated driveways for distinct vehicle types. Passenger vehicles, material delivery trucks, and outbound transport of
completed homes will each have separate points of access, reducing conflict points and improving on-site circulation. The distribution of traffic across three driveways will minimize queuing and congestion on Joe
Ramirez Road. All proposed driveways will comply with City of El Mirage sight distance, spacing, and construction standards, ensuring no adverse impact to adjacent properties or the public right-of-way.
Without this exception, all site traffic would be restricted to two driveways, forcing passenger vehicles and heavy trucks to share the same access points. This configuration would
create operational inefficiencies, increase congestion at the site entrances, and elevate the risk of vehicle conflicts. It could also result in truck queuing on Joe Ramirez Road,
impacting both public roadway operations and on-site productivity.
August 11, 2025

DEVELOPMENT SERVICES  
ENGINEERING DIVISION 
10000 N. El Mirage Road 
 
 
El Mirage, AZ 85335 
Phone:  623-876-2974 
www.elmirageaz.gov 
 
 
REQUEST FOR DESIGN EXCEPTION 
 
Applicant Information  
 
Name: 
 Telephone:_
 
Address:_
 City:_
 State:
 
E-mail:
 
Name of Development: 
 Permit No.:
 
Describe the Request:  
 
1. Cite City of El Mirage Design & Development Standard or condition of approval that you are requesting the 
Design Exception for. 
 
 
 
2. Reason that the Exception is needed. 
 
 
 
3. Impacts of granting the Exception. 
 
 
 
4. Alternatives to granting the Exception. 
 
 
 
 
 
 
____
 
Applicant 
 
 
 
 
 
 
 
Date 
 
 
 
For Office Use Only 
 APPROVED            DENIED 
Comments:_
 
____
 
____
 
____
 
____
 
City Engineer or Assigned Designee 
 
 
 
 
Date 
 
08-25-25
X
Tim Thielke
602-794-2180
6225 N 24th St # 250
Phoenix
AZ
tthielke@dlrgroup.com
CAVCO Manufacturing Facility
PA250010
We are requesting a Design Exception to City of El Mirage Detail EM-259, “Maximum Number of Driveways for Commercial/Industrial Projects,” which 
limits the number of driveways per street frontage to two (2). This request seeks approval for three (3) driveways along Joe Ramirez Road to 
accommodate the operational needs of the proposed manufacturing facility.
The proposed facility is a manufacturing plant for the production of manufactured homes, requiring distinct access points for different vehicle types to maintain safe and efficient operations. The easternmost driveway 
will serve inbound material delivery trucks, the westernmost driveway will serve outbound transport of completed homes and associated delivery vehicles, and the center driveway will be reserved for passenger 
vehicles, including employees and visitors. This separation of traffic types will reduce potential conflicts, i
Approval of this exception will enhance operational efficiency and traffic safety by providing dedicated driveways for distinct vehicle types. Passenger vehicles, material delivery 
trucks, and outbound transport of completed homes will each have separate points of access, reducing conflict points and improving on-site circulation. The distribution of traffic 
across three driveways will minimize queuing and congestion on Joe Ramirez Road. All proposed driveways will comply with City of El Mirage sight distance, spacing, and 
construction standards ensuring no adverse impact to adjacent properties or the public right-of-way
Without this exception, all site traffic would be restricted to two driveways, forcing passenger vehicles and heavy trucks to share the same access points. 
This configuration would create operational inefficiencies, increase congestion at the site entrances, and elevate the risk of vehicle conflicts. It could also 
result in truck queuing on Joe Ramirez Road, impacting both public roadway operations and on-site productivity.
August 11, 2025

Fire Department Site Plan Comments 
Date: August 27, 2025 
Project: SP250003 CAVCO Manufacturing Facility 
Project Location: 13201 W Joe R Ramirez Road 
 
 
ACCESS 
• Provide a letter of commitment from property owners along the proposed secondary access 
route between the West end of Joe R Ramirez Way and W Olive Ave agreeing to the future 
establishment of a recorded emergency access easement. The land-use process will be 
placed on hold until this commitment document is received in writing by the city. 
 
WATER 
• The submitted water report did not contain the appendices. Resubmit the report with all 
related appendices. 
 
 
Comments generated utilizing the 2018 International Fire Code and the City Municipal Code. 
 
Jason Napier | Fire Marshal  
El Mirage Fire Department 
13601 N. El Mirage Rd. 
El Mirage, Arizona 85335 
T. 623-251-3507 | F. 623-583-8257 
jnapier@elmirageaz.gov

PLANNING AND ZONING 
Development Services Department 
10000 N. El Mirage Road, El Mirage, Arizona 85335 
623-876-2996; Fax 623-876-4605; TDD 623-933-3258 
www.elmirageaz.gov 
 
 
Planning & Zoning Review Comments Memorandum 
TO: 
 
Richard South, DLR Group  
FROM: 
Jose A. Macias, Senior Planner 
 
 
Development Services Department, Planning & Zoning  
RE: 
SP250003 Cavco Manufacturing Facility  
DATE: 
August 20, 2025 
Mr. South,   
Please review the comments from the Planning and Zoning Division regarding the Preliminary 
Application submission for the proposed project outlined above. 
APPLICATION FORM 
• Property Owner: Cavco Exchange LLC 
• Assigned Address: 13201 W Joe R Ramirez, El Mirage, AZ 85335  
o One street number with a letter for each building.  
ZONING 
• El Mirage 2020 General Plan: Commercial/Industry Park 
• Zoning: Planned Area Development (PAD) 
• Overlay District: Luke AFB 80 LDN Zone, Accident Potential Zone II 
• Current Land Use: Undeveloped 
• Flood Area: Not Applicable 
• Proposed Land Use: Manufacturing, Light (Permitted)  
• Zoning Application Requirement: Site Plan Approval & Parking Waiver 
PROJECT NARRATIVE:  
1. A request for a conditional use permit is not required because outdoor storage is a 
permitted use on the Employment/Industrial zone. 
2. The Planning and Zoning Division has no issues with the parking waiver request and 
recommends approval.  
 
SITE PLAN 
The site plan application submittal did not address these pre-application (PA250010) comments. 
Please provide a response.  
3. Please add the following statement to the site plan:  
“Any change of use or occupancy of any building or buildings, including additions 
thereto requiring more parking, shall not be permitted until such additional parking 
spaces as required by this chapter are furnished.”

2 
 
4. The area around Trash Compactors and closed Dumpsters shall be identified by 
bollards to prevent them from moving around the yard.  
5. Identify the ground surface material and use it throughout the lot.  
 
ELVATIONS 
6. No comments.  
LANDSCAPE PLANS 
7. The retention area at the south of the property does not need plantings; decomposed 
granite will be required for dust and weed control since it is out of the public view.   
8. All required trees shall be a minimum of 15 gallons in size, and at least 50% of those 
trees must be 24-inch boxes or larger.  
9. All 24-inch box and larger trees shall be a minimum of ten feet in height, four feet in 
spread, and two and a half inches trunk caliper at the ground level.  
10. Decomposed granite shall be 1/2" or 3/4" screened material with a minimum of two 
(2) inches in depth. Decomposed granite is required in all non-paved areas, both on-
site and within the right-of-way adjacent to the site. 
11. All trees shall maintain a minimum of 6'-0" clearance from any city water or sewer 
line and a minimum of 5'-0" clearance from any city sidewalk and curb. All plantings 
shall maintain a sufficient distance from any sanitary and storm sewer manholes to 
allow access by maintenance vehicles. 
12. At maturity, all plantings shall maintain a minimum 3'-0" clearance around all fire 
hydrants and fire suppression devices. 
SIGNAGE 
13. Sign permits are required for all types of signs, including monuments, freestanding 
signs, wall signs, and others. Building address and number signs are excluded from 
this requirement. Separate fees will apply for obtaining these permits. Click here to 
access the sign regulations.  
FINAL PLAT 
14. A Final Plat will be required for staff review and City Council approval to accept any 
lot splits, lot combinations, land deeded to the City, utilities easements, and cross-
access easements before the building and engineering permits are issued. Process 
$1,000.00 plus $10.00 per lot/tract. 
 
ARS 28-8481 MILITARY LAND USE COMPATIBILITY 
15. The site is located inside the Luke Air Force Base (LAFB) Noise Contour Zone, 
Accident Potential Zone II, and the Military Airport Territory Area and is subject to 
review from LAFB for land use compatibility with ARS 28-8481. Please see the 
attached review letter from LAFB.  
MISCELLANEOUS  
16. Cavco Exchange LLC shall obtain and maintain a city business license.  
 
If you have any questions regarding these comments, please feel free to contact my office at 
(623)876-2996 or jmacias@elmirageaz.gov.