CITY OF TEMPE
Meeting Date: 4/16/2026  
REQUEST FOR COUNCIL ACTION
Agenda Item: 8A1
ACTION: Award a construction contract to Mid-America Golf and Landscape, Inc. for Project No. 
6311491 – Irrigation Replacement - Ken McDonald Golf Course.
FISCAL IMPACT: The construction contract amount is $3,237,654.22 and the contingency is 
$320,000. Funds to cover this contract, related costs and any future addenda are appropriated in Fiscal 
Year 2025/26 and future years, contingent upon City Council approval of the City’s annual budget, in 
Capital Improvement Project No. 6311499 (Ken McDonald Irrigation Renovation).
RECOMMENDATION:  Award contract
 
BACKGROUND INFORMATION:  The current Ken McDonald Golf Course (KMGC) irrigation system 
was installed in 1992 and has exceeded its useful life. A study completed in 2021 recommended a 
complete replacement due to below-ground polyvinyl chloride (PVC) pipes exceeding lifecycle, outdated 
control system, inadequate spacing of sprinkler heads and aging intakes and infrastructure. Both the 
north and south pump stations have been replaced since 2021 and will not need to be replaced as part 
of this project.
This project replaces the full irrigation system at KMGC.
Scope of Work: 

Golf course irrigation system

Cultural Resources/Archaeological coordination
ATTACHMENTS:    
1. 6311491 CMAR MID-AMERICA GOLF AND LANDSCAPE - IRRIGATION REPLACEMENT 
KMGC.PDF
STAFF CONTACT(S): 
Jodie Inman, P.E., Deputy Public Works Director - Engineering, (480) 350-
2972; Alex Jovanovic, Deputy Community Services Director - Parks, (480) 350-5811
Department Director:  Tara Ford, Public Works Director  
Legal review by:  Dave Park, Sr. Assistant City Attorney
Prepared by:  Decima Sever, Administrative Manager