Presentation

City of Mesa — Board of Adjustment Public Hearing (2026-06-03)

View PDF Meeting page

Extracted text (via pymupdf) 2541 characters
Board of Adjustment
City of Mesa

BOA26-00182
Spilsbury Future Site Plan
Sergio Solis

Request
DEVELOPMENT SERVICES
3
•
Special Use Permit (SUP) to allow 
the combined gross floor area of 
all detached accessory buildings 
or structures to exceed 100% of the 
gross floor area of the primary
•
SUP to allow a detached structure 
to exceed the height of the 
primary building

Location
DEVELOPMENT SERVICES – PLANNING DIVISION
4
•
521 East Lehi Road
•
East of Mesa Drive
•
South of Lehi Road

5
DEVELOPMENT SERVICES
General Plan
•
Rural Residential Placetype
•
Conserve Growth Strategy
•
Single-family residential is a 
principal land use

6
DEVELOPMENT SERVICES
Zoning
•
Single Residence 43 (RS-43)

7
Site Photo
Looking south towards the site
DEVELOPMENT SERVICES

• Primary Residence: 
Approximately 4,608 sq. ft.
• Proposed detached 
structures (combined): 
Approximately 9,924 sq. ft.
• 50’ x 150’ RV garage, 
• 25’ x 60’ carport, and 
• 20’ x 40’ BBQ ramada. 
8
DEVELOPMENT SERVICES
Site Plan

9
DEVELOPMENT SERVICES
Enlarged Site Plan

10
DEVELOPMENT SERVICES
Elevations

11
DEVELOPMENT SERVICES
Elevations

12
DEVELOPMENT SERVICES
Special Use Permit (SUP)
Per MZO Section 11-70-5, a SUP shall only be granted if the approving body determines that 
the project as submitted or modified conforms to all of the following criteria:
1.
Approval of the proposed project will advance the goals and objectives of and is 
consistent with the policies of the General Plan and any other applicable City plan and/or 
policies;
2. The location, size, design, and operating characteristics of the proposed project are 
consistent with the purposes of the district where it is located and conform with the 
General Plan and with any other applicable City plan or policies;
3. The proposed project will not be injurious or detrimental to the adjacent or surrounding 
properties in the area, nor will the proposed project or improvements be injurious or 
detrimental to the neighborhood or to the general welfare of the City; and
4. Adequate public services, public facilities and public infrastructure are available to serve 
the proposed project.

• Notified property owners 
within 150’, HOAs, and 
registered neighborhood 
• Staff has not received any 
calls or emails regarding the 
Proposed Project.
13
DEVELOPMENT SERVICES
Notification

14
DEVELOPMENT SERVICES
Findings
Complies with the 2050 Mesa General Plan
Meet the SUP findings of 11-70-5

15
DEVELOPMENT SERVICES
Recommendation
Approval with conditions

Board of Adjustment
City of Mesa