Council Report

City of Mesa — City Council (2026-06-01)

View PDF Meeting page

Extracted text (via pymupdf) 3515 characters
City Council Report 
 
 
Date:  
June 1, 2026 
To: 
 
City Council 
Through: 
Marc Heirshberg, Deputy City Manager 
From:  
Lance Webb, City Engineer 
 
 
Marc Ahlstrom, Assistant City Engineer 
 
Subject: 
Amendment 2 to Intergovernmental Agreement with Flood Control District 
of Maricopa County for Design, Rights-of-Way Acquisition, Utility 
Relocations, and Construction of Drainage Improvements on Baseline 
Road east of Signal Butte Road 
 
 
City Project No. CP1099 
Council District(s) 5 and 6 
 
 
Purpose and Recommendation 
 
The purpose of this report is to request Council approval of a resolution to amend the IGA 
in order to extend the Project construction and funding from June 30, 2026, to June 30, 
2027, and to update the estimated Project costs. (See Exhibit A for project location) 
 
Flood Control District of Maricopa County (District) has agreed to fund seventy-five (75%) 
of the construction costs, up to $500,000. The City will cover the full design costs and 
remaining construction costs. The City’s estimated contribution is $540,901. 
 
Staff recommends that the Council approve the resolution and authorize the City Manager 
to execute this IGA amendment on behalf of the City. 
 
Background 
 
Baseline and Signal Butte Roads Drainage Improvements Project intends to mitigate 
excess stormwater runoff impacting existing residences and businesses. This will be 
achieved through a drainage ditch and other drainage features that divert stormwater into 
the existing storm drain system. 
 
On October 19, 2022, the Board of Directors of the District (the Board) adopted Resolution 
FCD 2022R003 (C-69-23-013-X-00) authorizing the District to cost-share in projects 
recommended under the District’s Small Project Assistance Program. At this time, a draft

2
IGA was prepared that limited the District’s financial participation to charges for work 
completed and invoiced between July 1, 2022 and June 30, 2024. 
 
On October 18, 2023, the Board approved IGA FCD 2022A007 authorizing the District 
and the City to cost-share in the Project. On October 23, 2024, the Board approved IGA 
FCD 2022A007A extending the completion date for the Project from June 30, 2024 to 
June 30, 2026.   
Project development since authorization has taken longer than originally anticipated. 
Easement acquisition across Arizona State Land significantly contributed to the delay. 
Due to these circumstances, the City has requested and the District has agreed to extend 
the completion date from June 30, 2026, to June 30, 2027.    
 
Discussion 
 
The purpose of this IGA amendment is to extend the Project construction and funding 
from June 30, 2026 to June 30, 2027. It is anticipated that construction will start in Fall 
2026 and be completed in Summer 2027.  
 
Community Impact – This project will mitigate stormwater runoff that impacts existing 
residences and businesses.     
 
Alternatives 
 
The City Council could choose not to enter into this IGA.  This is not recommended 
because it will significantly affect residents and businesses along Baseline Road east of 
Signal Butte Road. 
 
Fiscal Impact 
 
The District has agreed to fund seventy-five (75%) of the construction costs, up to 
$500,000. The City will cover the full design costs and remaining construction costs. The 
City’s estimated contribution is $540,901. 
 
This project is funded by Local Streets, HURF and Transportation Funds.  
 
Coordinated With 
 
The Transportation Department concurs with this recommendation.