Council Report

City of Mesa — City Council (2026-06-01)

View PDF Meeting page

Extracted text (via pymupdf) 10780 characters
1 
 
 
Fees and Charges Report 
 
Date: 
To: 
June 1, 2026 
City Council 
Through:   Marc Heirshberg, Assistant City Manager 
 
From: 
Erik Guderian, Transportation Department Director 
 
Subject: 
Changes to the Transportation Department’s Schedule of Fees and 
Charges for In-Lieu Fees for Traffic Signals and Pavement Surfacing 
Replacement and an Administrative Update adding the Technology 
Improvement Fee Language (Citywide) 
 
Purpose and Recommendation 
The Transportation Department is proposing adjustments to the In-Lieu Fees for Traffic 
Signals and Pavement Surfacing Replacement in the Schedule of Fees and Charges. If 
the proposed changes are approved by City Council, the fees and charges will be effective 
July 1, 2026. 
 
Staff recommends that a standard payment in-lieu of construction for a traffic signal be 
set at $900,000 ($225,000 per quadrant) for a four-leg intersection and $600,000 
($200,000 per share) for a “T” intersection where no driveway access is planned for the 
top of the “T”. (see Exhibit A). 
 
Due to market price increases, the cost of slurry seal has increased to $4.00 per square 
yard. The Transportation Department is recommending an increase to the in-lieu payment 
for pavement surfacing replacement from $2.75 per square yard to $4.00 per square yard. 
 
An administrative update is being made to add the Technology Improvement Fee 
language to the Transportation section of the Schedule of Fees and Charges. This update 
applies to the Temporary Traffic Control Fees and aligns Transportation’s wording with 
how other departments reference the fee in their sections of the schedule. 
 
Background 
The traffic signal in-lieu fees were last updated in 2019. At that time, the in-lieu fee was 
set at $350,000 ($87,500 per quadrant) per traffic signal for a four-leg intersection and 
$320,000 ($80,000 per quadrant) per traffic signal for a “T” intersection. Construction 
costs of labor and materials for traffic signals have significantly increased. The proposed 
fees reflect the market cost the City is currently paying.

2 
 
Developers are required to pay an in-lieu fee proportional to the number of corners being 
developed adjacent to a proposed signal, if the traffic signal would benefit more than one 
development. If a traffic signal is directly benefitting one development, then that 
Developer is responsible for constructing the entire traffic signal as part of their off-site 
improvements. The City collects the in-lieu fee from the Developer and will construct the 
traffic signal when traffic volumes warrant the need for a traffic signal. Typically, the 
City collects less than three traffic signal in-lieu fees per year from Developers. 
 
Pavement cuts are extractions or modifications of roadways performed by the City to 
allow utility and communication companies and others access to underground utilities. 
Pavement cuts accelerate the rate of deterioration of the City’s streets, therefore, fees 
have been established to allow for an in-lieu payment made by the utility or 
telecommunication company to be credited to Transportation’s Field Operations budget. 
The fees are then utilized when the street undergoes future treatment based on an 
existing maintenance schedule. 
 
Research has shown that the quality and design life of a roadway is diminished by 
approximately 27% when pavement cuts are required as part of work performed. 
Maricopa Association of Governments (MAG) has developed specifications for pavement 
matching and surfacing replacement to minimize the level of roadway deterioration, which 
the City has adopted. 
MAG Specification 336 allows for the following: 
 
“In lieu of placing the seal coat as required previously, and with approval of the local 
jurisdiction, the Contractor may deposit with the Street Maintenance Department for 
credit, a negotiated agreed upon amount. The Street Maintenance Department will 
incorporate this work into their street maintenance program." 
 
Discussion 
The cost of constructing traffic signals has increased significantly since in-lieu fees 
were updated in 2019. 
Traffic signals that have been newly constructed or 
reconstructed by the City of Mesa, in recent years, have ranged in constructions costs 
from $682,656-$1,057,048, for a four-legged intersection. 
 
Based on this cost data, staff recommends setting the fee for a traffic signal at 
$900,000 ($225,000 per quadrant) for a four-leg intersection and $600,000 ($200,000 
per share) for a “T” intersection. “T” intersections are generally less complex and 
less costly to construct, and their costs will be assessed on a per-share basis that 
corresponds to the number of intersection legs and adjacent property frontages. Any 
difference in the actual cost of the traffic signal will be borne by the City as part of the 
Traffic Signal CIP Program. Based on recent prices and price increases, City 
contributions toward traffic signal construction will likely be ongoing, but at a much 
lower level than today, if the increase is approved. 
 
Since July 2011, contractors have been allowed to submit payment to the City in-lieu 
of placing seal coat as previously required. A fee based upon the City contract pricing

3 
 
for slurry seal coat materials, per square yard, was established for in-lieu payments and 
used 
as 
a 
negotiated 
agreed 
upon 
unit 
price 
amount. 
The 
$4.00 
fee 
recommendation is a direct, dollar-for-dollar result of the per square yard cost increase 
of the material to ensure cost recovery. The last fee increase was approved in 2023 to 
reflect market costs at a new rate of $2.75 per square yard. 
 
Alternatives 
The City could choose to leave the traffic signal in-lieu fees at the current rates of 
$350,000 ($87,500 per quadrant) for a four-leg intersection and $320,000 ($80,000 per 
quadrant) for a “T” intersection. This will result in the City bearing the additional cost of 
construction as the current traffic signal in-lieu fee only covers approximately 40 percent 
of the actual cost of a traffic signal. 
 
If the in-lieu payment for pavement surfacing replacement is not increased, the City could 
require the utility company cutting into the roadway to perform the required slurry seal 
coating per MAG specifications. With this alternative, the area seal coated by the utility 
company is then not aligned with the City’s established maintenance schedule for the 
roadway. The materials used by other companies not monitored under City contract are 
not consistent with those used by the City and, therefore, may not bond as well, further 
contributing to the deterioration of the life of the roadway. There is also limited availability 
of vendors and equipment for this type of work, making it difficult to complete smaller jobs. 
 
Fiscal Impact 
The fiscal impact of increasing the Traffic Signal In-Lieu Fees is approximately $0-
$412,500, per year for traffic signal construction, based on the assumption that 0-3 in-lieu 
fees are collected. The increase in fees allows the traffic signal that is driven by 
development to be funded by the development that benefits from the traffic signal. 
 
In-lieu payments received from companies making cuts in City roadways have allowed 
for the maintenance to be performed according to an established maintenance schedule. 
The increase to the fee will generate an additional $45,500 per year to recuperate the 
contract costs for the slurry seal. 
 
There is no fiscal impact by adding the Technology Improvement Fee language to 
Transportation’s section of the fee schedule. No changes are being made to this fee. It 
is merely an administrative update to be consistent with how the language is displayed in 
other sections of the fee schedule. 
 
Coordinated With 
The recommended fees and charges were coordinated with the Office of Management 
and Budget, as well as the Transportation Advisory Board for Traffic Signal In-Lieu fees, 
and Engineering for Pavement Surfacing Replacement.

4 
 
Fees & Charges Schedule – Key 
 
 
 
Heading Configuration 
Schedule of Fees & 
Charges 
Department 
Contact Information 
HEADING 1 
HEADING 2 
Heading 3 
Description of Fee 
Description of Fee 2 
 
 
Font Indications 
Font 
Font Indications 
Regular Font 
Existing fee or language 
Strikethrough 
Fee or language will be deleted 
from the Fee Schedule 
BOLD CAPS 
Language is being added to Fee 
Schedule 
Bold 
New or increased Fee Amount

5 
 
Schedule of Fees & Charges 
Exhibit A - Transportation In Lieu Fees 
Department: Transportation 
 
Description of Service 
Current Fee 
Range 
Proposed 
Fee Range 
Unit 
Total Fiscal 
Impact 
Notes 
Temporary Traffic Control Fee 
REFER TO THE DEVELOPMENT 
SERVICES PORTION OF THE 
SCHEDULE OF FEES AND 
CHARGES FOR TEMPORARY 
TRAFFIC CONTROL FEES. IN 
ADDITION TO THE TEMPORARY 
TRAFFIC CONTROL FEES 
LISTED, A TECHNOLOGY 
IMPROVEMENT FEE SHALL 
ALSO APPLY. 
EACH AND EVERY PERMIT FEE 
AND SERVICE FEE OF ALL 
TYPES SHALL BE ASSESSED 
AN ADDITIONAL TECHNOLOGY 
IMPROVEMENT FEE EQUAL TO 
FOUR PERCENT (4%) OF THE 
PERMIT AND/OR SERVICE FEE 
TOTAL TO FUND TECHNOLOGY 
IMPROVEMENTS. SUCH 
ADDITIONAL TECHNOLOGY 
IMPROVEMENT FEE SHALL BE 
LIMITED TO A MAXIMUM OF 
EIGHT HUNDRED DOLLARS 
($800.00) ON EACH PERMIT OR 
SERVICE FEE TRANSACTION. 
SUCH ADDITIONAL 
TECHNOLOGY IMPROVEMENT 
FEE SHALL ONLY BE USED TO 
ACQUIRE AND IMPLEMENT 
New paragraph – administrative 
update to add Technology 
Improvement Fee language to the 
Transportation section of the fee 
schedule, aligning it with how 
other departments display the fee.

6 
 
IMPROVEMENTS TO THE LAND 
DEVELOPMENT PROCESS 
TECHNOLOGIES APPROVED BY 
THE CITY MANAGER. 
TRANSPORTATION IN LIEU 
FEES 
New sub-section 
Per Quadrant at Arterial-To-Arterial 
FOUR-LEG Intersections 
$87,500.00 
$225,000.00 
Per Quadrant 
$412,500.00 Raising fee to reflect the actual 
cost of traffic signal construction 
as of 2025. Fiscal impact is 
dependent on number of 
developments requesting in-lieu 
fee. Typical collections range from 
0-3 per year. 
Per SHARE AT “T” intersectionS 
With No Driveway Access Planned 
at Top of “T” 
$80,000.00 
$200,000.00 
Per Quadrant 
SHARE 
$0 Raising fee to reflect the actual 
cost of traffic signal construction 
as of 2025. Fiscal impact is 
dependent on number of 
developments requesting in-lieu 
fee. Typical collections range from 
0-3 per year. 
In-Lieu Payments for Pavement 
Surfacing Replacement 
$2.75 
$4.00 
Per Square 
Yard 
$45,500.00 Revenues vary year to year based 
on development activity. $45,500 
of total fiscal impact is based on 
45.5% unit cost increase for an 
estimated $100K in collections. 
WILL BE COLLECTED BY DEV 
SVC & ENG TRANSFER TO 
THEIR DEPT 2019 E.G. 
Estimated Total Annual Fiscal Impact: 
$458,000.00